GOVERNMENT OF KHYBER PAKHTUNKHWA

MRS CELL COMMUNICATION & WORKS DEPARTMENT


MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-93-c Unit

Item Name : Supply & Installation, testing and commissioning of Solar Submersible
Pump (ISO - 9906 Certified) coupled with Submersible rewind-able
Electric Motor with AC winding and all accessories like Solar Pump
Controller, du/dt filter Complete in all accessories including cooling
jackets, NRV, Pressure Gauge, Sluice valves (02 Nos) except column pipe
and power cable for discharge greater than 3000 iGPH and output
capacity greater than 3 WHP and up to 6 WHP (As per Approved Technical
Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP

mentioned in the "item


name" for discharge >
3000 iGPH and Output
Capacity greater than 3
WHP and upto 6 WHP -93

LABOUR
Labourer 3.2
Skilled Labour 1.6
Plumber 1.6
Electrician 1.6
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,001

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK
CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-93-d Unit

Item Name : Supply & Installation, testing and commissioning of Solar Submersible
Pump (ISO - 9906 Certified) coupled with Submersible rewind-able
Electric Motor with AC winding and all accessories like Solar Pump
Controller, du/dt filter Complete in all accessories including cooling
jackets, NRV, Pressure Gauge, Sluice valves (02 Nos) except column pipe
and power cable for discharge greater than 3000 iGPH and output
capacity greater than 6 WHP and up to 10 WHP (As per Approved Technical
Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP

mentioned in the "item


name" for discharge >
3000 iGPH and Output
Capacity greater than 6
WHP and upto 10 WHP -93

LABOUR
Labourer 2.8
Skilled Labour 1.4
Plumber 1.4
Electrician 1.4
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,002

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-93-e Unit
Item Name : Supply & Installation, testing and commissioning of Solar Submersible
Pump (ISO - 9906 Certified) coupled with Submersible rewind-able
Electric Motor with AC winding and all accessories like Solar Pump
Controller, du/dt filter Complete in all accessories including cooling
jackets, NRV, Pressure Gauge, Sluice valves (02 Nos) except column pipe
and power cable for discharge greater than 3000 iGPH and output
capacity greater than 10 WHP and up to 15 WHP (As per Approved
Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP

mentioned in the "item


name" for discharge >
3000 iGPH and Output
Capacity greater than 10
WHP and upto 15 WHP -93

LABOUR
Labourer 2.4
Skilled Labour 1.2
Plumber 1.2
Electrician 1.2
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,003

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-93-f Unit

Item Name : Supply & Installation, testing and commissioning of Solar Submersible
Pump (ISO - 9906 Certified) coupled with Submersible rewind-able
Electric Motor with AC winding and all accessories like Solar Pump
Controller, du/dt filter Complete in all accessories including cooling
jackets, NRV, Pressure Gauge, Sluice valves (02 Nos) except column pipe
and power cable for discharge greater than 3000 iGPH and output
capacity greater than 15 WHP and up to 20 WHP (As per Approved
Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP

mentioned in the "item


name" for discharge >
3000 iGPH and Output
Capacity greater than 15
WHP and upto 20 WHP -93

LABOUR
Labourer 1.6
Skilled Labour 0.8
Plumber 0.8
Electrician 0.8
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,004

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-93-g Unit

Item Name : Supply & Installation, testing and commissioning of Solar Submersible
Pump (ISO - 9906 Certified) coupled with Submersible rewind-able
Electric Motor with AC winding and all accessories like Solar Pump
Controller, du/dt filter Complete in all accessories including cooling
jackets, NRV, Pressure Gauge, Sluice valves (02 Nos) except column pipe
and power cable for discharge greater than 3000 iGPH and output
capacity greater than 20 WHP and upto 30 (As per Approved Technical
Specifications)
Detail Qty Unit
MATERIAL
Machinery and equipment 1 WHP

mentioned in the "item


name" for discharge >
3000 iGPH and Output
Capacity greater than 20
WHP and up to 30 WHP -93

LABOUR
Labourer 1.2
Skilled Labour 0.6
Plumber 0.6
Electrician 0.6
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,005

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-93-h Unit

Item Name : Supply & Installation, testing and commissioning of Solar Submersible
Pump (ISO - 9906 Certified) coupled with Submersible rewind-able
Electric Motor with AC winding and all accessories like Solar Pump
Controller, du/dt filter Complete in all accessories including cooling
jackets, NRV, Pressure Gauge, Sluice valves (02 Nos) except column pipe
and power cable for discharge greater than 3000 iGPH and output
capacity greater than 30 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge >
3000 iGPH and Output
Capacity greater than 30
WHP -93

LABOUR
Labourer 0.8
Skilled Labour 0.4
Plumber 0.4
Electrician 0.4
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,006

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-94-a Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules ,Fixed Mounting
Structure and Foundation Civil work, Junction Boxes, Fuses, DC
Breakers, Wiring complete upto Solar Pump Inverter, sized at a sizing
factor of 1.75 capable of operating its intended solar pump having
discharge less than or equal to 3000 iGPH and output capacity up to 1
WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge upto
3000 iGPH and Output
Capacity upto 1 WHP -94

LABOUR
Mason 2
Labourer 4
Skilled Labour 2
Electrician 2
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,007

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-94-b Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules ,Fixed Mounting
Structure and Foundation Civil work, Junction Boxes, Fuses, DC
Breakers, Wiring complete upto Solar Pump Inverter, sized at a sizing
factor of 1.75 capable of operating its intended solar pump having
discharge less than or equal to 3000 iGPH and output capacity greater
than 1 WHP and up to 3 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge upto
3000 iGPH and Output
Capacity greater than 1
WHP and upto 3 WHP -94

LABOUR
Mason 1.8
Labourer 3.6
Skilled Labour 1.8
Electrician 1.8
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.
4,008

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-94-c Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules ,Fixed Mounting
Structure and Foundation Civil work, Junction Boxes, Fuses, DC
Breakers, Wiring complete upto Solar Pump Inverter, sized at a sizing
factor of 1.75 capable of operating its intended solar pump having
discharge less than or equal to 3000 iGPH and output capacity greater
than 3 WHP and up to 6 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge upto
3000 iGPH and Output
Capacity greater than 3
WHP and upto 6 WHP -94

LABOUR
Mason 1.6
Labourer 3.2
Skilled Labour 1.6
Electrician 1.6
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,009

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK
CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-94-d Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules ,Fixed Mounting
Structure and Foundation Civil work, Junction Boxes, Fuses, DC
Breakers, Wiring complete upto Solar Pump Inverter, sized at a sizing
factor of 1.75 capable of operating its intended solar pump having
discharge less than or equal to 3000 iGPH and output capacity greater
than 6 WHP and up to 10 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge upto
3000 iGPH and Output
Capacity greater than 6
WHP and upto 10 WHP -94

LABOUR
Mason 1.4
Labourer 2.8
Skilled Labour 1.4
Electrician 1.4
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,010

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-94-e Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules ,Fixed Mounting
Structure and Foundation Civil work, Junction Boxes, Fuses, DC
Breakers, Wiring complete upto Solar Pump Inverter, sized at a sizing
factor of 1.75 capable of operating its intended solar pump having
discharge less than or equal to 3000 iGPH and output capacity greater
than 10 WHP and up to 15 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge upto
3000 iGPH and Output
Capacity greater than 10
WHP and upto 15 WHP -94

LABOUR
Mason 1.2
Labourer 2.4
Skilled Labour 1.2
Electrician 1.2
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,011

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-94-f Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules ,Fixed Mounting
Structure and Foundation Civil work, Junction Boxes, Fuses, DC
Breakers, Wiring complete upto Solar Pump Inerter, sized at a sizing
factor of 1.75 capable of operating its intended solar pump having
discharge less than or equal to 3000 iGPH and output capacity greater
than 15 WHP and up to 20 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge upto
3000 iGPH and Output
Capacity greater than 15
WHP and upto 20 WHP -94

LABOUR
Mason 0.8
Labourer 1.6
Skilled Labour 0.8
Electrician 0.8
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,012

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-94-g Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules ,Fixed Mounting
Structure and Foundation Civil work, Junction Boxes, Fuses, DC
Breakers, Wiring complete upto Solar Pump Inverter, sized at a sizing
factor of 1.75 capable of operating its intended solar pump having
discharge less than or equal to 3000 iGPH and output capacity greater
than 20 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge upto
3000 iGPH and Output
Capacity greater than 20
WHP -94
LABOUR
Mason 0.4
Labourer 0.8
Skilled Labour 0.4
Electrician 0.4
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,013

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-95-a Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules ,Fixed Mounting
Structure and Foundation Civil work, Junction Boxes, Fuses, DC
Breakers, Wiring complete upto Solar Pump Inverter, sized at a sizing
factor of 1.75 capable of operating its intended solar pump having
discharge greater than 3000 iGPH and output capacity up to 1 WHP (As
per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge >
3000 iGPH and Output
Capacity upto 1 WHP -95

LABOUR
Mason 1.9
Labourer 3.8
Skilled Labour 1.9
Electrician 1.9
Sundries (Labour Only):
Contractor Profit 10% + Over Heads on(M+L+E) 2% +
Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,014

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-95-b Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules ,Fixed Mounting
Structure and Foundation Civil work, Junction Boxes, Fuses, DC
Breakers, Wiring complete upto Solar Pump Inverter, sized at a sizing
factor of 1.75 capable of operating its intended solar pump having
discharge greater than 3000 iGPH and output capacity greater than 1 WHP
and up to 3 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge >
3000 iGPH and Output
Capacity greater than 1
WHP and upto 3 WHP -95

LABOUR
Mason 1.8
Labourer 3.6
Skilled Labour 1.8
Electrician 1.8
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,015
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-95-c Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules ,Fixed Mounting
Structure and Foundation Civil work, Junction Boxes, Fuses, DC
Breakers, Wiring complete upto Solar Pump Inverter, sized at a sizing
factor of 1.75 capable of operating its intended solar pump having
discharge greater than 3000 iGPH and output capacity greater than 3 WHP
and up to 6 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge >
3000 iGPH and Output
Capacity greater than 3
WHP and upto 6 WHP -95

LABOUR
Mason 1.6
Labourer 3.2
Skilled Labour 1.6
Electrician 1.6
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,016

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY


DESCRIPTION OF ITEM : Spec. No :
Item Code : 24-95-d Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules ,Fixed Mounting
Structure and Foundation Civil work, Junction Boxes, Fuses, DC
Breakers, Wiring complete upto Solar Pump Inverter, sized at a sizing
factor of 1.75 capable of operating its intended solar pump having
discharge greater than 3000 iGPH and output capacity greater than 6 WHP
and up to 10 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge >
3000 iGPH and Output
Capacity greater than 6
WHP and upto 10 WHP -95

LABOUR
Mason 1.4
Labourer 2.8
Skilled Labour 1.4
Electrician 1.4
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,017

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-95-e Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules ,Fixed Mounting
Structure and Foundation Civil work, Junction Boxes, Fuses, DC
Breakers, Wiring complete upto Solar Pump Inverter, sized at a sizing
factor of 1.75 capable of operating its intended solar pump having
discharge greater than 3000 iGPH and output capacity greater than 10
WHP and up to 15 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge >
3000 iGPH and Output
Capacity greater than 10
WHP and upto 15 WHP -95

LABOUR
Mason 1.2
Labourer 2.4
Skilled Labour 1.2
Electrician 1.2
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,018

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-95-f Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules ,Fixed Mounting
Structure and Foundation Civil work, Junction Boxes, Fuses, DC
Breakers, Wiring complete upto Solar Pump Inverter, sized at a sizing
factor of 1.75 capable of operating its intended solar pump having
discharge greater than 3000 iGPH and output capacity greater than 15
WHP and up to 20 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge >
3000 iGPH and Output
Capacity greater than 15
WHP and upto 20 WHP -95

LABOUR
Mason 0.8
Labourer 1.6
Skilled Labour 0.8
Electrician 0.8
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,019

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-95-g Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules ,Fixed Mounting
Structure and Foundation Civil work, Junction Boxes, Fuses, DC
Breakers, Wiring complete upto Solar Pump Inverter, sized at a sizing
factor of 1.75 capable of operating its intended solar pump having
discharge greater than 3000 iGPH and output capacity greater than 20
WHP and up to 30 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge >
3000 iGPH and Output
Capacity greater than 20
WHP and up to 30 WHP -95
LABOUR
Mason 0.6
Labourer 1.2
Skilled Labour 0.6
Electrician 0.6
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,020

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-95-h Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules ,Fixed Mounting
Structure and Foundation Civil work, Junction Boxes, Fuses, DC
Breakers, Wiring complete upto Solar Pump Inverter, sized at a sizing
factor of 1.75 capable of operating its intended solar pump having
discharge greater than 3000 iGPH and output capacity greater than 30
WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge >
3000 iGPH and Output
Capacity greater than 30
WHP -95

LABOUR
Mason 0.4
Labourer 0.8
Skilled Labour 0.4
Electrician 0.4
Sundries (Labour Only):
Contractor Profit 10% + Over Heads on(M+L+E) 2% +
Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,021

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-96-a Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules , Manual
Tracker Mounting Structure and Foundation Civil work, Junction Boxes,
Fuses, DC Breakers, Wiring complete upto Solar Pump Inerter, sized at a
sizing factor of 1.50 capable of operating its intended solar pump
having discharge less than or equal to 3000 iGPH and output capacity up
to 1 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge upto
3000 iGPH and Output
Capacity upto 1 WHP -96

LABOUR
Mason 2
Labourer 4
Skilled Labour 2
Electrician 2
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,022

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-96-b Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules , Manual Tacker
Mounting Structure and Foundation Civil work, Junction Boxes, Fuses, DC
Breakers, Wiring complete upto Solar Pump Inerter, sized at a sizing
factor of 1.50 capable of operating its intended solar pump having
discharge less than or equal to 3000 iGPH and output capacity greater
than 1 WHP and up to 3 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge upto
3000 iGPH and Output
Capacity greater than 1
WHP and upto 3 WHP -96

LABOUR
Mason 1.8
Labourer 3.6
Skilled Labour 1.8
Electrician 1.8
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,023

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-96-c Unit
Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules , Manual Tacker
Mounting Structure and Foundation Civil work, Junction Boxes, Fuses, DC
Breakers, Wiring complete upto Solar Pump Inerter, sized at a sizing
factor of 1.50 capable of operating its intended solar pump having
discharge less than or equal to 3000 iGPH and output capacity greater
than 3 WHP and up to 6 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge upto
3000 iGPH and Output
Capacity greater than 3
WHP and upto 6 WHP -96

LABOUR
Mason 1.6
Labourer 3.2
Skilled Labour 1.6
Electrician 1.6
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,024

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-96-d Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules , Manual
Tracker Mounting Structure and Foundation Civil work, Junction Boxes,
Fuses, DC Breakers, Wiring complete upto Solar Pump Inerter, sized at a
sizing factor of 1.50 capable of operating its intended solar pump
having discharge less than or equal to 3000 iGPH and output capacity
greater than 6 WHP and up to 10 WHP (As per Approved Technical
Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP

mentioned in the "item


name" for discharge upto
3000 iGPH and Output
Capacity greater than 6
WHP and upto 10 WHP -96

LABOUR
Mason 1.4
Labourer 2.8
Skilled Labour 1.4
Electrician 1.4
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,025

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-96-e Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules , Manual
Tracker Mounting Structure and Foundation Civil work, Junction Boxes,
Fuses, DC Breakers, Wiring complete upto Solar Pump Inerter, sized at a
sizing factor of 1.50 capable of operating its intended solar pump
having discharge less than or equal to 3000 iGPH and output capacity
greater than 10 WHP and up to 15 WHP (As per Approved Technical
Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP

mentioned in the "item


name" for discharge upto
3000 iGPH and Output
Capacity greater than 10
WHP and upto 15 WHP -96

LABOUR
Mason 1.2
Labourer 2.4
Skilled Labour 1.2
Electrician 1.2
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,026

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-96-f Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules ,Manual Tracker
Mounting Structure and Foundation Civil work, Junction Boxes, Fuses, DC
Breakers, Wiring complete upto Solar Pump Inerter, sized at a sizing
factor of 1.50 capable of operating its intended solar pump having
discharge less than or equal to 3000 iGPH and output capacity greater
than 15 WHP and up to 20 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge upto
3000 iGPH and Output
Capacity greater than 15
WHP and upto 20 WHP -96
LABOUR
Mason 0.8
Labourer 1.6
Skilled Labour 0.8
Electrician 0.8
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,027

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-96-g Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules ,Manual Tracker
Mounting Structure and Foundation Civil work, Junction Boxes, Fuses, DC
Breakers, Wiring complete upto Solar Pump Inerter, sized at a sizing
factor of 1.50 capable of operating its intended solar pump having
discharge less than or equal to 3000 iGPH and output capacity greater
than 20 (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge upto
3000 iGPH and Output
Capacity greater than 20
WHP -96

LABOUR
Mason 0.4
Labourer 0.8
Skilled Labour 0.4
Electrician 0.4
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,028

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-97-a Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules , Manual
Tracker Mounting Structure and Foundation Civil work, Junction Boxes,
Fuses, DC Breakers, Wiring complete upto Solar Pump Inerter, sized at a
sizing factor of 1.50 capable of operating its intended solar pump
having discharge greater than 3000 iGPH and output capacity up to 1 WHP
(As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge >
3000 iGPH and Output
Capacity upto 1 WHP -97

LABOUR
Mason 1.9
Labourer 3.8
Skilled Labour 1.9
Electrician 1.9
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,029
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-97-b Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules , Manual Tacker
Mounting Structure and Foundation Civil work, Junction Boxes, Fuses, DC
Breakers, Wiring complete upto Solar Pump Inerter, sized at a sizing
factor of 1.50 capable of operating its intended solar pump having
discharge greater than 3000 iGPH and output capacity greater than 1 WHP
and up to 3 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge >
3000 iGPH and Output
Capacity greater than 1
WHP and upto 3 WHP -97

LABOUR
Mason 1.8
Labourer 3.6
Skilled Labour 1.8
Electrician 1.8
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,030

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY


DESCRIPTION OF ITEM : Spec. No :
Item Code : 24-97-c Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules , Manual Tacker
Mounting Structure and Foundation Civil work, Junction Boxes, Fuses, DC
Breakers, Wiring complete upto Solar Pump Inerter, sized at a sizing
factor of 1.50 capable of operating its intended solar pump having
discharge greater than 3000 iGPH and output capacity greater than 3 WHP
and up to 6 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge >
3000 iGPH and Output
Capacity greater than 3
WHP and upto 6 WHP -97

LABOUR
Mason 1.6
Labourer 3.2
Skilled Labour 1.6
Electrician 1.6
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,031

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-97-d Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules , Manual
Tracker Mounting Structure and Foundation Civil work, Junction Boxes,
Fuses, DC Breakers, Wiring complete upto Solar Pump Inerter, sized at a
sizing factor of 1.50 capable of operating its intended solar pump
having discharge greater than 3000 iGPH and output capacity greater
than 6 WHP and up to 10 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge >
3000 iGPH and Output
Capacity greater than 6
WHP and upto 10 WHP -97

LABOUR
Mason 1.4
Labourer 2.8
Skilled Labour 1.4
Electrician 1.4
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,032

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-97-e Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules , Manual
Tracker Mounting Structure and Foundation Civil work, Junction Boxes,
Fuses, DC Breakers, Wiring complete upto Solar Pump Inerter, sized at a
sizing factor of 1.50 capable of operating its intended solar pump
having discharge greater than 3000 iGPH and output capacity greater
than 10 WHP and up to 15 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge >
3000 iGPH and Output
Capacity greater than 10
WHP and upto 15 WHP -97

LABOUR
Mason 1.2
Labourer 2.4
Skilled Labour 1.2
Electrician 1.2
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,033

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-97-f Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules ,Manual Tracker
Mounting Structure and Foundation Civil work, Junction Boxes, Fuses, DC
Breakers, Wiring complete upto Solar Pump Inerter, sized at a sizing
factor of 1.50 capable of operating its intended solar pump having
discharge greater than 3000 iGPH and output capacity greater than 15
WHP and up to 20 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge >
3000 iGPH and Output
Capacity greater than 15
WHP and upto 20 WHP -97
LABOUR
Mason 0.8
Labourer 1.6
Skilled Labour 0.8
Electrician 0.8
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,034

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-97-g Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules ,Manual Tracker
Mounting Structure and Foundation Civil work, Junction Boxes, Fuses, DC
Breakers, Wiring complete upto Solar Pump Inerter, sized at a sizing
factor of 1.50 capable of operating its intended solar pump having
discharge greater than 3000 iGPH and output capacity greater than 20
WHP and up to 30 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge >
3000 iGPH and Output
Capacity greater than 20
WHP and up to 30 WHP -97

LABOUR
Mason 0.4
Labourer 0.8
Skilled Labour 0.4
Electrician 0.4
Sundries (Labour Only):
Contractor Profit 10% + Over Heads on(M+L+E) 2% +
Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,035

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-97-h Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules ,Manual Tracker
Mounting Structure and Foundation Civil work, Junction Boxes, Fuses, DC
Breakers, Wiring complete upto Solar Pump Inerter, sized at a sizing
factor of 1.50 capable of operating its intended solar pump having
discharge greater than 3000 iGPH and output capacity greater than 30
WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge >
3000 iGPH and Output
Capacity greater than 30
WHP -97

LABOUR
Mason 0.4
Labourer 0.8
Skilled Labour 0.4
Electrician 0.4
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,036
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-98-a Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules , Auto sun
Tracker Mounting Structure and Foundation Civil work, Junction Boxes,
Fuses, DC Breakers, Wiring complete upto Solar Pump Inerter, sized at a
sizing factor of 1.50 capable of operating its intended solar pump
having discharge less than or equal to 3000 iGPH and output capacity up
to 1 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge upto
3000 iGPH and Output
Capacity upto 1 WHP -98

LABOUR
Mason 2.2
Labourer 4.4
Skilled Labour 2.2
Electrician 2.2
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,037

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-98-b Unit
Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules , Auto sun
Tacker Mounting Structure and Foundation Civil work, Junction Boxes,
Fuses, DC Breakers, Wiring complete upto Solar Pump Inerter, sized at a
sizing factor of 1.50 capable of operating its intended solar pump
having discharge less than or eual to 3000 iGPH and output capacity
greater than 1 WHP and up to 3 WHP (As per Approved Technical
Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP

mentioned in the "item


name" for discharge upto
3000 iGPH and Output
Capacity greater than 1
WHP and upto 3 WHP -98

LABOUR
Mason 2.1
Labourer 4.2
Skilled Labour 2.1
Electrician 2.1
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,038

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-98-c Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules , Auto sun
Tacker Mounting Structure and Foundation Civil work, Junction Boxes,
Fuses, DC Breakers, Wiring complete upto Solar Pump Inerter, sized at a
sizing factor of 1.50 capable of operating its intended solar pump
having discharge less than or eual to 3000 iGPH and output capacity
greater than 3 WHP and up to 6 WHP (As per Approved Technical
Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP

mentioned in the "item


name" for discharge upto
3000 iGPH and Output
Capacity greater than 3
WHP and upto 6 WHP -98

LABOUR
Mason 1.9
Labourer 3.8
Skilled Labour 1.9
Electrician 1.9
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,039

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-98-d Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules , Auto sun
Tacker Mounting Structure and Foundation Civil work, Junction Boxes,
Fuses, DC Breakers, Wiring complete upto Solar Pump Inerter, sized at a
sizing factor of 1.50 capable of operating its intended solar pump
having discharge less than or eual to 3000 iGPH and output capacity
greater than 6 WHP and up to 10 WHP (As per Approved Technical
Specifications)
Detail Qty Unit
MATERIAL
Machinery and equipment 1 WHP

mentioned in the "item


name" for discharge upto
3000 iGPH and Output
Capacity greater than 6
WHP and upto 10 WHP -98

LABOUR
Mason 1.7
Labourer 3.4
Skilled Labour 1.7
Electrician 1.7
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,040

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-98-e Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules , Auto sun
Tacker Mounting Structure and Foundation Civil work, Junction Boxes,
Fuses, DC Breakers, Wiring complete upto Solar Pump Inerter, sized at a
sizing factor of 1.50 capable of operating its intended solar pump
having discharge less than or eual to 3000 iGPH and output capacity
greater than 10 WHP and up to 15 WHP (As per Approved Technical
Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP

mentioned in the "item


name" for discharge upto
3000 iGPH and Output
Capacity greater than 10
WHP and upto 15 WHP -98

LABOUR
Mason 1.2
Labourer 2.4
Skilled Labour 1.2
Electrician 1.2
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,041

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-98-f Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules , Auto sun
Tacker Mounting Structure and Foundation Civil work, Junction Boxes,
Fuses, DC Breakers, Wiring complete upto Solar Pump Inerter, sized at a
sizing factor of 1.50 capable of operating its intended solar pump
having discharge less than or eual to 3000 iGPH and output capacity
greater than 15 WHP and up to 20 WHP (As per Approved Technical
Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP

mentioned in the "item


name" for discharge upto
3000 iGPH and Output
Capacity greater than 15
WHP and upto 20 WHP -98
LABOUR
Mason 0.8
Labourer 1.6
Skilled Labour 0.8
Electrician 0.8
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,042

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-98-g Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules , Auto sun
Tacker Mounting Structure and Foundation Civil work, Junction Boxes,
Fuses, DC Breakers, Wiring complete upto Solar Pump Inerter, sized at a
sizing factor of 1.50 capable of operating its intended solar pump
having discharge less than or eual to 3000 iGPH and output capacity
greater than 20 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge upto
3000 iGPH and Output
Capacity greater than 20
WHP -98

LABOUR
Mason 0.4
Labourer 0.8
Skilled Labour 0.4
Electrician 0.4
Sundries (Labour Only):
Contractor Profit 10% + Over Heads on(M+L+E) 2% +
Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,043

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-99-a Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules , Auto sun
Tracker Mounting Structure and Foundation Civil work, Junction Boxes,
Fuses, DC Breakers, Wiring complete upto Solar Pump Inerter, sized at a
sizing factor of 1.50 capable of operating its intended solar pump
having discharge greater than 3000 iGPH and output capacity up to 1 WHP
(As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge >
3000 iGPH and Output
Capacity upto 1 WHP -99

LABOUR
Mason 2
Labourer 2.5
Skilled Labour 2
Electrician 2
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,044
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-99-b Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules , Auto sun
Tacker Mounting Structure and Foundation Civil work, Junction Boxes,
Fuses, DC Breakers, Wiring complete upto Solar Pump Inerter, sized at a
sizing factor of 1.50 capable of operating its intended solar pump
having discharge greater than 3000 iGPH and output capacity greater
than 1 WHP and up to 3 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge >
3000 iGPH and Output
Capacity greater than 1
WHP and upto 3 WHP -99

LABOUR
Mason 1.8
Labourer 3.6
Skilled Labour 1.8
Electrician 1.8
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,045

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-99-c Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules , Auto sun
Tacker Mounting Structure and Foundation Civil work, Junction Boxes,
Fuses, DC Breakers, Wiring complete upto Solar Pump Inerter, sized at a
sizing factor of 1.50 capable of operating its intended solar pump
having discharge greater than 3000 iGPH and output capacity greater
than 3 WHP and up to 6 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge >
3000 iGPH and Output
Capacity greater than 3
WHP and upto 6 WHP -99

LABOUR
Mason 1.6
Labourer 3.2
Skilled Labour 1.6
Electrician 1.6
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,046

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-99-d Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules , Auto sun
Tacker Mounting Structure and Foundation Civil work, Junction Boxes,
Fuses, DC Breakers, Wiring complete upto Solar Pump Inerter, sized at a
sizing factor of 1.50 capable of operating its intended solar pump
having discharge greater than 3000 iGPH and output capacity greater
than 6 WHP and up to 10 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge >
3000 iGPH and Output
Capacity greater than 6
WHP and upto 10 WHP -99

LABOUR
Mason 1.4
Labourer 2.8
Skilled Labour 1.4
Electrician 1.4
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,047

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-99-e Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules , Auto sun
Tacker Mounting Structure and Foundation Civil work, Junction Boxes,
Fuses, DC Breakers, Wiring complete upto Solar Pump Inerter, sized at a
sizing factor of 1.50 capable of operating its intended solar pump
having discharge greater than 3000 iGPH and output capacity greater
than 10 WHP and up to 15 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge >
3000 iGPH and Output
Capacity greater than 10
WHP and upto 15 WHP -99

LABOUR
Mason 1.2
Labourer 2.4
Skilled Labour 1.2
Electrician 1.2
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,048

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-99-f Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules , Auto sun
Tacker Mounting Structure and Foundation Civil work, Junction Boxes,
Fuses, DC Breakers, Wiring complete upto Solar Pump Inerter, sized at a
sizing factor of 1.50 capable of operating its intended solar pump
having discharge greater than 3000 iGPH and output capacity greater
than 15 WHP and up to 20 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge >
3000 iGPH and Output
Capacity greater than 15
WHP and upto 20 WHP -99

LABOUR
Mason 1
Labourer 2
Skilled Labour 1
Electrician 1
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,049

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-99-g Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules , Auto sun
Tacker Mounting Structure and Foundation Civil work, Junction Boxes,
Fuses, DC Breakers, Wiring complete upto Solar Pump Inerter, sized at a
sizing factor of 1.50 capable of operating its intended solar pump
having discharge greater than 3000 iGPH and output capacity greater
than 20 WHP and up to 30 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge >
3000 iGPH and Output
Capacity greater than 20
WHP and up to 30 WHP -99

LABOUR
Mason 0.8
Labourer 1.6
Skilled Labour 0.8
Electrician 0.8
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,050

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 24 , TUBEWELL AND WATER SUPPLY

DESCRIPTION OF ITEM : Spec. No :


Item Code : 24-99-h Unit

Item Name : Supply & Installation, testing and commissioning of complete Solar PV
Generator including A-Grade Mono Crystalline PV Modules , Auto sun
Tacker Mounting Structure and Foundation Civil work, Junction Boxes,
Fuses, DC Breakers, Wiring complete upto Solar Pump Inerter, sized at a
sizing factor of 1.50 capable of operating its intended solar pump
having discharge greater than 3000 iGPH and output capacity greater
than 30 WHP (As per Approved Technical Specifications)

Detail Qty Unit


MATERIAL
Machinery and equipment 1 WHP
mentioned in the "item
name" for discharge >
3000 iGPH and Output
Capacity greater than 30
WHP -99

LABOUR
Mason 0.4
Labourer 0.8
Skilled Labour 0.4
Electrician 0.4
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per WHP Rs.
Labour Rates Per WHP Rs.

