Professional Documents
Culture Documents
Ogl421 Risk Register Tyler Hubertus
Ogl421 Risk Register Tyler Hubertus
Ogl421 Risk Register Tyler Hubertus
Risk Register
1 Missed 6/1/2022 Tyler The source of this risk High Project Good The way we will Closed 8/22/22
Website Hube is the project deadline, Manager/We mitigate the risk of
Launch Date rtus the 3 test phases, and b missing the website
the resources. The Developer/W launch date will be to
test phases will drive eb Experts have three testing
the needed resources phases before the
and not completing website goes live.
the testing phases will Additionally, the
cause the deadline to website will need to
be missed. be fully functional the
week prior to launch.
The resources
needed for this risk
will be the additional
web developer, and
weekly coordination
meetings between
the web developers,
web experts, and the
project manager.
This action will be
preventive based as I
don’t anticipate any
cost to be associated
with this. It is
contingent on
passing beta testing
before the launch
date.
The solution to
dealing with funding
issues will be to have
an early estimate put
in for the total cost of
the project.
Additionally, there
will be contingency in
The source of this risk place for any
Proje is material going up in surprise cost that
ct cost, extra testing Project arise. The
5 Funding 6/1/2022 Mana needing to be Low Manager/Ow Good contingency will be Closed 7/15/22
ger/O performed, and the ner 10% and added into
wner team needing more the total cost of the
resources. project after all over
head is accounted
for. The resources
needed for this will
be owner funding.
Any additional
funding needs will
come from
contingency.
The risk is this source Unforeseen risk will
is not having a plan in be managed the
place to combat entire team. The
Proje
unforeseen risk. main solution will be
ct
determined by the
Mana
Project associated risk and
ger/T
Manager/Tea the use of the risk
Unforeseen eam/
6 6/1/2022 Low m/Risk Good management plan. Closed 8/1/22
Risk Risk
Management This will come from
Mana
Plan contingency if there
geme
are any cost
nt
associated with the
Plan
risk. The rest will be
preventative on a
case-by-case bases.