Electrical Maintenance Schedule (3~4Hrs) 18th June, 2016

Shafaat, Musawer, Imtiaz, Zeeshan, Zaib-Ullah, Waqas, Noroz, Kashif, Ghafoor (Shift-A)
am
Te

Atta-ur-Rehman, Mukhtiyar, Adil, Ihtiram, Abdullah (Shift B)

S.No. Work Description Done By Status Remarks

Section: Refiner
1 DC Plug Screw Carbon Bushes Checking & Cleaning

2 ID FAN Motor Connection Box Checking

3 Pneumatic Fan Motor Connection Box Checking

4 Star/Delta and Main Contactors Checking of ID Fan and Pneumatic

5 Transport Screw Carbon Bushes Checking & Cleaning

6 HT Motor Water Rheostat Checking for Water Level

7 HT Motor Cleaning & Carbon Bushes Checking

Section: Energy Plant


8 AC Drives Cleaning

9 Control Panels Cleaning with Vacuum Cleaner

Section: Press & Forming

Page 1 of 2
10 Checking of Sensors and Limit Switches in Loader, Press and Unloader

11 Star/Delta and Main Contactors Checking of Press Hydraulic Motors

12 DC Motor Carbon Bushes Checking and Cleaning

13 AC & DC Drives Cleaning with Blowers

Section: Trimming
14 Checking of High Speed Saw Motors for abnormal sound of Bearings

Section: Forming Exhaust Blowers


15 Forming Exhaust System Blowers' Star/Delta Contactors Checking

16 Cleaning of All AC Drive and Panels

Section: Miscellaneous
17 Cleaning of All Indoor Motors

18 Cleaning of All Indoor Sensor and Limit Switches

19 All Rotary Valve Sensors Checking

20

Page 2 of 2