4,051

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM :
Item Code : 25-01
Item Name : Laying, linking and packing tramway line
Detail Qty Unit
LABOUR
Labourer 0.023 Day
Skilled Labour 0.0033 Day
Mate 0.0033 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,052

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM :
Item Code : 25-02
Item Name : Dismantling tramway track
Detail Qty Unit
LABOUR
Labourer 0.008 Day
Skilled Labour 0.0008 Day
Mate 0.0008 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,053

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK
CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-03 Unit

Item Name : Laying, linking of BG track, including packing, straightening and


levelling

Detail Qty Unit


LABOUR
Labourer 0.06 Day
Skilled Labour 0.01 Day
Mate 0.01 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,054

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM :
Item Code : 25-04
Item Name : Linking points and crossings, complete with fastening
Detail Qty Unit
LABOUR
Labourer 7.5 Day
Mate 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,055

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK
CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM :
Item Code : 25-05
Item Name : Bending or straightening BG rail with jim crow
Detail Qty Unit
LABOUR
Labourer 0.5 Day
Black Smith 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,056

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM :
Item Code : 25-06
Item Name : Fixing street lamp posts
Detail Qty Unit
LABOUR
Labourer 0.85 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,057

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-07 Unit
Item Name : Binding ends of sleepers and timbers of all sizes & kinds, including
spreading & restacking

Detail Qty Unit


LABOUR
Labourer 0.075 Day
Mate 0.005 Day
Fitter Sewerage / Gas 0.02 Day
Pipe Fitter / Fitter II
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,058

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-08 Unit

Item Name : Opening stacks of sleepers & timber of all kinds and sizes,
including spreading for inspection

Detail Qty Unit


LABOUR
Labourer 0.0115 Day
Mate 0.0008 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,059

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK
CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-09 Unit

Item Name : Small iron work, such as gusset plates, knees, bends, stirrups, straps,
rings etc excluding erection

Detail Qty
MATERIAL
Steel (Struct. Sections) 1000

LABOUR
Labourer 80
Mate 8
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Tonne Rs.
Labour Rates Per Tonne Rs.

4,060

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-10 Unit

Item Name : Fabrication of heavy steel work with angle, tees, sheet iron etc for
making trusses, girders etc

Detail Qty
MATERIAL
Welding Rod 2
Steel (Struct. Sections) 1000

LABOUR
Labourer 5
Black Smith 5
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Tonne Rs.
Labour Rates Per Tonne Rs.

4,061

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-11 Unit

Item Name : Erection and fitting in position iron trusses, staging of water tanks,
etc

Detail Qty Unit


LABOUR
Labourer 6.349 Day
Fitter Sewerage / Gas 6.349 Day
Pipe Fitter / Fitter II
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Tonne Rs.
Labour Rates Per Tonne Rs.

4,062

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-12 Unit

Item Name : Fixing corrugated iron sheet including rivetting, etc


24 SWG to 26 SWG

Detail Qty Unit


LABOUR
Labourer 0.008 Day
Black Smith 0.008 Day
Sundries (Labour Only):
Contractor Profit 10% + Over Heads on(M+L+E) 2% +
Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,063

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM :
Item Code : 25-13
Item Name : Erecting corrugated iron sheet tanks, upto 20' height
Detail Qty Unit
LABOUR
Labourer 15.2 Day
Black Smith 3.2 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Tonne Rs.
Labour Rates Per Tonne Rs.

4,064

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-14 Unit

Item Name : Erecting rolled steel beams or old rails, in roof etc, erection &
fixing in position

Detail Qty Unit


LABOUR
Labourer 1.16 Day
Black Smith 0.04 Day
Sundries (Labour Only):
Contractor Profit 10% + Over Heads on(M+L+E) 2% +
Income Tax 7.5%
Composite Rates Per Tonne Rs.
Labour Rates Per Tonne Rs.

4,065

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-15 Unit

Item Name : Erecting rolled steel beams or rails, erection for posts etc (other
than in roofs)

Detail Qty Unit


LABOUR
Labourer 0.54 Day
Black Smith 0.04 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Tonne Rs.
Labour Rates Per Tonne Rs.

4,066

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM :

Item Code : 25-16


Item Name : Making bolts & nuts of iron rods
Detail Qty Unit
MATERIAL
Steel (Struct. Sections) 0.74 Kg

LABOUR
Labourer 0.035 Day
Black Smith 0.07 Day
Mason (Second Class) 0.035 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Kg Rs.
Labour Rates Per Kg Rs.

4,067

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM :

Item Code : 25-17-a


Item Name :
Detail Qty Unit
LABOUR
Labourer 0.1667 Day
Fitter Sewerage / Gas 0.1667 Day
Pipe Fitter / Fitter II
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each cut Rs.
Labour Rates Per Each cut Rs.

4,068

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM :

Item Code : 25-17-b


Item Name :
Detail Qty Unit
LABOUR
Labourer 0.25 Day
Fitter Sewerage / Gas 0.25 Day
Pipe Fitter / Fitter II
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each cut Rs.
Labour Rates Per Each cut Rs.

4,069

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM :

Item Code : 25-18


Item Name :
Detail Qty Unit
LABOUR
Labourer 0.0833 Day
Fitter Sewerage / Gas 0.0833 Day
Pipe Fitter / Fitter II
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each cut Rs.
Labour Rates Per Each cut Rs.

4,070

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM :

Item Code : 25-19


Item Name : Bending rolled steel beams or rails
Detail Qty Unit
MATERIAL
Coal 21.429 Kg
LABOUR
Labourer 0.1429 Day
Fitter Sewerage / Gas 0.1429 Day
Pipe Fitter / Fitter II
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Per Bend Rs.
Labour Rates Per Per Bend Rs.

4,071

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM :
Item Code : 25-20
Item Name :
Detail Qty Unit
LABOUR
Labourer 0.0667 Day
Fitter Sewerage / Gas 0.0167 Day
Pipe Fitter / Fitter II
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each hole Rs.
Labour Rates Per Each hole Rs.

4,072

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-21 Unit

Item Name : Extra for drilling holes in plates upto 1/2" thick per inch dia, or
part thereof
Detail Qty Unit
LABOUR
Labourer 0.04 Day
Fitter Sewerage / Gas 0.0025 Day
Pipe Fitter / Fitter II
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each hole Rs.
Labour Rates Per Each hole Rs.

4,073

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM :
Item Code : 25-22
Item Name : Rivetting 1/8" dia
Detail Qty Unit
LABOUR
Labourer 0.005 Day
Fitter Sewerage / Gas 0.005 Day
Pipe Fitter / Fitter II
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,074

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM :

Item Code : 25-23


Item Name : Cutting out Rivets, all sizes.
Detail Qty Unit
LABOUR
Hammer Man 0.0139 Day
Fitter Sewerage / Gas 0.0139 Day
Pipe Fitter / Fitter II
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,075

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM :
Item Code : 25-24
Item Name : Fitting and erection of gutters of sheet iron
Detail Qty Unit
LABOUR
Labourer 0.05 Day
Black Smith 0.005 Day
Fitter Sewerage / Gas 0.005 Day
Pipe Fitter / Fitter II
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,076

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM :

Item Code : 25-25


Item Name : Cutting and fixing iron bars, for barred windows
Detail Qty Unit
LABOUR
Labourer 0.0333 Day
Carpenter 0.0167 Day
Fitter Sewerage / Gas 0.0167 Day
Pipe Fitter / Fitter II
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,077

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM :

Item Code : 25-26


Item Name : Cutting GI sheets of 2'-8" wide.
Detail Qty Unit
LABOUR
Hammer Man 0.0167 Day
Fitter Sewerage / Gas 0.0167 Day
Pipe Fitter / Fitter II
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,078

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM :
Item Code : 25-27
Item Name : Notching web or foot of rail posts for housing rail beams
Detail Qty Unit
MATERIAL
Coal 0.8333 Kg

LABOUR
Labourer 0.3333 Day
Fitter Sewerage / Gas 0.3333 Day
Pipe Fitter / Fitter II
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each cut Rs.
Labour Rates Per Each cut Rs.

4,079

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM :

Item Code : 25-28


Item Name : Hoop iron netted trellis work fixed with nails
Detail Qty Unit
MATERIAL
Nails for netted Treils 0.0143 Kg

LABOUR
Black Smith 0.0278 Day
Hammer Man 0.0278 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,080

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK


DESCRIPTION OF ITEM :

Item Code : 25-29


Item Name : Fixing zinc, iron or GI sheet on table tops
Detail Qty
MATERIAL
Nails for netted Treils 0.005 Kg

LABOUR
Labourer 0.0133 Day
Carpenter 0.0133 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,081

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :

Item Code : 25-30-a Unit

Item Name : Providing and fixing steel grated doors, complete with locking
arrangement, angle iron frame 2"x2"x3/8" and 3/4" round bars 4" center
to center.

Detail Qty Unit

MATERIAL
Hold Fast With Bolt 0.2143 Kg
Paint : Enamel 0.036 Ltr
Steel (Struct. Sections) 5.78 Kg
Locking arrangements 0.0357 No.
steel
Rivets and Bolts 0.0804 Kg

LABOUR
Black Smith 0.1859 Day
Bellowman 0.1859 Day
Mason (Second Class) 0.1859 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,082

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :

Item Code : 25-30-b Unit

Item Name : Providing and fixing steel grated doors, complete with locking
arrangement, angle iron frame 2"x2"x3/8" and 1" square bars 4" center
to center.

Detail Qty Unit

MATERIAL
Hold Fast With Bolt 0.2143 Kg
Paint : Enamel 0.036 Ltr
Steel (Struct. Sections) 6.52 Kg
Locking arrangements 0.0357 No.
steel
Rivets and Bolts 0.0804 Kg

LABOUR
Black Smith 0.1859 Day
Bellowman 0.1859 Day
Mason (Second Class) 0.1859 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,083
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :

Item Code : 25-31 Unit

Item Name : Providing and fixing steel grated doors, with 1/16" thick sheeting
including angle iron frame 2"x2"x3/8" and 3/4" square bars 4" center to
center with locking arrangement.

Detail Qty Unit

MATERIAL
Steel (bars/rods/section) 5.78 Kg
Iron Sheet 1.2 Kg
Hold Fast With Bolt 0.2143 Kg
Paint : Enamel 0.06 Ltr
Locking arrangements 0.0357 Kg
steel
Rivets and Bolts 0.0804 Kg

LABOUR
Black Smith 0.1859 Day
Hammer Man 0.1859 Day
Bellowman 0.1719 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,084

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-32 Unit

Item Name : Providing and fixing grating in opening including fixing at site with
flat iron 2" x 3/8" and 3/4" round bars at 4" center to center.

Detail Qty Unit


MATERIAL
Coal 0.1 Kg
Steel (Struct. Sections) 3.14 Kg

LABOUR
Black Smith 0.05 Day
Hammer Man 0.05 Day
Black Smith Helper/ 0.05 Day
Bellow man
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,085

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-33-a Unit

Item Name : Providing and fixing terrace railing 2" i/d conduit pipe 16 SWG, welded
with 5/8" x 5/8" square bar 2.75 ft. high fixed at 5" centre to centre,
in RCC slab with suitable arrangement, complete in all resppects as per
design and drawing.

Detail Qty Unit


MATERIAL
Steel (bars/rods/section) 4.171 Kg
Conduit pipe 2" dia 1 Rft

LABOUR
Skilled Labour 0.025 Day
Black Smith 0.04 Day
Welder 0.05 Day
Sundries (Labour Only):
Contractor Profit 10% + Over Heads on(M+L+E) 2% +
Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,086

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-33-b Unit

Item Name : Providing and fixing steel square pipe size l-l/2" x l-l/2" of 16 gauge
including its welding, complete in all respect, as specified

Detail Qty Unit


MATERIAL
Welding Rod 0.091 Pack
steel square pipe size 1 Rft
l-l/2" x l-l/2" of 16
gauge-light

LABOUR
Black Smith 0.01 Day
Welding Plant Charges 0.01 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,087

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-34 Unit
Item Name : Providing and fixing collapsible gate made of 2"x2"x1/4" tee iron at
top and bottom, channel iron verticals 3/4" x 1/4" x 1/4" x 1/8" at 3"
to 5" centre to centre (approximate) and flat iron crosses 3/4" x 3/16"
and best quality rollers at bottom of 3" diameters including holdfast,
handles 12" long of 3/4" x 1/4" x 1/4" x 1/8" channel iron, locking
arrangment inside and outside, painting 3 coats of black enamel,
complete in working order.

Detail Qty Unit


MATERIAL
Paint : Enamel 0.05 Ltr
Collapsible Gate 1 Sft

LABOUR
Skilled Labour 0.0799 Day
Painter / Polisher 0.0401 Day
Black Smith 0.0799 Day
Fitter Sewerage / Gas 0.0799 Day
Pipe Fitter / Fitter II
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,088

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-35 Unit

Item Name : Providing and Fixing 24 SWG GI sheet rolling shutter of steel frame of
MS channel 2"x1.25"x1/8" complete

Detail Qty Unit


MATERIAL
Paint : Enamel 0.05 Ltr
G.I Sheet Shutter 1 Sft
Spring Roller 0.1 No

LABOUR
Skilled Labour 0.01 Day
Painter / Polisher 0.005 Day
Black Smith 0.01 Day
Fitter Sewerage / Gas 0.01 Day
Pipe Fitter / Fitter II
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,089

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-36 Unit

Item Name : Providing and Fixing MS angle iron 1"x1"x1/4" edge protector nozing of
steps of stairs, complete

Detail Qty Unit


MATERIAL
Steel (bars/rods/section) 1.6505 Kg

LABOUR
Mason 0.02 Day
Labourer 0.02 Day
Black Smith 0.0025 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,090

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK


DESCRIPTION OF ITEM : Spec. No :
Item Code : 25-37 Unit

Item Name : Providing and Fixing stair railing of 2.5" i/d GI pipe, welded with
5/8"x5/8" MS bars 2'-9" high, fixed in each step

Detail Qty Unit


MATERIAL
Steel (bars/rods/section) 1.2104 Kg
Paint : Enamel 0.045 Ltr
G.I pipe (light) 2" 0.71 RFT
Welding Rod 0.0093 Pack

LABOUR
Mason 0.01 Day
Labourer 0.03 Day
Painter / Polisher 0.01 Day
Black Smith 0.04 Day
Hammer Man 0.04 Day
Black Smith Helper/ 0.04 Day
Bellow man
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,091

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-38 Unit

Item Name : Providing and Fixing GI wire gauze 24 SWG, (12x12) meshes per sq.in.,
fixed to steel windows or doors etc, complete in all respects

Detail Qty Unit


MATERIAL
Steel (bars/rods/section) 0.08 KG
Welding Rod 0.0534 Pack
G.I Wire Gauze 12x12 1 RFT
LABOUR
Mason 0.056 Day
Labourer 0.05 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,092

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-39-a-01 Unit

Item Name : Providing and fixing steel windows with openable glazed pannels, using
beam section for frame 1-1/2" x 1" x 5/8" x 1/8", z-section for leaves
3/4" x 1" x 3/4" x 1/8", T- section sashes 1"x1"x1/8", glass panes,
wooden screed for glazing embded over a thin layer of putty duly
screwed with leaves, brass fittings holdfast, duly painted, complete in
all respects, including all cost of material and labour etc. as per
approved design and as directed by the engineer - in -charge: Glass
pane 2mm thick

Detail Qty Unit


MATERIAL
Paint : Enamel 0.1765 Ltr
Glass 2mm Thick-Local 1 SFT
Steel window 1 SFT

LABOUR
Labourer 0.01 Day
Painter / Polisher 0.01 Day
Black Smith 0.01 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.
4,093

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-39-a-02 Unit

Item Name : Providing and fixing steel windows with openable glazed pannels, using
beam section for frame 1-1/2" x 1" x 5/8" x 1/8", z-section for leaves
3/4" x 1" x 3/4" x 1/8", T- section sashes 1"x1"x1/8", glass panes,
wooden screed for glazing embded over a thin layer of putty duly
screwed with leaves, brass fittings holdfast, duly painted, complete in
all respects, including all cost of material and labour etc. as per
approved design and as directed by the engineer - in -charge Glass pane
2.5mm thick

Detail Qty Unit


MATERIAL
Paint : Enamel 0.1765 Ltr
Glass 2.5 mm Thick-Local 1 SFT
Steel window 1 SFT

LABOUR
Labourer 0.01 Day
Painter / Polisher 0.01 Day
Black Smith 0.01 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,094

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-39-a-03 Unit
Item Name : Providing and fixing steel windows with openable glazed pannels, using
beam section for frame 1-1/2" x 1" x 5/8" x 1/8", z-section for leaves
3/4" x 1" x 3/4" x 1/8", T- section sashes 1"x1"x1/8", glass panes,
wooden screed for glazing embded over a thin layer of putty duly
screwed with leaves, brass fittings holdfast, duly painted, complete in
all respects, including all cost of material and labour etc. as per
approved design and as directed by the engineer - in -charge Glass pane
3mm thick

Detail Qty Unit


MATERIAL
Paint : Enamel 0.1765 Ltr
Glass 3 mm Thick-Local 1 SFT
Steel window 1 SFT

LABOUR
Labourer 0.01 Day
Painter / Polisher 0.01 Day
Black Smith 0.01 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,095

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-39-a-04 Unit

Item Name : Providing and fixing steel windows with openable glazed pannels, using
beam section for frame 1-1/2" x 1" x 5/8" x 1/8", z-section for leaves
3/4" x 1" x 3/4" x 1/8", T- section sashes 1"x1"x1/8", glass panes,
wooden screed for glazing embded over a thin layer of putty duly
screwed with leaves, brass fittings holdfast, duly painted, complete in
all respects, including all cost of material and labour etc. as per
approved design and as directed by the engineer - in -charge: Glass
pane 4mm thick

Detail Qty Unit


MATERIAL
Paint : Enamel 0.1765 Ltr
Glass 4 mm Thick-Local 1 SFT
Steel window 1 SFT

LABOUR
Labourer 0.01 Day
Painter / Polisher 0.01 Day
Black Smith 0.01 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,096

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-39-a-05 Unit

Item Name : Providing and fixing steel windows with openable glazed pannels, using
beam section for frame 1-1/2" x 1" x 5/8" x 1/8", z-section for leaves
3/4" x 1" x 3/4" x 1/8", T- section sashes 1"x1"x1/8", glass panes,
wooden screed for glazing embded over a thin layer of putty duly
screwed with leaves, brass fittings holdfast, duly painted, complete in
all respects, including all cost of material and labour etc. as per
approved design and as directed by the engineer - in -charge Glass pane
5mm thick

Detail Qty Unit


MATERIAL
Paint : Enamel 0.1765 Ltr
Glass5 mm Thick-Imported 1 SFT
Steel window 1 SFT

LABOUR
Labourer 0.01 Day
Painter / Polisher 0.01 Day
Black Smith 0.01 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,097

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-39-b-01 Unit

Item Name : Providing and Fixing steel windows 18 gauge with openable glazed panels
With 22 SWG wire gauze : Glass pane 2mm

Detail Qty Unit


MATERIAL
Paint : Enamel 0.2353 Ltr
G.I Wire Gauze 12x12 1 SFT
Glass 2mm Thick-Local 1 SFT
Steel window 1 SFT

LABOUR
Labourer 0.01 Day
Painter / Polisher 0.0125 Day
Black Smith 0.01 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,098

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-39-b-02 Unit

Item Name : Providing and Fixing steel windows 18 gauge with openable glazed panels
With 22 SWG wire gauze : Glass pane 2.5mm

Detail Qty Unit


MATERIAL
Paint : Enamel 0.2353 Ltr
G.I Wire Gauze 12x12 1 SFT
Glass 2mm Thick-Local 1 SFT
Steel window 1 SFT

LABOUR
Labourer 0.01 Day
Painter / Polisher 0.0125 Day
Black Smith 0.01 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,099

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-39-b-03 Unit

Item Name : Providing and Fixing steel windows 18 gauge with openable glazed panels
With 22 SWG wire gauze : Glass pane 3mm

Detail Qty Unit


MATERIAL
Paint : Enamel 0.2353 Ltr
G.I Wire Gauze 12x12 1 SFT
Glass 3 mm Thick-Local 1 SFT
Steel window 1 SFT

LABOUR
Labourer 0.01 Day
Painter / Polisher 0.0125 Day
Black Smith 0.01 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,100

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-39-b-04 Unit

Item Name : Providing and Fixing steel windows 18 gauge with openable glazed panels
With 22 SWG wire gauze : Glass pane 4mm

Detail Qty Unit


MATERIAL
Paint : Enamel 0.2353 Ltr
G.I Wire Gauze 12x12 1 SFT
Glass 4 mm Thick-Local 1 SFT
Steel window 1 SFT

LABOUR
Labourer 0.01 Day
Painter / Polisher 0.0125 Day
Black Smith 0.01 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,101

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-39-b-05 Unit

Item Name : Providing and Fixing steel windows 18 gauge with openable glazed panels
With 22 SWG wire gauze : Glass pane 5mm

Detail Qty Unit


MATERIAL
Paint : Enamel 0.2353 Ltr
G.I Wire Gauze 12x12 1 SFT
Glass5 mm Thick-Imported 1 SFT
Steel window 1 SFT

LABOUR
Labourer 0.01 Day
Painter / Polisher 0.0125 Day
Black Smith 0.01 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,102

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-40 Unit

Item Name : Providing and Fixing steel windows 18 gauge with openable glazed panels
With 22 SWG wire gauze :

Detail Qty Unit


MATERIAL
Steel (bars/rods/section) 3 Kg
Wire Guaze - 22 SWG 1 Sft

LABOUR
Labourer 0.5 Day
Fitter Sewerage / Gas 0.25 Day
Pipe Fitter / Fitter II
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,103

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-41 Unit

Item Name : Providing and Fixing angle iron railing with MS Pipe 2" dia at top and
at Mid-height, using 2.5"x2.5"x3/8" angle iron post 4.5' long, 5" to 6"
apart, complete

Detail Qty Unit

MATERIAL
Paint : Enamel 0.3501
Steel (Struct. Sections) 6.4517
U Bolt 1.5" Long 0.3
Conduit pipe 2" dia 2

LABOUR
Mason 0.075
Labourer 0.075
Black Smith 0.075
Fitter Sewerage / Gas 0.075
Pipe Fitter / Fitter II
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft
Labour Rates Per Rft

4,104

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM :
Item Code : 25-42
Item Name :
1.5"x1.5"x3/16" angle iron post

Detail Qty Unit


MATERIAL
Ordinary Portland Cement 0.0117 Bag
Fine Sand 0.002 Cft
1/2" size screened bajri 0.004 Cft
Barbed Wire 0.1137 Kg
Paint : Enamel 0.1067 Ltr
Steel (Struct. Sections) 0.305 Kg

LABOUR
Mason 0.0153 Day
Labourer 0.0153 Day
Painter / Polisher 0.0046 Day
Black Smith 0.0153 Day
Hammer Man 0.0153 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,105

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM :
Item Code : 25-43
Item Name :
consisting of 1.5"x1.5"x3/16" angle iron post

all respects.
Detail Qty Unit
MATERIAL
Ordinary Portland Cement 0.0048 Bag
Fine Sand 0.001 Cft
1/2" size screened bajri 0.0014 Cft
Barbed Wire 0.1515 Kg
Paint : Enamel 0.1067 Ltr
Steel (Struct. Sections) 0.427 Kg

LABOUR
Mason 0.0152 Day
Labourer 0.0198 Day
Painter / Polisher 0.0046 Day
Black Smith 0.0168 Day
Hammer Man 0.0152 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,106

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-44 Unit

Item Name : Supplying and Fixing 18SWG Steel Almirah, 12" max depth including box
shelves, back, shelves, lock, spray paint complete

Detail Qty Unit


MATERIAL
Iron Sheet 3.8392 Kg
Paint : Enamel 0.0625 Ltr
Welding Rod 0.1 Pack
Terpentine oil 0.093 Ltr
Locking arrangements 0.0625 No
Iron handle 150 mm (6") 0.125 No
long

LABOUR
Labourer 0.0781 Day
Painter / Polisher 0.0156 Day
Black Smith 0.0156 Day
Welder 0.0313 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,107

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-45-a Unit

Item Name : Supplying and Fixing 18 SWG MS Sheet Door with angle iron frame
(1.5"x1.5"x1/8"), bolt, hinges, paint etc complete

Detail Qty Unit


MATERIAL
Iron Sheet 2.04 Kg
Hold Fast With Bolt 0.1428 Kg
Paint : Enamel 0.0357 Ltr
Welding Rod 0.125 Pack
Terpentine oil 0.0357 Ltr
Iron handle 150 mm (6") 0.1069 No
long
Hinges5" 0.0179 Doz
Tower Bolt 10"-light 0.0714 No

LABOUR
Labourer 0.0089 Day
Painter / Polisher 0.0179 Day
Black Smith 0.0536 Day
Welder 0.0357 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,108

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK


DESCRIPTION OF ITEM : Spec. No :
Item Code : 25-45-b Unit

Item Name : Supplying and Fixing 18 SWG MS Sheet Gate with angle iron frame
(2"x2"x3/16") with side window, lock, painting etc

Detail Qty Unit


MATERIAL
Iron Sheet 2.04 Kg
Hold Fast With Bolt 0.0555 Kg
Paint : Enamel 0.0278 Ltr
Welding Rod 0.125 Pack
Terpentine oil 0.0278 Ltr
Steel (Struct. Sections) 1.4302 Kg
Tower Bolt 10"-light 0.0278 No
Sliding bolt 18 Inch Long 0.0139 No

LABOUR
Mason 0.0278 Day
Labourer 0.0972 Day
Painter / Polisher 0.0139 Day
Black Smith 0.0556 Day
Welder 0.0278 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,109

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-46 Unit

Item Name : Erection of Steel Girder 4"x8"x3/16" (Commercial size) including


fitting in position

Detail Qty Unit


MATERIAL
Steel Girder 4"x8"x3/16" 1 Rft
LABOUR
Labourer 0.1375 Day
Black Smith 0.1375 Day
Hammer Man 0.1375 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,110

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-47 Unit

Item Name : Supply and fixing of fancy type stainless steel chromium plate 2" dia
pipes stair railing 3/4" dia pipe fixed on specified space on steps in
horizontal positions, complete in all respects

Detail Qty Unit

MATERIAL
Stainless steel chromium 1 ft
plated 2" dia pipe

LABOUR
Labourer 0.2 Day
Black Smith 0.125 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,111

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK
CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-48 Unit

Item Name : Removing & folding design paracutist cloth shade with steel rope size
85'×50' complete in all respects

Detail Qty Unit


LABOUR
Labourer 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per sft Rs.
Labour Rates Per sft Rs.

