Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

EXPERT OPINION Global Business Reports Industry Explorations EXPERT OPINION

Modifying Factors and


Optimized Cut-Off FIGURE 1
NPV FOR VARIOUS COG

Grade Determination NPV ($ million)


Source: SRK, 2020

80

70

60

50

Gary M Poxleitner, PEng, PMP


Practice Leader/Principal Consultant 40

SRK CONSULTING (CANADA) INC.


gpoxleitner@srk.com 30

gmpoxleitner@gmail.com
20

10

0
3.00 3.50 4.00 4.50 5.00 5.50
COG

TABLE 1 BIO
Cut-off grade (COG) is a standard, cally, it is value in the form of NPV and ing factors are used in the industry, a This resulted in the material not being
REVENUE
industry-accepted method used to de- internal rate of return (IRR) but may 2019 survey of approximately 100 glob- able to cover all costs and therefore Gary M Poxleitner is involved in leader-
termine which part of a mineral deposit also include a COG that produces high al mines and projects were accessed. lower NPVs. Inversely higher COG sce- ship within the mining consulting indus-
Metal Price ($) 100%
to include in a Mineral Resource or a metal content or ounces at the risk of Table 1 summarizes our findings as to narios of 5.0 and 5.5 g/mt generated try and provides technical advice, mine
Mineral Reserve estimate, or poten- resulting in lower net present value Mill Recovery (%) (Fixed) 100% the modifying factors used along with high feed grade but the tonnes were and project reviews, due diligence and
tially in an operation’s Life of Mine Plan (NPV). the percent of those surveyed that ap- too low to cover all the fixed operating audits, cut-off grade analysis, operating
(LOM). It is the minimum grade (or val- The widely-adopted method to calcu- Payable Metal (%) 85% plied them. costs and capital costs. This is summa- cost estimation, mine design and econo-
ue) at which mineralized material can be late the COG is a break-even method- A strategic optimization methodology rized in Figure 1. mic and productivity improvement stud-
Treatment and Refinery ($) 80%
economically mined or processed. The ology. This approach accepts mining can be used to select the preferred Aside from NPV, other corporate ob- ies, as well as training and mentoring in
selected COG is essentially a trade-off material which will generate revenue Transportation ($) 75% COG. It involves first running multiple jective criteria are also accessed, such all aspects of mine orebody extraction in
between the revenue (inclusive of loss- from the sale of the finished product scenarios at a range of different COGs as long life mine life, scenario with low the underground environment. This in-
es) that the potentially-economic mate- that is equal to the cost of certain modi- Royalties (%) 75% inside a flexible evaluation model. A upfront capital, or high ounces. These volves high level concept projects, PEA,
rial contributes to the mine’s cash flow fying factors, such as mining, process- Mill Recovery (Variable) 20% mine plan is first performed for each criteria are compiled and summarized in PFS, Feasibility, project execution and
vs. the cost to extract that same mate- ing, general administrative expenses COG (balancing effort with value), thus the form of a decision matrix tool. This operational assistance. He assists clients
rial. COG is an essential parameter for (G&A), sustaining capital costs, treat- producing a mine schedule. Costs are approach is developed collaboratively in providing innovative albeit practical
determining reserves, for generating ment and refining of contained metal(s) UPSTREAM (OPERATING) COSTS then included for each scenario and with mine planners and stakeholders, solutions to complex problems.
production and business plans, and as- and is often inclusive of applicable roy- then fed into the economical model. where each objective is ranked for each Gary's technical experience covers a
certaining the potential profitability of alties. The pitfall here is that it does not Mining Cost 100% This then produces an individual NPV COG scenario against the weighted wide range of commodities, geographic
a stope or open-pit bench. guarantee that the orebody will cover and IRR for each COG scenario. The objectives. Depending on the selected and mining settings.
Selecting the correct COG is essential. those costs that are excluded from the Milling Cost 100% highest value scenario for the related company criteria, mine site preferences Gary a professional engineer registered
It affects the mine plan, cash flow, mine calculation (such as initial capital cost). COG may then be agreed as the pre- and the ranking, the results will be a in Ontario and a professional project
G&A 90%
cost, sustainability and profitability of It also does not clarify what technical ferred option. COG which combines all these criteria. manager, he has previously held positions
the operation. However, the work re- and economic modifying factors to Dilution 70% Figure 1 demonstrates an example of Selecting a COG with prudence will as Vice Chairman of Camiro, Membership
quired to generate the optimum COG include, which can have wide implica- an underground gold mine that we ac- set the course for your entire opera- Chair of the CIM Sudbury Branch, and is
Sustaining Capital 55%
is often not given the requisite atten- tions on the future and profitability of cessed with this approach. In this exam- tion and environment. Determining the currently on the Canadian CIM Council
tion and diligence. the mine Corporate G&A 25% ple, a COG of 4.5 g/mt produced the correct modifying factors will assist in and Chair of the CIM Underground Mi-
The process of selecting a COG should The decision of which modifying fac- greatest value overall. Additional sce- getting the right answer and taking a ning Society. Gary has a P.Eng in Mining
begin with an understanding of what tors to include is often left to the per- Profit Margin 10% narios, using lower COGs of 3.0 g/mt strategic optimization approach will Engineering and a graduate from Lauren-
the over-arching corporate and mine sonal judgement of mine professionals. and 3.5 g/mt, led to higher production ensure that all objectives are reviewed, tian University, Canada (1991).
Project Capital 10%
objectives are for the deposit. Typi- In determining which common modify- tonnages with low plant feed grades. validated and considered. ■

MINING IN ONTARIO AND TORONTO’S GLOBAL REACH 2020 46 Industry Explorations Global Business Reports 47 MINING IN ONTARIO AND TORONTO’S GLOBAL REACH 2020

You might also like