TECHNICAL SERVICE PROCEDURE FOR ELECTROLESS NICKEL:

CHEMSHIELD PROCESS

CONDITION CAUSE REMEDY

1. No deposit and a. Low temperature. a. Adjust temperature.


or slow plating
rate
b. Low pH. b. Adjust pH .
c. Poor Cleaning or wrong c. Define if cleaning
pretreatment cycle for cycle is appropriate or
various alloys and metals. chemically adjusted to
Possible source of metallic optimum operating
impurities. levels. May need 2%
Ammonium predip.
d. Metallic impurities – d. Plate out/dummy or
Cd,Pb,Zn or Sn. Also look dilute solution.
for cross contamination
from other processes.
e. Organic impurities. e. Dilute/discard or
carbon treat.
f. Too high stabilizer f. Dilute/discard or
concentration. dummy if possible.
g. Bath loading too low. g. Increase workload to
a minimum of
0.25ft 2/gal.
h. High orthophosphite h. Discard and replace.
(breakdown product)
content.
i. Too low a nickel i. Analyze and adjust
concentration. nickel concentration.
j. Too low hypophosphite j. Analyze and adjust
concentration. hypophosphite
concentration.
2.Skip Plating, a. Improper cleaning. a. Temperature should
poor coverage, edge be checked as well as
pullback and all other parameters
Technical Service Procedure for ChemShield Products Page 2
frosted edges. associated with
pretreatment solutions.
b. Improper Activation. b. Activators should be
2.Skip Plating, checked for proper
poor coverage, edge parameters and
pullback and potential metallic
frosted edges. contaminates.

c. Improper rinsing. c. Rinse temperature


and rinsing time should
be checked.
d. Metallic contamination. d. Bath should be
dummied, or discarded
and replaced.
e. Organic contamination. e. Bath should be
cooled, carbon treated
filtered. Rinses should
be checked for residual
drag in.
f. Too much air agitation. f. Air agitation should
be reduced.
3. Excessive plate a. High temperature. a. Adjust temperature.
out
b. High pH. b. Adjust pH with
dilute H2SO4.
c. Additive imbalance. c. Analyze and adjust.
d. Tank not stripped d. Pump solution out of
properly before new make tank and strip tank
up. with >25% nitric acid
until all nickel plate
out is removed from
tank.
4. Streaks in a. Gas streaks from a. Either solution or
Deposit position of work. work rod agitation
should be provided.
Work should be
repositioned and/or
agitation should be
increased.
b. Silicate Drag-in. b. Non-Silicated
cleaners should be
used.
c. Poor rinsing. c. Process cycle should
be checked, rinsing
improved.
d. Improper cleaning. d. Cleaning and/or
rinses should be
improved.
e. High concentration of e. Bath should be
metals. dummied to remove
metals. Bath may have
to be discarded and
replaced with new
Technical Service Procedure for ChemShield Products Page 3
solution.
f. Organic contamination. f. Bath should be
carbon treated and
filtered, or discarded
and replaced with new
solution.
g. Poor agitation. g. Air agitation should
be increased, or a
different air pattern
developed.
4. Streaks in h. Low surface area. h. Surface area should
Deposit be increased to
recommended ranges.
i. Low reducer content. i. Reducer should be
checked and adjusted.
j. Too much agitation. j. Agitation should be
reduced.
k. Too much complexor. k. Complexor should be
reduced.
5. Bath becomes a. Poor mixing of bath Make addition more
Turbid after solution additions. slowly into tank and
allow to mix.
b. High pH. b. Adjust pH with
dilute H2SO4.
c. Excessive hypophosphite c. Check ratio of
added. nickel to
hypophosphite.
d. Impurities from air. d. Use a clean air
filter and check for
area of air input.
e. Impurites from water. e. Use Deionized water.
f. Old plating bath. f. Discard.
g. Impurities from g. Improve rinsing.
pretreatment.
6. Non-uniform a. Organic contamination. a. Dilute or Carbon
deposition treat.
b. Metallic impurities (Al b. Dummy/dilute.
& Zn).
c. Poor cleaning or c. Examine pretreatment
activation. solutions and cycle.
d. Poor agitation. d. Examine movement
from air and filter.
7. Rough deposits a. Poor filtration and a. Bath should be
improper removal of filtered 10 times per
particulates. hour with a minimum of
a 5 µm filter.
b. Make-up solution added b. Make additions more
too quickly or mixed slowly/separately and
together. evenly distribute
through out the tank.
c. Residual magnetism in c. Have supplier
the work. demagnetize parts.
d. Over-active plating d. Slow plating rate
Technical Service Procedure for ChemShield Products Page 4
bath. down. i.e. low temp
and/ or pH.
e. Bath contaminated with e. Trace source and
air-borne partials. eliminate.
f. Poor pretreatment. f. Examine
pretreatment solutions
and cycle.
g. Additive imbalance. g. Analyze and adjust.
h. Plate out of plastic h. Strip with >25%
tank not stripped properly. nitric acid.
i. Plate out of stainless i. Increase passivation
steel tank not properly time with a >25% nitric
passivated or anodically acid solution or set
protected. potential to 0.8 V.
8. Poor adhesion a. Poor or incorrect a. Test and correct.
pretreatment. May need 2% Ammonium
predip.
b. Old/contaminated bath. b. Discard.
c. Metallic impurities. c. Dummy or discard.
9. High consumption a. High temperature. a. Adjust temperature.
of additives
b. High pH. b. Adjust pH.
c. High Bath loading. c. Reduce Plating Area.
d. Additive imbalance. d. Analyze and adjust.
10. Dark, dull or a. Low pH. a. Adjust pH .
streaking deposits.
b. Organic contamination. b. Dilute or Carbon
treat.
c. Metallic impurities. c. Dummy/dilute.
d. Poor cleaning or d. Examine pretreatment
activation. solutions and cycle.
e. Post treatment e. Raise the pH between
contamination. 8-9 in the rinses
following the plating
tank with Ammonium
Hydroxide.
f. Bath loading too low. f. Increase workload to
a minimum of
0.25ft 2/gal.
g. Additive imbalance. g. Analyze and adjust.
h. High or low pH H. Ph should be
adjusted with acid or
alkali.
11. Pitting a. Organic contamination. a. Dilute or Carbon
treat.
b. Metallic impurities. b. Dummy/dilute.
c. Poor cleaning or c. Examine pretreatment
activation. solutions and cycle.
d. Poor solution agitation. d. Increase solution
agitation.
e. Hard Water e. Use D.I in the
pretreatment cycle.
Technical Service Procedure for ChemShield Products Page 5
f. Excessive bath activity. f. pH should be lowered
g. Base metal pitted. g. Base metal should be
check after each step
in the plating cycle.