4,112

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-49 Unit

Item Name : Providing and Fixing of Steel chowkat including GI sheet (heavy gauge)
with holdfast embedded in PCC 5" to 6" wide

Detail Qty Unit


MATERIAL
Steel chowkat including 1 Kg
GI sheet (heavy gauge)
with holdfast

LABOUR
Labourer 0.076 Day
Welder 0.02 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Kg Rs.
Labour Rates Per Kg Rs.
4,113

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM :
Item Code : 25-50-a
Item Name :
Detail Qty Unit
MATERIAL
Steel Bracket with Nut, 1 No
bolt for AC Unit

LABOUR
Labourer 0.13 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,114

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM :
Item Code : 25-50-b
Item Name : Supply and fixing of steel bracket for curtain pipe
Detail Qty Unit
MATERIAL
Steel bracket for curtain 2 Each
pipe

LABOUR
Labourer 0.05 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,115

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM :
Item Code : 25-51
Item Name : Supply and Fixing of Tee Iron (2''x2''x1/8'')
Detail Qty Unit
MATERIAL
Tee Iron (2''x2''x1/8'') 1 Kg

LABOUR
Black Smith 0.02 Day
Hammer Man 0.02 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per RFT Rs.
Labour Rates Per RFT Rs.

4,116

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-52 Unit

Item Name : Providing, making & fixing of Steel manhole cover i/c angle iron (1
1/2" x 1 1/4" x 1/8") frame with M.S. sheet'complete .

Detail Qty Unit


MATERIAL
M.S. sheet 10 SWG 2.2 Kg
Angle iron (1 1/2" x 1 0.95 Kg
1/4" x 1/8") frame
LABOUR
Mason 0.2 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,117

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-53 Unit

Item Name : Providing, making and fixing of steel grill of MS pipe (2"x1")
omamental design i/c cost of paiting complete.

Detail Qty Unit


MATERIAL
Paint : Enamel 0.1 kg
MS Pipe (2" x 1") 1 sft

LABOUR
Painter / Polisher 0.06 Day
Welder 0.08 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,118

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM :
Item Code : 25-54
Item Name : Minor repair of steel joinery complete.
Detail Qty Unit
MATERIAL
Welding Rod 0.0063 Packet

LABOUR
Labourer 0.0208 Day
Welder 0.0167 Day
Sundries (Labour Only):

EQUIPMENT
Welding Plant Unit 0.047 hr

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,119

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-55 Unit

Item Name : Supply and Fixing of steel ladder 5' dia upto 15' height with umbrella
railing complete in all respect

Detail Qty Unit


MATERIAL
Steel Ladder 5' dia and 1 Each
15' Height inclunding
railing

LABOUR
Labourer 1 Day
Welder 2 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.
4,120

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-56 Unit

Item Name : Providing and fixing steel gate of 16-18 SWG MS Sheet Gate with angle
iron frame (2"x2"x3/16") with side window, lock, painting etc M.S.
sheet covering including hold fast, with or without rollers and track
arrangement including providing wicket shutter of required size with
all accessories and locking arrangement complete

Detail Qty Unit


MATERIAL
Ordinary Portland Cement 0.0029 bag
Fine Sand 0.0069 cft
G.I pipe (light) 1.5" 0.1167 ft
Steel (Struct. Sections) 0.8143 Kg
M.S. sheet 22-24 SWG 0.7969 Kg
Items including GI 0.0278 no.
Bracket, Holdfast,
Spring, Handle, Rivets
and Greasing

LABOUR
Mason 0.01 Day
Labourer 0.0139 Day
Skilled Labour 0.0278 Day
Black Smith 0.1333 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,121

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK
CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-57 Unit

Item Name : Providing & Fixing of M.S Girder (WF 10x30) Duly painted including red
oxide primer, complete in all respects.

Detail Qty Unit


MATERIAL
Steel (Struct. Sections) 1 Rft
W10 x 30
Red Oxide primer 0.1 ltr

LABOUR
Mason 0.4332 Day
Labourer 0.1375 Day
Painter / Polisher 0.08 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,122

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-58-a Unit

Item Name : Supply and Fixing of 27-SWG CGI sheets on existing truss frame complete
in all respect.

Detail Qty Unit


MATERIAL
G.I. Plain sheet 27-SWG 1 Sft

LABOUR
Labourer 0.08 Day
Black Smith 0.08 Day
Sundries (Labour Only):
Contractor Profit 10% + Over Heads on(M+L+E) 2% +
Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,123

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-58-b Unit

Item Name : Providing and fixing of parking shed consisting of CGI Sheet, tubular
pipe frame (heavy) quality and circular columns excluding cost of
foundation.

Detail Qty Unit

MATERIAL
Welding Rod 0.0111 Packet
2.5" Nominal Pipe Size 0.22 Rft
-3/16" thick MS blind
pipe
3" Nominal Pipe Size 0.21 Rft
-3/16" thick MS blind
pipe
4" Nominal Pipe Size 0.1 Rft
-3/16" thick MS blind
pipe
Steel (Struct. Sections) 0.0944 kg
G.I. Plain sheet 27-SWG 1 Sft

LABOUR
Labourer 0.0111 Day
Welder 0.0111 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,124
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-58-c Unit

Item Name : Providing and fixing of parking shed consisting of fiber glass Sheet,
tubular pipe frame (heavy) quality and circular columns excluding cost
of foundation.

Detail Qty Unit

MATERIAL
Welding Rod 0.0111 Packet
2.5" Nominal Pipe Size 0.26 Rft
-3/16" thick MS blind
pipe
3" Nominal Pipe Size 0.22 Rft
-3/16" thick MS blind
pipe
4" Nominal Pipe Size 0.21 Rft
-3/16" thick MS blind
pipe
Steel (Struct. Sections) 0.0944 kg
Fiber Glass sheet 1 sft

LABOUR
Labourer 0.0111 Day
Welder 0.0111 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,125

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK


DESCRIPTION OF ITEM : Spec. No :
Item Code : 25-58-d Unit

Item Name : Providing and fixing of cantiliver type parking shed consisting of
fiber glass sheet, tubular pipe frame (heavy) quality , triangular
frame supports excluding cost of foundation.

Detail Qty Unit

MATERIAL
Welding Rod 0.05 Pkt
2.5" Nominal Pipe Size 0.5 Rft
-3/16" thick MS blind
pipe
3" Nominal Pipe Size 0.32 Rft
-3/16" thick MS blind
pipe
4" Nominal Pipe Size 0.42 Rft
-3/16" thick MS blind
pipe
Steel (Struct. Sections) 0.25 KG
Fiber Glass sheet 1 sft

LABOUR
Labourer 0.011 Day
Welder 0.011 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,126

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-59 Unit

Item Name : Making & Fixing of steel racks 1.5" depth i/e angle iron welding
jointing with 3- coats painting complete

Detail Qty Unit


MATERIAL
Paint : Enamel 0.0426 Ltr
Welding Rod 0.0128 Pack
Angle Iron M.S. Angle 1.4792 Rft
Iron 1½"x1½"x¼"
(40x40x6mm)
G.I. Plain sheet 27-SWG 1 Sft

LABOUR
Labourer 0.0026 Day
Painter / Polisher 0.0201 Day
Black Smith 0.0026 Day
Welder 0.0011 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,127

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-60-a Unit

Item Name : Supply and fixing razor wire (2'-0" dia) consisting of
1-1/2"X1-1/2"X3/16" angle iron Y post 2'-6" long 6' to 8' center to
center embedded in concrete block of size 3"X9"X6" (PCC 1:2:4), at top
of boundary wall including painting posts etc. Complete in all
respects.

Detail Qty Unit


MATERIAL
Ordinary Portland Cement 0.004 Bag
Fine Sand 0.008 Cft
Crushed Aggregate 0.016 Cft
Angle Iron M.S. Angle 0.2 Kg
Iron 1½"x1½"x¼"
(40x40x6mm)
M.S. Round bar ¾" 0.3 Kg
Razor Wire 0.5 Kg
LABOUR
Mason 0.01 Day
Labourer 0.02 Day
Black Smith 0.01 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,128

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-60-b Unit

Item Name : Supply and fixing razor wire (1'-6" dia) consisting of
1-1/2"X1-1/2"X3/16" angle iron Y post 2'-6" long 6' to 8' center to
center embedded in concrete block of size 3"X9"X6" (PCC 1:2:4), at top
of boundary wall including painting posts etc. Complete in all
respects.

Detail Qty Unit


MATERIAL
Ordinary Portland Cement 0.004 Bag
Fine Sand 0.008 Cft
Crushed Aggregate 0.016 Cft
Angle Iron M.S. Angle 0.2 Kg
Iron 1½"x1½"x¼"
(40x40x6mm)
M.S. Round bar ¾" 0.3 Kg
Razor Wire 1'-6" 11 SWG 0.375 Kg

LABOUR
Mason 0.01 Day
Labourer 0.02 Day
Black Smith 0.01 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,129

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-60-c Unit

Item Name : Supply and fixing razor wire (2'-0" dia) consisting of
1-1/2"X1-1/2"X3/16" angle iron Y post 2'-6" long 6' to 8' center to
center fixed with bolt anchorage, at top of boundary wall including
painting posts etc. Complete in all respects.

Detail Qty Unit


MATERIAL
Angle Iron M.S. Angle 0.2 Kg
Iron 1½"x1½"x¼"
(40x40x6mm)
M.S. Round bar ¾" 0.3 Kg
Steel (Struct. Sections) 0.12 Kg
Razor Wire 0.5 Kg

LABOUR
Mason 0.01 Day
Labourer 0.02 Day
Black Smith 0.01 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,130

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-60-d Unit

Item Name : Supply and fixing razor wire (1'-6" dia) consisting of
1-1/2"X1-1/2"X3/16" angle iron Y post 2'-6" long 6' to 8' center to
center fixed with bolt anchorage, at top of boundary wall including
painting posts etc. Complete in all respects.

Detail Qty Unit


MATERIAL
Angle Iron M.S. Angle 0.2 Kg
Iron 1½"x1½"x¼"
(40x40x6mm)
M.S. Round bar ¾" 0.3 Kg
Steel (Struct. Sections) 0.12 Kg
Razor Wire 1'-6" 11 SWG 0.375 Kg

LABOUR
Mason 0.01 Day
Labourer 0.02 Day
Black Smith 0.01 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,131

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 25 , IRON WORK

DESCRIPTION OF ITEM : Spec. No :


Item Code : 25-61 Unit

Item Name : Supply and fixing of steel door comprising of steel pipe frame of size
1.25" x 2.5" & 1.25" x 2.5" square pipe at lock rail & devider above
and below lock rail using 28 SWG plain sheet on both sides injcluding
hold fast, hinges & painting complete.

Detail Qty Unit


MATERIAL
Sand Paper 0.0357 Job
Welding Rod 0.125 Pack
Pipe 1.25"x2.5" square 1.3929 Rft
MS sheet 28 SWG paint 2 Sft
coated
Hinges 0.1429 No.
Sliding bolt 12" 0.0357 No.
Tower bolt 10" Heavy 0.0357 No.

LABOUR
Labourer 0.009 Day
Painter / Polisher 0.036 Day
Black Smith 0.054 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,132

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-a-01 Unit

Item Name : Double arm round conical Pole, Hot dipped galvanized (80 microns) 6
meters overall thickness 4mm Arm length 1.5 meters each with OD 60 mm,
base dia 150 mm and top dia 75mm with base plate arrangement 350mm x
350 mm x 20mm, 4 No of Stiffners (150mm 75mm 13mm), Complete in all
respects

Detail Qty Unit

MATERIAL
Double arm round conical 1 No
Pole 6 meter long

LABOUR
Electrician 0.25 Day
Sundries (Labour Only):

EQUIPMENT
Mobile Crane 10 Ton 1 Hour

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,133

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-a-02 Unit

Item Name : Single arm round conical Pole, hot dipped galvanized (80 microns) 6
meters overall thickness 4mm Arm length 1.5 meters each with OD 60 mm,
base dia 150 mm and top dia 75mm with base plate arrangement 350mm x
350 mm x 20mm, 4 No of Stiffners (150mm 75mm 13mm), Complete in all
respects

Detail Qty Unit

MATERIAL
Single arm round conical 1 No
pole 6 meter long

LABOUR
Skilled Labour 0.25 Day
Electrician 0.25 Day
Sundries (Labour Only):

EQUIPMENT
Mobile Crane 10 Ton 1 Hour

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,134

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC


DESCRIPTION OF ITEM : Spec. No :
Item Code : 26-01-a-03 Unit

Item Name : Double arm round Conical Pole, hot dipped galvanized (80 microns) 8
meters overall thickness 4mm Arm length 1.5 meters each with OD 60 mm,
base dia 180 mm and top dia 75mm with base plate arrangement 400mm x
400 mm x 20mm, 4 No of Stiffners (200mm x 100mm x 20mm), complete in
all respects

Detail Qty Unit


MATERIAL
Double arm round conical 1 No
Pole 8 meter long

LABOUR
Skilled Labour 0.33 Day
Electrician 0.33 Day
Sundries (Labour Only):

EQUIPMENT
Mobile Crane 10 Ton 1 Hour

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,135

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-a-04 Unit

Item Name : Single arm round conical Pole, hot dipped galvanized (80 microns) 8
meters overall thickness 4mm Arm length 1.5 meters each with OD 60 mm,
base dia 180 mm and top dia 75mm with base plate arrangement (400mm x
400 mm x 20mm), 4 No of Stiffners (200mm x 100mm x 20mm), complete in
all respects

Detail Qty Unit


MATERIAL
Single arm round conical 1 No
pole 8 meter long
LABOUR
Skilled Labour 0.33 Day
Electrician 0.33 Day
Sundries (Labour Only):

EQUIPMENT
Mobile Crane 10 Ton 1 Hour

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,136

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-a-05 Unit

Item Name : Double arm round conical Pole, hot dipped galvanized 10m overall
thickness 5mm Arm length 1.5 meters each with OD 60 mm, base dia 200
mm and top dia 100mm with base plate arrangement 450mm x 450 mm x 25mm,
Stiffners size (250mm x 100mm x 20mm), complete in all respects

Detail Qty
MATERIAL
Double arm round conical 1
Pole 10 meter long

LABOUR
Skilled Labour 0.5
Electrician 0.5
Sundries (Labour Only):

EQUIPMENT
Mobile Crane 10 Ton 1

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.
4,137

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-a-06 Unit

Item Name : Single arm round conical Pole, hot dipped galvanized 10m overall
thickness 5mm Arm length 1.5 meters each with OD 60 mm, base dia 200
mm and top dia 100mm with base plate arrangement 450mm x 450 mm x 25mm,
Stiffners size (250mm x 100mm x 20mm), Complete in all respects

Detail Qty
MATERIAL
Single arm round conical 1
pole 10 meter long

LABOUR
Skilled Labour 0.5
Electrician 0.5
Sundries (Labour Only):

EQUIPMENT
Mobile Crane 10 Ton 1

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,138

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-b-01
Item Name : Supply and Erection PVC flexible pipe
Detail Qty Unit
MATERIAL
1" dia PVC flexible pipe 1 Rft
LABOUR
Electrician 0.005 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,139

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-b-02
Item Name : Supply and Erection PVC flexible pipe
Detail Qty Unit
MATERIAL
1.5" dia PVC flexible 1 Rft
pipe

LABOUR
Electrician 0.005 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,140

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-b-03
Item Name : Supply and Erection PVC flexible pipe
Detail Qty Unit
MATERIAL
2" dia PVC flexible pipe 1 Rft

LABOUR
Electrician 0.005 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,141

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-c-01 Unit

Item Name : Supply and Erection of pole mounted SMD type light road light fixture
in Aluminium dia cast body with corrosioresisted powder coated finish
(30-40 watts) with 12/24V DC LED

Detail Qty Unit

MATERIAL
LED road Light fixture 1 No
30-40 Watt

LABOUR
Electrician 0.0625 Day
Crane operator / Driver 0.0625 Day
Sundries (Labour Only):

EQUIPMENT
Mobile Crane 10 Ton 0.05 Hour

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,142

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-c-02 Unit

Item Name : Supply and Erection of pole mounted SMD type light road light fixture
in Aluminium dia cast body with corrosion resisted powder coated finish
(60-70 watts) with 12/24V DC LED

Detail Qty Unit

MATERIAL
LED road Light 1 No
fixture60-70 Watt

LABOUR
Electrician 0.0625 Day
Crane operator / Driver 0.0625 Day
Sundries (Labour Only):

EQUIPMENT
Mobile Crane 10 Ton 0.5 Hour

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,143

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-c-03 Unit

Item Name : Supply and Erection of pole mounted SMD type light road light fixture
in Aluminium dia cast body with corrosion resisted powder coated finish
(90-100) with 12/24V DC LED

Detail Qty Unit


MATERIAL
LED road Light 1 No
fixture90-100 Watt

LABOUR
Electrician 0.0625 Day
Crane operator / Driver 0.0625 Day
Sundries (Labour Only):

EQUIPMENT
Mobile Crane 10 Ton 0.5 Hour

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,144

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-c-04 Unit

Item Name : Supply and Erection of pole mounted SMD type light road light fixture
in Aluminium dia cast body with corrosion resisted powder coated finish
(120-130) with 12/24V DC LED

Detail Qty Unit

MATERIAL
LED road Light 1 No
fixture120-130 Watt

LABOUR
Electrician 0.0625 Day
Crane operator / Driver 0.0625 Day
Sundries (Labour Only):

EQUIPMENT
Mobile Crane 10 Ton 0.5 Hour

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,145

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-c-05
Item Name :
Detail Qty Unit
MATERIAL
AC ENERGY EFFICIENT LED 1 No
LIGHT BULBS (7-10W)

LABOUR
Electrician 0.063 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,146

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-c-06
Item Name :
Detail Qty Unit
MATERIAL
AC ENERGY EFFICIENT LED 1 No
LIGHT BULBS (16-20W)

LABOUR
Electrician 0.063 Day
Sundries (Labour Only):
Contractor Profit 10% + Over Heads on(M+L+E) 2% +
Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,147

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-c-07
Item Name :
Detail Qty Unit
MATERIAL
AC ENERGY EFFICIENT LED 1 No
LIGHT BULBS (21-30W)

LABOUR
Electrician 0.063 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,148

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-c-08
Item Name :
Detail Qty Unit
MATERIAL
AC ENERGY EFFICIENT LED 1 No
LIGHT BULBS (31-50W)

LABOUR
Electrician 0.063 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,149

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-c-09
Item Name :
Detail Qty Unit
MATERIAL
DC ENERGY EFFICIENT LED 1 No
LIGHT BULBS (51-100 W)

LABOUR
Electrician 0.063 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,150

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-c-10
Item Name :
Detail Qty Unit
MATERIAL
AC ENERGY EFFICIENT LED 1 No
LIGHT BULBS (11-15 W)
LABOUR
Electrician 0.063 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,151

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-d-01 Unit

Item Name : Supply and Erection of Solar PV Module (Solar Panel) Mono-crystalline
A-Grade (per Watt) (As per Approved Specifications)

Detail Qty Unit


MATERIAL
Mono-crystalline A-Grade 1 Watt
Solar PV Module

LABOUR
Electrician 0.0006 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Watt Rs.
Labour Rates Per Watt Rs.

4,152

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-d-02 Unit
Item Name : Supply and Erection of Solar PV Module (Solar Panel) Poly-crystalline
A-Grade (per Watt) (As per Approved Specifications)

Detail Qty Unit


MATERIAL
Poly-crystalline A-Grade 1 Watt
Solar PV Module

LABOUR
Electrician 0.0006 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Watt Rs.
Labour Rates Per Watt Rs.

4,153

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-e-01 Unit

Item Name : Supply and Erection of MPPT Solar Light Charge Controller (10 Amps,
12/24 V) with all sort of electronic protections

Detail Qty Unit


MATERIAL
10 Amps, 12/24 V Charge 1 No
controller

LABOUR
Electrician 0.063 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,154

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-e-02 Unit

Item Name : Supply and Erection of MPPT Solar Light Charge Controller (15 Amps,
12/24 V) with all sort of electronic protections

Detail Qty Unit


MATERIAL
15 Amps, 12/24 V Charge 1 No
controler

LABOUR
Electrician 0.063 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,155

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-e-03 Unit

Item Name : Supply and Erection of MPPT Solar Light Charge Controller (20 Amps,
12/24 V) with all sort of electronic protections

Detail Qty Unit


MATERIAL
20 Amps, 12/24 V Charge 1 No.
controller

LABOUR
Electrician 0.063 Day
Sundries (Labour Only):
Contractor Profit 10% + Over Heads on(M+L+E) 2% +
Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,156

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-e-04 Unit

Item Name : Supply and Erection of MPPT Solar Light Charge Controller (30 Amps,
12/24 V) with all sort of electronic protections

Detail Qty Unit


MATERIAL
30Amps, 12/24 V Charge 1 No.
controller

LABOUR
Electrician 0.063 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,157

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-e-05 Unit

Item Name : Supply and Erection of MPPT Solar Light Charge Controller (40 Amps,
12/24 V) with all sort of electronic protections

Detail Qty Unit


MATERIAL
40Amps, 12/24 V Charge 1 No
controller

LABOUR
Electrician 0.063 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,158

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-e-06 Unit

Item Name : Supply and Erection of MPPT Solar Light Charge Controller (45 Amps,
12/24 V) with all sort of electronic protections

Detail Qty Unit


MATERIAL
45Amps, 12/24 V Charge 1 No.
controller

LABOUR
Electrician 0.063 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,159

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC


DESCRIPTION OF ITEM : Spec. No :
Item Code : 26-01-e-07 Unit

Item Name : Supply and Erection of MPPT Solar Light Charge Controller (50 Amps,
(12/24/48 V) with all sort of electronic protections

Detail Qty Unit


MATERIAL
50 Amps, 12/24/48 V 1 No
Charge controler

LABOUR
Electrician 0.063 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,160

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-e-08 Unit

Item Name : Supply and Erection of MPPT Solar Light Charge Controller (60 Amps,
(12/24/48 V) with all sort of electronic protections

Detail Qty Unit


MATERIAL
60 Amps, 12/24/48 V 1 No
Charge controler

LABOUR
Electrician 0.063 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.
4,161

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-f-01
Item Name : Supply and Erection of 12 V VRLA GEL battery per AH
Detail Qty Unit
MATERIAL
12 V VRLA GEL battery 1 AH

LABOUR
Electrician 0.003 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per AH Rs.
Labour Rates Per AH Rs.

4,162

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-f-02
Item Name : Supply and Erection of 12 V VRLA AGM Battery per AH
Detail Qty Unit
MATERIAL
12 V VRLA AGM Battery 1 AH

LABOUR
Electrician 0.003 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per AH Rs.
Labour Rates Per AH Rs.
4,163

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-f-03
Item Name : Supply and Erection of 12 V Lead Carbon Battery per AH
Detail Qty Unit
MATERIAL
12 V Lead Carbon Battery 1 AH

LABOUR
Electrician 0.003 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per AH Rs.
Labour Rates Per AH Rs.

4,164

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-f-04
Item Name : Supply and Erection of 12V OPzV battery per AH
Detail Qty Unit
MATERIAL
12V OPzV battery 1 AH

LABOUR
Electrician 0.003 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per AH Rs.
Labour Rates Per AH Rs.
4,165

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-f-05
Item Name : Supply and Erection of 12V OPzS battery per AH
Detail Qty Unit
MATERIAL
12V OPzS battery 1 AH

LABOUR
Electrician 0.003 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per AH Rs.
Labour Rates Per AH Rs.

4,166

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-f-06
Item Name :
Detail Qty Unit
MATERIAL
Lithium LiFeP04 battery 1 AH

LABOUR
Electrician 1 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per AH Rs.
Labour Rates Per AH Rs.
4,167

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-f-07
Item Name : Supply and Erection of
Detail Qty Unit
MATERIAL
2 V OPzV battery 1 AH

LABOUR
Electrician 0.001 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per AH Rs.
Labour Rates Per AH Rs.

4,168

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-f-08
Item Name : Supply and Erection of
Detail Qty Unit
MATERIAL
2 V OPzS battery 1 AH

LABOUR
Electrician 0.001 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per AH Rs.
Labour Rates Per AH Rs.
4,169

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-g-01
Item Name : Supply and Erection 1x2.5 sq.mm flexible copper cable
Detail Qty Unit
MATERIAL
1x2.5 sq.mm flexible 1 Rft
copper cable

LABOUR
Electrician 0.001 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,170

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-g-02
Item Name :
Detail Qty Unit
MATERIAL
1x4 sq.mm flexible copper 1 Rft
cable

LABOUR
Electrician 0.001 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,171

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-g-03 Unit

Item Name : Supply and Erection 1x6 sq.mm single core (XPLE/XPLO insulated/PCV
sheathed) flexible copper cable

Detail Qty Unit


MATERIAL
1x6 sq.mm flexible copper 1 Rft
cable

LABOUR
Electrician 0.001 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,172

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-g-04
Item Name : Supply and Erection 1x10 sq.mm flexible copper cable
Detail Qty Unit
MATERIAL
1x10 sq.mm flexible 1 Rft
copper cable

LABOUR
Electrician 0.001 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,173

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-g-05
Item Name : Supply and Erection 1x16 sq.mm Copper cable
Detail Qty Unit
MATERIAL
1x16 sq.mm Copper cable 1 Rft
DC

LABOUR
Electrician I 0.001 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,174

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-g-06
Item Name : Supply and Erection 1x25sq.mm Copper cable
Detail Qty Unit
MATERIAL
1x25sq.mm Copper cable DC 1 Rft
LABOUR
Electrician I 0.001 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,175

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-g-07
Item Name : Supply and Erection 1x35 sq.mm Copper cable
Detail Qty Unit
MATERIAL
1x35 sq.mm Copper cable 1 Rft
DC

LABOUR
Electrician I 0.001 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,176

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-g-08
Item Name : Supply and Erection 2x2.5 sq.mm flexible copper cable
Detail Qty Unit
MATERIAL
2x2.5 sq.mm flexible 1 Rft
copper cable

LABOUR
Electrician 0.001 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,177

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-g-09
Item Name : Supply and Erection 2x4 sq.mm flexible copper cable
Detail Qty Unit
MATERIAL
2x4 sq.mm flexible copper 1 Rft
cable

LABOUR
Electrician 0.001 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,178

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-g-10
Item Name : Supply and Erection 2x6 sq.mm flexible copper cable
Detail Qty Unit
MATERIAL
2x6 sq.mm flexible copper 1 Rft
cable

LABOUR
Electrician 0.001 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,179

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-g-11
Item Name : Supply and Erection 2x10 sq.mm flexible copper cable
Detail Qty Unit
MATERIAL
2x10 sq.mm flexible 1 Rft
copper cable

LABOUR
Electrician 0.001 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,180

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-g-12
Item Name : Supply and Erection 2x16 sq.mm Copper cable
Detail Qty Unit
MATERIAL
2x16 sq.mm Copper cable 1 Rft

LABOUR
Electrician 0.001 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,181

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-g-13
Item Name : Supply and Erection 2x25sq.mm Copper cable
Detail Qty Unit
MATERIAL
2x25sq.mm Copper cable 1 Rft

LABOUR
Electrician 0.001 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,182

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-g-14
Item Name : Supply and Erection 2x35 sq.mm Copper cable
Detail Qty Unit
MATERIAL
2x35 sq.mm Copper cable 1 Rft

LABOUR
Electrician 0.001 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,183

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-h-01
Item Name : Supply and Erection MC4 connector (TUV Approved)
Detail Qty Unit
MATERIAL
MC4 connector (TUV 1 Pair
Approved)

LABOUR
Electrician 0.0313 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Pair Rs.
Labour Rates Per Pair Rs.

