Professional Documents
Culture Documents
Land Grading Design
Land Grading Design
Structure
11.1 Introduction
Objectives
11.1 INTRODUCTION
Natural landscape is rarely plane enough for undertaking efficient cultivation. Land
developinent for agriculture requires levelling the land flat or preparing it to suitable
slopes, that is, grading.This is often a strenuous and expensive operation. It requires
surveying to be carried out first to get data on the natural profile of the terrain.
Decisions are to be made about suitable layout of field plots, roads, irrigation supply
channel system as well as the drainage system. Once an acceptable layout is arrived at,
the optimum grades are designed. Lastly, earth moving operations are to be undertaken
-- - -
I
Land LevdUng and Gnding to construct irrigation supply channels, drainage ditches, and proceed for leveling or
grading the field plots.
Objectives
After studying this unit, you should be able to:
appreciate the need for land levelling,
decide on a suitable range of slopes to be provided,
determine the best slopes for land g a , based on earth movement
consideration, that is, balancing the cut and fill,
estimate v:$-fill volumes for contractual purpose,
-1"
- -
Lana ~ e v a ~gl s ~d r a d i i l
11.3.4 Irrigation Methods
The field slope and crosswise slope, to which a field is trimmed, have to be within
specific limits. These limits depend on the method of surface irrigation proposed to be
adopted. Otherwise, uniformity and application efficiency would be adversely affected
for the border strip and the check basin irrigation methods. It is ideal to grade land to a
uniform slope in the flow direction with no slope in the direction normal to it, such that
the irrigation water may propagate with a straight front. Furrow irrigation method can
accommodate a certain degree of cross slope within the field boundaries.
Where the cross slope could be removed only through excessive cutting, the field may
be divided into strips widthwise, so that the individual strips can be prepared with zero
cross slope, but set at different levels with respect to the adjacent strips. This type is
referred to as bench levelling.
L L E
oL" 2-
Land Levelling and Grading
The method of least squares has been applied to derive expressions for the optimum
values of slopes in both Ule advance direction and cross-direction. The resulting plane
leads to minimum for the sum of the squares of its deviations from the existing ground
surface, while ensuring that the cut-volume will be equal to fill-volume. This method
can be classified as analytical. The rlumerical computations to evaluate the slopes are
most direct when the stake-grid forms a rectangle (n stakes per row and m stakes per
-
column) all cells enclose an area of (A x.A y). When the grid layout is not rectangular,
but encoinpases a polygon, the nuinber of stakes in a row may vary from row to row. In
addition, the area represented by a border cell nlay be only a fraction of (A x.A y). The
weighted least square procedure that takes into account the variation in the area
represented by the different cells can be used to derive the expressions for the optimum
slopes under such conditions.
This amount would be a cut fit is positive, and it would be a fill if it is negative.
The values of Sx and Sy and h (0,O) can be obtained based on the least squares error
criterion. The following four-step procedure can be followed for this purpose:
i) Determine the average elevation of each series of stakes in both the
directions;
ii) Locate the centroid, in plan, of the field plot.
iii) Compute the best-fit slopes Sx and Syusing the equations pertinent to the leasr
square method; and
iv) Compute the parameter h (0,0), which is the formation elevation at the origin,
on the condition that the average field elevation should be the elevation of the
formation surface at the centriod, for the cut volume to balance the fill
volume.
Let us use the subscript i to identify the series of stakes aligned in y-direction or S-N
direction (it" column of stakes) andj for the series of stakes aligned in x-direction or
W- E direction bdhrow of stakes). Then, any grid point can be specified by 0)). Let the
maximum number of columns of stakes be M and the maximuin number of rows of
stakes be N. Then the average elevation of the ith column, Zi is given by:
N
Let the origin be located at one half the grid spacing in each direction from the first
stake position. Then the distances of the centroid from the origin, such as Xc and Yc,
can be determined through the following equations:
Herein Xc is the x-distance from the origin to the ith stake-column and Y, is the
y-distance from the origin to the.jfhstake-row.
