Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

10/4/21, 3:51 PM Gmail - Fwd: FW: DIL_IC- Status of Mill Pre-stressing Material

DIL - IC PLANNING <planning.ayoki@gmail.com>

Fwd: FW: DIL_IC- Status of Mill Pre-stressing Material

2 messages

Dipak Patel <dipakpatel.ayoki@gmail.com> Wed, Jan 15, 2020 at 12:39 PM


To: "planning.ayoki" <planning.ayoki@gmail.com>

FYI.

---
Thanks & Warm Regards,
Dipak Patel
Project Manager - Civil
Ayoki Fabricon 
DIL
Ivory Coast
+225 7401 3588

---------- Forwarded message ---------

From: Kishor Adwani <kishor.adwani@ayokifabricon.com>

Date: Wed, Jan 15, 2020 at 7:05 AM

Subject: FW: DIL_IC- Status of Mill Pre-stressing Material

To: Dipak Patel <dipakpatel.ayoki@gmail.com>

Cc: S.Kaimal <skaimal@ayokifabricon.com>, C. Shaji <cshaji@ayokifabricon.com>, Dilip Saptarshi


<dilip.s@ayokifabricon.com>, Alok Tiwari <alokt@ayokifabricon.com>

Dear Sir,

Please check availability of local party for testing and arrange quotation , so same we can submit to TKIS for confirmation.

Regards,

Kishor Adwani

From: Jumale, Nilesh <Nilesh.Jumale@ThyssenKrupp.com>

Sent: 09 January 2020 09:11

To: Kishor Adwani <kishor.adwani@ayokifabricon.com>

Cc: S.Kaimal <skaimal@ayokifabricon.com>; C. Shaji <cshaji@ayokifabricon.com>; Laddhad, Manish


<Manish.Laddhad@ThyssenKrupp.com>; Pandit, Chinmay <chinmay.pandit@thyssenkrupp.com>; Nagpure, Pravin
<pravin.nagpure@thyssenkrupp.com>; Kangarkar, Sachin <sachin.kangarkar@thyssenkrupp.com>; Alok Tiwari
<alokt@ayokifabricon.com>; Dilip Saptarshi <dilip.s@ayokifabricon.com>

Subject: RE: DIL_IC- Status of Mill Pre-stressing Material

Dear Mr Kishor Adwani,

Further to the yellow highlighted portion of below mail, we have discussed the matter with OEM i.e. M/s USHA MARTIN for the
possible measures regarding the expiry of HT cable.

After discussion with their QC Team, we understood that if the material has got no rust / slightly rust ( that cannot be so harmful
to the strength of the material ) then the same material can be utilised. If the material has got slightly rust then the same needs
to be removed by any means & can be utilised. Also, before using the material the same needs to be checked by UTS of the
material as per standard norms of IS 14268:2017.

 
https://mail.google.com/mail/u/0?ik=19d97601d5&view=pt&search=all&permthid=thread-f%3A1655797927733932006&simpl=msg-f%3A1655797… 1/8
10/4/21, 3:51 PM Gmail - Fwd: FW: DIL_IC- Status of Mill Pre-stressing Material
Please carry out the test and shared the report with us for onward submission to OEM of HT Cable.

Best regards,

Nilesh Jumale

From: Jumale, Nilesh

Sent: Friday, December 6, 2019 11:03 AM

To: 'Kishor Adwani'

Cc: 'S.Kaimal'; 'C.Shaji'; Laddhad, Manish; Pandit, Chinmay; Nagpure, Pravin; Kangarkar, Sachin; 'Alok Tiwari'; 'Dilip Saptarshi'

Subject: RE: DIL_IC- Status of Mill Pre-stressing Material

Dear Mr Kishor,

We hereby referring  below mail for pre-stressing of mill Foundation.

As per MOM of Sept-19 for splitting of Le 1 and Line2, it is mentioned that only execution related to Line 2 to be kept on hold.
Below is the screenshot of same.

As already informed to you, all the material required for pre-stressing is already shipped and received at site. There are certain
material like HT Cable which has a self-life of 6 to 8 months. And pre-stressing work has to be completed before it gets expired.

Considering above, you are requested to proceed with the pre-stressing work of Mill 1. Please confirm the plan of action,
enable us to arrange for the deputation of expert at site.

