WL-1.2.1 Water injection flowline construction work 22 2/May/20 31/May/20 4 31/May/20
A1040 flowline R.O.W survey and underground line detection 1 2/May/20 2/May/20 4 flowline R.O.W survey and underground line detection A1050 R.O.W preparation and opening 1 2/May/20 2/May/20 4 R.O.W preparation and opening A1060 stringing of pipes , support installation 8 2/May/20 10/May/20 4 stringing of pipes , support installation A1070 welding activities 12 2/May/20 19/May/20 4 welding activities A1080 RT 12 2/May/20 19/May/20 4 RT A1090 crossing activities 10 2/May/20 17/May/20 6 crossing activities A1100 sections cleaning and hydro test preparation 3 20/May/20 23/May/20 4 sections cleaning and hydro test preparation A1110 hydro test activities 1 24/May/20 24/May/20 4 hydro test activities A1120 dewatering and section drying 2 25/May/20 26/May/20 4 dewatering and section drying A1130 coating activities and holiday test 4 27/May/20 31/May/20 4 coating activities and holiday test
WL-1.2.2 CPS tie-in construction 3 9/Jun/20 11/Jun/20 0 11/Jun/20
A1140 final tie-in CPS construction 3 9/Jun/20 11/Jun/20 0 final tie-in CPS construction
WL-1.3 wellhead piping construction 26 2/May/20 4/Jun/20 0 4/Jun/20
WL-1.3.1 site preparation 1 2/May/20 2/May/20 0 2/May/20
A1150 survey and wellhead layout 1 2/May/20 2/May/20 0 survey and wellhead layout A1160 material collect 1 2/May/20 2/May/20 0 material collect WL-1.3.2 construction work 25 3/May/20 4/Jun/20 0 4/Jun/20 A1170 civil work including excavation , pipe support , backfilling .... 2 3/May/20 4/May/20 0 civil work including excavation , pipe support , backfilling .... A1180 piping spools fabrication and welding 5 3/May/20 7/May/20 0 piping spools fabrication and welding A1190 RT 5 9/May/20 18/May/20 0 RT A1200 Valve & fitting installtion 5 19/May/20 24/May/20 0 Valve & fitting installtion A1210 hydro test activities 5 25/May/20 30/May/20 0 hydro test activities A1220 coating work 5 31/May/20 4/Jun/20 0 coating work 3 6/Jun/20 WL-1.4 Water injection flowline Mechanical completion certificate 8/Jun/20 0 8/Jun/20
A1230 punch list closed 2 6/Jun/20 7/Jun/20 0 punch list closed
A1240 final inspection and FL MCC approved 1 8/Jun/20 8/Jun/20 0 final inspection and FL MCC approved WL-1.5 project hand over 2 13/Jun/20 14/Jun/20 0 14/Jun/20 A1250 Final MCC 1 13/Jun/20 13/Jun/20 0 Final MCC A1260 commissioning & project hand over 1 14/Jun/20 14/Jun/20 0 commissioning & project hand over