Land Levelling nnd Grading Next the optimum slopes are computed using the following equations.
Finally, to obtain the parameter h (0,O) we need the average elevation of the field plot
Zc. This can be computed using any one of the following equations :
Defining, Wi = C w,.,
j= 1
M Land Grading Design
and, Wj=Cwii
l=l
We can write:
I I 1
2 -
A
'
l
0
A
I
l
i I i ' ;
,----I-- -1 - - J - - A - - -I
1 - ' I
I
' I . I ' I ,Sta
A , *# I A
I b
It may be pointed out that the equation defining Sx, S' and h (0,O) remain unchanged.
The weighting factor concept is useful when one wants to adopt different values of
A x and A y for different blocks; especially the boundary blocks may sometimes have to
be fixed with smaller or larger widths than the standard block dimensions (A x and A y).
When A x and A y values for a boundary block are greater than the standard values used
for most of the blocks, the weightage factor wg can be greater than 1.00 such a case -
is shown in Figure 11.4(b).
In the equations for the slopes Sx, Sy one can avoid dealing with large values if the
distances x and y are scaled in terms of the standard block sizes A x and A y.
i.', : ts the 1 aluc efrllc we~ghtagefactor M), fc?rblock P # n Fiyur(: 11 :(a) '
Land Levelling end Grading
1 2 3 4 \Sl.kD
Figure ll.d(b): A Plot wit11 Cells with D i t Y c ~ l gWeiglrtages Strkcv with Lincqunl Cells
Example 11.1
A rectangular field 180 m x 150 m is to be levelled to make it suitable for irrigation.
Figure 1 1.1 shows the locations of stakes and the existing field elevations at the
stake-locations. For convenience, values with reference to a datum level of +35.00 are
given. To help in visualisi~lgthe nature of the field surface as it exits, contours at
0.25 m i~ltenlalsare also shown plotted. The recorded minimum elevation happens to
be 1.20m and the maximum to be 2.37 m.
To facilitate the application of least square equations, the origin and the Cartesian
co-ordinate axes are to be specified suitably. In this example, the bottom left hand
comer of the field is chosen as the origin and the axes are ~narkedas shown in the
figure. Then in the x-direction, there are six stakes in all the rows: thus along the x-axis.
i.e. i = 1 to 6. The number of stakes in the columns along y-axis is 5, such that j =1 to 5.
The si7s of the standard rectangle (in the present case it is a square) is 30 m x 30 m,
with an area of 900 m2. The stake (1,l) is at a half distance along both the axes, that is,
at the point (15 In: 15 m).
Solution
Row-wise Average Elevations
n the values of Zi, for i = 1 to 6, work out as: 1.61,l SO, 1SO,
Based on ~ ~ u s t i o11.3,
1.60,1.89 and 2.00 m.
Like-wise, based on Equation 11.4, the average elevations along the x-direction, Zj, for
the 5 rows at different y-coordinates are obtained as: 1.77, 1.70, 1.66, 1.62. and
1.67 m.
The average elevation of the entire field, as per Equation 11.9 as well as by Equation
11.10works out as 1.682 m.
Co-ordinates of the Centroid
Using Equation 1 1.5 and Equation 11.6, the co-ordinates of the centroid are obtained as
Xc= 90 ~nand Yc = 75 m.
Optimum Slopes Land Grading Design
Let us compute the best slope along the x-direction using Equation 1 1.7. Let us first
evaluate the individual terms of this equation.
The frrst term in the numerator
M
Zx,Zi=(15 X 1.61)+(45 X 1.50)+(75 X 1.50)+(105 x 1.60)
i= 1
+ (135 x 1.89) + (165 x 2.00) = 957.3 (The ~111itof this quantity being m2)
The f ~ sterm
t in t l ~ edenominator
J = 1
N / M 7
I
Therefore, Sy = 0.095%
Elnploying a computer program suitable for use on a personal computer (James, 1988),
this example problem has bekn solved. The resulting values of optimum slopes are
obtained as Sx = 0.306% and Sy = 0.095%. (The small differences from the manually
computed values are due to the rounding off to two decimal places the values of Zi and
Zj). Let us adopt tl~ecomputer-based results in further calculations given below.