Best regards,

Nilesh Jumale

Project Management

T: +91-20-6612 4532, M: +91 88056 38346, F: +91-20-2742 5788, nilesh.jumale@thyssenkrupp.com

thyssenkrupp Industries India Pvt. Ltd., Pimpri, Pune 411 018, India. www.thyssenkrupp-industries-india.com

From: Jumale, Nilesh

Sent: Wednesday, July 24, 2019 12:06 PM

To: 'Kishor Adwani'

https://mail.google.com/mail/u/0?ik=19d97601d5&view=pt&search=all&permthid=thread-f%3A1655797927733932006&simpl=msg-f%3A1655797… 2/8
10/4/21, 3:51 PM Gmail - Fwd: FW: DIL_IC- Status of Mill Pre-stressing Material
Cc: S.Kaimal; C.Shaji; Laddhad, Manish; Pandit, Chinmay; Nagpure, Pravin; Kangarkar, Sachin; Alok Tiwari; Dilip Saptarshi

Subject: RE: DIL_IC- Status of Mill Pre-stressing Material

Dear Kishor,

We already instructed you vide email dated 28.02.2019 to go ahead with the structural fabrication with the raw steel available at
site. You should have initiated the same earlier. Now, please take up the structural fabrication in full swing and confirm your
schedule per return.

From your below mail, we understand that pre stressing work of VRM foundation (supplied material of M/s Dynamic) will initiate
tentatively by end of Aug’19 at site. Accordingly, we keep pre-stressing supplier (M/s Dynamic) informed about deputation.
Kindly keep us informed once the pre stressing material reached ABIDJAN port.

We are sure M/s Ayoki will undertake the pre stressing work for both the Mill foundation simultaneously considering HT stands
validity as informed vide enclosed mail.

Awaiting for your swift response.

Best regards,

Nilesh Jumale

Project Management

T: +91-20-6612 4532, M: +91 88056 38346, F: +91-20-2742 5788, nilesh.jumale@thyssenkrupp.com

thyssenkrupp Industries India Pvt. Ltd., Pimpri, Pune 411 018, India. www.thyssenkrupp-industries-india.com

From: Kishor Adwani [mailto:kishor.adwani@ayokifabricon.com]

Sent: Tuesday, July 23, 2019 11:11 AM

To: Jumale, Nilesh

Cc: S.Kaimal; C.Shaji; Laddhad, Manish; Pandit, Chinmay; Nagpure, Pravin; Kangarkar, Sachin; Alok Tiwari; Dilip Saptarshi

Subject: RE: DIL_IC- Status of Mill Pre-stressing Material

Dear Mr. Nilesh,

Please refer attached mail for  schedule and duration required for pre stressing work. Transit time of shipment from Mumbai to
Abidjan is 45- 50 days and we need only 1-2 days to transport material from port to site. Custom formalities is under client scope and
duration only they can confirm.

This is for your information and planning for deputation of engineer.

Regards,

Kishor Adwani

https://mail.google.com/mail/u/0?ik=19d97601d5&view=pt&search=all&permthid=thread-f%3A1655797927733932006&simpl=msg-f%3A1655797… 3/8
10/4/21, 3:51 PM Gmail - Fwd: FW: DIL_IC- Status of Mill Pre-stressing Material
 

From: Jumale, Nilesh <Nilesh.Jumale@ThyssenKrupp.com>

Sent: 23 July 2019 10:40

To: Kishor Adwani <kishor.adwani@ayokifabricon.com>

Cc: S.Kaimal <skaimal@ayokifabricon.com>; C. Shaji <cshaji@ayokifabricon.com>; Laddhad, Manish


<Manish.Laddhad@ThyssenKrupp.com>; Pandit, Chinmay <chinmay.pandit@thyssenkrupp.com>; Nagpure, Pravin
<pravin.nagpure@thyssenkrupp.com>; Kangarkar, Sachin <sachin.kangarkar@thyssenkrupp.com>

Subject: RE: DIL_IC- Status of Mill Pre-stressing Material

Dear Kishor,

You may be aware that the pre-stressing material of VRM has been shipped from JNPT port, Mumbai on 16.06.2019. Please
find attached herewith the shipping advice and packing list of same.  

Kindly let us know the expected receipt date of cargo at site. In addition to that please inform us the schedule for taking up the
pre-stressing work for VRM foundations. Please note that M/s Dymanic  (Pre-stressing material supplier) need 4 to 5 week
advance intimation for arranging the deputation of an engineer / technicians.  

Please revert with your confirmation on above.

Best regards,

Nilesh Jumale

Project Management

T: +91-20-6612 4532, M: +91 88056 38346, F: +91-20-2742 5788, nilesh.jumale@thyssenkrupp.com

thyssenkrupp Industries India Pvt. Ltd., Pimpri, Pune 411 018, India. www.thyssenkrupp-industries-india.com

From: Jumale, Nilesh

Sent: Friday, May 17, 2019 7:27 PM

To: Kishor Adwani

Cc: S.Kaimal; Laddhad, Manish; Pandit, Chinmay; Nagpure, Pravin; Kangarkar, Sachin

Subject: DIL_IC- Status of Mill Pre-stressing Material

Dear Kishor,

As discussed in today’s meeting, please find enclosed herewith the shipment status of Mill foundation pre-stressing material.

