Engineering Staff College of India

Autonomous Organ of The Institution of Engineers (India)


(ISO 9001: 2015 Certified, AICTE & CEA Recognized Institution)

THIRD PARTY QUALITY CONTROL REPORT

Report No.: ESCI.DIV-21.2018-19.2038.R Dt:07/01/2020

a. Inspection Report No. : 1st and part

b. Name of work : Laying of CC road in Satyanarayana enclave from


P. No 1-26/38 & P.no 1-26/9 to 1-26/34, Maktha,
Miyapur, W.No 108, Chandnagar Div-21, SLPZ,
GHMC.

c. Estimated Cost : Rs. 19.98 Lakhs

i. Administrative sanction : –––

ii. Technical sanction : –––

d. Name of the Construction Agency : Sri. Shiva Kumar

e. Work Order No. and WIN Code :

i. Agreement No. : ____

ii. Agreement Value :

iii. Tender Premium : ––––

iv. Agreement Period : ––––

v. Scheduled date of completion : ____

vi. EOT if any : ____

f. Executing Agency : Executive Engineer, Chandanagar, Circle 21, West


Zone, GHMC. Nagar Division 21 HMC.

g. Date of Inspection : 12/12/2019

h. Name(s) of Inspecting Officers : Sri. A. Muralidhar Rao (Sr. TPQC Consultant, ESCI)

i. Name(s) of Dept. Officers present : –––

j. Name(s) of Construction Agency : Sri. Shiva Mudhiraj


representatives present

k. Date of collection of sample : ––––

l. Date of Testing : ––––

m. Date of Reporting : 30/12/2019

n. Important provisions : 1) Supplying and placing ready mix concrete of M10


grade as per IS 456-2000 and standard mix design as
per IS-10262-1982 with the coarse aggregates of

Page 1 of 3
nominal size 20mm and fine aggregates of zone II.
75mm thick.

2) Supplying and placing ready mix concrete of M30


grade as per IS 456-2000 and standard mix design as
per IS-10262-1982 with the coarse aggregates of
nominal size 20mm and fine aggregates of zone II.
150mm thick.

o. Physical Progress : WMM is completed


RMC M10 is completed.

OBSERVATIONS:

The following items are verified at random and item wise remarks are tabulated
below.
WMM:

The thickness of WMM is verified and tabulated below.

Observed Avg
Width Short fall
thickness (mm) thickness Specified
S. of thickness
Location of cross thickness
No road L C R observed
section (mm)
(mts) (mm)
(mm)

@ Ch 10m 5.0 125 104 80 103 150 47


1. from
Foundation

General observations:

1. It is observed that the average thickness of WMM is 103mm against 150mm thick
specified. Necessary recovery shall be effected.

RMC M10:

The thickness of RMC M10 is verified and tabulated below.

Observed Avg
Width Short fall
thickness (mm) thickness Specified
S. of thickness
Location of cross thickness
No road L C R observed
section (mm)
(mts) (mm)
(mm)

@ Ch 10m 5.0 75 ––– 105 90.5 75 NIL


1. from

Page 2 of 3
Foundation

General observations:

1. It is observed that the average thickness of RMC M10 is 90.5mm against 75mm thick
specified.
2. The field have not informed the progress of M10 work during execution. Hence, the
ingredients of RMC M10 could not be verified by TPQC-ESCI. The field staff are
advised to certify the content of fine aggregate provided in RMC M10 before making
the payment.

Verification of depth of RMC M10 and WMM.

Overall observations:

1. It is observed that the average thickness of WMM is 103mm against 150mm thick
specified. Necessary recovery shall be effected.
2. It is observed that the average thickness of RMC M10 is 90.5mm against 75mm thick
specified.
3. The field have not informed the progress of M10 work during execution. Hence, the
ingredients of RMC M10 could not be verified by TPQC-ESCI. The field staff are
advised to certify the content of fine aggregate provided in RMC M10 before making
the payment.
4. Ensure proper curing for RMC M10 and M30 as curing plays a vital role in attaining
Compressive strength.
5. The field staff are advised to obtain design mix for RMC M30 in advance and ensure
that same shall be achieved in batch mixing plant.

Page 3 of 3
A.MURALIDHAR RAO B. JAGADISHWER
(TPQC Consultant ESCI) (Chief Projects Co-ordinator, ESCI)