Using the optimum values of slopes, the third parameter h (0,O) in Equation 1 1 . 1 1 can
now be computed, (writing Zc = h ( Xc , Yc )) as follows:
Land Levelling and Grading
h(O,O)=h(Xc,Yc)-Sx.Xc-Sy.Yc
We can now calculate the formation level as per these slopes for any location within
the field, in particular at any of the stakes. For instance, at the location of the stake
(1,1),x= 15 m andy= 15 m.Then,wecanwritewithreferencetoEquation 11.1:
Since this formation level is higher than the natural ground level of 1.05 m at this stake,
the standard square area represented by this stake needs to be filled up through a height
of 1.453 - 1.050 = 0.403 m.
Likewise, for the stake (6,2), X = 15 + 5 x 30 = 165 m, and Y =15 + 30 = 45 m.;and
the formation level works out as
Since the natural ground level here is higher at 2.04 m, the levelling operation involves
a cut of 2.04 - 1.883 = 0.1 57 m. The volume of cut over this square is 0.157 x 900 =
141.3 m3.
The increments in the formation-levels at the various X-distances of 15,45,75, 105,
135, and 165 m are 0.0459,O. 1377,0.2295,0.3213,0.4131 and 0.5049 m respectively
for SX= 0.306%. Likewise for Y=15,45,75, 105, and 135 m ywith Sv= 0.095%, the
increments in the Ydirection work out as 0.01425,0.04275,0.07125,0.09975 and
0.12825 m, respectively (refer Figure 113). Tile formation level at any of the stakes
can be calculated based on its X and Y distances from the origin. The results, rounded
off to three decimal places are shown in Table 11.1. For clarity, values are entered in
the cells at each stake with the following notation: contents of the fmt quadrant is the
formation level, the second quadrant contains the existing ground level, the height of
cut is entered in the third quadrant and the height of fill is shown in the fourth quadrant.
At any of the stakes, either the third quadrant or the fourth one would carry a value. as
both cut and fill would not be necessary at the same location. It is noted that a
maximum cut of 0.515 nl is required and a maxi~numfill of 0.345 m is needed. The
total volumes of cut and fill both equal to 2599 m3.
Tilhle 11.2 : Stake-wise Cut/Fill Requirements
Lnnd Gnding Design
Notation: All values in metres
-
y dl rectional
average elevation S + * Sd
4 4 # S x = 0.3%
0
e 1.25
-
x directional
1 an elevation higher than the average field elevation, the cut-volume for a given slope
decreases and the fill-volume increases -and, the cutlfdl ratio decreases below unity.
This feature is effectively brought out in Figure 11.6.
In this figure, the volumes of cut and of fill and also the cutlfill ratio for different
centroidal elevations of the formation surface varying from 1.62 m to 1.74 m are shown
plotted, for specific values of slopes arbitrarily chosen as S ~ 0 . 3 % and Sy= 0.1%. Over
this range of centroidal elevation, cut-volume is largest at 3740 m3 and the fill-volume
least at 2066 m3 for h (Xc. Ye) = 1.62 m.The cut-volume is smallest at 2079m3 and the
fill-volume largest at 3645 1113 when the centroid elevation is 1.74 m. The cutlfill ratio
has its largest value of 1.81 for 1.62 m and least value of 0.57 for 1.74 m. As expected,
when the centroidal elevation equals the average terrain elevation, namely, 1.682 m, the
L,;mcl L,evelliig ancl Grading cut is equal in volume to the fill at 2599 m3. with a cutlfill ratio of 1. A plot as shown in
Figure 11.6 would be useful when a cutlfill ratio is larger than 1 is to be adopted, may
be, due to practical considerations.
r
E
-
Y
-
U
e2 3000
--
.-
--
r
0
0
I-
average elevati
Slope ( 1 in-)
ii) The quantum of haulage of earth from cut areas to fill areas should be
minimised. Also after accomplishing the initial land grading as per design
there is need to maintain the design grades in the long run, since the land
levels tend to get altered sightly due to various reasons over the seasons.