4,184

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-h-02
Item Name : Supply and Erection MC4 Branch connector
Detail Qty Unit
MATERIAL
MC4 Branch connector 1 Pair

LABOUR
Electrician 0.0313 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Pair Rs.
Labour Rates Per Pair Rs.

4,185

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-i-01 Unit

Item Name : Supply and Erection of 3 Phase 220/380V Solar Pump inverter (MPPT) upto
1.1 KW

Detail Qty Unit


MATERIAL
3 Phase 220/380V Solar 1 Watt
Pump inverter (MPPT) upto
1.1 KW

LABOUR
Electrician 0.001 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Per Watt Rs.
Labour Rates Per Per Watt Rs.

4,186

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-i-02 Unit

Item Name : Supply and Erection of 3 Phase 220/380V Solar Pump inverter (MPPT) 1.2
to 2.9 KW

Detail Qty Unit


MATERIAL
3 Phase 220/380V Solar 1 Watt
Pump inverter (MPPT) 1.2
to 2.9 KW

LABOUR
Electrician 0.001 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Per Watt Rs.
Labour Rates Per Per Watt Rs.

4,187

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-i-03 Unit

Item Name : Supply and Erection of 3 Phase 220/380V Solar Pump inverter (MPPT) 3 KW
to 7 KW

Detail Qty Unit


MATERIAL
3 Phase 220/380V Solar 1 per Watt
Pump inverter (MPPT) 3 KW
to 7 KW

LABOUR
Electrician 0.001 Day
Sundries (Labour Only):
Contractor Profit 10% + Over Heads on(M+L+E) 2% +
Income Tax 7.5%
Composite Rates Per Per Watt Rs.
Labour Rates Per Per Watt Rs.

4,188

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-i-04 Unit

Item Name : Supply and Erection of 3 Phase 220/380V Solar Pump inverter (MPPT) 7.5
KW and above

Detail Qty Unit


MATERIAL
3 Phase 220/380V Solar 1 Per Watt
Pump inverter (MPPT) 7.5
KW and above

LABOUR
Electrician 0.001 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Per Watt Rs.
Labour Rates Per Per Watt Rs.

4,189

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-i-05
Item Name : Supply and Erection of off Grid Hybrid inverter
Detail Qty Unit
MATERIAL
OFF Grid / Hybrid 1
Inverter

LABOUR
Electrician 0.001 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Per Watt Rs.
Labour Rates Per Per Watt Rs.

4,190

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-i-06
Item Name : Supply and Erection of On Grid Hybrid inverter
Detail Qty Unit
MATERIAL
On Grid Hybrid Inverter 1

LABOUR
Electrician 0.001 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Per Watt Rs.
Labour Rates Per Per Watt Rs.

4,191

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-i-03-a
Item Name :
Detail Qty
MATERIAL
GRID TIE INVERTER 1
(ON-Grid Inverter) (0-10
KW)

LABOUR
Electrician 0.0005 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Per Watt Rs.
Labour Rates Per Per Watt Rs.

4,192

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-i-03-b
Item Name :
Detail Qty
MATERIAL
GRID TIE INVERTER 1
(ON-Grid Inverter) (10-20
KW)

LABOUR
Electrician 0.0005 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Per Watt Rs.
Labour Rates Per Per Watt Rs.

4,193

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK
CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-i-03-c
Item Name :
Detail Qty
MATERIAL
GRID TIE INVERTER 1
(ON-Grid Inverter)
(20-30KW)

LABOUR
Electrician 0.0005 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Per Watt Rs.
Labour Rates Per Per Watt Rs.

4,194

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-i-03-d Unit

Item Name : Supply and Erection of GRID TIE INVERTER (ON-Grid Inverter) (above 30
KW)

Detail Qty Unit


MATERIAL
GRID TIE INVERTER 1 Watt
(ON-Grid Inverter) (above
30 KW)

LABOUR
Electrician 0.0005 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Per Watt Rs.
Labour Rates Per Per Watt Rs.

4,195

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-j-01
Item Name :
Detail Qty Unit
MATERIAL
dV /dT or Sine Filters 11 1 No
KW to 18.5 KW

LABOUR
Electrician 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,196

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-j-02 Unit

Item Name : Supply and Erection of dV /dT or Sine Filter or dV/dT filter 22 KW to
45 KW

Detail Qty Unit


MATERIAL
dV /dT or Sine Filters 22 1 No
KW to 45 KW

LABOUR
Electrician 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,197

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-k-01 Unit

Item Name : Supply installation and commissioning of DC Submersible (1HP 1200W, 40


meter head)

Detail Qty Unit


MATERIAL
DC Submersible Pump (1 1 No
Hp)

LABOUR
Electrician 1 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,198

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-k-02 Unit

Item Name : Supply installation and commissioning of DC Submersible (2HP (2000w),


50 meter head)

Detail Qty Unit


MATERIAL
DC Submersible Pump (2 1 No
Hp)

LABOUR
Electrician 1 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,199

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-k-03 Unit

Item Name : Supply installation and commissioning of DC Submersible (3HP (3000w),


100 meter head)

Detail Qty Unit


MATERIAL
DC Submersible Pump (3 1 No
Hp)

LABOUR
Electrician 1 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,200

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-k-04 Unit

Item Name : Supply installation and commissioning of DC Submersible (5HP (5000w),


100 meter head)

Detail Qty Unit


MATERIAL
DC Submersible Pump (5 1 No
Hp)

LABOUR
Electrician 1 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,201

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-k-05 Unit

Item Name : Supply installation and commissioning of DC Submersible (10 HP (10 kw),
140 meter head)

Detail Qty Unit


MATERIAL
DC Submersible Pump (10 1 No
Hp)

LABOUR
Electrician 2 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,202

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-l-01
Item Name :
Detail Qty
MATERIAL
AC ENERGY EFFICIENT 1
CEILING FANS 56 inch, 50
W

LABOUR
Electrician 0.11 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,203

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-l-02
Item Name : Supply and Erection of DC CEILING FANS 48 inch 30-36 W
Detail Qty Unit
MATERIAL
DC CEILING FANS 48 inch 1 No
30-36 W

LABOUR
Electrician 0.11 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,204

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-l-03
Item Name : Supply and Erection of DC PEDISTAL FANS 18 inch 18-30
Detail Qty Unit
MATERIAL
DC PEDISTAL FANS 18 inch 1 No
18-30 W

LABOUR
Electrician 0.11 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,205

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-m-01 Unit

Item Name : Supply and Erection of hot dipped (80 microns Average) galvanized steel
of minimum thickness of 12 SWG / 2.64 mm Channel / Pipe or 8 SWG / 4.06
mm Angle
Detail Qty Unit

MATERIAL
hot dipped (80 microns 1 Watt

Average) galvanized steel


of minimum thickness of
12 SWG / 2.64 mm Channel
/ Pipe or 8 SWG / 4.06 mm
Angle

LABOUR
Electrician 0.001 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Per Watt Rs.
Labour Rates Per Per Watt Rs.

4,206

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-n-01
Item Name : Supply and Erection of Copper Conductor of 10 AWG
Detail Qty Unit
MATERIAL
Copper Conductor of 10 1 Watt
AWG

LABOUR
Electrician 0.001 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Watt Rs.
Labour Rates Per Watt Rs.

4,207
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-n-02
Item Name :
Detail Qty
MATERIAL
Copper Earthing Plate of 1
appropriate size and
design

LABOUR
Electrician 0.001 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Watt Rs.
Labour Rates Per Watt Rs.

4,208

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-n-03
Item Name :
Detail Qty
MATERIAL
Copper Earthing Plate of 1
appropriate size and
design

LABOUR
Electrician 0.001 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Watt Rs.
Labour Rates Per Watt Rs.

4,209

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM : Spec. No :


Item Code : 26-01-o Unit

Item Name : Supply and Erection of BOX / STAND for Batteries SHS Inverter & Charge
Controller

Detail Qty Unit


MATERIAL
BOX / STAND for Batteries 1 Watt
SHS Inverter & Charge
Controller

LABOUR
Electrician 0.001 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Watt Rs.
Labour Rates Per Watt Rs.

4,210

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-p-01
Item Name : Supply and Erection of INVERTER BASED SPLIT AC (01
Detail Qty Unit
MATERIAL
1 Ton 1 No
LABOUR
Electrician 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,211

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-p-02
Item Name : Supply and Erection of INVERTER BASED SPLIT AC (1.5
Detail Qty Unit
MATERIAL
1.5 Ton 1 No

LABOUR
Electrician 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,212

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-p-03
Item Name : Supply and Erection of INVERTER BASED SPLIT AC (02
Detail Qty Unit
MATERIAL
2 Ton 1 No
LABOUR
Electrician 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,213

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-q
Item Name :
Detail Qty Unit
MATERIAL
SOLAR AUTO TRACKER for 1 No
3.6 KW PV system

LABOUR
Electrician 1 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,214

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 26 , PHOTOVOLTAIC

DESCRIPTION OF ITEM :
Item Code : 26-01-r
Item Name :
Detail Qty Unit
MATERIAL
PV MOUNTING FRAME WITH 1 kW
MANUAL TRAKERING per kW

LABOUR
Electrician 0.031 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per kW Rs.
Labour Rates Per kW Rs.

4,215

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-01 Unit

Item Name : Repair of leakages in valve of already laid pipe line in trenches /
building i/c cost of extractiion / exvacation, complete in all respect
of the following sizes.
a) 3" to 6" dia of Valve

Detail Qty Unit


MATERIAL
Coal Tar (in canisters) 0.4 Kg
Welding Rod 0.15 Pack

LABOUR
Labourer 0.07 Day
Plumber 0.12 Day
Welder 0.11 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,216

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK
CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-02 Unit

Item Name : Repair of leakages in valve of already laid pipe line in trenches /
building i/c cost of extractiion / exvacation, complete in all respect
of the following sizes.
a) 1" to 2.5" dia of Valve

Detail Qty Unit


MATERIAL
Coal Tar (in canisters) 0.3 Kg
Tyflon Tape 0.35 Pack

LABOUR
Plumber 0.11 Day
Welder 0.1 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,217

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-03 Unit

Item Name : Removing of existing damaged rusted & chocked G.I pipe from 1/2" to 4 "
Nominal Pipe Size (NPS)

Detail Qty Unit


MATERIAL
Micelleanous Items for 1 RFT
Removing damaged rusted &
chocked G.I pipe from
1/2" to 4 "
LABOUR
Labourer 0.0039 Day
Plumber 0.0025 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,218

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-04 Unit

Item Name : Repairing & re-fixing of steel main gate i/c hold fast, welding
complete in all respects

Detail Qty Unit


MATERIAL
Welding Rod 0.0208

LABOUR
Labourer 0.0146 Day
Welder 0.0208 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,219

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-05 Unit
Item Name : Repair of existing G.I. damaged connection 1/2" to 4" dia i/c
required jointing of union,socket,nipple,elbow etc, complete in all
respect.

Detail Qty Unit

LABOUR
Plumber 0.1 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per each Rs.
Labour Rates Per each Rs.

4,220

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-06 Unit

Item Name : Repairing welding of suigas water heater 35-gallons capacity with
replacement of Centre pipe and Bottom sheet, complete In all respect
i/c carriage etc

Detail Qty Unit

MATERIAL
Size 20 mm (3/4") Nominal 6 RFT
Pipe Size (NPS) Medium
Quality Galvanized Iron
(G.I.) Pipe
Steel (Struct. Sections) 1 KG

LABOUR
Plumber 0.25 Day
Welder 0.06 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,221

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-07 Unit

Item Name : Replacement of rusted/leaking G.I water tank with new for water geyser
30/35 gallens

Detail Qty
MATERIAL
G.I. Water Tank 1

LABOUR
Labourer 0.5
Plumber 0.45
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,222

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-08 Unit

Item Name : Removing of glazed earthen ware WC European type of approved make/size
including cost of double seat & cover (plastic & bakelite), complete in
all respects: All Colours

Detail Qty Unit


MATERIAL
Removing of Washroom 1 Each

Accessories like
WC,WHB,WC
squatting,Mirror vanity,
Sink Soap Dish, Towel
Rail & Etc.

LABOUR
Skilled Labour 0.125 Day
Plumber 0.125 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,223

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-09 Unit

Item Name : Removing of glazed earthen ware WC squatting type, complete in all
respects: All Colours

Detail Qty Unit


MATERIAL
Removing of Washroom 1 Each
Accessories like
WC,WHB,WC
squatting,Mirror vanity,
Sink Soap Dish, Towel
Rail & Etc.

LABOUR
Skilled Labour 0.15 Day
Plumber 0.15 Day
Sundries (Labour Only):
Contractor Profit 10% + Over Heads on(M+L+E) 2% +
Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,224

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-10 Unit

Item Name : Removing of glazed earthen ware wash hand basin (WHB), complete in all
respects: All colours

Detail Qty Unit


MATERIAL
Removing of Washroom 1 Each
Accessories like
WC,WHB,WC
squatting,Mirror vanity,
Sink Soap Dish, Towel
Rail & Etc.

LABOUR
Skilled Labour 0.125 Day
Plumber 0.175 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,225

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE


DESCRIPTION OF ITEM : Spec. No :
Item Code : 27-11 Unit

Item Name : Removing of stainless steel sink with drain board, complete in all
respect.

Detail Qty Unit


MATERIAL
Removing of Washroom 1 Each
Accessories like
WC,WHB,WC
squatting,Mirror vanity,
Sink Soap Dish, Towel
Rail & Etc.

LABOUR
Labourer 0.275 Day
Plumber 0.2 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,226

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-12 Unit

Item Name : Removing terrazzo concrete sink, with drain board of mosaic, complete
in all respect

Detail Qty Unit


MATERIAL
Removing of Washroom 1 Each
Accessories like
WC,WHB,WC
squatting,Mirror vanity,
Sink Soap Dish, Towel
Rail & Etc.
LABOUR
Labourer 0.425 Day
Plumber 0.2 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,227

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-13 Unit

Item Name : Removing chorimum plated (CP) shower rose of approved quality complete
:
Size 1/2"x4" (15 mm x 100 mm)

Detail Qty Unit


MATERIAL
Removing of Washroom 1 No

Accessories like
WC,WHB,WC
squatting,Mirror vanity,
Sink Soap Dish, Towel
Rail & Etc.

LABOUR
Plumber 0.07 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,228
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-14-a Unit

Item Name : Furnishing and Installation thrust bearing for motor (10-25 H.P)
(V.H.S.) turbine

Detail Qty Unit


MATERIAL
Bearing for 10 - 25 HP 1 No.
motor

LABOUR
Labourer 0.25 Day
Black Smith 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,229

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-14-b Unit

Item Name : Furnishing and Installation thrust bearing for motor (30-50 H.P)
(V.H.S.) turbine

Detail Qty Unit


MATERIAL
Bearing for 30 - 50 HP 1 No.
motor

LABOUR
Labourer 0.25 Day
Black Smith 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,230

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-14-c Unit

Item Name : Furnishing and Installation ball bearing for Hollow Shaft Vertical
Elec. / Motor Turbine (10-25 H.P)

Detail Qty Unit


MATERIAL
Bearing for 10 - 25 Hp 1 No.
for Hollow Shaft

LABOUR
Labourer 0.25 Day
Black Smith 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,231

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-14-d Unit
Item Name : Furnishing and Installation ball bearing for Hollow Shaft Vertical
Elec. / Motor Turbine (30-50 H.P)

Detail Qty Unit


MATERIAL
Bearing for 30 - 50 HP 1 No.
motor for Hollow Shaft

LABOUR
Labourer 0.25 Day
Black Smith 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,232

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-15-a Unit

Item Name : Rewinding of Submersible electric motor i/c carriage from site of work
and back i/c testing installation complete with all respects: From 0.75
to 20 H.P

Detail Qty Unit

MATERIAL
Rewinding of Submersible 1 HP
Pump
From 0.75 to 20 H.P

LABOUR
Labourer 0.25 Day
Electrician 0.35 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per H.P Rs.
Labour Rates Per H.P Rs.

4,233

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-15-b Unit

Item Name : Rewinding of Submersible electric motor i/c carriage from site of work
and back i/c testing installation complete with all respects: Above 20
H.P

Detail Qty Unit

MATERIAL
Rewinding of Submersible 1 HP
Pump
Above 20 HP

LABOUR
Labourer 0.3 Day
Electrician 0.4 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per H.P Rs.
Labour Rates Per H.P Rs.

4,234

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-16-a Unit
Item Name : Rewinding of turbine electric motor i/c carriage from site of work and
back i/c testing installation complete with all respects: From 0.75 to
20 H.P

Detail Qty Unit

MATERIAL
Rewinding of Submersible 1 HP
Pump
From 0.75 to 20 H.P

LABOUR
Labourer 0.25 Day
Electrician 0.35 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per H.P Rs.
Labour Rates Per H.P Rs.

4,235

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-16-b Unit

Item Name : Rewinding of turbine electric motor i/c carriage from site of work and
back i/c testing installation complete with all respects: Above 20 H.P

Detail Qty Unit


MATERIAL
Rewinding of Submersible 1 HP
Pump
Above 20 HP

LABOUR
Labourer 0.3 Day
Electrician 0.4 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per H.P Rs.
Labour Rates Per H.P Rs.

4,236

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-17
Item Name : Supply and fixing of C.T Coil for Ampere meter
Detail Qty Unit
MATERIAL
C.T Coil 1 Each

LABOUR
Labourer 0.1 Day
Electrician 0.15 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,237

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-18-a Unit

Item Name : Extraction of Turbine/Submersible Pump & lowering/installation of the


same after necessary repair (0 to 200 ft)

Detail Qty
MATERIAL
Extraction of Submersible 1
Pump
(0 to 200 ft)
LABOUR
Labourer 0.4
Plumber 0.5
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,238

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-18-b Unit

Item Name : Extraction of Turbine/Submersible Pump & lowering/installation of the


same after necessary repair (Above 200 ft)

Detail Qty
MATERIAL
Extraction of Submersible 1
Pump
(Above 200 ft)

LABOUR
Labourer 0.5
Plumber 0.75
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,239

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE


DESCRIPTION OF ITEM :
Item Code : 27-19
Item Name : S/Fixing of Top nut any size
Detail Qty Unit
MATERIAL
Top Nut any size 1 Each

LABOUR
Plumber 0.04 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,240

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-20
Item Name : S/Fixing of Top shaft any size (Turbine/Submersible)
Detail Qty Unit
MATERIAL
Top shaft any size 1 Each
(Turbine/Submersible)

LABOUR
Plumber 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,241

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK
CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-21
Item Name : S/Fixing of staffing box gland
Detail Qty Unit
MATERIAL
Staffing box gland 1 Each

LABOUR
Plumber 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Set Rs.
Labour Rates Per Set Rs.

4,242

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-22
Item Name : S/Fixing of threaded coupling
Detail Qty Unit
MATERIAL
threaded coupling 1 Each

LABOUR
Plumber 0.1 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Set Rs.
Labour Rates Per Set Rs.

4,243

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK
CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-23-a
Item Name : Supply and Fixing for Coloumn Pipe Turbine
Detail Qty Unit
MATERIAL
Coloumn Pipe Turbine 1 Rft

LABOUR
Plumber 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,244

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-23-b
Item Name : For Stage (Turbine/Submersible)
Detail Qty Unit
MATERIAL
Stage 1 Rft
(Turbine/Submersible)

LABOUR
Plumber 0.2 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,245

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK
CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-24-a
Item Name :
Detail Qty Unit
MATERIAL
Rewinding of Voltage 1 Job
Regulator 3 Coil

LABOUR
Electrician 1 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,246

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-24-b
Item Name :
Detail Qty Unit
MATERIAL
Rewinding Voltage 1 No.
Regulator coil

LABOUR
Electrician 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No. Rs.
Labour Rates Per No. Rs.

4,247

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-25
Item Name : Repair of Voltage regulator point control machine
Detail Qty Unit
MATERIAL
Repair of Voltage 1 Job
regulator point

LABOUR
Electrician 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,248

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-26
Item Name : Repair of Voltage regulator point control machine
Detail Qty Unit
MATERIAL
Repair of Voltage 1 Job
regulator point

LABOUR
Electrician 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,249
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-27
Item Name : Replacement of pump shaft stainless steel
Detail Qty
MATERIAL
Replacement of pump shaft 1
stainless steel

LABOUR
Plumber 0.6
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No.
Labour Rates Per No.

4,250

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-28
Item Name : Replacement of Impellar
Detail Qty Unit
MATERIAL
Impellar 1 No

LABOUR
Plumber 0.6 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No. Rs.
Labour Rates Per No. Rs.
4,251

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-29
Item Name : Supply and Fixing of Column shaft Sleeve 20 to 30 mm
Detail Qty Unit
MATERIAL
Column shaft Sleeve 20 to 1 No
30 mm

LABOUR
Plumber 0.15 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No. Rs.
Labour Rates Per No. Rs.

4,252

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-30
Item Name : Replacement of Column pipe socket 3" to 6" i/d
Detail Qty Unit
MATERIAL
Column pipe socket 3" to 1 No
6" i/d

LABOUR
Plumber 0.3 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No. Rs.
Labour Rates Per No. Rs.

4,253

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-31
Item Name : Replacement of column shaft any size
Detail Qty Unit
MATERIAL
column shaft any size 1 No

LABOUR
Plumber 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No. Rs.
Labour Rates Per No. Rs.

4,254

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-32
Item Name : Replacement of wearing ring
Detail Qty Unit
MATERIAL
Replacement of wearing 1 No
ring

LABOUR
Plumber 0.15 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No. Rs.
Labour Rates Per No. Rs.

4,255

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-33
Item Name : Replacement of studs for intermediate bowl
Detail Qty Unit
MATERIAL
Studs for intermediate 1 No
bowl

LABOUR
Plumber 0.016 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No. Rs.
Labour Rates Per No. Rs.

4,256

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-34
Item Name : Replacement of nut, bolts of any size
Detail Qty Unit
MATERIAL
Nut, bolts of any size 1 No

LABOUR
Plumber 0.018 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No. Rs.
Labour Rates Per No. Rs.

4,257

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-35
Item Name : Repair/reconditioning of impellars
Detail Qty Unit
MATERIAL
Repair/reconditioning of 1 LS
impellars

LABOUR
Black Smith 0.275 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No. Rs.
Labour Rates Per No. Rs.

4,258

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-36
Item Name : Replacing the Submersible motor thrust bearing and disc
Detail Qty Unit
MATERIAL
motor thrust bearing and 1 No
disc

LABOUR
Labourer 0.25 Day
Electrician 0.75 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No. Rs.
Labour Rates Per No. Rs.

4,259

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-37 Unit

Item Name : Replacing the carbon bushes / steel bushes for submersible motor
complete

Detail Qty Unit


MATERIAL
carbon bushes Submersible 1 per set
motor

LABOUR
Labourer 0.25 Day
Black Smith 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,260

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-38
Item Name : Replacing of brass bush any size
Detail Qty Unit
MATERIAL
carbon bushes / steel 1 No
bushes

LABOUR
Black Smith 0.2 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,261

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-39
Item Name : Replacing of bearing bushes/houseing
Detail Qty Unit
MATERIAL
bearing bushes/houseing 1 per set

LABOUR
Black Smith 0.22 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,262

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-40
Item Name : Replacing of rubber packing 3" to 6"i/d
Detail Qty Unit
MATERIAL
ubber packing 3" to 6"i/d 1 Pair

LABOUR
Labourer 0.05 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Pair Rs.
Labour Rates Per Pair Rs.

4,263

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-41-a
Item Name : Rewinding of H.T Coil 25 KVA
Detail Qty Unit
MATERIAL
Rewinding H.T Coil 25 KVA 1 No

LABOUR
Electrician 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,264

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-41-b
Item Name : Rewinding of H.T Coil 50 KVA
Detail Qty Unit
MATERIAL
Rewinding of H.T Coil 50 1 No
KVA

LABOUR
Electrician 0.35 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,265

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-41-c
Item Name : Rewinding of H.T Coil 100 KVA
Detail Qty Unit
MATERIAL
Rewinding H.T Coil 100 1 No
KVA

LABOUR
Electrician 0.7 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,266

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-42-a
Item Name : Rewinding of L.T Coil 25 KVA
Detail Qty Unit
MATERIAL
Rewinding of L.T Coil 25 1 No
KVA

LABOUR
Electrician 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,267

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-42-b
Item Name : Rewinding of L.T Coil 50 KVA
Detail Qty Unit
MATERIAL
Rewinding of L.T Coil 50 1 No
KVA

LABOUR
Electrician 0.35 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,268

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE


DESCRIPTION OF ITEM :
Item Code : 27-42-c
Item Name : Rewinding of L.T Coil 100 KVA
Detail Qty Unit
MATERIAL
Rewinding of L.T Coil 100 1 No
KVA

LABOUR
Electrician 0.7 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,269

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-43
Item Name : Replacement of insulator (HT) Bush for 25 to 50 KVA
Detail Qty Unit
MATERIAL
(HT) Bush for 25 to 50 1 No
KVA

LABOUR
Black Smith 0.275 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No. Rs.
Labour Rates Per No. Rs.

4,270

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK
CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-44-a
Item Name : Replacement of Transformer L.T bush for 25 to 50 KVA
Detail Qty Unit
MATERIAL
L.T bush for 25 to 50 1 No
KVA

LABOUR
Electrician 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No. Rs.
Labour Rates Per No. Rs.

4,271

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-44-b
Item Name : Replacement of transfomer link of different KVS
Detail Qty Unit
MATERIAL
Transfomer link different 1 No
Kvs

LABOUR
Electrician 0.3 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No. Rs.
Labour Rates Per No. Rs.

4,272

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-45
Item Name : Replacement of S-Y-II unit for 25 to 100 KVA
Detail Qty Unit
MATERIAL
S-Y-II unit for 25 to 1 No
100 KVA

LABOUR
Electrician 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No. Rs.
Labour Rates Per No. Rs.

4,273

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-46
Item Name : Replacement of transformer oil
Detail Qty Unit
MATERIAL
Transformer oil 1 No

LABOUR
Electrician 0.07 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Liter Rs.
Labour Rates Per Liter Rs.

4,274
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-47 Unit

Item Name : Loading unloading of Transformer asper wapda specification &


installation with cariage complete for 25 to 100 KVA

Detail Qty Unit


MATERIAL
Miscellaneous items for 1 LS
loading unloading of
Transformer
Carriage 1 No

LABOUR
Electrician 1 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,275

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-48
Item Name : Rubber packing 1/32" to 1/16"thick
Detail Qty Unit
MATERIAL
Rubber packing 1/32" to 1 No
1/16"thick

LABOUR
Labourer 0.036 Day
Sundries (Labour Only):
Contractor Profit 10% + Over Heads on(M+L+E) 2% +
Income Tax 7.5%
Composite Rates Per No. Rs.
Labour Rates Per No. Rs.