DEFINITIONS OF ELECTROLESS NICKEL REMEDYS

BATH LOADING

This is the ratio of work area plated verse the volume of the EN
solution. Optimum situation is 0.5ft 2 of work plated for every gallon of
EN solution.

Total Surface Area ÷ Tank Volume = Bath Loading

pH ADJUSTMENT

Typically, during normal operations, the pH is adjusted upwards with


ammonium hydroxide diluted with DI water (1:1). However, lower the pH
with a dilute sulfuric acid (1:4) and DI water mix is not common and the
source of the high pH should be investigated.

CLEANING

Examine and compare the concentrations, temperature and other parameters


stated in the technical bulletin of the pretreatment products. Also,
ensure that the substrates or base metals are used with the correct
pretreatment cycle. Most of the problems associated with an electroless
nickel solution can be located in the pretreatment cycle.

DUMMY

This term is use as reference for scrap work put into an electroless
nickel solution for the purpose of plating out the impurities and
discarding them in the deposit. Dummying will remove copper, zinc and
some organics.

CARBON TREATMENT

In a separate storage tank, add 1-4 pounds of activated carbon for every
100 gallons of room temperature electroless nickel solution. Filter back
the solution and remove any trace of carbon particles. Caution – first
carbon treat the EN solution in a beaker and test in the lab before
resuming production. Carbon treatment may remove some stablizers.

ADDITIVE ADJUSTMENTS

Do not make a single addition that requires more than a 15% add back.
Addition above this amount should be broken up and put into the bath
during a reasonable time frame. This will depend on the normal usage and
addition rate of the additives.
Technical Service Procedure for ChemShield Products Page 6

Chemtech Finishing Systems, Inc "The information presented herein is our interpretation of certain test results and field experience
23177 Commerce Drive to date. This information is not to be taken as warranty or representation for which we assume
Farmington Hills, MI 48335 legal responsibility, nor as permission or recommendation to practice any patented invention
Telephone: 248-478-5200 without a license. It is offered solely for your consideration, investigation and verification." ©
Fax: 248-478-6810 Chemtech Finishing Systems, Inc.

You might also like