These aspects are discussed, herein, with reference to their significance.
CutIFill Ratio
The need to genetate a larger cut-volume than the fill-volume arises due to following
reasons:
i) There would be a gradual co~npactionof the soil in the fill areas during and
after the colnpletio~lof the levelling operations. Usually, in this co~mection,a
shrinkage factor of 20%)to 40% is assumed.
ii) Earth may be required for ~niscellaneouspurposes, such as raising the
elevations of nearby farm roads or forming supply channel portions in filling.
L d Lcvdlhg md Gmding iii) Certsun amount of soil may be lost in the transit during the haul-fill
operations.
iv) There is the problem of optical illusion faced by earth moving machinery
operators that results in addit~onalfilling between the stakes called crowning.
While the usual range of cuthill ratio adopted is 1 2 to 1 6, extremes like 1.1 and 2.0
are also necessitated under certain conditions. In case of heavy soils and deep cuts, I . 1
may be a reasonable value, but when llght textured soils especially with high organic
content coupled with small cut depths, are to be levelled, a cut/fill ratio as high as 2.0
may have to be adopted.
We have already seen that the lower the elevat~oilof the fonnation plane at the
centroid, the higher is the cutlfill ratio. A decrease in the formation plane by 10 mm
would increase the difference between the cut-volume and the fill-volume by about 100
m3 per hectare. Once an appropriate cutlfill ratio value 1s decided by judgement, the
height of the formation plane, which is at the optimum slope, can be worked out.
Minimum Haulage
Tlle nlagnitude of haulage of the excavated earth (expresed, say, in tonne-metres)
depends on the location of the cut-area from which the earth is moved, and the
fill-area; and the route that is followed for this operation. The assignment of the cut-
and fill-area and the routing to connect tl~einshould be optimised. Additional aspects to
be considered include empty rehli-n trips, and restrictions on machinery movement.
Computer programs have been developed based on techniques like transportation
method of linear programming to work out the minimal equipment movement; these
are particularly useful where the earth work volumes are really large.
Periodic Maintenance
The made-up levels of surface-irrigated fields undergo gradual changes due to
agricultural operations and the action of irrigation water. So as a sequel to large scale
land levelling operations. periodical maintenance levelling should be undertaken to
sustain high irrigation efficiency. Cut areas need additional care, such as: i) in case of
insufficient top soil, fertility management should be undertaken through addihon of
chemical fertilisers. and ii) when cut areas face soil salinit?/. leaching provision must be
made.
;.I =Dr (
API+&z
1 , .. (11.111)
/
where, VFll= Volume of fill reqmred between row-1 and row-2 of stakes in the
X-direcbon; AF1,AFZ= Cross-sectional area of fill along row-1 and row-2,
I respectively; and Dy = the depth of fill.
56
I A similar formula call bc \witten for evaluating tlic cut volu~iiebctwee~irow-1 and
row-2. With suitable ~iiodificatioiisof the nuinbcrs of the pair of rows, we can compute
Land Grading Design
I the cut-fill volulnes for other segments contained by rows (2 aid 3), (3 and 4) and (4
and 5) . Of course, we should compute A F I ,~ 4 , ~. 4 ~2 3,A F and
~ .4,:5 as a pre-requisite; as
also ACI to Acj. The profile for row-1 is shown in Figure 1 1.#(a). and that for row-2 in
Figure 11.8(b).
