Construction plan of 16 " Flexline

Activity ID Activity Name Original Start Finish Total Day


Duration Float
1 2 3 4 5 6 7 8 9 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 5 5 5 5 5 5 5 5 5 5 6 6 6 6 6 6 6 6 66
Flex construction of 3.5 KM 16" above ground flexline 52 2/May/20 5/Jul/20 0 5/Jul/20

Flex.1 Keys of project 51 2/May/20 4/Jul/20 1 4/Jul/20


A1000 PO issued 0 2/May/20 0
A1010 materials collection from client yard 0 2/May/20 0
A1020 mechanical complete 0 4/Jul/20 1
A1030 project handover 0 4/Jul/20 1
Flex.2 Flexline construction work 49 2/May/20 1/Jul/20 0 1/Jul/20
A1040 flowline R.O.W survey and underground line detection 3 2/May/20 4/May/20 0 flowline R.O.W survey and underground line detection
A1050 R.O.W preparation and opening 5 2/May/20 6/May/20 0 R.O.W preparation and opening
A1060 stringing of pipes , support installation 15 2/May/20 23/May/20 0 stringing of pipes , support installation
A1070 welding activities 41 2/May/20 22/Jun/20 0 welding activities
A1080 RT 41 2/May/20 22/Jun/20 0 RT
A1090 crossing activities & tie-in activities 30 2/May/20 9/Jun/20 11 crossing activities & tie-in activities
A1100 sections cleaning and hydro test preparation 3 23/Jun/20 25/Jun/20 0 sections cleaning and hydro test preparation
A1110 hydro test activities 1 27/Jun/20 27/Jun/20 0 hydro test activities
A1120 dewatering and section drying 2 28/Jun/20 29/Jun/20 0 dewatering and section drying
A1130 coating activities and holiday test 4 28/Jun/20 1/Jul/20 0 coating activities and holiday test
Flex.3 Fexline Mechanical completion certificate 3 2/Jul/20 5/Jul/20 0 5/Jul/20
A1140 punch list closed 2 2/Jul/20 4/Jul/20 0 punch list closed
A1150 final inspection and FL MCC approved 1 5/Jul/20 5/Jul/20 0 final inspection and FL MCC appro
Flex.4 project hand over 2 2/May/20 3/May/20 50 3/May/20

A1170 Final MCC 1 2/May/20 2/May/20 50 Final MCC


A1180 commissioning & project hand over 1 3/May/20 3/May/20 50 commissioning & project hand over

Date Revision Checked Approved


Actual Work
Remaining Work Maraba AL-IRAQ DR.CONCRETE 27/Feb/20 R1 ENG. Wael...

Critical Remaining Work


Milestone AL-KHADRA CO. CO.