4,276

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-49
Item Name : Replacement of gland dori
Detail Qty Unit
MATERIAL
gland dori 1 Rft

LABOUR
Labourer 0.03 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,277

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-50
Item Name : Replacing of Kit kat grips 60 to 200 Amp
Detail Qty Unit
MATERIAL
Kit kat grips 60 to 200 1 No
Amp

LABOUR
Electrician 0.125 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No. Rs.
Labour Rates Per No. Rs.

4,278

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-51
Item Name : Replacing of pressure gauge 0 to 500
Detail Qty Unit
MATERIAL
Pressure gauge 0 to 500 1 No

LABOUR
Black Smith 0.1458 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No. Rs.
Labour Rates Per No. Rs.

4,279

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-52
Item Name : Flexsible conduct pipe 1-1/2" to 2"dia
Detail Qty Unit
MATERIAL
Flexsible Conduct pipe 1 Rft
1-1/2" to 2"dia

LABOUR
Plumber 0.0417 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,280

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-53
Item Name : Replacing of clamps 3" to 6"s ize
Detail Qty Unit
MATERIAL
clamps 3" to 6"s ize 1 No

LABOUR
Labourer 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No. Rs.
Labour Rates Per No. Rs.

4,281

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-54
Item Name : Submersible plate
Detail Qty Unit
MATERIAL
Submersiblepump plate 1 No

LABOUR
Labourer 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No. Rs.
Labour Rates Per No. Rs.

4,282

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-55
Item Name : Cutting & threading MS column pipe of various size
Detail Qty Unit
MATERIAL
Miscelleaous items for 1 No
cutting & Threading

LABOUR
Black Smith 0.7 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,283

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-56-a Unit

Item Name : Replacing of single core cable of the following gauge (Cupper):
PVC Cable 7/064

Detail Qty Unit


MATERIAL
Single Core Cable PVC 1 Rft
Cable 7/064

LABOUR
Electrician 0.0313 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,284

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-56-b Unit

Item Name : Replacing of single core cable of the following gauge (Cupper):
PVC Cable 7/052

Detail Qty Unit


MATERIAL
Single Core Cable PVC 1 Rft
Cable 7/052

LABOUR
Electrician 0.0313 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,285

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE


DESCRIPTION OF ITEM : Spec. No :
Item Code : 27-56-c Unit

Item Name : Replacing of single core cable of the following gauge (Cupper):
PVC Cable 19/052

Detail Qty Unit


MATERIAL
Single Core Cable PVC 1 Rft
Cable 19/052

LABOUR
Electrician 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,286

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-56-d Unit

Item Name : Replacing of single core cable of the following gauge (Cupper):
PVC Cable 19/064

Detail Qty Unit


MATERIAL
Single Core Cable PVC 1 Rft
Cable 19/064

LABOUR
Electrician 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.
4,287

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-57-a Unit

Item Name : Replacing of 3 core submersible cable (cupper) of the following gauge.
14/16mm.

Detail Qty Unit


MATERIAL
3 core submersible cable 1 Rft
14/16 mm

LABOUR
Electrician 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,288

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-57-b Unit

Item Name : Replacing of 3 core submersible cable (cupper) of the following gauge.
25 mm

Detail Qty Unit


MATERIAL
3 core submersible cable 1 Rft
25 mm
LABOUR
Electrician 0.0938 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,289

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-58-a Unit

Item Name : Replacing of 4 core cable of the following gauge


PVC Cable 19/083

Detail Qty Unit


MATERIAL
4 Core PVC Cable 19/083 1 Rft

LABOUR
Electrician 0.0938 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,290

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-58-b Unit

Item Name : Replacing of 4 core cable of the following gauge


PVC Cable 19/064

Detail Qty Unit


MATERIAL
4 Core PVC Cable 19/064 1 Rft

LABOUR
Electrician 0.0938 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,291

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-59 Unit

Item Name : Test & develope tubewell of size 6" & above continously up to 1.5 cuse
cs (Air compressor)

Detail Qty Unit


MATERIAL
Test & develope tubewell 1 Hr
Size 6 "and above

LABOUR
Electrician 0.125 Day
Black Smith 0.125 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Hr Rs.
Labour Rates Per Hr Rs.

4,292

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-60
Item Name :
Detail Qty Unit
LABOUR
Skilled Labour 0.31 Day
Plumber 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Per Job Rs.
Labour Rates Per Per Job Rs.

4,293

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-61 Unit

Item Name : Making holes upto 3" dia, 18" depth in cement concrete or stone masonry
walls and repairing

Detail Qty Unit


LABOUR
Mason 0.1429 Day
Labourer 0.1429 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Per Job Rs.
Labour Rates Per Per Job Rs.

4,294

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK
CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-62
Item Name : Replacing kallar eaten bricks
Detail Qty Unit
MATERIAL
Burnt Brick 1 No

LABOUR
Mason 0.02 Day
Labourer 0.02 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,295

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-63
Item Name :
Detail Qty Unit
LABOUR
Mason 0.25 Day
Labourer 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,296

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK
CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-64 Unit

Item Name : Rubbing and polishing old grit/mosaic floor, including repairing voids,
uneven surface, complete

Detail Qty Unit


MATERIAL
Ordinary Portland Cement 0.007 Bag
Marble Chips 0.011 Bag

EQUIPMENT
Polisher with Machine 1 Sft
(Chemical)

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,297

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-65 Unit

Item Name : Rubbing & polishing grit floor, including repairing voids, uneven
surface, complete

Detail Qty Unit


MATERIAL
Ordinary Portland Cement 0.0125 Bag
Marble Chips 0.025 Bag

EQUIPMENT
Polisher with Machine 1 Sft
(Chemical)

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,298

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-66
Item Name : Racking and washing joints of stone masonry (old work)
Detail Qty Unit
LABOUR
Labourer 1 Day
Water Man 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,299

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-67
Item Name : Racking and washing joints of brick masonry (old work)
Detail Qty Unit
LABOUR
Labourer 0.5 Day
Water Man 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,300
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-68-a
Item Name : Petty repairs to Fire Place
Detail Qty Unit
MATERIAL
Petty Items of Repair 1 LS

LABOUR
Mason 0.14 Day
Skilled Labour 0.14 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,301

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-68-b
Item Name : Petty repairs to Floor
Detail Qty Unit
MATERIAL
Ordinary Portland Cement 0.03 Bag
Coarse Sand 0.08 Cft
Crushed Aggregate 0.15 Cft

LABOUR
Mason 0.025 Day
Labourer 0.0313 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,302

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-69-a-i Unit

Item Name : Removing and Fixing new approved heavy safety brass handle with
necessary screws of the same metal : 6''-7" Size

Detail Qty Unit


MATERIAL
Brass handle size 7" 1 No
Brass screw 1.25" size 6 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,303

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-69-a-ii Unit

Item Name : Removing and Fixing new approved heavy safety brass handle with
necessary screws of the same metal : 5" Size

Detail Qty Unit


MATERIAL
Brass handle size 5" 1 No
Brass screw 1.25" size 5 No
LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,304

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-69-a-iii Unit

Item Name : Removing and Fixing new approved heavy safety brass handle with
necessary screws of the same metal : 4" Size

Detail Qty Unit


MATERIAL
Brass handle size 4" 1 No
Brass screw 1.25" size 5 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,305

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-69-b-i Unit
Item Name : Removing and Fixing new approved heavy safety iron handle with
necessary screws of the same metal : 5" Size

Detail Qty Unit


MATERIAL
Iron handle 5" Size 1 No
Iron screw 1.25" Size 6 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,306

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-69-b-ii Unit

Item Name : Removing and Fixing new approved heavy safety iron handle with
necessary screws of the same metal : 4" Size

Detail Qty Unit


MATERIAL
Iron handle 4" Size 1 No
Iron screw 1.25" Size 5 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,307
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-69-b-iii Unit

Item Name : Removing and Fixing new approved heavy safety iron handle with
necessary screws of the same metal : 6''-7" Size (Chromium Plated)

Detail Qty Unit


MATERIAL
C.P. brass handle 7" size 1 No
C.P. brass screw (1.5") 6 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,308

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-70-a Unit

Item Name : Prfoviding and Fixing approved curved or circular 5/8" dia rod handle
upto 5" size with brass screws : Brass Handle

Detail Qty Unit


MATERIAL
C.P. brass handle 5" size 1 No
C.P. brass screw (1.5") 5 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):
Contractor Profit 10% + Over Heads on(M+L+E) 2% +
Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,309

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-70-b Unit

Item Name : Prfoviding and Fixing approved curved or circular 5/8" dia rod handle
upto 4" size with brass screws : Chromium Plated Handle

Detail Qty Unit


MATERIAL
C.P. brass handle 4" size 1 No
C.P. brass screw (1.5") 5 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,310

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-71 Unit

Item Name : Prfoviding and Fixing approved 6" size Fancy Brass Heavy Type door
handle with plate and screws.
Detail Qty Unit
MATERIAL
Brass handle with plate 1 No
Brass screw 1.25" size 6 No

LABOUR
Carpenter 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,311

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-72-a-i
Item Name :
Detail Qty Unit
MATERIAL
Brass hook & eye 6" 1 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,312

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-72-a-ii
Item Name :
Detail Qty Unit
MATERIAL
Brass hook & eye 4" 1 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,313

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-72-b-i Unit

Item Name : Removing and Fixing new approved section hook and eye : Galvanized Iron
6"

Detail Qty Unit


MATERIAL
G.I. hook & eye 6" 1 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,314

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE


DESCRIPTION OF ITEM : Spec. No :
Item Code : 27-72-b-ii Unit

Item Name : Removing and Fixing new approved section hook and eye : Galvanized Iron
4"

Detail Qty Unit


MATERIAL
G.I. hook & eye 4" 1 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,315

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-73
Item Name : Replacement of Aluminum door closer of approved quality
Detail Qty Unit
MATERIAL
Door closer of approved 1 No
quality

LABOUR
Carpenter 0.075 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,316

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-74-a Unit

Item Name : Removing & refixing cleats for doors & windows including hinges and
screws.

Detail Qty Unit


MATERIAL
Wood - Deodar 0.0353 Cft
Nails 0.06 Kg
Brass piano hinge 1 No

LABOUR
Carpenter 0.05 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,317

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-74-b
Item Name :
Detail Qty Unit
MATERIAL
Wood - Deodar 0.001 Cft
Nails 0.02 Kg
Brass Hook 1 No

LABOUR
Carpenter 0.05 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,318

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-74-c
Item Name : Removing & refixing Door stops of 1.5" dia rubber block
Detail Qty Unit
MATERIAL
Magnet Door Stop 1 No

LABOUR
Carpenter 0.0083 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,319

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-74-d
Item Name : Removing & refixing GI hook with clamps for doors
Detail Qty Unit
MATERIAL
G.I Hook With Clamps 1 No

LABOUR
Carpenter 0.0027 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,320

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-75
Item Name : Making deodar punkha pole 10'x6"x6"
Detail Qty Unit
MATERIAL
Wood - Deodar 2.5 Cft
Iron Hooks 24 No

LABOUR
Labourer 0.1 Day
Carpenter 0.2 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,321

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-76
Item Name : Dismantling and refixing eave boards
Detail Qty Unit
LABOUR
Labourer 0.0167 Day
Carpenter 0.0167 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,322

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-77
Item Name : Removing old paint from woodwork/steel with paint remove
Detail Qty Unit
MATERIAL
Paint Remover 0.25 Litre

LABOUR
Skilled Labour 0.2 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,323

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-78
Item Name : Brushing & scraping blisters of old paints from woodwork
Detail Qty Unit
LABOUR
Labourer 0.418 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.
4,324

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-79
Item Name :
Detail Qty Unit
LABOUR
Labourer 2 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,325

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-80
Item Name :
Detail Qty Unit
MATERIAL
Kerosene Oil 3.4 Ltr

LABOUR
Labourer 1 Day
Skilled Labour 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,326
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-81
Item Name : Removing with caustic soda,old paint from wood work
Detail Qty Unit
MATERIAL
Caustic Soda 0.5 Kg

LABOUR
Labourer 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,327

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-82
Item Name : Removing paint or varnish from wall
Detail Qty Unit
LABOUR
Labourer 1 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,328

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-83-a
Item Name : Scraping of Khanki paint from barrage gates
Detail Qty Unit
MATERIAL
Scraping Material 0.5 Doz

LABOUR
Labourer 0.12 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,329

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-83-b
Item Name : Scraping of Aluminium paint from barrage headworks
Detail Qty Unit
MATERIAL
Scraping Material 0.5 Doz

LABOUR
Labourer 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,330

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-84
Item Name : Scraping rust from old rails or girders
Detail Qty Unit
MATERIAL
Scraping Material 0.5 Doz

LABOUR
Labourer 1.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,331

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-85
Item Name : Chiselling old paint from brick work
Detail Qty Unit
MATERIAL
Scraping Material 0.5 Doz

LABOUR
Labourer 2 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,332

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-86
Item Name : Cleaning glasses with chalk and spirit etc
Detail Qty Unit
MATERIAL
Scraping Material 0.5 Doz

LABOUR
Labourer 1 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,333

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-87
Item Name : Cleaning and oiling rafter or rolled steel beams
Detail Qty Unit
MATERIAL
Diesel Oil 0.222 Ltr

LABOUR
Labourer 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,334

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-88
Item Name : Cleaning and painting punkha poles, including fixing hooks
Detail Qty Unit
MATERIAL
Brush II 0.013 No
Paint : Enamel 0.038 Ltr

LABOUR
Labourer 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,335

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-89 Unit

Item Name : Repainting of ceiling fan (all sizes & types) incl painting of blades,
canopy etc with syn. Enamel

Detail Qty Unit


MATERIAL
Brush II 0.12 No
Paint : Enamel 0.136 Ltr

LABOUR
Painter / Polisher 0.07 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.
4,336

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-90 Unit

Item Name : Repainting of iron poles with cross arms, with bitumen or other
approved paint

Detail Qty Unit


MATERIAL
Brush II 0.12 No
Paint : Enamel 0.59 Ltr

LABOUR
Labourer 0.5 Day
Painter / Polisher 0.166 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,337

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-91-a Unit

Item Name : Repainting of pipes and specials of GI, MS or PVC conduit etc : Upto
1.5" i/d

Detail Qty Unit


MATERIAL
Brush II 1.71 No
Paint : Enamel 1.4 Ltr
LABOUR
Painter / Polisher 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 RFT Rs.
Labour Rates Per 100 RFT Rs.

4,338

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-91-b Unit

Item Name : Repainting of pipes and specials of GI, MS or PVC conduit etc : From
1.5" to 2" i/d

Detail Qty Unit


MATERIAL
Brush II 1.71 No
Paint : Enamel 2.85 Ltr

LABOUR
Painter / Polisher 1 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 RFT Rs.
Labour Rates Per 100 RFT Rs.

4,339

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-91-c Unit
Item Name : Repainting of pipes and specials of GI, MS or PVC conduit etc : From 2"
to 4" i/d

Detail Qty Unit


MATERIAL
Brush II 2.571 No
Paint : Enamel 4.2 Ltr

LABOUR
Painter / Polisher 1.66 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 RFT Rs.
Labour Rates Per 100 RFT Rs.

4,340

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-92 Unit

Item Name : Repainting main switches & branch distribution boards of all sizes &
types with approved paint

Detail Qty Unit


MATERIAL
Brush II 0.16 No
Paint : Enamel 0.2 Ltr

LABOUR
Painter / Polisher 0.03 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,341
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-93 Unit

Item Name : Scarifying old road surface, including removal of debris within one
chain

Detail Qty Unit


LABOUR
Labourer 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,342

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-94 Unit

Item Name : Repair to cracks to reinforced or plain cement concrete work by


grouting with cement gun in (1:2) cement sand mortar including cutting
the chase of required size.

Detail Qty Unit

MATERIAL
Ordinary Portland Cement 1.05 Bag
Coarse Sand 2 Cft

LABOUR
Mason 1 Day
Labourer 1 Day
Water Man 0.25 Day
Chiseler 1 Day
Sundries (Labour Only):

EQUIPMENT
Hire Charges of cement 0.5 Hour
gun

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Rft Rs.
Labour Rates Per 100 Rft Rs.

4,343

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-95 Unit

Item Name : Dismantling bitumen carpet of any description from existing roads
surface including its removal and disposal within 3 chains lead as
desired.

Detail Qty Unit

LABOUR
Labourer 1 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,344

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-96 Unit
Item Name : Removing the existing worn out bitumanious surface having pot holes and
ruts in patches of regular shape brushing and re-carpeting with 1"
thick (consolidated) asphalt macadam as per specifications.

Detail Qty Unit

MATERIAL
Coarse Sand 2.5
1/2" size screened bajri 10
Liquid Asphalt 34
Wire Brush and Broom 1

LABOUR
Labourer 2.15
Sundries (Labour Only):

EQUIPMENT
Static Tandom Roller ( 8 0.167
T)
Tar Boiler 0.167
Concrete Mixer 1 bag 0.167

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,345

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-97 Unit

Item Name : Removing the existing worn out bitumanious surface pot holes and ruts
in patches of regular shape brushing and re-carpeting with 2"
thick(consolidated) asphalt macadam as per specificaiton complete

Detail Qty Unit

MATERIAL
Crushed Aggregate 26
Liquid Asphalt 43.2
Wire Brush and Broom 2
Lock of approved quality 5

LABOUR
Labourer 2.35
Sundries (Labour Only):

EQUIPMENT
Static Tandom Roller ( 8 0.227
T)
Tar Boiler 0.227
Concrete Mixer 1 bag 0.227

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,346

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-98 Unit

Item Name : Removing of existing worn out bitumanious surface pot holes and ruts in
patches and re-carpeting with 3" thick(consolidated) asphalt macadam
as per specifiedcomplete including disposal of excavated stuff within
one chain

Detail Qty
MATERIAL
Crushed Aggregate 38
Liquid Asphalt 51
Wire Brush and Broom 3
G.I. tee hinges 12" 7.5

LABOUR
Labourer 2.95
Sundries (Labour Only):

EQUIPMENT
Static Tandom Roller ( 8 0.394
T)
Tar Boiler 0.394
Concrete Mixer 1 bag 0.3939

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,347

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-99 Unit

Item Name : Clarification existing Base/Sub base / ploughed to a specified depth in


the drawings, and compacted specified density.

Detail Qty Unit


MATERIAL
Cloth 4.9514 Rft
Caustic Soda 0.45 Kg

LABOUR
Water Man 0.12 Day
Skilled Labour 0.23 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,348

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-100 Unit

Item Name : Tucking and chipping of road surface before hot surface dressing over
existing road.

Detail Qty Unit


LABOUR
Labourer 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,349

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-101 Unit

Item Name : Repair to pot holes including cleaning, brushing, removal of loose
material and filling of the same with clean stone of size 0.75" to 1.5"
with hot bitumen manual compaction with rammer (water bound 3% biutmen)

Detail Qty Unit

MATERIAL
Fuel Wood 9.33 Kg
Wire Brush and Broom 1 No
Crushed aggregate 0.75" 20 Cft
to 1.5
Crushed aggregate 0.25" 9.5143 Cft
to 0.5
Bitumen 3 % (in Drums) 30 Kg

LABOUR
Labourer 3.04 Day
Water Man 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.
4,350

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-102
Item Name : Repairs to hand pump, pulling out & refitting
Detail Qty Unit
LABOUR
Labourer 0.012 Day
Black Smith 0.05 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,351

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-103-a
Item Name : Recaning of chairs/stools : With plastic cane.
Detail Qty Unit
MATERIAL
Plastic Cane 0.75 Kg

LABOUR
Canner 1.2 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per kg Rs.
Labour Rates Per kg Rs.

4,352
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-103-b
Item Name : Recaning of chairs/stools : With willow cane.
Detail Qty Unit
MATERIAL
Cane 1.916 Kg

LABOUR
Canner 0.35 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per kg Rs.
Labour Rates Per kg Rs.

4,353

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-104-a Unit

Item Name : Dismantling removing and stacking of heavy design steel grill from
compound wall & re-fixing painting complete.

Detail Qty Unit


LABOUR
Labourer 0.228 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Ton Rs.
Labour Rates Per Ton Rs.

4,354
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-104-b Unit

Item Name : Removing, Repairing, re-fixing of wooden joinery i/c replacement of


Deodar wooden strips, nail etc.

Detail Qty Unit


MATERIAL
Wood - Deodar 0.021 Dft
Nails 0.08 Kg
Glue 0.01 Kg

LABOUR
Carpenter 0.0125 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,355

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-104-c Unit

Item Name : Repair of almirah/wardrobe i/c replacement of wooden strips, sheet,


hinges where required complete in all respects.

Detail Qty Unit


MATERIAL
Wood - Deodar 0.0036 Cft
Nails 0.0002 Kg
Screw 0.0009 Kg
Hinges 5" 0.0025 Doz
LABOUR
Labourer 0.0008 Day
Carpenter 0.0011 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,356

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-105-a
Item Name : Cleaning of choked manhole
Detail Qty Unit
LABOUR
Labourer 0.75 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,357

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-105-b
Item Name : Cleaning of septic tank including disposal of waste
Detail Qty Unit
LABOUR
Labourer 0.094 Day
Sundries (Labour Only):
Contractor Profit 10% + Over Heads on(M+L+E) 2% +
Income Tax 7.5%
Composite Rates Per Cft Rs.
Labour Rates Per Cft Rs.

4,358

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-106 Unit

Item Name : Preparing surface using chemical and applying lacquer polish finish
with 3-coats on existing wooden joinery complete in all respects.

Detail Qty Unit


MATERIAL
Lacquer Polish 0.055 Ltr

LABOUR
Painter / Polisher 0.0125 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,359

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-107 Unit

Item Name : Removing, Repairing & Fixing of aluminium joinery i/c opening of frame
with rubber packing complete

Detail Qty Unit


MATERIAL
Screw 0.12 Kg
Rubber Packing 4 Rft

LABOUR
Aluminum Fixer 0.125 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,360

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-108 Unit

Item Name : Removing & re-fixing of wooden joinery (doors & windows) i/e addition
and alteration complete

Detail Qty Unit


MATERIAL
Wood - Deodar 0.005 Cft
Nails 0.07 Kg
Glue 0.095 Kg

LABOUR
Carpenter 0.01 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,361

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE


DESCRIPTION OF ITEM : Spec. No :
Item Code : 27-109-a Unit

Item Name : Removing of existing wire guaze & re-fixing GI wire gauze of 22 guage
and 12 mesh per square inch complete in all respects

Detail Qty Unit


MATERIAL
Wire Gauze - 22 SWG 1 Sft

LABOUR
Carpenter 0.075 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,362

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-109-b Unit

Item Name : Removing of existing wire guaze & re-fixing plastic wire gauze with 22
mesh per square inch complete in all respects

Detail Qty Unit


MATERIAL
Plastic Wire Gauze 1 Sft

LABOUR
Carpenter 0.075 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,363
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-109-c Unit

Item Name : Removing of existing aluminum wire guaze & re-fixing Aluminum wire
gauze of 30 guage and 14 mesh per square inch complete in all respects

Detail Qty Unit


MATERIAL
Aluminum Wire Gauze 1 Sft

LABOUR
Carpenter 0.075 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,364

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-110 Unit

Item Name : Removing, repairing and re-Fixing of wooden (heavy) sheesham railing
i/c rawal bolts, painting complete in all respects

Detail Qty Unit


MATERIAL
Nails 0.07 Kg
Rawal Bolts 4 No
Sand Paper 0.025 Doz
Lacquer Polish 0.3 Ltr

LABOUR
Carpenter 0.1 Day
Painter / Polisher 0.085 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,365

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-111
Item Name : Removing and Re-Fixing of aluminium windows
Detail Qty
LABOUR
Labourer 1.25
Aluminum Fixer 0.25
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,366

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-112-a Unit

Item Name : Repair of aluminium door/windows, fly sutter screen openable door or
window R/q handle rubber, silicon complete in all respects

Detail Qty Unit


MATERIAL
Screw 0.01 Pkt
Silicon 0.01 Ltr
Rubber Packing 1 Rft

LABOUR
Aluminum Fixer 0.015 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,367

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-112-b Unit

Item Name : Repair of wooden wardrobe =of required wooden batten, hinges, hasp
staple or commercial ply 3/4" shelf

Detail Qty Unit


MATERIAL
Ply Commercial 0.2 Sft
Nails 0.0072 Kg
Screw 0.0268 Pkt
Hinges 5" 0.01 1 Doz
Hasp and Staple Iron 0.02 No

LABOUR
Labourer 0.05 Day
Carpenter 0.05 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,368

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-112-c Unit

Item Name : Removing, repairing, cleaning, washing of vertical blind curtain &
re-fixing complete

Detail Qty Unit


MATERIAL
Screw 0.07 Kg
Washing powder 0.5 Kg
Sockets 3/4'' dia 2 No
Rod 4 Rft

LABOUR
Labourer 0.0625 Day
Skilled Labour 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,369

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-113
Item Name : Repair of doors/windows complete
Detail Qty Unit
MATERIAL
Iron Holdfasts 1-1/2x1/4 0.0015 kg
Wood - Deodar 0.001 Cft
Nails 0.0072 Kg
Screw 0.0268 Pkt
Hinges 5" 0.0179 Doz
Hinger Chocks / Lock 0.0715 No
Handles 6" 0.1071 No
Door Stops 6 " 0.012 1 No
Glass 3mm Local 0.11 Sft
Tower bolt 9" 0.014 No

LABOUR
Labourer 0.015 Day
Carpenter 0.015 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,370

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-114
Item Name : Reinstatement Of Road Surface
Detail Qty
LABOUR
Labourer 0.1239
Helper 0.1239
Sundries (Labour Only):

EQUIPMENT
Bull Dozer 90 HP 0.3716
Front End Loader 2.5 m³ 0.3716
Motor Grader 140 HP 0.2477
Dumper ( 10 T ) 1.8581
Pump 4" delivery (Diesel) 0.2477
Water Tank Bowser Type 0.3716
12000 l
Combination Roller 18T 0.6194

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 1000 Cft Rs.
Labour Rates Per 1000 Cft Rs.

4,371
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-115 Unit

Item Name : Repair / refixing of kitchen wall cabinet i/c commercial ply, new
drawers, fancy handle, shutter etc required for painting.

Detail Qty Unit


MATERIAL
Wood - Deodar 0.05 Cft
Lamination Board 1 sft
Nails 0.042 Kg
Spring Hinges 0.12 No
Handle Brass 6" 0.5 No

LABOUR
Labourer 0.125 Day
Carpenter 0.125 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,372

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-116 Unit

Item Name : Repairs to plaster of thickness 1/2" to 3/4" in cement sand mortar 1:4
patches of area 27 Sft and under, including cutting the patch in proper
shape, raking out joints and preparing and plastering the surface of
the walls complete, including disposal of rubbish to the dumping ground
within 30 metres lead.

Detail Qty Unit


MATERIAL
Scaffolding (for Plaster) 20 Sft
Cement Sand Mortar 1:4 6.0065 Cft
(Rate as per 5-23)

LABOUR
Mason 1 Day
Labourer 1.25 Day
Water Man 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,373

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :

Item Code : 27-117 Unit

Item Name : Fixing door chowkat in existing opening including embeddin


floors or walls cutting masonry for holdfasts, embedding hold fasts in
cement concrete blocks of size 6"x4"x4", with cement concrete 1:3:6 (1
cement : 3 coarse sand : 6 aggregate), painting two coats of approved
wood preservative to sides of chowkhats and making good the damages to
walls and floors as required complete, including disposal of debris to
the dumping ground within 30 meters lead.