CUT
C bm. 30m -0.2 Cut 8
I Fill depths
0.0 (m)
0.0
#a t* 4 \ 19 12 t l (5.1) (6*1) (7.1)
0.4
(b) Stake lables and end points
Flgurc 11.8: Cut u11l Pill ProNes alorlg Selected Rows for the Ernn~ple11.1 (a) Along Row-1. (b) Along Row-2.
As regards the boundary portions, the end-state value is assumed to hold good. Thus
between (0,l) and (1,l) the cut is constant at 0.345 ni. Likewise between (6.1) and
(7,1), the cut is assumed to be constant at 0.5 15 ni . In the reach between (4,l) and (5,l)
the forniation requirement is partly fill and partly cut. But the fill varies linearly from
0.11 1 m to zero over a length of 5.56 m, and the cut varies linearly from zero to 0.487
m over the rest of the 30 m spacing which works out to be 24.44 m. Based on the
eeometn, of the ~rofilethe fill and cut areas are summed UD as follows:
In a similar manner: areas for otlier sectiolis are worked out, sutd presented in the
~ - I I - - :-A
-. *-LI-.
Land Levding ant1 Grading Description Row Numbers
1 2 3 4 5
Area of 20.603 17.108 13.297 19.178 12.095
Fill-section
(m2)
Area of 28.706 10.179 8.437 17.288 17.679
Cut-section
(m2)
Using the Equation 11.18. the fill values seuarated by 30 m are worked out for sections 1
1 and 2 shown below: .
After calculating such values for the other sections, the total volume of fill is obtained
as:
Note that the values are same for both cut and fill and is less by about 131 m3
compared to the estimated value of 2599.3 m' as obtained, based on the assumption
that fill or cut over the area of the surrounding cell for a given stake is a constant.
Herein,
1/CI2 = volunie of cut between section 1 and 2,
In this notation, F and C as prefix indicate fill and cut, respectively. Note that at the
point (4, 1.5) which is midway between the two points, one point carries a fill and the
other a cut. The larger of the two values decides whether it would be a fill or a cut at
the mid section and half difference between these two values is the magnitude at the
mid section. (Similar consistent results would be obtained if fills are treated as positive
quantities and cuts are treated as negative quantities.) A similar procedure is then
applied to other adjacent pairs of sections too. The resulting areas required for the
computation of the volumes of cut and fill by the prismoidal procedure are obtained as
follows:
RowlCross-section Label
%scrip tion
1 1.5 2 2.5 3 3.5 4 4.5 5
Fill-section 20.603 18.712 17.108 13.274 13.297 15.010 13.297 15.467 12.095
area (12)
Cut-section 28.706 19.396 10.179 7.378 8.437 11.651 19.178 17.270 17.679
area (m2)
From the three profiles, we l':t the following values, for earth work in cutting:
Then as per Equation 11.19, 11,,, =30 (28.706 + 4 x 19.396 + 10.179) = 582.34 m3
6
Similarly, the fill volume between section 1 and 2 works out as:
= 2399 m3
Herein, also the total cut volume is equal to the total fill volume. It is less than 2599 m3
by 200 m3.
Land Levdling rad Gnding
11.6.3 Four-Corners Method
clr
In this-method, the basic grid area that is considered is formed out ol'four adjacent
stakes, as a square or a rectangle. Note that this grid is different from the basic cell
surrounding a stake. The equations for computing the volumes of cut and fill within a
given grid area can be expressed as:
and
where,
k = the index for the grid centre in Xdirection
Nc = number of stakes out of the four that require cut, which can differ
with k, I
AM= area of the grid formed around the centre point pertaining to k, I
Let us carry out sample calculatiens for two grids, identified by (k = 1,1= 1) and
(k= 4,1= 2). These are shown in Figure 11.')(a) and 11.9(b).
m = {1,2,3,4)
n = {nil) i.e., none of the stakes requires cutting
900
Then, 1/cll = -
4
4 10 =I;$+
NC= 0; so, here, 4-NC = 4
02
o
900 x (0'812)2 -
Then, Vpll = - -- x 0.812 = 182.7 m3
4 0 + (0.812)
For the grid (4,2), the four comers are (4,2), (5,2), (5,3) and (4,3). The respective
levelling requirements are C 0.041, C 0.159, F'0.02 and F 0.168, all in metric units.
