construction of 3.

5km 8" water injection flowline & water wellhead


Activity ID Activity Name Original Start Finish Total Day
Duration Float
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 4647
34 2/May/20
WL-1 construction of 3.5 KM8" water injection flowline & Water14/Jun/20
wellhead 0 14/Jun/20

WL-1.1 Keys of project 34 2/May/20 14/Jun/20 0 14/Jun/20


A1000 PO issued 0 2/May/20 0
A1010 materials collection from client yard 0 2/May/20 0
A1020 mechanical complete 0 8/Jun/20 5
A1030 project handover 0 14/Jun/20 0
WL-1.2 Waterline construction 32 2/May/20 11/Jun/20 0 11/Jun/20

WL-1.2.1 Water injection flowline construction work 22 2/May/20 31/May/20 4 31/May/20


A1040 flowline R.O.W survey and underground line detection 1 2/May/20 2/May/20 4 flowline R.O.W survey and underground line detection
A1050 R.O.W preparation and opening 1 2/May/20 2/May/20 4 R.O.W preparation and opening
A1060 stringing of pipes , support installation 8 2/May/20 10/May/20 4 stringing of pipes , support installation
A1070 welding activities 12 2/May/20 19/May/20 4 welding activities
A1080 RT 12 2/May/20 19/May/20 4 RT
A1090 crossing activities 10 2/May/20 17/May/20 6 crossing activities
A1100 sections cleaning and hydro test preparation 3 20/May/20 23/May/20 4 sections cleaning and hydro test preparation
A1110 hydro test activities 1 24/May/20 24/May/20 4 hydro test activities
A1120 dewatering and section drying 2 25/May/20 26/May/20 4 dewatering and section drying
A1130 coating activities and holiday test 4 27/May/20 31/May/20 4 coating activities and holiday test

WL-1.2.2 CPS tie-in construction 3 9/Jun/20 11/Jun/20 0 11/Jun/20


A1140 final tie-in CPS construction 3 9/Jun/20 11/Jun/20 0 final tie-in CPS construction

WL-1.3 wellhead piping construction 26 2/May/20 4/Jun/20 0 4/Jun/20

WL-1.3.1 site preparation 1 2/May/20 2/May/20 0 2/May/20


A1150 survey and wellhead layout 1 2/May/20 2/May/20 0 survey and wellhead layout
A1160 material collect 1 2/May/20 2/May/20 0 material collect
WL-1.3.2 construction work 25 3/May/20 4/Jun/20 0 4/Jun/20
A1170 civil work including excavation , pipe support , backfilling .... 2 3/May/20 4/May/20 0 civil work including excavation , pipe support , backfilling ....
A1180 piping spools fabrication and welding 5 3/May/20 7/May/20 0 piping spools fabrication and welding
A1190 RT 5 9/May/20 18/May/20 0 RT
A1200 Valve & fitting installtion 5 19/May/20 24/May/20 0 Valve & fitting installtion
A1210 hydro test activities 5 25/May/20 30/May/20 0 hydro test activities
A1220 coating work 5 31/May/20 4/Jun/20 0 coating work
3 6/Jun/20
WL-1.4 Water injection flowline Mechanical completion certificate 8/Jun/20 0 8/Jun/20

A1230 punch list closed 2 6/Jun/20 7/Jun/20 0 punch list closed


A1240 final inspection and FL MCC approved 1 8/Jun/20 8/Jun/20 0 final inspection and FL MCC approved
WL-1.5 project hand over 2 13/Jun/20 14/Jun/20 0 14/Jun/20
A1250 Final MCC 1 13/Jun/20 13/Jun/20 0 Final MCC
A1260 commissioning & project hand over 1 14/Jun/20 14/Jun/20 0 commissioning & project hand over

Date Revision Checked Approved


Actual Work
Remaining Work Maraba AL-IRAQ DR.CONCRETE 27/Feb/20 R1 ENG. Wael...

Critical Remaining Work


Milestone AL-KHADRA CO. CO.