Detail Qty Unit


MATERIAL
Ordinary Portland Cement 0.132 Bag
Coarse Sand 0.498 Cft
Crushed Aggregate 2 Cft

LABOUR
Mason 0.0132 Day
Labourer 0.0465 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,374

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-118 Unit

Item Name : Making the opening in brick masonry including dismantling in floor or
walls by cutting masonry and making good the damages to walls and jambs
complete, to match existing surface i/c disposal of debris to the
nearest municipal dumping ground.

Detail Qty Unit


MATERIAL
Cement Sand Mortar 1:6 0.0168 Cft
(Rate as per 5-25)

LABOUR
Mason 0.0238 Day
Labourer 0.0762 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,375

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-119 Unit

Item Name : Renewing wooden battens in roofs, including making good the holes in
wall and painting with oil type wood preservative of approved brand and
manufacture complete, including removal of rubbish to the dumping
ground within 30 metres lead:

Detail Qty Unit


MATERIAL
Wood - Deodar 1 Cft
Lacquer Polish 0.11 Ltr

LABOUR
Labourer 0.1968 Day
Carpenter 0.0451 Day
Painter / Polisher 0.0165 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Cft Rs.
Labour Rates Per Cft Rs.

4,376

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-120 Unit

Item Name : Raking out joints in lime or cement mortar and preparing the surface
for re-pointing or replastering,including disposal of rubbish to the
dumping ground within 50 metres lead.

Detail Qty Unit

LABOUR
Labourer 0.5269 Day
Water Man 0.0605 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,377
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-121 Unit

Item Name : Removing white or colour wash by scrapping and sand papering and
preparing the surface smooth including necessary repairs to scratches
etc. complete.

Detail Qty Unit

LABOUR
Labourer 0.0012 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,378

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-122 Unit

Item Name : Removing distemper, water proofing cement paint and the like by
scrapping, sand papering and preparing the surface smooth including
necessary repairs to scratches etc. complete.

Detail Qty Unit

MATERIAL
Sand Paper 0.0048 Doz

LABOUR
Labourer 0.0015 Day
Sundries (Labour Only):
Contractor Profit 10% + Over Heads on(M+L+E) 2% +
Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,379

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-123 Unit

Item Name : Painting on old G.I. sheet with synthetic enamel paint of approved
quality of required colour to give an even shade:

Detail Qty
MATERIAL
Paint : Enamel 0.0043

LABOUR
Labourer 0.0033
Painter / Polisher 0.0033
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,380

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-124 Unit

Item Name : Providing and fixing deodar wood First class wooden curtain rods 1" to
1.25" (25mm to 32mm) dia with end stay.

Detail Qty Unit


MATERIAL
Wood - Deodar 0.0123 Cft

LABOUR
Labourer 0.0134 Day
Carpenter 0.0067 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,381

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-125 Unit

Item Name : Providing and fixing 3/4" (19mm) dia. approved Brass tubes with Brass
sockets as curtain rods.

Detail Qty Unit


MATERIAL
Brass screw 3/4" size 1.2857 No
Brass tube 3/4" dia 1 Rft
Brass socket 3/4" dia 0.5714 No

LABOUR
Carpenter 0.0089 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,382

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK
CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-126 Unit

Item Name : Providing and fixing 3/4" (19mm) dia. approved Chromium Plated Brass
tubes with Chromium Plated Brass sockets as curtain rods.

Detail Qty Unit


MATERIAL
C.P. brass screw (1.5" ) 1.2857 No
C.P. brass tube 3/4" dia. 1 Rft
C.P. brass socket 3/4" 0.5714 No
dia.

LABOUR
Carpenter 0.0089 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,383

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-127 Unit

Item Name : Providing and fixing Chromium Plated curtain rails with double roller
runners, clamps, including cost of Chromium Plated brass screws and
rawl plugs.

Detail Qty Unit

MATERIAL
C.P. brass screw (1.5" ) 1.2857 No
C.P. brass curtain rail 1 Rft
Brass rollers 3.2143 No
C.P. brass clamp 1.4286 No
Rawal plug 1" long 1.0714 No
Brass stopper 0.6429 No
LABOUR
Labourer 0.0179 Day
Carpenter 0.0357 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,384

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-128 Unit

Item Name : Providing and fixing Aluminium curtain rails with double roller
runners, clamps, including cost of screws and rawl plugs.

Detail Qty Unit


MATERIAL
C.P. brass screw (1.5" ) 1.2857 No
C.P. brass curtain rail 1 Rft
Brass rollers 3.2143 No
C.P. brass clamp 1.4286 No
Rawal plug 1" long 1.0714 No
Brass stopper 0.6429 No

LABOUR
Labourer 0.0179 Day
Carpenter 0.0357 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,385

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-129-a-i Unit

Item Name : Replacement of existing door lock with new door lock. : Rim Lock
(Local)

Detail Qty Unit


MATERIAL
Screw 0.0852 Kg
Rim Lock (Local) 1 No

LABOUR
Carpenter 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,386

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-129-a-ii Unit

Item Name : Replacement of existing door lock with new door lock. : Heavy Duty Rim
Lock

Detail Qty Unit


MATERIAL
Screw 0.2727 Kg
Heavy Duty Rim Lock 1 No

LABOUR
Carpenter 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,387

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-129-a-iii Unit

Item Name : Replacement of existing door lock with new door handle lock of imported
quality heavy duty

Detail Qty Unit


MATERIAL
Screw 0.4545 Kg
Heavy Duty Handle Lock of 1 No
imported quality

LABOUR
Carpenter 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,388

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-129-c Unit

Item Name : Replacement of existing floor hinges with new floor hinges. : Floor
Hinges

Detail Qty Unit


MATERIAL
Screw 1.1364 Kg
Floor Hinges of approved 1 No
quality

LABOUR
Carpenter 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,389

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-130 Unit

Item Name : Replacement of existing brass drawer and cupboard lock with brass
screws.

Detail Qty Unit


MATERIAL
Screw 0.0852 Kg
Lock of approved quality 1 No

LABOUR
Carpenter 0.125 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,390

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK
CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-131-a Unit

Item Name : Replacement of existing finger plate with screws. : Aluminium finger
plate 6" x 2.25"

Detail Qty Unit


MATERIAL
Aluminium finger plate 1 No
Aluminium screw 3/4" size 6 No

LABOUR
Carpenter 0.0938 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,391

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-131-b Unit

Item Name : Replacement of existing finger plate with screws. : Brass finger plate
6" x 2.25"

Detail Qty Unit


MATERIAL
Brass finger plate 1 No
Brass screw 3/4" size 6 No

LABOUR
Carpenter 0.0938 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,392

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-132-a-i Unit

Item Name : Replacement of existing approved helical brass spring hinges 6" (150mm)
size with brass screws. : Single action

Detail Qty Unit


MATERIAL
Brass helical spring 4" - 1 No
single action
Brass screw 1.25" size 9 No

LABOUR
Carpenter 0.0813 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,393

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-132-a-ii Unit

Item Name : Replacement of existing helical brass spring hinges 6" (150mm) size
with brass screws. : Double action

Detail Qty Unit


MATERIAL
Brass helical spring 6" - 1 No
double action
Brass screw 1.25" size 9 No

LABOUR
Carpenter 0.1 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,394

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-132-b-i Unit

Item Name : Replacement of existing helical iron spring hinges 6" (150mm) size
with iron screws. : Single action

Detail Qty Unit


MATERIAL
Iron screw 1.25" Size 9 No
Iron spring hinges 6" - 1 No
single action

LABOUR
Carpenter 0.0813 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,395

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK
CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-132-b-ii Unit

Item Name : Replacement of existing helical iron spring hinges 6" (150mm) size
with iron screws. : Double action

Detail Qty Unit


MATERIAL
Iron screw 1.25" Size 9 No
Iron spring hinges 6" - 1 No
double action

LABOUR
Carpenter 0.1 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,396

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-133-a Unit

Item Name : Replacement of existing piano hinges of sheet 3/4" (19mm) wide with
brass screws. : Brass piano hinges

Detail Qty Unit


MATERIAL
Brass screw 3/4" size 9 No
Brass piano hinge 5 No

LABOUR
Carpenter 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,397

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-133-b Unit

Item Name : Replacement of existing piano hinges of sheet 3/4" (19mm) wide with
brass screws. : Iron piano hinges

Detail Qty Unit


MATERIAL
Iron piano hinge 5 No
Iron screw 3/4" 9 No

LABOUR
Carpenter 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,398

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-134-a-i Unit

Item Name : Replacement of existing parliament hinges with screws. : Brass


parliament hinges 5" x 5", 12 SWG

Detail Qty Unit


MATERIAL
Brass parliament hinges 1 No
5" x 5"
Brass screw 1.5" size 12 No

LABOUR
Carpenter 0.075 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,399

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-134-a-ii Unit

Item Name : Replacement of existing parliament hinges with screws. : Brass


parliament hinges 4" x 4", 12 SWG

Detail Qty Unit


MATERIAL
Brass screw 1.5" size 12 No
Brass helical spring 6" - 1 No
single action

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,400

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK
CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-134-b-i Unit

Item Name : Replacement of existing parliament hinges with screws. : Iron


parliament hinges 5" x 5", 12 SWG

Detail Qty Unit


MATERIAL
Iron parliament hinges 5" 1 No
x 5"
Iron screw 1.5" 12 No

LABOUR
Carpenter 0.075 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,401

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-134-b-ii Unit

Item Name : Replacement of existing parliament hinges with screws. : Iron


parliament hinges 4" x 4", 12 SWG

Detail Qty Unit


MATERIAL
Iron screw 1.5" 12 No
Iron parliament hinges 4" 1 No
x 4"

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):
Contractor Profit 10% + Over Heads on(M+L+E) 2% +
Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,402

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-135-a Unit

Item Name : Replacement of existing heavy type G.I tee hinges with screws. : Tee
hinges 18"

Detail Qty Unit


MATERIAL
Iron screw 1.5" 6 No
G.I. tee hinges 18" 1 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,403

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-135-b Unit

Item Name : Replacement of existing heavy type G.I tee hinges with screws. : Tee
hinges 12"
Detail Qty Unit
MATERIAL
Iron screw 1.5" 6 No
G.I. tee hinges 12" 1 No

LABOUR
Carpenter 0.075 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,404

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-135-c Unit

Item Name : Replacement of existing heavy type G.I tee hinges with screws. : Tee
hinges 10"

Detail Qty Unit


MATERIAL
Iron screw 1.5" 6 No
G.I. tee hinges 10" 1 No

LABOUR
Carpenter 0.075 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,405

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK
CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-136-a-i Unit

Item Name : Replacement of existing tower bolts with screws of same metal. : Brass
tower bolts of 6" Size

Detail Qty Unit


MATERIAL
Brass screw 3/4" size 6 No
Tower Bolt 6" 1 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,406

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-136-a-ii Unit

Item Name : Replacement of existing tower bolts with screws of same metal. : Brass
tower bolts of 9" Size

Detail Qty Unit


MATERIAL
Brass screw 3/4" size 8 No
Tower bolt 9" 1 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,407

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-136-a-iii Unit

Item Name : Replacement of existing tower bolts with screws of same metal. : Brass
tower bolts of 12" Size

Detail Qty Unit


MATERIAL
Brass screw 3/4" size 12 No
Tower bolt 12" 1 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,408

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-136-b-i Unit

Item Name : Replacement of existing tower bolts with screws of same metal.
:Chromium plated brass tower bolts of 6" Size

Detail Qty Unit


MATERIAL
Brass screw 3/4" size 6 No
C.P. brass tower bolt 6" 1 No
LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,409

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-136-b-ii Unit

Item Name : Replacement of existing tower bolts with screws of same metal.
:Chromium plated brass tower bolts of 9" Size

Detail Qty Unit


MATERIAL
Brass screw 3/4" size 8 No
C.P. brass tower bolt 9" 1 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,410

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-136-b-iii Unit
Item Name : Replacement of existing tower bolts with screws of same metal. :
Chromium plated brass tower bolts of 12" Size

Detail Qty Unit


MATERIAL
Brass screw 3/4" size 12 No
C.P. brass tower bolt 12" 1 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,411

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-136-c-i Unit

Item Name : Replacement of existing tower bolts with screws of same metal. :
Aluminium tower bolts of 4" Size

Detail Qty Unit


MATERIAL
Brass screw 3/4" size 6 No
Aluminium tower bolt 4" 1 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,412
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-136-c-ii Unit

Item Name : Replacement of existing tower bolts with screws of same metal. :
Aluminium tower bolts of 6" Size

Detail Qty Unit


MATERIAL
Brass screw 3/4" size 6 No
Aluminium tower bolt 6" 1 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,413

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-136-c-iii Unit

Item Name : Replacement of existing tower bolts with screws of same metal. :
Aluminium tower bolts of 8" Size

Detail Qty Unit


MATERIAL
Brass screw 3/4" size 6 No
Aluminium tower bolt 8" 1 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):
Contractor Profit 10% + Over Heads on(M+L+E) 2% +
Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,414

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-137-a-i Unit

Item Name : Replacement of existing heavy duty safety hasp and staple with
necessary screws of the same metal. : Brass hasp and staple of Size 5"

Detail Qty Unit


MATERIAL
Brass screw 3/4" size 7 No
Brass hasp & staple 5" 1 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,415

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-137-a-ii Unit

Item Name : Replacement of existing heavy duty safety hasp and staple with
necessary screws of the same metal. : Brass hasp and staple of Size 4"
Detail Qty Unit
MATERIAL
Brass screw 3/4" size 7 No
Brass hasp & staple 4" 1 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,416

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-137-a-iii Unit

Item Name : Replacement of existing heavy duty safety hasp and staple with
necessary screws of the same metal. : Brass hasp and staple of Size 3"

Detail Qty Unit


MATERIAL
Brass screw 3/4" size 7 No
Brass hasp & staple 3" 1 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,417

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK
CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-137-a-iv Unit

Item Name : Replacement of existing heavy duty safety hasp and staple with
necessary screws of the same metal. : Brass hasp and staple of Size 2"

Detail Qty Unit


MATERIAL
Brass screw 3/4" size 7 No
Brass hasp & staple 2" 1 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,418

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-137-b-i Unit

Item Name : Replacement of existing heavy duty safety hasp and staple with
necessary screws of the same metal. : Iron hasp and staple of Size 5"

Detail Qty Unit


MATERIAL
Iron screw 3/4" 7 No
Iron hasp & staple 5" 1 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,419

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-137-b-ii Unit

Item Name : Replacement of existing heavy duty safety hasp and staple with
necessary screws of the same metal. : Iron hasp and staple of Size 4"

Detail Qty Unit


MATERIAL
Iron screw 3/4" 7 No
Iron hasp & staple 4" 1 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,420

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-137-b-iii Unit

Item Name : Replacement of existing heavy duty safety hasp and staple with
necessary screws of the same metal. : Iron hasp and staple of Size 3"

Detail Qty Unit


MATERIAL
Iron screw 3/4" 7 No
Iron hasp & staple 3" 1 No
LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,421

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-137-b-iv Unit

Item Name : Replacement of existing heavy duty safety hasp and staple with
necessary screws of the same metal. : Iron hasp and staple of Size 2"

Detail Qty Unit


MATERIAL
Iron screw 3/4" 7 No
Iron hasp & staple 2" 1 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,422

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-137-c-i Unit
Item Name : Replacement of existing heavy duty safety hasp and staple with
necessary screws of the same metal. : Chromium plated hasp and staple
of Size 5"

Detail Qty Unit

MATERIAL
C.P. hasp & staple 5" 1 No
C.P. brass screw (1.5" ) 6 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,423

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-137-c-ii Unit

Item Name : Replacement of existing heavy duty safety hasp and staple with
necessary screws of the same metal. : Chromium plated hasp and staple
of Size 4"

Detail Qty Unit

MATERIAL
C.P. brass screw (1.5" ) 6 No
C.P. hasp & staple 4" 1 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,424

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-137-c-iii Unit

Item Name : Replacement of existing heavy duty safety hasp and staple with
necessary screws of the same metal. : Chromium plated hasp and staple
of Size 3"

Detail Qty Unit

MATERIAL
C.P. brass screw (1.5" ) 6 No
C.P. hasp & staple 3" 1 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,425

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM : Spec. No :


Item Code : 27-137-c-iv Unit

Item Name : Replacement of existing heavy duty safety hasp and staple with
necessary screws of the same metal. : Chromium plated hasp and staple
of Size 2"

Detail Qty Unit


MATERIAL
C.P. brass screw (1.5" ) 6 No
C.P. hasp & staple 2" 1 No

LABOUR
Carpenter 0.0625 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,426

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-140-a
Item Name : Servicing of window type AC
Detail Qty Unit
MATERIAL
Servicing material for 1 Job
Window AC

LABOUR
AC Mechanic 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,427

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-141-i
Item Name :
Detail Qty Unit
MATERIAL
Gas charging to 2.0 Ton 1 1 Job
Split AC

LABOUR
AC Mechanic 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,428

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-141-a
Item Name : Servicing for floor stand AC unit
Detail Qty Unit
MATERIAL
Servicing material for 1 Job
floor stand AC

LABOUR
AC Mechanic 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,429

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE


DESCRIPTION OF ITEM :
Item Code : 27-141-b
Item Name : Servicing of Split type AC
Detail Qty Unit
MATERIAL
Servicing material for 1 Job
Split AC

LABOUR
Labourer 0.5 Day
AC Mechanic 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,430

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-141-c
Item Name :
Detail Qty Unit
MATERIAL
Compressor for 1.5 Ton 1 1 No
Split AC

LABOUR
Labourer 0.6 Day
AC Mechanic 0.6 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,431

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-141-d
Item Name :
Detail Qty Unit
MATERIAL
Compressor for 2.0 Ton 1 1 No
Split AC

LABOUR
Labourer 0.6 Day
test electrcian 0.6 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,432

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-141-e
Item Name :
Detail Qty Unit
MATERIAL
Compressor for 1.5 Ton 1 1 No
Window AC

LABOUR
Labourer 0.5 Day
AC Mechanic 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.
4,433

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-141-f
Item Name :
Detail Qty Unit
MATERIAL
Compressor for 2.0 Ton 1 1 No
Window AC

LABOUR
Labourer 0.5 Day
AC Mechanic 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,434

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-141-g
Item Name : Supply and fixing of compressor for Electric Water Cooler
Detail Qty Unit
MATERIAL
Compressor for Electric 1 1 No
Water Cooler

LABOUR
AC Mechanic 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,435

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-141-h
Item Name :
Detail Qty Unit
MATERIAL
Gas charging to 1.5 Ton 1 1 Job
Split AC

LABOUR
AC Mechanic 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,436

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-141-j
Item Name :
Detail Qty Unit
MATERIAL
Gas charging to 1.5 Ton 1 1 Job
Window AC

LABOUR
AC Mechanic 0.25 Day
Sundries (Labour Only):
Contractor Profit 10% + Over Heads on(M+L+E) 2% +
Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,437

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-141-k
Item Name :
Detail Qty Unit
MATERIAL
Gas charging to 2.0 Ton 1 1 Job
Window AC

LABOUR
AC Mechanic 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,438

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-141-l
Item Name :
Detail Qty Unit
MATERIAL
Gas charging for Electric 1 1 Job
water cooler

LABOUR
AC Mechanic 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,439

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-141-m
Item Name :
Detail Qty Unit
MATERIAL
Gas charging for floor 1 1 Job
stand AC

LABOUR
Labourer 0.2 Day
AC Mechanic 0.2 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,440

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-141-n
Item Name :
Detail Qty
MATERIAL
Repair of PC Circuit 1
Board complete for Split
AC

LABOUR
Labourer 0.2 Day
AC Mechanic 0.2 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,441

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-142-a
Item Name :
Detail Qty Unit
MATERIAL
PC Circuit Board complete 1 1 No
for Split AC

LABOUR
Labourer 0.2 Day
AC Mechanic 0.2 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,442

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE


DESCRIPTION OF ITEM :
Item Code : 27-142-b
Item Name : Supply and Replacement of Sensor for Split AC unit
Detail Qty Unit
MATERIAL
Sensor for Split AC unit 1 1 No

LABOUR
Labourer 0.2 Day
AC Mechanic 0.2 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,443

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-142-c
Item Name : Supply and Replacement of running capacitor
Detail Qty Unit
MATERIAL
Running Capacitor 1 1 No

LABOUR
AC Mechanic 0.2 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,444

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE


DESCRIPTION OF ITEM :
Item Code : 27-142-d
Item Name :
Detail Qty Unit
MATERIAL
Insulation Copper pipe 1 1 No
for split AC unit

LABOUR
AC Mechanic 0.1 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,445

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-142-e
Item Name : Supply and providing of Remote Control for Split AC unit
Detail Qty Unit
MATERIAL
Remote Control for split 1 1 No
AC unit

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per No Rs.
Labour Rates Per No Rs.

4,446

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-142-f
Item Name :
Detail Qty Unit
MATERIAL
Drain pipe flexible for 1 1 No
outdoor unit of split AC

LABOUR
AC Mechanic 0.05 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,447

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-142-g
Item Name : Supply and fixing of fan motor for outdoor unit of split AC
Detail Qty Unit
MATERIAL
Fan motor for outdoor 1 1 No
unit of split AC

LABOUR
AC Mechanic 0.2 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,448

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE


DESCRIPTION OF ITEM :
Item Code : 27-142-h
Item Name : Supply and fixing of fan motor for window AC unit
Detail Qty Unit
MATERIAL
Fan Motor for window AC 1 1 No
unit

LABOUR
AC Mechanic 0.15 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,449

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-143
Item Name : Supply and fixing of fan motor for Electric Water Cooler
Detail Qty Unit
MATERIAL
Fan motor for Electric 1 1 No
water cooler

LABOUR
AC Mechanic 0.15 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,450

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK
CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-144-a
Item Name :
Detail Qty Unit
MATERIAL
Set of steel brackets 1 1 No
with rawal bolts for AC

LABOUR
AC Mechanic 0.1 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,451

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-144-b
Item Name : Supply and fixing of 110/76 - 3 core wire for split AC
Detail Qty Unit
MATERIAL
110/76 - 3 core wire for 1 1 No
split AC

LABOUR
AC Mechanic 0.03 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,452

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-145-a
Item Name : Removing of window AC
Detail Qty Unit
LABOUR
Labourer 0.25 Day
AC Mechanic 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,453

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-145-b
Item Name : Refixing of window AC
Detail Qty Unit
LABOUR
Labourer 0.25 Day
AC Mechanic 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,454

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE


DESCRIPTION OF ITEM :
Item Code : 27-145-c
Item Name : Removing of Split AC
Detail Qty Unit
LABOUR
Labourer 0.4 Day
AC Mechanic 0.4 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,455

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-145-d
Item Name : Refixing of Split AC complete
Detail Qty Unit
LABOUR
Labourer 0.5 Day
AC Mechanic 0.5 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,456

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 27 , REPAIR & MAINTENANCE

DESCRIPTION OF ITEM :
Item Code : 27-146
Item Name : Providing and fixing of contact relay for split AC complete
Detail Qty Unit
MATERIAL
Contact relay for split 1 1 No
AC

LABOUR
AC Mechanic 0.1 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Job Rs.
Labour Rates Per Job Rs.

4,457

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM : Spec. No :


Item Code : 28-01 Unit

Item Name : Supplying bamboo jhandies 10' to 12' with iron shoes and flags 15"
square

Detail Qty Unit


MATERIAL
Iron Shoe 1 No
Cloth 1.563 Sft
Bamboo 8'-10' Long 1 No

LABOUR
Labourer 0.05 Day
Carpenter 0.04 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,458

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM :
Item Code : 28-02
Item Name : Supplying wooden pegs for levelling 1.5" square 6" long
Detail Qty Unit
MATERIAL
Wood - Kiker 3.1815 Cft

LABOUR
Labourer 0.25 Day
Carpenter 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 No. Rs.
Labour Rates Per 100 No. Rs.

4,459

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM :
Item Code : 28-03
Item Name :
Detail Qty Unit
MATERIAL
Wood - Kiker 4.6875 Cft

LABOUR
Labourer 0.25 Day
Carpenter 0.4 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 No. Rs.
Labour Rates Per 100 No. Rs.

4,460
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM :
Item Code : 28-04
Item Name :
Detail Qty Unit
MATERIAL
Hook 0.5 No

LABOUR
Mason 0.0418 Day
Labourer 0.0418 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,461

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM :
Item Code : 28-05
Item Name :
Detail Qty Unit
MATERIAL
Ordinary Portland Cement 0.1786 Bag
Coarse Sand 0.446 Cft
Crushed Aggregate 0.8932 Cft

LABOUR
Labourer 0.5
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.
4,462

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM : Spec. No :


Item Code : 28-06 Unit

Item Name : Fixing main line type distance mark in position including making 1:3:6
cement concrete base block

Detail Qty Unit


MATERIAL
Ordinary Portland Cement 0.3022 Bag
Coarse Sand 0.7556 Cft
Crushed Aggregate 1.5111 Cft
Rfcnt Steel: Grd-40 KSM 0.04 kg
Wire Gauze 12" x 24" 0.235 sft
Brush II 1 No

LABOUR
Labourer 0.3 Day
Painter / Polisher 0.045 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,463

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM :
Item Code : 28-07-a
Item Name : Boring and fixing 1.5" dia pressure pipe in ordinary soil
Detail Qty Unit
LABOUR
Labourer 0.116 Day
Fitter 0.0305 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,464

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM :
Item Code : 28-07-b
Item Name : Boring and fixing 1.5 dia pressure pipe in clay
Detail Qty Unit
LABOUR
Labourer 0.267 Day
Fitter 0.0305 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,465

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM :
Item Code : 28-07-c
Item Name : Boring and fixing 1.5" dia pressure pipe in shingle
Detail Qty Unit
LABOUR
Labourer 0.416 Day
Fitter 0.0305 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,466

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM :
Item Code : 28-08
Item Name : Fixing hand pump (machine only)
Detail Qty Unit
LABOUR
Fitter 0.4 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,467

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM :
Item Code : 28-09-a
Item Name : Washing of Durries / Synthetic Matting
Detail Qty Unit
MATERIAL
Washing powder 1 kg

LABOUR
Skilled Labour 1 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.
4,468

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM :
Item Code : 28-09-b
Item Name : Washing of Bed Sheets
Detail Qty Unit
MATERIAL
Washing powder 0.5 kg

LABOUR
Skilled Labour 0.432 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,469

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM :
Item Code : 28-09-c
Item Name : Washing of Table Cloth / Napkins / Dusters etc
Detail Qty Unit
MATERIAL
Washing powder 0.1 kg

LABOUR
Skilled Labour 0.063 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.
4,470

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM :
Item Code : 28-10
Item Name : Sweeping chimneys
Detail Qty Unit
MATERIAL
Rope 3.28 Rft

LABOUR
Labourer 0.25 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,471

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM :
Item Code : 28-11
Item Name : Cleaning of water tanks per gallon capacity
Detail Qty
MATERIAL
Washing powder 0.01
Cleaning Bleach 0.001

LABOUR
Labourer 0.0006
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Per Gallo Rs.
Labour Rates Per Per Gallo Rs.

4,472

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM : Spec. No :


Item Code : 28-12 Unit

Item Name : Cleaning and washing of bath rooms / toilets by using recommended
chemicals i/c refilling of joints with grout material.

Detail Qty Unit


MATERIAL
Washing chemical 0.25 pkt

LABOUR
Labourer 0.151 Days
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,473

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM :
Item Code : 28-13
Item Name : Supplying manure
Detail Qty Unit
MATERIAL
Manure 100 Cft

LABOUR
Labourer 0.4 Day
Sundries (Labour Only):
Contractor Profit 10% + Over Heads on(M+L+E) 2% +
Income Tax 7.5%
Composite Rates Per 100 Cft Rs.
Labour Rates Per 100 Cft Rs.