Accordingly,
The volumes of cut and fill required for all the grids as per the four-corner method, are
worked out by the procedure as shown above, and are given in Table 11.2.
P P P W W W W W
h)-OW w 4 m u
P P P P
Vlcnu,cn
P P P P
Vl Ul u, Vl
w\C\C\C\C w\CwU)w
C C O C C O C C O O
c o c c 0 0 0 0 O O C C C c c c o c
coo-
b 'c.:& i, PPPPP--
O C C C P - V l
gg28888 PPPPP
c o c - w
C 4 U P OOC'4JwRh) O\040000 WOOWW
C m C P C C C P W O P O P P C O O O W O O 4 P
C C C O
La'w .o .c
WBPOC
occz
P . C P P
C C W
C, g .g: . g g g
W\CCWCCC
C O C C O C -
c c k L, Ll ;c w
0 C W C V l O\ a?
W C C O O = W w m w P C C C C C C W C W P O
Table 11.3: CutIFill Volumes from the Four Methods L a d Grading Design
I 2 I ~ n urea
d 1 2470 1 95
I
3 P~ismoidal 2400 92
4 Four poii~t 23 90 92
[Note :All the values are rounded off to the nearest 10 m?]
The results from the more detailed methods based on prismoids and four-points can be
taken as accurate. It is noted that in Example 11.1, the level grid method overestimates
by about 8%. The prisiiioidal method is considered a good compromise between
accuracy and manual effort involved. Recently developed coqputei packages for
terrain modeling use higher accuracy procedures.
By way of applying a manual method or cut-fill zonation' Figme 11.10 shows a
subjective delineation for this example, based on the contour-inspection method.
C 0 .2.00
2.00- Formation -Surface -1 .so
1.so- A/
Prof il - 1 .OO
1-00,
-*
0
-
8. ?
- Z
- -
? -
o
=!
8
N
uf Cut and F
Figure 11.10 : DeL~c?rtio~~ il
l Zolles by Cu~~tuur-l~~speetiut~
hlctllud
A general agreement with the results of the least square method ma?. be observed.
Certain degree of experience with a few cases is desirable for adopting this approach
for serious esti~nationof earthwork volumes.
The four-conier mcthod_is to be applied tbr calculating cut aid fill volurnc f o r a
grid cvith all area 400 mL. In one case the grid (3.2) (with the four comers are
(3.2). (4,2j, (4.3) and (3.3)) has the folla\\~iagrespective levelling requireinents in
lueters: C 0.073, F 0.032, F 0.145 aid C 0.083
a) Write down the m-set and n-set and indicate the value of Nc.
b) Work out tlie volume of the cut and fill in this grid and the ratio of-cut and fill.
Drain
Ditch
brnatraam
shauw C h8nnrl
Ommrtraam
... (1 1.23)
IdandLwdling and Grading
F]
Then, Tw - Tlrr - = Bw + tlv + 2 8 x -
s Id
Tw = PI!? fW + 2dh x
1 Sd
(=)
Note that the height of the terrace does not appear explicitly in this equation.
Origin01 Ground
Slopr
There are certain guidelines regarding the various dimensions from practical point of
view, such as, width of the cultivable bench BW should preferably be an
integer-multiple of the maximum width of the machinery to be employed, in case of
mechanized agriculture. The convenient range of width is 5 to 15 m. Of course, the
correspondiilg vertical difference BW should be in the range of 0.3 to 0.G m. The
longitudinal slope of the terrace should be sufficient to lead the excess water so as to
safely pass down drop-structures connecting adjacent terraces. while at the same time
limiting the water velocity to avoid erosion -of soil. Further the bund I dike should be
high enough to contail1 the higher of the expected maximum depth of design runoff and
the irrigation supply depth in any one session. There should also be a free board of
about 100 to 150 mm for purposes of safety, etc. The top width of the bund may be set
equal to the height of the bund. The side slope may be chosen from within the range
1V: W (that is 0.5V : 1H) and 2V : lH, depending on the type of soil used for bund
formation, because the bund would usually be in filling.