Best regards,

Nilesh Jumale

Project Management

https://mail.google.com/mail/u/0?ik=19d97601d5&view=pt&search=all&permthid=thread-f%3A1655797927733932006&simpl=msg-f%3A1655797… 4/8
10/4/21, 3:51 PM Gmail - Fwd: FW: DIL_IC- Status of Mill Pre-stressing Material
 

T: +91-20-6612 4532, M: +91 88056 38346, F: +91-20-2742 5788, nilesh.jumale@thyssenkrupp.com

thyssenkrupp Industries India Pvt. Ltd., Pimpri, Pune 411 018, India. www.thyssenkrupp-industries-india.com

This e-mail (including any attachments) may contain confidential and/or privileged information. Any unauthorized 

use or dissemination of this message in whole or in part is strictly prohibited. If you are not the intended recipient 

(or have received this e-mail in error) please notify the sender immediately and destroy this e-mail.

DISCLAIMER:-

Please note that this e-mail including any attachment may contain confidential or privileged information for
the intended recipient only. Access to this e-mail by anyone else is unauthorized. If you have received this
message in error please notify the sender immediately and delete it without disclosing, copying, using,
distributing or storing its contents.

We do not guarantee the security of internet communications and are not liable for any errors or omissions.

DISCLAIMER:-

Please note that this e-mail including any attachment may contain confidential or privileged information for
the intended recipient only. Access to this e-mail by anyone else is unauthorized. If you have received this
message in error please notify the sender immediately and delete it without disclosing, copying, using,
distributing or storing its contents.

We do not guarantee the security of internet communications and are not liable for any errors or omissions.

-----------------------------------

Ayoki Fabricon Pvt Ltd, Pune, India

Dilip Saptarshi <dilip.s@ayokifabricon.com> Sat, Jan 9, 2021 at 4:50 AM


To: Dipak Patel <dipakpatel.ayoki@gmail.com>, DIL - IC PLANNING <planning.ayoki@gmail.com>
Cc: Kishor Adwani <kishor.adwani@ayokifabricon.com>, Swapnil Gaikwad <swapnil.gaikwad@ayokifabricon.com>

Dear Mr. Dipak,

Please refer trailing communications.

We had conducted such test on pre-stressing strands through LBTP for the strands available at premises of our client in
Abidjan. Please find enclosed test certificate as a proof. Mr. Fayaz & Mr. Anish know about this.

You may share contact details of LBTP to Mr. Dixit accordingly.

Regards,
https://mail.google.com/mail/u/0?ik=19d97601d5&view=pt&search=all&permthid=thread-f%3A1655797927733932006&simpl=msg-f%3A1655797… 5/8
10/4/21, 3:51 PM Gmail - Fwd: FW: DIL_IC- Status of Mill Pre-stressing Material

Dilip Saptarshi

From: Dixit Vidya [mailto:dixit.vs@dangoteprojects.com]

Sent: Friday, January 08, 2021 9:45 PM

To: Jumale, Nilesh

Cc: S.Kaimal; C. Shaji; Laddhad, Manish; Pandit, Chinmay; Nagpure, Pravin; Kangarkar, Sachin; Alok Tiwari; Dilip Saptarshi;
Kishor Adwani

Subject: Re: DIL_IC- Status of Mill Pre-stressing Material


 

Dear Mr. Nilesh,

Thank you for the contact details of the Agency, we shall check with them and get the test done here.

However, I did not say to send material back to India or Germany, I proposed to send samples, maybe  3 pieces of 12 " long
each) only to conduct a test.

Regards,

V.S.Dixit

Ivory Coast

On Fri, Jan 8, 2021 at 3:00 PM Jumale, Nilesh <nilesh.jumale@thyssenkrupp.com> wrote:

Dear Sir,

Sending back the material to India / Germany will be very time consuming and expensive process. Hence the better
option is to test the material in Ivory Coast only.

Below is the agency we came to know, who can perform such task. You may try to reach out them.