4,474

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM : Spec. No :


Item Code : 28-14 Unit

Item Name : Spraying anti-termite liquid on Wood mixed with water of mixing ratio
as per the manufacturer's certified manual (1 Spray = 10 Litre mixture)

Detail Qty Unit


MATERIAL
Anti Termite Liquid for 1 Job
Wood including water

LABOUR
Skilled Labour 0.1 Day
Sundries (Labour Only):

EQUIPMENT
Anti Termite Spray 0.0313 Day
machine

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per per spray Rs.
Labour Rates Per per spray Rs.

4,475

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM : Spec. No :


Item Code : 28-15 Unit
Item Name : Pre anti Termite Treatment in the building mixed with water of mixing
ratio as per the manufacturer's certified manual

Detail Qty Unit


MATERIAL
Pre Anti Termite Liquid 100 Sft
including water

LABOUR
Skilled Labour 0.0174 Day
Sundries (Labour Only):

EQUIPMENT
Anti Termite Spray 0.1389 Hour
machine

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,476

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM : Spec. No :


Item Code : 28-16 Unit

Item Name : Post anti Termite Treatment in the building mixed with water of mixing
ratio as per the manufacturer's certified manual including boreholes as
specified

Detail Qty Unit

MATERIAL
Post Anti Termite Liquid 100 Sft
including water

LABOUR
Skilled Labour 0.0174 Day
Sundries (Labour Only):

EQUIPMENT
Anti Termite Spray 0.1389 Hour
machine

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,477

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM : Spec. No :


Item Code : 28-17-a Unit

Item Name : Providing and Fixing barbed wire fencing with 4 horizontal & 2 cross
wires : Without PCC base

Detail Qty Unit


MATERIAL
Steel (bars/rods/section) 0.0043 Kg
Barbed Wire 0.0871 Kg
Limpet Washer 0.2745 Doz
Eye Bolt 0.0824 Kg
RCC in raft foundation 0.2868 Cft
slab, base slab of column
& ret. wall etc, not
including in 06-06.
(1:2:4)

LABOUR
Labourer 0.2647 Day
Black Smith 0.1176 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,478

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM : Spec. No :


Item Code : 28-17-b Unit

Item Name : Providing and Fixing barbed wire fencing with 4 horizontal & 2 cross
wires : With PCC 1:4:8 base 12"x12"x21"

Detail Qty Unit


MATERIAL
Steel (bars/rods/section) 0.0043 Kg
Barbed Wire 0.0871 Kg
Limpet Washer 0.2745 Doz
Eye Bolt 0.0824 Kg
RCC in raft foundation 0.2868 Cft
slab, base slab of column
& ret. wall etc, not
including in 06-06.
(1:2:4)
Plain Cement Concrete 0.2059 Cft
including placing,
compacting, finishing &
curing (Ratio 1:4:8)

LABOUR
Labourer 0.2647 Day
Black Smith 0.1176 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,479

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM : Spec. No :


Item Code : 28-18 Unit
Item Name : Providing and fixing with steel nails and washers, the chicken wire
mesh of approved quality, at joint of concrete and masonry work (4"
wide strip) before plastering etc complete.

Detail Qty Unit

MATERIAL
22 SWG Chicken Wire Mesh 1 Sft
Steel Nails and Washers

LABOUR
Skilled Labour 0.015 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,480

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM :
Item Code : 28-19
Item Name :
Detail Qty Unit
MATERIAL
Ordinary Portland Cement 1.5 Bag
Coarse Sand 6 Cft

LABOUR
Mason 0.75 Day
Labourer 1 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,481

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM :
Item Code : 28-20
Item Name : Binding office books/registers.
Detail Qty Unit
MATERIAL
Soft Board 1 Sft
Covering Sheet 1 No
Gum Bottle 1 No

LABOUR
Book Binder 0.05 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,482

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM :
Item Code : 28-21
Item Name : Cutting of Pipes upto 2" Dia
Detail Qty Unit
LABOUR
Plumber 0.08 Days
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Per Cut Rs.
Labour Rates Per Per Cut Rs.

4,483

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM :
Item Code : 28-22
Item Name : Cutting of Pipes above 2" Dia upto 4" dia
Detail Qty
LABOUR
Plumber 0.151
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Per Cut Rs.
Labour Rates Per Per Cut Rs.

4,484

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM : Spec. No :


Item Code : 28-23 Unit

Item Name : Providing and fixing of 1-1/2" thick Thermopore in cavity wall,
including all necessary fittings complete in all respect .

Detail Qty Unit


MATERIAL
Thermopore Sheet 1-1/2" 105 Sft

LABOUR
Labourer 0.75 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,485

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM : Spec. No :


Item Code : 28-24 Unit

Item Name : Providing and fixing hot dipped galvanized fully glazed fixed steel sky
light of Z section 1.25" (32.5 mm) width or as approved by Engineer
incharge including iron lugs, cutting holes and making good the damages
to walls.

Detail Qty Unit


MATERIAL
Ordinary Portland Cement 0.0039 bag
Coarse Sand 0.0194 Cft
Wood - Partal 0.0429 cft
Glass Pane 5mm thick 0.7143 Sft
Oil Putty 0.0143 kg
Clamp Screw 10 No
Skylight frame steel 1 Sft

LABOUR
Mason 0.0268 Day
Labourer 0.0714 Day
Glazier 0.0179 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Sft Rs.
Labour Rates Per Sft Rs.

4,486

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM : Spec. No :


Item Code : 28-25 Unit

Item Name : Providing and placing of geotextile fabric as shown in the drawings as
directed by the Engineer.

Detail Qty Unit


MATERIAL
Brush II 0.25 No
Paint : Solignum 0.91 Ltr

LABOUR
Painter / Polisher 0.33 Day
Sundries (Labour Only):

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per 100 Sft Rs.
Labour Rates Per 100 Sft Rs.

4,487

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM : Spec. No :


Item Code : 28-26-a Unit

Item Name : Providing and fixing 25 mm dia. 3 m long deformed steel dowel bars
(Grade 60) with one end driven into 38 mm diameter 1.50 m deep hole
drilled in bed rock and other end provided with L-bend for embedding in
concrete / masonry of over flow / non-over flow blocks and other
appurtenant works including cost of all materials, machinery, labour,
drilling and cleaning hole, filling hole with specified cement mortar,
driving anchor rod etc. complete with all lead and lifts.

Detail Qty Unit


MATERIAL
Ordinary Portland Cement 0.03 Bag
Coarse Sand 0.05 100 Cft
Steel (bars/rods/section) 11.91 Kg

LABOUR
Mason 0.25 Day
Labourer 0.25 Day
Skilled Labour 0.25 Day
Sundries (Labour Only):

EQUIPMENT
Rock Driller 3.5 Day

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,488

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM : Spec. No :


Item Code : 28-26-b Unit

Item Name : Providing and fixing 25 mm dia. 2.75 m long ribbed/deformed steel bars
(Grade 60) with one end split and driven firmly using steel wedge into
38 mm diameter 1.25 m deep hole drilled in bed rock and other end
provided with L-bend for embedding in concrete / masonry for spillway
and appurtenant works including cost of all materials, machinery,
labour, steel wedge, drilling and cleaning hole, filling hole with
thick cement slurry, driving anchor rod etc. complete with all lead and
lifts.

Detail Qty Unit


MATERIAL
Ordinary Portland Cement 0.03 Bag
Coarse Sand 0.05 100 Cft
Steel (bars/rods/section) 10.91 Kg

LABOUR
Mason 0.25 Day
Labourer 0.4 Day
Skilled Labour 0.25 Day
Sundries (Labour Only):

EQUIPMENT
Rock Driller 3.4 Day

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Each Rs.
Labour Rates Per Each Rs.

4,489

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM : Spec. No :


Item Code : 28-27-a Unit

Item Name : Drilling approximately 75 mm dia. holes by calyx or any other rotary
process (except diamond drilling) through over burden providing black
steel or suitable casing pipe, using casing shoe bit, vertical or
inclined upto 10 degrees to vertical as directed including cost of all
materials, machinery, labour, water charges, reaming, collection of
wash samples/disturbed samples at suitable intervals, logging and
labelling, supplying wooden core box, fixing casing pipes etc.
complete. from depth (0 to 50 m), excluding cost of mobilization &
demobilization.

Detail Qty Unit


LABOUR
Labourer 0.4 Day
Fitter 0.2 Day
Sundries (Labour Only):

EQUIPMENT
Drilling of Boreholes 1 Rft
with boring bailer/Rotary
rig, Generator set light
arrangement etc. for
collection of disturbed
soil samples

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,490

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM : Spec. No :


Item Code : 28-27-b Unit
Item Name : Drilling approximately 75 mm dia. holes by calyx or any other rotary
process (except diamond drilling) through over burden providing black
steel or suitable casing pipe, using casing shoe bit, vertical or
inclined upto 10 degrees to vertical as directed including cost of all
materials, machinery, labour, water charges, reaming, collection of
wash samples/disturbed samples at suitable intervals, logging and
labelling, supplying wooden core box, fixing casing pipes etc.
complete. from depth (beyond 50 m), excluding cost of mobilization &
demobilization.

Detail Qty Unit


LABOUR
Labourer 0.7 Day
Fitter 0.2 Day
Sundries (Labour Only):

EQUIPMENT
Drilling of Boreholes 1 Rft
with boring bailer/Rotary
rig, Generator set light
arrangement etc. for
collection of disturbed
soil samples

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,491

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM : Spec. No :


Item Code : 28-27-c Unit

Item Name : Drilling by diamond drilling, holes of minimum 75 mm dia. vertical or


at specified inclination using diamond core drilling bit, double barrel
tube in masonry, concrete or rock including cost of all materials,
machinery, labour, water, collection of core samples, logging &
labelling samples, supplying wooden core box and re-drilling in case of
collapse of sides etc. complete. excluding cost of mobilization &
demobilization. (For depth 0 to 50 m and inclined at 0? to 10?
vertically downward)

Detail Qty Unit


LABOUR
Labourer 0.4 Day
Fitter 0.2 Day
Sundries (Labour Only):

EQUIPMENT
Drilling of Boreholes 1 Rft
using diamond bit with
boring bailer/Rotary rig,
Generator set light
arrangement etc, for
collection of undisturbed
soil samples

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,492

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM : Spec. No :


Item Code : 28-27-d Unit

Item Name : Drilling by diamond drilling, holes of minimum 75 mm dia. vertical or


at specified inclination using diamond core drilling bit, double barrel
tube in masonry, concrete or rock including cost of all materials,
machinery, labour, water, collection of core samples, logging &
labelling samples, supplying wooden core box and re-drilling in case of
collapse of sides etc. complete. excluding cost of mobilization &
demobilization. (For depth 0 to 50 m and inclined at 10? to 45?
vertically downward)

Detail Qty Unit


LABOUR
Labourer 0.48 Day
Fitter 0.24 Day
Sundries (Labour Only):
EQUIPMENT
Drilling of Boreholes 1 Rft
using diamond bit with
boring bailer/Rotary rig,
Generator set light
arrangement etc. for
collection of undisturbed
soil samples

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,493

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM : Spec. No :


Item Code : 28-27-e Unit

Item Name : Drilling by diamond drilling, holes of minimum 75 mm dia. vertical or


at specified inclination using diamond core drilling bit, double barrel
tube in masonry, concrete or rock including cost of all materials,
machinery, labour, water, collection of core samples, logging &
labelling samples, supplying wooden core box and re-drilling in case of
collapse of sides etc. complete. excluding cost of mobilization &
demobilization. (For depth beyond 50 m and inclined at 0? to 10?
vertically downward)

Detail Qty Unit


LABOUR
Labourer 0.5 Day
Fitter 0.25 Day
Sundries (Labour Only):

EQUIPMENT
Drilling of Boreholes 1 Rft
using diamond bit with
boring bailer/Rotary rig,
Generator set light
arrangement etc. for
collection of undisturbed
soil samples

Contractor Profit 10% + Over Heads on(M+L+E) 2% +


Income Tax 7.5%
Composite Rates Per Rft Rs.
Labour Rates Per Rft Rs.

4,494

GOVERNMENT OF KHYBER PAKHTUNKHWA


MRS CELL COMMUNICATION & WORKS DEPARTMENT
MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 28 , MISCELLANEOUS

DESCRIPTION OF ITEM : Spec. No :


Item Code : 28-28 Unit

Item Name : Topographic and cadastral survey for head works/Dams & other irrigation
projects by using Total station GPS, etc. with minimum 30 number of
point reading per acre, to generate 15mx15m grid and 0.5 m interval
contours including transfer of entire data to computer system in
different geo-referenced layers / themes using features of standard
software, compatible with design software packages, including supply of
soft and hard copies of point readings, including digitizing village
maps and super imposing the contours on village map (scale 1 in 4000)
including marking all permanent features like roads, cart tracks,
existing canals, mosques, tanks, forest boundary and electric poles,
etc. including marking of ridges and valleys on survey sheet including
supply of 4 soft copies and 4 hard copies after approval of competent
authority, preparation & submission of grid and L-section nallah etc.
complete

Detail Qty Unit


LABOUR
Skilled Labour 0.12 Day
Surveyor 0.04 Day
survey Engineer 0.015 Day
Sundries (Labour Only):

EQUIPMENT
Total station GPS, 0.02 Day
including computer,
Printers etc
Contractor Profit 10% + Over Heads on(M+L+E) 2% +
Income Tax 7.5%
Composite Rates Per Acre Rs.
Labour Rates Per Acre Rs.

4,495
(British) : WHP

Rate (Rs)

78,000.00 1 WHP

TOTAL MATERIAL 71.02

Day 600.00 1
Day 850.00 1
Day 1,200.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 9.48
19.50

101,932.00 Cost Per 746 HW: 101,932.00


8,722.00 Cost Per 746 HW: 8,722.00
(British) : WHP

Rate (Rs)

55,000.00 1 WHP

TOTAL MATERIAL 69.61

Day 600.00 1
Day 850.00 1
Day 1,200.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 10.89
19.50

73,356.75 Cost Per 746 HW: 73,356.75


7,631.75 Cost Per 746 HW: 7,631.75

(British) : WHP
Rate (Rs)

44,600.00 1 WHP

TOTAL MATERIAL 69.21

Day 600.00 1
Day 850.00 1
Day 1,200.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 11.29
19.50

59,838.50 Cost Per 746 HW: 59,838.50


6,541.50 Cost Per 746 HW: 6,541.50

(British) : WHP
Rate (Rs)

38,500.00 1 WHP

TOTAL MATERIAL 70.94

Day 600.00 1
Day 850.00 1
Day 1,200.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 9.56
19.50

50,368.50 Cost Per 746 HW: 50,368.50


4,361.00 Cost Per 746 HW: 4,361.00

(British) : WHP
Rate (Rs)

37,000.00 1 WHP

TOTAL MATERIAL 72.28

Day 600.00 1
Day 850.00 1
Day 1,200.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 8.22
19.50

47,485.75 Cost Per 746 HW: 47,485.75


3,270.75 Cost Per 746 HW: 3,270.75

(British) : WHP

Rate (Rs)

34,500.00 1 WHP
TOTAL MATERIAL 73.70

Day 600.00 1
Day 850.00 1
Day 1,200.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 6.80
19.50

43,408.00 Cost Per 746 HW: 43,408.00


2,180.50 Cost Per 746 HW: 2,180.50

(British) : WHP

Rate (Rs)

315,000.00 1 WHP

TOTAL MATERIAL 75.37

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 5.13
19.50

387,327.50 Cost Per 746 HW: 387,327.50


10,902.50 Cost Per 746 HW: 10,902.50

(British) : WHP

Rate (Rs)

294,000.00 1 WHP

TOTAL MATERIAL 75.44

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 5.06
19.50

361,142.25 Cost Per 746 HW: 361,142.25


9,812.25 Cost Per 746 HW: 9,812.25
(British) : WHP

Rate (Rs)

262,000.00 1 WHP

TOTAL MATERIAL 75.45

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 5.05
19.50

321,812.00 Cost Per 746 HW: 321,812.00


8,722.00 Cost Per 746 HW: 8,722.00
(British) : WHP

Rate (Rs)

174,000.00 1 WHP

TOTAL MATERIAL 74.82

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 5.68
19.50

215,561.75 Cost Per 746 HW: 215,561.75


7,631.75 Cost Per 746 HW: 7,631.75

(British) : WHP
Rate (Rs)

169,000.00 1 WHP

TOTAL MATERIAL 75.13

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 5.37
19.50

208,496.50 Cost Per 746 HW: 208,496.50


6,541.50 Cost Per 746 HW: 6,541.50

(British) : WHP

Rate (Rs)
161,000.00 1 WHP

TOTAL MATERIAL 75.82

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 4.68
19.50

196,756.00 Cost Per 746 HW: 196,756.00


4,361.00 Cost Per 746 HW: 4,361.00

(British) : WHP

Rate (Rs)

157,000.00 1 WHP
TOTAL MATERIAL 76.63

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 3.87
19.50

189,795.50 Cost Per 746 HW: 189,795.50


2,180.50 Cost Per 746 HW: 2,180.50

(British) : WHP

Rate (Rs)

213,000.00 1 WHP

TOTAL MATERIAL 74.54

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 5.96
19.50

264,892.38 Cost Per 746 HW: 264,892.38


10,357.38 Cost Per 746 HW: 10,357.38

(British) : WHP

Rate (Rs)

207,000.00 1 WHP

TOTAL MATERIAL 74.61

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 5.89
19.50

257,177.25 Cost Per 746 HW: 257,177.25


9,812.25 Cost Per 746 HW: 9,812.25
(British) : WHP

Rate (Rs)

190,000.00 1 WHP

TOTAL MATERIAL 74.70

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 5.80
19.50

235,772.00 Cost Per 746 HW: 235,772.00


8,722.00 Cost Per 746 HW: 8,722.00
(British) : WHP

Rate (Rs)

176,000.00 1 WHP

TOTAL MATERIAL 74.85

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 5.65
19.50

217,951.75 Cost Per 746 HW: 217,951.75


7,631.75 Cost Per 746 HW: 7,631.75

(British) : WHP
Rate (Rs)

163,500.00 1 WHP

TOTAL MATERIAL 75.05

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 5.45
19.50

201,924.00 Cost Per 746 HW: 201,924.00


6,541.50 Cost Per 746 HW: 6,541.50

(British) : WHP

Rate (Rs)

155,000.00 1 WHP
TOTAL MATERIAL 75.76

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 4.74
19.50

189,586.00 Cost Per 746 HW: 189,586.00


4,361.00 Cost Per 746 HW: 4,361.00

(British) : WHP

Rate (Rs)

152,000.00 1 WHP

TOTAL MATERIAL 76.16


Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 4.34
19.50

184,910.75 Cost Per 746 HW: 184,910.75


3,270.75 Cost Per 746 HW: 3,270.75

(British) : WHP

Rate (Rs)

148,000.00 1 WHP

TOTAL MATERIAL 76.58

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 3.92
19.50

179,040.50 Cost Per 746 HW: 179,040.50


2,180.50 Cost Per 746 HW: 2,180.50

(British) : WHP

Rate (Rs)

325,000.00 1 WHP

TOTAL MATERIAL 75.43

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 5.07
19.50

399,277.50 Cost Per 746 HW: 399,277.50


10,902.50 Cost Per 746 HW: 10,902.50
(British) : WHP

Rate (Rs)

320,000.00 1 WHP

TOTAL MATERIAL 75.61

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 4.89
19.50

392,212.25 Cost Per 746 HW: 392,212.25


9,812.25 Cost Per 746 HW: 9,812.25

(British) : WHP
Rate (Rs)

270,000.00 1 WHP

TOTAL MATERIAL 75.51

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 4.99
19.50

331,372.00 Cost Per 746 HW: 331,372.00


8,722.00 Cost Per 746 HW: 8,722.00

(British) : WHP
Rate (Rs)

164,000.00 1 WHP

TOTAL MATERIAL 74.66

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 5.84
19.50

203,611.75 Cost Per 746 HW: 203,611.75


7,631.75 Cost Per 746 HW: 7,631.75

(British) : WHP

Rate (Rs)
152,000.00 1 WHP

TOTAL MATERIAL 74.87

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 5.63
19.50

188,181.50 Cost Per 746 HW: 188,181.50


6,541.50 Cost Per 746 HW: 6,541.50

(British) : WHP

Rate (Rs)

150,000.00 1 WHP
TOTAL MATERIAL 75.70

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 4.80
19.50

183,611.00 Cost Per 746 HW: 183,611.00


4,361.00 Cost Per 746 HW: 4,361.00

(British) : WHP

Rate (Rs)

147,000.00 1 WHP

TOTAL MATERIAL 76.57

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 3.93
19.50

177,845.50 Cost Per 746 HW: 177,845.50


2,180.50 Cost Per 746 HW: 2,180.50

(British) : WHP

Rate (Rs)

227,000.00 1 WHP

TOTAL MATERIAL 74.72

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 5.78
19.50

281,622.38 Cost Per 746 HW: 281,622.38


10,357.38 Cost Per 746 HW: 10,357.38
(British) : WHP

Rate (Rs)

215,000.00 1 WHP

TOTAL MATERIAL 74.72

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 5.78
19.50

266,737.25 Cost Per 746 HW: 266,737.25


9,812.25 Cost Per 746 HW: 9,812.25
(British) : WHP

Rate (Rs)

190,000.00 1 WHP

TOTAL MATERIAL 74.70

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 5.80
19.50

235,772.00 Cost Per 746 HW: 235,772.00


8,722.00 Cost Per 746 HW: 8,722.00

(British) : WHP
Rate (Rs)

151,000.00 1 WHP

TOTAL MATERIAL 74.43

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 6.07
19.50

188,076.75 Cost Per 746 HW: 188,076.75


7,631.75 Cost Per 746 HW: 7,631.75

(British) : WHP

Rate (Rs)

145,000.00 1 WHP
TOTAL MATERIAL 74.75

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 5.75
19.50

179,816.50 Cost Per 746 HW: 179,816.50


6,541.50 Cost Per 746 HW: 6,541.50

(British) : WHP

Rate (Rs)

141,000.00 1 WHP

TOTAL MATERIAL 75.59


Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 4.91
19.50

172,856.00 Cost Per 746 HW: 172,856.00


4,361.00 Cost Per 746 HW: 4,361.00

(British) : WHP

Rate (Rs)

138,000.00 1 WHP

TOTAL MATERIAL 76.51

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 3.99
19.50

167,090.50 Cost Per 746 HW: 167,090.50


2,180.50 Cost Per 746 HW: 2,180.50

(British) : WHP

Rate (Rs)

135,000.00 1 WHP

TOTAL MATERIAL 76.49

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 4.01
19.50

163,505.50 Cost Per 746 HW: 163,505.50


2,180.50 Cost Per 746 HW: 2,180.50
(British) : WHP

Rate (Rs)

404,000.00 1 WHP

TOTAL MATERIAL 75.67

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 4.83
19.50

494,772.75 Cost Per 746 HW: 494,772.75


11,992.75 Cost Per 746 HW: 11,992.75

(British) : WHP
Rate (Rs)

397,000.00 1 WHP

TOTAL MATERIAL 75.72

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 4.78
19.50

485,862.62 Cost Per 746 HW: 485,862.62


11,447.63 Cost Per 746 HW: 11,447.63

(British) : WHP
Rate (Rs)

349,000.00 1 WHP

TOTAL MATERIAL 75.67

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 4.83
19.50

427,412.38 Cost Per 746 HW: 427,412.38


10,357.38 Cost Per 746 HW: 10,357.38

(British) : WHP
Rate (Rs)

220,000.00 1 WHP

TOTAL MATERIAL 74.92

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 5.58
19.50

272,167.13 Cost Per 746 HW: 272,167.13


9,267.13 Cost Per 746 HW: 9,267.13

(British) : WHP

Rate (Rs)

209,000.00 1 WHP
TOTAL MATERIAL 75.57

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 4.93
19.50

256,296.50 Cost Per 746 HW: 256,296.50


6,541.50 Cost Per 746 HW: 6,541.50

(British) : WHP

Rate (Rs)

198,000.00 1 WHP
TOTAL MATERIAL 76.13

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 4.37
19.50

240,971.00 Cost Per 746 HW: 240,971.00


4,361.00 Cost Per 746 HW: 4,361.00

(British) : WHP

Rate (Rs)

193,000.00 1 WHP

TOTAL MATERIAL 76.79

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 3.71
19.50

232,815.50 Cost Per 746 HW: 232,815.50


2,180.50 Cost Per 746 HW: 2,180.50

(British) : WHP

Rate (Rs)

304,000.00 1 WHP

TOTAL MATERIAL 75.51

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 4.99
19.50

373,080.00 Cost Per 746 HW: 373,080.00


9,800.00 Cost Per 746 HW: 9,800.00
(British) : WHP

Rate (Rs)

295,000.00 1 WHP

TOTAL MATERIAL 75.45

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 5.05
19.50

362,337.25 Cost Per 746 HW: 362,337.25


9,812.25 Cost Per 746 HW: 9,812.25
(British) : WHP

Rate (Rs)

265,000.00 1 WHP

TOTAL MATERIAL 75.47

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 5.03
19.50

325,397.00 Cost Per 746 HW: 325,397.00


8,722.00 Cost Per 746 HW: 8,722.00

(British) : WHP
Rate (Rs)

216,000.00 1 WHP

TOTAL MATERIAL 75.33

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 5.17
19.50

265,751.75 Cost Per 746 HW: 265,751.75


7,631.75 Cost Per 746 HW: 7,631.75

(British) : WHP

Rate (Rs)

196,000.00 1 WHP
TOTAL MATERIAL 75.44

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 5.06
19.50

240,761.50 Cost Per 746 HW: 240,761.50


6,541.50 Cost Per 746 HW: 6,541.50

(British) : WHP

Rate (Rs)

178,000.00 1 WHP

TOTAL MATERIAL 75.61


Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 4.89
19.50

218,161.25 Cost Per 746 HW: 218,161.25


5,451.25 Cost Per 746 HW: 5,451.25

(British) : WHP

Rate (Rs)

174,000.00 1 WHP

TOTAL MATERIAL 75.95

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 4.55
19.50
212,291.00 Cost Per 746 HW: 212,291.00
4,361.00 Cost Per 746 HW: 4,361.00

(British) : WHP

Rate (Rs)

170,000.00 1 WHP

TOTAL MATERIAL 76.70

Day 1,200.00 1
Day 600.00 1
Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 3.80
19.50

205,330.50 Cost Per 746 HW: 205,330.50


2,180.50 Cost Per 746 HW: 2,180.50
Spec. No :
Unit (British) : Rft
ing tramway line
Rate (Rs)

600.00 1
850.00 1
600.00 1
3.00
TOTAL LABOUR 80.50
19.50

22.77 Per Meter : Rs 74.67


22.77 Per Meter : Rs 74.67

Spec. No :
Unit (British) : Rft

Rate (Rs)

600.00 1
850.00 1
600.00 1
3.00
TOTAL LABOUR 80.50
19.50

7.30 Per Meter : Rs 23.95


7.30 Per Meter : Rs 23.95
25.3 , 25.4
(British) : Rft

Rate (Rs)

600.00 1
850.00 1
600.00 1
3.00
TOTAL LABOUR 80.50
19.50

61.86 Per Meter : Rs 202.91


61.86 Per Meter : Rs 202.91

Spec. No :
Unit (British) : Each
ngs, complete with fastening
Rate (Rs)

600.00 1
600.00 1
3.00
TOTAL LABOUR 80.50
19.50

5,880.00 Cost Per Each: 5,880.00


5,880.00 Cost Per Each: 5,880.00
Spec. No :
Unit (British) : Each
BG rail with jim crow
Rate (Rs)

600.00 1
1,050.00 1
3.00
TOTAL LABOUR 80.50
19.50

689.06 Cost Per Each: 689.06


689.06 Cost Per Each: 689.06

Spec. No :
Unit (British) : Each

Rate (Rs)

600.00 1
3.00
TOTAL LABOUR 80.50
19.50

624.75 Cost Per Each: 624.75


624.75 Cost Per Each: 624.75

25.3 , 25.4
(British) : Each
Rate (Rs)