Example 11.2
Design a contour bench cross-section for the following mildition :
The average cross slope of the natural ground at the terrace is 5%. The width of the
cultivable part should be a multiple of 2.5 m. The bund side slope may be 1V: W
and its top width, 0.5 m. The maximum depth of any single irrigation episode is 140
mm ;and the design storm runoff depth may be taken as 180 nun.
Solution
The bench width B m a be either 2.5,5 or 7.5 or 10 m ( a multiple of 2.5 m). We do
not choose to consider widths above 10 m because the elevation-difference between the
adjacent benches may exceed 0.G m, since the cross slope is 5%.
We may note that tw = 0.5 IT/. Sd= 0.5; and we can choose d as (0.18 + 0.15) = 0.33
m. Herein, 0.18 m is the runoff depth which is &her than the maximum irrigation
depth. Also, 0.15 m is the free board assumed. The slopes are specified as, Sb = 5% =
0.05 (or 1 in 20) and Sd = 0.5 ( since the bund side slope is 0.5 vertical to 1 horizontal).
Then, using Equation 11.24, the total terrace width is given by:
i
Tw = Bw + 0.5 +
= 1.111 (1.82+Bw)
Let us now. with the help of this relationship. get TI,, for different BW values . We can
also calculate the elevation-difference between adjacent benches, that is, Bh as the
product of TWand Sb. Th
We may recommend a bench width of 7.5 nl leading to a total terrace width of 10.4 m,
and terrace height of 0.5 m
.,
. .r';::.- !; :;i;i!C>!~:<
.. "
is i~ be cgrried out for 2: tcrra~n\vith a land slope oE4?4 Tile
,. !i * .: ,- .: , .%r7 .la,
;,. ,j
.;.. ..%,.
. i:i.t14 bc: in rnu!aiyles of 2 nl. Tile buud would !lave a top width
.. "
of i .iH: 1 k' 'The ~ n ; ! s i l ~ l l ~depth
1
.: i i t :;i?i; srGi: )-ii\i>cs rn of irrig;-ltlon water to
,.; .,...
,:: ,...,- :>,.;
.,; ,>,.,I :c i I?:.' ~:::u.;:id a.hc ii~!ensityof sionn nm off may be laicen as 230 m m .
-. ." :!......' &.--
:':..< ...,%..
>$;; ."
.$\?didli:: ific bund may be taker? its 0.21n. Estililate a suitable step height
f. - j , - ,...
I I I ..;:.. ,rccr?and st~liable lxidtir.
<
As a typical instance of calculations, considering the key area 11, and the random line
4, we find that the 2.00 m-contour is located at 19.75 m from the base line. Likewise,
the distances of the intersections of 1.75 m and 1.50 m contours on the random line 4
are obtained as 23.25 m and 27.75 m. Based on the first moment, we obtain the
distance of the average contour as 23.58 m from the baseline. Table 11.4 (a) gives the
set of values of all the random lines for key-area I covering the contours 2.75 m down
to 2.25 m. Likewise Table 11.4 (b) presents these values for the key-area I1 .
1 2 3 4 5 6 7 8 9
2.75 -3.25 0.50 3.25 3.75 4.25 4.25 3.75 0.00 -5.75
2.50 4.25 7.0 10.20 10.75 9.0 10.0 9.25 7.5 5.5
Distance in metres
0 5 10 15 20 25 30
A B C D E F
' w
zc n
a
m Key Area 1 2.75,2.50,2.25 0 Location of Avemged
Key Area P 2d00,1.75,1.50 Elevation
Location of Guiding
Datum = + 1320 Point
1 2 3 4 5 6 7 8 9
Contour Distance from N-S base line
2.00 14.25 16.5 19.0 19.75 19.5 20.0 19.75 19.5 18.75
1.75 18.25 21.5 23.0 23.25 23.0 23.0 23.25 22.5 21.75
contour
Then we compute the average land slope along each rand0111 line in each key-area.