 
SICOMP SARL: capital 2 000 000, Abidjan-plateau Dokui, 01 BP 4677 Abidjan 01, Tel : 21 77 26 42, Cel: 75 13 95 76, RCCM :
CIABJ-

2019-B-17100, C.C : 1946898U, Régime Imp : Réel Simplifié, Centre Imp : Abobo 3, Compte bancaire : GTBank

CI16301204000000187815-79

sicompcommercial@gmail.com www.sicomp-ci.com

Regards,

Nilesh Jumale

https://mail.google.com/mail/u/0?ik=19d97601d5&view=pt&search=all&permthid=thread-f%3A1655797927733932006&simpl=msg-f%3A1655797… 6/8
10/4/21, 3:51 PM Gmail - Fwd: FW: DIL_IC- Status of Mill Pre-stressing Material

From: Dixit Vidya [mailto:dixit.vs@dangoteprojects.com]

Sent: 08 January 2021 18:20

To: Jumale, Nilesh <nilesh.jumale@thyssenkrupp.com>

Cc: S.Kaimal <skaimal@ayokifabricon.com>; C. Shaji <cshaji@ayokifabricon.com>; Laddhad, Manish


<manish.laddhad@thyssenkrupp.com>; Pandit, Chinmay <chinmay.pandit@thyssenkrupp.com>; Nagpure, Pravin
<pravin.nagpure@thyssenkrupp.com>; Kangarkar, Sachin <sachin.kangarkar@thyssenkrupp.com>; Alok Tiwari
<alokt@ayokifabricon.com>; Dilip Saptarshi <dilip.s@ayokifabricon.com>; Kishor Adwani
<kishor.adwani@ayokifabricon.com>

Subject: Re: DIL_IC- Status of Mill Pre-stressing Material


 

Dear Mr. Nilesh,

You are well aware that in this place getting a reliable agency for UTS testing of 15MM diameter cable having a tensile
strength of 190Kg/Sq MM is very difficult.

I am trying but I don't think we shall get it here.

I propose to work on alternatives:

1) Please send the test certificate of the Prestressing cable manufacturer (usually Manufacturer is responsible to provide a
Test certificate from a reputed third party lab approved by the customer) to the OEM and ask them for a waiver of testing
at site as facility is not available

2) Find out a Testing Lab in India or Germany in consultation with OEM and we shall advise Ayoki to send the sample from
site for the test.

Regards,

V.S.Dixit

Ivory Coast

On Fri, Jan 8, 2021 at 8:10 AM Jumale, Nilesh <nilesh.jumale@thyssenkrupp.com> wrote:

Dear Sir,

We understand from M/s Ayoki that the pre-stressing activities of Mill foundations are being initiated at site. However
before doing so, as informed in trailing mail, it is mandatory to check the UTS of HT Cables before using the same.

You are requested to support the Ayoki for the test of HT Cable. After testing the reports to be shared with us for getting
consent from OEM.

Regards,

Nilesh Jumale

From: Jumale, Nilesh

Sent: 10 August 2020 07:42

To: Kishor Adwani <kishor.adwani@ayokifabricon.com>

Cc: 'S.Kaimal' <skaimal@ayokifabricon.com>; 'C. Shaji' <cshaji@ayokifabricon.com>; 'Laddhad, Manish'


https://mail.google.com/mail/u/0?ik=19d97601d5&view=pt&search=all&permthid=thread-f%3A1655797927733932006&simpl=msg-f%3A1655797… 7/8
10/4/21, 3:51 PM Gmail - Fwd: FW: DIL_IC- Status of Mill Pre-stressing Material
<Manish.Laddhad@ThyssenKrupp.com>; 'Pandit, Chinmay' <chinmay.pandit@thyssenkrupp.com>; 'Nagpure, Pravin'
<pravin.nagpure@thyssenkrupp.com>; 'Kangarkar, Sachin' <sachin.kangarkar@thyssenkrupp.com>; 'Alok Tiwari'
<alokt@ayokifabricon.com>; 'Dilip Saptarshi' <dilip.s@ayokifabricon.com>; 'V. S. Dixit' <dixit.vs@dangoteprojects.com>

Subject: RE: DIL_IC- Status of Mill Pre-stressing Material

Dear Mr Kishor,

Please update the status of UTS testing of HT Cables required for the pre-stressing of Mill Foundation

As informed earlier, it is mandatory to check the UTS of material before using the same, hence please carry out the test
of HT Cable and shared the report with us for consent from OEM.

We are hereby taking Mr Dixit in the loop for his advice and guidance.

Regards,

Nilesh Jumale

[Quoted text hidden]

[Quoted text hidden]

PV_CABLE DE PRECONTRAINTE_AYOKI FABRICON_2020-DRF-RA-0184.pdf

360K

https://mail.google.com/mail/u/0?ik=19d97601d5&view=pt&search=all&permthid=thread-f%3A1655797927733932006&simpl=msg-f%3A1655797… 8/8

You might also like