Activity ID Activity Name Original Start Finish Total Week
Duration Float 1 2 3 11 2/May/20 WHC new drilling oil production wellhead (NDW) hook up 18/May/20 0 18/May/20
WHC.1 Keys of project 11 2/May/20 18/May/20 0 18/May/20
A1000 award of contract and PO issued to MIK CO. 0 2/May/20 0 A1010 issue and collecting materials from client yard and construction starting 0 2/May/20 0 A1020 pre-commissioning & mechanical comletion 0 11/May/20* 3 A1030 commissioning & end of project 0 18/May/20 0 WHC.2 Logistic 5 2/May/20 6/May/20 0 6/May/20 A1040 collect and transport construction materials to workshop 1 2/May/20 2/May/20 0 collect and transport construction materials to workshop A1050 Transportion of piping spools to site 1 6/May/20 6/May/20 0 Transportion of piping spools to site WHC.3 construction 8 2/May/20 10/May/20 0 10/May/20
WHC.3.4 fabrication work in workshop 4 2/May/20 5/May/20 0 5/May/20
A1060grinding & leveling pipe spools and welding of joints 4 2/May/20 5/May/20 0 grinding & leveling pipe spools and welding of joints A1070RT activities 4 2/May/20 5/May/20 0 RT activities WHC.3.5 work in site 8 2/May/20 10/May/20 0 10/May/20 A1080PRC from client 1 2/May/20 2/May/20 4 PRC from client A1090site lay out & survey 1 2/May/20 2/May/20 4 site lay out & survey A1100piping support & spools installation 1 6/May/20 6/May/20 0 piping support & spools installation A1140hydrotest activities 1 10/May/20 10/May/20 0 hydrotest activities A1150reinstatement 1 10/May/20 10/May/20 0 reinstatement A1110field joints welding 3 6/May/20 9/May/20 0 field joints welding A1120RT activities 3 6/May/20 9/May/20 0 RT activities A1130valves installation & preparation for hydrotest 3 6/May/20 9/May/20 0 valves installation & preparation for hydrotest WHC.4 mechanical completetion certificate work 3 11/May/20 18/May/20 0 18/May/20 A1170 final inspection 1 18/May/20 18/May/20 0 final inspection A1160 internal punchlist 2 11/May/20 17/May/20 0 internal punchlist WHC.5 commissioning & end of project 1 18/May/20 18/May/20 0 18/May/20 A1180 handover of well head project 1 18/May/20 18/May/20 0 handover of well head project
Date Revision Checked Approved
Actual Work Remaining Work Maraba AL-IRAQ DR.CONCRETE 27/Feb/20 R1 ENG. Wael...