Sufficiently accurate value of the slope may be obtained using the extreme contours in
each key-area. Thus the average slope along random line 4, in key-area I is given by:
where, 3.75 and 15.5 are the distances of respective contours from the base line.
Percentage slope values for other random lines are also computed in a similar manner.
These are included in Table 11.4 (a) and 11.4(b).
Since there is a lollgitudinal slope of 1 in 500, we need to work out the location of the
guiding points as distinct from the average contour points. These offsets are worked out
based on the longitudinal distance between adjacent random lines, which is uniformly 5
m in the present case.'We assume also that these two points namely, point of average
elevation and the guiding point coincide for the first random line. From then on we
note that the longitudinal fall gives rise to an offset between each successive random
line pairs as :
Now, random line 2 has an average cross slope of 4.44%. Thus the offset between the
two points along the random line 2 is obtained as :
The values corresponding to the other random lines are contained in the Table
11.4 (a) and 11.4 (b).
The guiding points are connected through a smooth line to obtain the guiding line for
key -area I and also for key-area 11.
LaEd ClwPisrg Design
A suitable choice is made for the value of terrace width as shown in example (1 1.2).
Let us assume that in the present case, we choose 6 rn as the width of the terrace. We
sketch a band or a strip of width 6 m around the guiding lines so as to contain them
within the master strips, one each for each key-area. Figure 1 1.15 shows one such
possibility. The area in between is now covered by strips sketched parallel to the
master strip in that particular key-area. It is seen that the there are two small portions
emerging as buffer areas. These have to be absorbed in one of the adjacent strips.
Since the buffer areas are quite small we may conclude that a strip demarcatio~ishave
been carried out quite satisfactorily.
I
~ u i d i n gline 1
Cut-fill asscsslilelit call be made treating each bcllch as a separate field. Becausc of the
nature of the slope. we would find that cutting will be required ]\ear the higher terrace
and filling 1\0uld be liecessary over tlic other half towards Ilic lower terrace. As usual.
Land Levelling and Gruding allowances for compeilsation towards compaction, fonnation of bund, irrigation and
drainage cllannels have to be made.
It might appear that, in tlie present example, the master strips could as well have been
heuristically sketched even without going through this kind of rigorous calculations.
However, rvlien the coiitour lines pattern is quite jagged. such calculations would
become necessary.
In the execution of the work. staking of the bench layout would be carried out on the
field. Bench foriliation would be undertaken to cover a cascade of 3 to 4 terraces in a
series of excavation-cunl-fill operations. This will be done alteniatively. once
down-the-slope followed an up-the-slope pass. Tlie haulage distances would be limited
to the width of a bench and would onl!. very rarely span across the benches. The
longitudinal slope grading \vill have also to be camcd out smii~ltaneously,and finally
land-snioothing, using wooden floats or levclcrs should be carried out.
I11 this Unit we first considered the necessity for land grading, and then dwelt on the
various considerations influencing the design of land grading. Step-by-step procedure
of land grading is presented. Analytical methods for deciding the best slopes that
nliniinise the cut-and-fill operations. and improsed methods of cut-fill cstinlation were
presented. A special h p e of land grading called contour benching was discussed in
some detail. Soine issues related to land formation as an earth work activity wcre also
.
considered. Certaiii recei~tdevelopments such as GIs, GPS, and their role in
inodemizing land grading operations were indicated
SAQ 3
We will consider terrain width of 4 m. 6 ni, 8 m and 10 m respectively; and work out
1
the total width of the available bench and the corresponding elevation difference of tlie
terraces.
In the present case t~ = 0.5 m
We nlay adopt a Bw of 6 or 8 m.