Cast in place, Raft (MAT) Foundation, Including Forms & Steel, over 1000m³

Daily Output 1000 cu.m

UNIT QTY UNIT RATE AMOUNT


MATERIAL'S

Labor
1 Skilled Foreman man days 0.0005 1135.26 0.56763
8 Carpenter's & Steel Fixer's (reinf) man days 0.056 775.7 43.4392
4 Cement Finisher man days 0.001 775.7 0.7757
6 Laborers man days 0.004 518.06 2.07224
5 Equipment Operator man days 0.0005 1936.64 0.96832
47.82309
Labor cost per cu.m

Equipment
1 Gas Engine Vibrator eqp days 0.00025 904.11 0.2260275
1 Crane 35 Ton eqp days 0.00025 9296.00 2.324
1 Truck eqp days 0.00025 4016.00 1.004
1 Concrete Pump eqp days 0.000125 1143.26 0.1429075
1 Power Tool eqp days 0.002 720 1.44
5.136935
Labor cost sq.m

Cast in place, Raft (MAT) Foundation, Including Forms & Steel, over 500m³
Daily Output 500 cu.m
UNIT QTY UNIT RATE AMOUNT
MATERIAL'S

Labor
1 Skilled Foreman man days 0.001 1135.26 1.13526
8 Carpenter's & Steel Fixer's (reinf) man days 0.112 775.7 86.8784
4 Cement Finisher man days 0.002 775.7 1.5514
6 Laborers man days 0.008 518.06 4.14448
5 Equipment Operator man days 0.001 1936.64 1.93664
95.64618
Labor cost per cu.m

Equipment
1 Gas Engine Vibrator eqp days 0.0005 904.11 0.452055
1 Crane 35 Ton eqp days 0.0005 9296.00 4.648
1 Truck eqp days 0.0005 4016.00 2.008
1 Concrete Pump eqp days 0.00025 1143.26 0.285815
1 Power Tool eqp days 0.004 720 2.88

Labor cost sq.m 10.27387


Cast in place, Raft (MAT) Foundation, Including Forms & Steel, over 25m³
Daily Output 25 cu.m
MATERIAL'S UNIT QTY UNIT RATE AMOUNT

Labor
1 Skilled Foreman man days 0.02 1135.26 22.7052
8 Carpenter's & Steel Fixer's (reinf) man days 2.24 775.7 1737.568
4 Cement Finisher man days 0.04 775.7 31.028
6 Laborers man days 0.16 518.06 82.8896
5 Equipment Operator man days 0.02 1936.64 38.7328
1912.9236
Labor cost per cu.m

Equipment
1 Gas Engine Vibrator eqp days 0.01 904.11 9.0411
1 Crane 35 Ton eqp days 0.01 9296.00 92.96
1 Truck eqp days 0.01 4016.00 40.16
1 Concrete Pump eqp days 0.005 1143.26 5.7163
1 Power Tool eqp days 0.08 720 57.6

Labor cost sq.m 205.4774