600.00 1
600.00 1
750.00 1

3.00
TOTAL LABOUR 80.50
19.50

77.18 Cost Per Each: 77.18


77.18 Cost Per Each: 77.18

(British) : Each

Rate (Rs)

600.00 1
600.00 1
3.00
TOTAL LABOUR 80.50
19.50

9.04 Cost Per Each: 9.04


9.04 Cost Per Each: 9.04
(British) : Tonne

Unit Rate (Rs)

Kg 110.00 1
TOTAL MATERIAL 52.36

Day 600.00 1
Day 600.00 1
3.00
TOTAL LABOUR 28.14
19.50

196,130.00 Per Tonne : Rs 196,130.00


64,680.00 Per Tonne : Rs 64,680.00

25.3 , 25.4
(British) : Tonne

Unit Rate (Rs)

Pkt 464.10 1
Kg 110.00 1
TOTAL MATERIAL 72.14

Day 600.00 1
Day 1,050.00 1
3.00
TOTAL LABOUR 8.36
19.50
142,665.45 Per Tonne : Rs 142,665.45
10,106.25 Per Tonne : Rs 10,106.25

25.3 , 25.4
(British) : Tonne

Rate (Rs)

600.00 1
750.00 1

3.00
TOTAL LABOUR 80.50
19.50

10,499.66 Per Tonne : Rs 10,499.66


10,499.66 Per Tonne : Rs 10,499.66

25.3 , 25.4
(British) : Sft

Rate (Rs)

600.00 1
1,050.00 1
3.00
TOTAL LABOUR 80.50
19.50

16.17 Per SQM : Rs 173.99


16.17 Per SQM : Rs 173.99

Spec. No :
Unit (British) : Tonne
sheet tanks, upto 20' height
Rate (Rs)

600.00 1
1,050.00 1
3.00
TOTAL LABOUR 80.50
19.50

15,288.00 Per Tonne : Rs 15,288.00


15,288.00 Per Tonne : Rs 15,288.00

25.3 , 25.4
(British) : Tonne

Rate (Rs)

600.00 1
1,050.00 1
3.00
TOTAL LABOUR 80.50
19.50

904.05 Per Tonne : Rs 904.05


904.05 Per Tonne : Rs 904.05

25.3 , 25.4
(British) : Tonne

Rate (Rs)

600.00 1
1,050.00 1
3.00
TOTAL LABOUR 80.50
19.50

448.35 Per Tonne : Rs 448.35


448.35 Per Tonne : Rs 448.35

Spec. No :

Unit (British) : Kg

Rate (Rs)

110.00 1
TOTAL MATERIAL 30.68

600.00 1
1,050.00 1
850.00 1
3.00
TOTAL LABOUR 49.82
19.50

249.48 Cost Per Kg: 249.48


152.21 Cost Per Kg: 152.21

Spec. No :

Unit (British) : Each cut


Cutting rails,rolled steel joist & beams, with hacksaw : Upto 6" size
Rate (Rs)

600.00 1
750.00 1

3.00
TOTAL LABOUR 80.50
19.50

275.68 Cost Per Each cut: 275.68


275.68 Cost Per Each cut: 275.68

Spec. No :

Unit (British) : Each cut


Cutting rails,rolled steel joist & beams, with hacksaw : Above 6" size
Rate (Rs)

600.00 1
750.00 1

3.00
TOTAL LABOUR 80.50
19.50

413.44 Cost Per Each cut: 413.44


413.44 Cost Per Each cut: 413.44

Spec. No :

Unit (British) : Each cut


Cutting rails or rolled steel beams of size below 6" with jim
Rate (Rs)

600.00 1
750.00 1

3.00
TOTAL LABOUR 80.50
19.50

137.76 Cost Per Each cut: 137.76


137.76 Cost Per Each cut: 137.76

Spec. No :

Unit (British) : Per Bend

Rate (Rs)

53.60 1
TOTAL MATERIAL 66.36

600.00 1
750.00 1

3.00
TOTAL LABOUR 14.14
19.50

1,608.89 Cost Per Per Bend: 1,608.89


236.32 Cost Per Per Bend: 236.32

Spec. No :
Unit (British) : Each hole
Drilling holes,in plates over 1/2" thick per inch dia. or part thereof
Rate (Rs)

600.00 1
750.00 1

3.00
TOTAL LABOUR 80.50
19.50

64.37 Cost Per Each hole: 64.37


64.37 Cost Per Each hole: 64.37

25.4.2.3
(British) : Each hole
Rate (Rs)

600.00 1
750.00 1

3.00
TOTAL LABOUR 80.50
19.50

31.70 Cost Per Each hole: 31.70


31.70 Cost Per Each hole: 31.70

Spec. No :
Unit (British) : Each

Rate (Rs)

600.00 1
750.00 1

3.00
TOTAL LABOUR 80.50
19.50

8.27 Cost Per Each: 8.27


8.27 Cost Per Each: 8.27

Spec. No :
25.4.5
Unit (British) : Each
Rate (Rs)

600.00 1
750.00 1

3.00
TOTAL LABOUR 80.50
19.50

22.99 Cost Per Each: 22.99


22.99 Cost Per Each: 22.99

Spec. No : 25.4.8
Unit (British) : Rft
tters of sheet iron
Rate (Rs)

600.00 1
1,050.00 1
750.00 1

3.00
TOTAL LABOUR 80.50
19.50

47.78 Per Meter : Rs 156.70


47.78 Per Meter : Rs 156.70

Spec. No :
25.4.8
Unit (British) : Each
ars, for barred windows
Rate (Rs)

600.00 1
1,200.00 1
750.00 1

3.00
TOTAL LABOUR 80.50
19.50

64.37 Cost Per Each: 64.37


64.37 Cost Per Each: 64.37

Spec. No :
25.4.8
Unit (British) : Each

Rate (Rs)

600.00 1
750.00 1

3.00
TOTAL LABOUR 80.50
19.50

27.62 Cost Per Each: 27.62


27.62 Cost Per Each: 27.62

Spec. No :
Unit (British) : Each cut
rail posts for housing rail beams
Rate (Rs)

53.60 1
TOTAL MATERIAL 7.00

600.00 1
750.00 1

3.00
TOTAL LABOUR 73.50
19.50

604.57 Cost Per Each cut: 604.57


551.19 Cost Per Each cut: 551.19

Spec. No :

Unit (British) : Sft


work fixed with nails
Rate (Rs)

130.00 1
TOTAL MATERIAL 3.02

1,050.00 1
600.00 1
3.00
TOTAL LABOUR 77.48
19.50

58.41 Per SQM : Rs 628.52


56.19 Per SQM : Rs 604.61
Spec. No :

Unit (British) : Sft


eet on table tops
Unit Rate (Rs)

130.00 1
TOTAL MATERIAL 2.05

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 78.45
19.50

30.10 Per SQM : Rs 323.91


29.33 Per SQM : Rs 315.55

25.3, 25.4.2,
25.4.3,
(British) : Sft 25.4.13 , 25.5

Rate (Rs) Amount

194.00 1 Kg
401.22 1 Ltr
110.00 1 Kg
157.50 1 No.

120.00 1 Kg

TOTAL MATERIAL 46.03

1,050.00 1
700.00 1
850.00 1
3.00
TOTAL LABOUR 34.47
19.50

1,437.06 Per SQM : Rs 15,462.80


592.09 Per SQM : Rs 6,370.90

25.3, 25.4.2,
25.4.3,
(British) : Sft 25.4.13 , 25.5

Rate (Rs) Amount

194.00 1 Kg
401.22 1 Ltr
110.00 1 Kg
157.50 1 No.

120.00 1 Kg

TOTAL MATERIAL 48.05

1,050.00 1
700.00 1
850.00 1
3.00
TOTAL LABOUR 32.45
19.50

1,534.34 Per SQM : Rs 16,509.45


592.09 Per SQM : Rs 6,370.90
25.3, 25.4.2,
25.4.3,
(British) : Sft 25.4.13 , 25.5

Rate (Rs) Amount

120.00 1 Kg
143.20 1 Kg
194.00 1 Kg
401.22 1 Ltr
157.50 1 Kg

120.00 1 Kg

TOTAL MATERIAL 53.40

1,050.00 1
600.00 1
700.00 1
3.00
TOTAL LABOUR 27.10
19.50

1,654.05 Per SQM : Rs 17,797.61


523.15 Per SQM : Rs 5,629.14

25.3, 25.4.2,
25.4.3 ,
(British) : Sft 25.4.13

Rate (Rs)

53.60 1
110.00 1
TOTAL MATERIAL 58.68

1,050.00 1
600.00 1
600.00 1

3.00
TOTAL LABOUR 21.82
19.50

556.97 Per SQM : Rs 5,993.01


137.81 Per SQM : Rs 1,482.86

25.7.4
(British) : Rft

Rate (Rs)

120.00 1
45.00 1
TOTAL MATERIAL 63.93

850.00 1
1,050.00 1
1,050.00 1
3.00
TOTAL LABOUR 16.57
19.50

793.69 Per Meter : Rs 2,603.30


141.79 Per Meter : Rs 465.08

25.7.4
(British) : Rft

Rate (Rs)

464.10 1 Pack
85.00 1 Rft

TOTAL MATERIAL 62.51

1,050.00 1
2,000.00 1
3.00
TOTAL LABOUR 17.99
19.50

189.41 Per Meter : Rs 621.25


37.36 Per Meter : Rs 122.55

(British) : Sft
Rate (Rs)

401.22 1
525.00 1
TOTAL MATERIAL 52.48

850.00 1
1,200.00 1
1,050.00 1
750.00 1

3.00
TOTAL LABOUR 28.02
19.50

969.67 Per SQM : Rs 10,433.65


318.32 Per SQM : Rs 3,425.15

25.3 , 25.4
(British) : Sft

Rate (Rs)

401.22 1
165.00 1
95.00 1
TOTAL MATERIAL 66.41
850.00 1
1,200.00 1
1,050.00 1
750.00 1

3.00
TOTAL LABOUR 14.09
19.50

272.31 Per SQM : Rs 2,930.09


39.81 Per SQM : Rs 428.38

25.3 , 25.4
(British) : Rft

Rate (Rs)

120.00 1
TOTAL MATERIAL 64.85

1,200.00 1
600.00 1
1,050.00 1
3.00
TOTAL LABOUR 15.65
19.50

284.00 Per Meter : Rs 931.51


47.32 Per Meter : Rs 155.20
25.3 , 25.4
(British) : Rft

Rate (Rs)

120.00 1
401.22 1
187.25 1
464.10 1
TOTAL MATERIAL 53.85

1,200.00 1
600.00 1
1,200.00 1
1,050.00 1
600.00 1
600.00 1

3.00
TOTAL LABOUR 26.65
19.50

520.88 Per Meter : Rs 1,708.48


161.70 Per Meter : Rs 530.38

25.3 , 25.4
(British) : Sft

Rate (Rs)

120.00 1
464.10 1
55.00 1
TOTAL MATERIAL 37.13

1,200.00 1
600.00 1
3.00
TOTAL LABOUR 43.37
19.50

225.88 Per SQM : Rs 2,430.50


119.07 Per SQM : Rs 1,281.19

25.3 , 25.4
(British) : Sft

Rate (Rs)

401.22 1
35.00 1
437.00 1
TOTAL MATERIAL 73.63

600.00 1
1,200.00 1
1,050.00 1
3.00
TOTAL LABOUR 6.87
19.50

683.58 Per SQM : Rs 7,355.29


34.91 Per SQM : Rs 375.66
(British) : Sft

Rate (Rs)

401.22 1
40.00 1
437.00 1
TOTAL MATERIAL 73.67

600.00 1
1,200.00 1
1,050.00 1
3.00
TOTAL LABOUR 6.83
19.50

689.55 Per SQM : Rs 7,419.58


34.91 Per SQM : Rs 375.66

(British) : Sft
Rate (Rs)

401.22 1
48.00 1
437.00 1
TOTAL MATERIAL 73.72

600.00 1
1,200.00 1
1,050.00 1
3.00
TOTAL LABOUR 6.78
19.50

699.11 Per SQM : Rs 7,522.44


34.91 Per SQM : Rs 375.66

(British) : Sft

Rate (Rs)
401.22 1
55.00 1
437.00 1
TOTAL MATERIAL 73.76

600.00 1
1,200.00 1
1,050.00 1
3.00
TOTAL LABOUR 6.74
19.50

707.48 Per SQM : Rs 7,612.45


34.91 Per SQM : Rs 375.66

(British) : Sft

Rate (Rs)

401.22 1
62.50 1
437.00 1
TOTAL MATERIAL 73.81

600.00 1
1,200.00 1
1,050.00 1
3.00
TOTAL LABOUR 6.69
19.50
716.44 Per SQM : Rs 7,708.89
34.91 Per SQM : Rs 375.66

(British) : Sft

Rate (Rs)

401.22 1
55.00 1
35.00 1
437.00 1
TOTAL MATERIAL 73.76

600.00 1
1,200.00 1
1,050.00 1
3.00
TOTAL LABOUR 6.74
19.50

781.17 Per SQM : Rs 8,405.38


38.59 Per SQM : Rs 415.20

(British) : Sft
Rate (Rs)

401.22 1
55.00 1
35.00 1
437.00 1
TOTAL MATERIAL 73.76

600.00 1
1,200.00 1
1,050.00 1
3.00
TOTAL LABOUR 6.74
19.50

781.17 Per SQM : Rs 8,405.38


38.59 Per SQM : Rs 415.20

(British) : Sft

Rate (Rs)

401.22 1
55.00 1
48.00 1
437.00 1
TOTAL MATERIAL 73.83

600.00 1
1,200.00 1
1,050.00 1
3.00
TOTAL LABOUR 6.67
19.50
796.70 Per SQM : Rs 8,572.53
38.59 Per SQM : Rs 415.20

(British) : Sft

Rate (Rs)

401.22 1
55.00 1
55.00 1
437.00 1
TOTAL MATERIAL 73.87

600.00 1
1,200.00 1
1,050.00 1
3.00
TOTAL LABOUR 6.63
19.50

805.07 Per SQM : Rs 8,662.54


38.59 Per SQM : Rs 415.20

(British) : Sft
Rate (Rs)

401.22 1
55.00 1
62.50 1
437.00 1
TOTAL MATERIAL 73.91

600.00 1
1,200.00 1
1,050.00 1
3.00
TOTAL LABOUR 6.59
19.50

814.03 Per SQM : Rs 8,758.98


38.59 Per SQM : Rs 415.20

(British) : Sft

Rate (Rs)

120.00 1
60.00 1
TOTAL MATERIAL 35.87

600.00 1
750.00 1

3.00
TOTAL LABOUR 44.63
19.50

1,099.09 Per SQM : Rs 11,826.18


597.19 Per SQM : Rs 6,425.74

25.7.4
(British) : Rft

Rate (Rs) Amount

Ltr 401.22
Kg 110.00
No 45.00
Rft 45.00
TOTAL MATERIAL

Day 1,200.00
Day 600.00
Day 1,050.00
Day 750.00

TOTAL LABOUR
Over Heads on(M+L+E) 2% +

Rs. 1,470.37
Rs. 330.75

Spec. No :
Unit (British) : Rft
Providing and fixing barbed wire (12 Guage) fencing consisting of
3.25 ft long, 5 to 6 ft centre to
centre embedded in cement concrete 1:2:4 base of size 9"x9"x12", and 3
rows of barbed wire, painting posts, etc. complete in all respects.
Rate (Rs)

550.00 1
2,000.00 100 Cft
3,290.00 100 Cft
167.00 1
401.22 1
110.00 1
TOTAL MATERIAL 49.30

1,200.00 1
600.00 1
1,200.00 1
1,050.00 1
600.00 1
3.00
TOTAL LABOUR 31.20
19.50

193.26 Per Meter : Rs 633.89


71.42 Per Meter : Rs 234.27

Spec. No : 25.7.4
Unit (British) : Rft
Providing and fixing barbed (22 SWG) wire fence on compound wall,
/16" angle iron post 3 ft long, 4 ft apart
embedded in cement concrete 1:2:4 base of size 6"x6"x9", and 4 rows of
barbed wire, including binding wire, painting posts, etc. complete in

Rate (Rs)

550.00 1
2,000.00 100 Cft
3,290.00 100 Cft
167.00 1
401.22 1
110.00 1
TOTAL MATERIAL 50.66

1,200.00 1
600.00 1
1,200.00 1
1,050.00 1
600.00 1
3.00
TOTAL LABOUR 29.84
19.50

217.20 Per Meter : Rs 712.40


76.44 Per Meter : Rs 250.72

(British) : Sft

Rate (Rs)

143.20 1
401.22 1
464.10 1
146.00 1
101.00 1
80.00 1

TOTAL MATERIAL 65.88

600.00 1
1,200.00 1
1,050.00 1
1,050.00 1
3.00
TOTAL LABOUR 14.62
19.50
918.79 Per SQM : Rs 9,886.13
140.66 Per SQM : Rs 1,513.51

(British) : Sft

Rate (Rs)

143.20 1
194.00 1
401.22 1
464.10 1
146.00 1
80.00 1

494.00 1
66.00 1
TOTAL MATERIAL 60.20

600.00 1
1,200.00 1
1,050.00 1
1,050.00 1
3.00
TOTAL LABOUR 20.30
19.50

649.00 Per SQM : Rs 6,983.27


147.72 Per SQM : Rs 1,589.43
(British) : Sft

Rate (Rs)

143.20 1
194.00 1
401.22 1
464.10 1
146.00 1
110.00 1
66.00 1
535.00 1
TOTAL MATERIAL 56.94

1,200.00 1
600.00 1
1,200.00 1
1,050.00 1
1,050.00 1
3.00
TOTAL LABOUR 23.56
19.50

888.56 Per SQM : Rs 9,560.87


240.01 Per SQM : Rs 2,582.55

25.4.2
(British) : Rft

Rate (Rs)

230.00 1
TOTAL MATERIAL 33.05

600.00 1
1,050.00 1
600.00 1
3.00
TOTAL LABOUR 47.45
19.50

653.83 Per Meter : Rs 2,144.58


378.98 Per Meter : Rs 1,243.07

25.7.4
(British) : Rft

Rate (Rs) Amount

900.00 1

TOTAL MATERIAL 60.59

600.00 1
1,050.00 1
3.00
TOTAL LABOUR 19.91
19.50

1,383.28 Per Meter : Rs 4,537.16


307.78 Per Meter : Rs 1,009.52
(British) : sft

Rate (Rs)

600.00 1
3.00
TOTAL LABOUR 80.50
19.50

367.50 Per SQM : Rs 3,954.30


367.50 Per SQM : Rs 3,954.30

25.4.8
(British) : Kg

Rate (Rs)

145.00 1

TOTAL MATERIAL 53.11

600.00 1
1,050.00 1
3.00
TOTAL LABOUR 27.39
19.50

254.86 Cost Per Kg: 254.86


81.58 Cost Per Kg: 81.58
Spec. No :
Unit (British) : Each
Providing and Fixing of Steel Bracket (heavy) for Split Unit outside
Rate (Rs)

500.00 1

TOTAL MATERIAL 67.04

600.00 1
3.00
TOTAL LABOUR 13.46
19.50

693.05 Cost Per Each: 693.05


95.55 Cost Per Each: 95.55

Spec. No :
Unit (British) : Each
l bracket for curtain pipe
Rate (Rs)

50.00 1

TOTAL MATERIAL 59.62

600.00 1
3.00
TOTAL LABOUR 20.88
19.50
156.25 Cost Per Each: 156.25
36.75 Cost Per Each: 36.75

Spec. No : 25.3.8
Unit (British) : RFT
Iron (2''x2''x1/8'')
Rate (Rs)

110.00 1
TOTAL MATERIAL 59.62

1,050.00 1
600.00 1
3.00
TOTAL LABOUR 20.88
19.50

171.88 Per Meter : Rs 563.75


40.43 Per Meter : Rs 132.59

(British) : Each

Rate (Rs)

95.00 1
120.00 1

TOTAL MATERIAL 44.46


1,200.00 1
3.00
TOTAL LABOUR 36.04
19.50

679.99 Cost Per Each: 679.99


294.00 Cost Per Each: 294.00

(British) : Sft

Rate (Rs)

401.22 1
300.00 1
TOTAL MATERIAL 53.13

1,200.00 1
1,050.00 1
3.00
TOTAL LABOUR 27.37
19.50

597.55 Per SQM : Rs 6,429.59


191.10 Per SQM : Rs 2,056.24

Spec. No :
Unit (British) : Sft
Rate (Rs)

464.10 1
TOTAL MATERIAL 5.22

600.00 1
1,050.00 1
3.00
TOTAL LABOUR 56.64

221.90 1
TOTAL EQUIPMENT 18.64
19.50

52.73 Per SQM : Rs 567.32


36.77 Per SQM : Rs 395.63

(British) : Each

Rate (Rs)

9,000.00 1

TOTAL MATERIAL 59.62

600.00 1
1,050.00 1
3.00
TOTAL LABOUR 20.88
19.50

14,062.50 Cost Per Each: 14,062.50


3,307.50 Cost Per Each: 3,307.50
(British) : Sft

Rate (Rs)

550.00 1 bag
2,000.00 1 cft
164.00 1 ft
110.00 1 Kg
131.75 1 Kg
1,500.00 1 no.

TOTAL MATERIAL 46.15

1,200.00 1
600.00 1
850.00 1
1,050.00 1
3.00
TOTAL LABOUR 34.35
19.50

548.92 Per SQM : Rs 5,906.43


225.32 Per SQM : Rs 2,424.45
(British) : Rft

Rate (Rs)

140.00 1 Rft

1,500.00 1 ltr

TOTAL MATERIAL 23.90

1,200.00 1
600.00 1
1,200.00 2
3.00
TOTAL LABOUR 56.60
19.50

1,143.22 Per Meter : Rs 3,749.75


796.67 Per Meter : Rs 2,613.07

(British) : Sft

Rate (Rs)

110.00 1
TOTAL MATERIAL 35.23

600.00 1
1,050.00 1
3.00
TOTAL LABOUR 45.27
19.50

293.15 Per SQM : Rs 3,154.29


161.70 Per SQM : Rs 1,739.89

(British) : Sft

Rate (Rs) Amount

464.10 1
370.00 1

440.00 1

580.00 1

110.00 1
110.00 1
TOTAL MATERIAL 73.72

600.00 1
1,050.00 1
3.00
TOTAL LABOUR 6.78
19.50

449.45 Per SQM : Rs 4,836.10


22.44 Per SQM : Rs 241.41
(British) : Sft

Rate (Rs) Amount

464.10 1
370.00 1

440.00 1

580.00 1

110.00 1
100.00 1
TOTAL MATERIAL 74.34

600.00 1
1,050.00 1
3.00
TOTAL LABOUR 6.16
19.50

536.69 Per SQM : Rs 5,774.75


22.44 Per SQM : Rs 241.41
(British) : Sft

Rate (Rs) Amount

464.10 1
370.00 1

440.00 1

580.00 1

110.00 1
100.00 1
TOTAL MATERIAL 75.59

600.00 1
1,050.00 1
3.00
TOTAL LABOUR 4.91
19.50

882.76 Per SQM : Rs 9,498.49


22.23 Per SQM : Rs 239.24

(British) : Sft

Rate (Rs)
401.22 1 Ltr
464.10 1 Pack
122.00 1 Rft

110.00 1 Sft

TOTAL MATERIAL 70.82

600.00 1
1,200.00 1
1,050.00 1
1,050.00 1
3.00
TOTAL LABOUR 9.68
19.50

410.84 Per SQM : Rs 4,420.68


36.22 Per SQM : Rs 389.70

(British) : Rft

Rate (Rs)

550.00 1
2,000.00 100 Cft
3,438.00 100 Cft
122.00 1

91.60 1
250.00 1
TOTAL MATERIAL 65.02

1,200.00 1
600.00 1
1,050.00 1
3.00
TOTAL LABOUR 15.48
19.50

257.11 Per Meter : Rs 843.33


42.26 Per Meter : Rs 138.62

(British) : Rft

Rate (Rs)

550.00 1
2,000.00 100 Cft
3,438.00 100 Cft
122.00 1

91.60 1
160.00 1
TOTAL MATERIAL 59.59

1,200.00 1
600.00 1
1,050.00 1
3.00
TOTAL LABOUR 20.91
19.50
179.44 Per Meter : Rs 588.55
42.26 Per Meter : Rs 138.62

(British) : Rft

Rate (Rs)

122.00 1

91.60 1
110.00 1
250.00 1
TOTAL MATERIAL 65.59

1,200.00 1
600.00 1
1,050.00 1
3.00
TOTAL LABOUR 14.91
19.50

269.41 Per Meter : Rs 883.66


42.26 Per Meter : Rs 138.62
(British) : Rft

Rate (Rs)

122.00 1

91.60 1
110.00 1
160.00 1
TOTAL MATERIAL 60.75

1,200.00 1
600.00 1
1,050.00 1
3.00
TOTAL LABOUR 19.75
19.50

191.73 Per Meter : Rs 628.88


42.26 Per Meter : Rs 138.62

(British) : Sft

Rate (Rs)

346.00 1
464.10 1
116.13 1
75.00 1

70.00 1
267.00 1
140.00 1
TOTAL MATERIAL 61.56

600.00 1
1,200.00 1
1,050.00 1
3.00
TOTAL LABOUR 18.94
19.50

614.95 Per SQM : Rs 6,616.81


128.99 Per SQM : Rs 1,387.96

26.6.6
(British) : No

Rate (Rs) Amount

26,000.00 1

TOTAL MATERIAL 71.82

1,200.00 1
3.00
TOTAL LABOUR 3.83

1,756.18 1
TOTAL EQUIPMENT 4.85
19.50
33,536.14 Cost Per No: 33,536.14
367.50 Cost Per No: 367.50

26.6.6
(British) : No

Rate (Rs) Amount

24,000.00 1

TOTAL MATERIAL 70.81

850.00 1
1,200.00 1
3.00
TOTAL LABOUR 4.51

1,756.18 1
TOTAL EQUIPMENT 5.18
19.50

31,406.45 Cost Per No: 31,406.45


627.81 Cost Per No: 627.81
26.6.6
(British) : No

Rate (Rs)

37,000.00 1

TOTAL MATERIAL 72.72

850.00 1
1,200.00 1
3.00
TOTAL LABOUR 4.33

1,756.18 1
TOTAL EQUIPMENT 3.45
19.50

47,142.35 Cost Per No: 47,142.35


828.71 Cost Per No: 828.71

26.6.6
(British) : No

Rate (Rs)

35,000.00 1
TOTAL MATERIAL 72.46

850.00 1
1,200.00 1
3.00
TOTAL LABOUR 4.40

1,756.18 1
TOTAL EQUIPMENT 3.64
19.50

44,752.35 Cost Per No: 44,752.35


828.71 Cost Per No: 828.71

26.6.6
(British) : No

Unit Rate (Rs)

No 50,000.00 1

TOTAL MATERIAL 73.42

Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 4.51

Hour 1,756.18 1
TOTAL EQUIPMENT 2.58
19.50

63,104.26 Cost Per No: 63,104.26


1,255.63 Cost Per No: 1,255.63
0.00
(British) : No

Unit Rate (Rs)

No 48,000.00 1

TOTAL MATERIAL 73.26

Day 850.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 4.56

Hour 1,756.18 1
TOTAL EQUIPMENT 2.68
19.50

60,714.26 Cost Per No: 60,714.26


1,255.63 Cost Per No: 1,255.63

Spec. No :
Unit (British) : Rft
: 1" i/d
Rate (Rs)

65.00 1
TOTAL MATERIAL 70.95

1,200.00 1
3.00
TOTAL LABOUR 9.55
19.50

85.03 Per Meter : Rs 278.88


7.35 Per Meter : Rs 24.11

Spec. No :
Unit (British) : Rft
: 1.5" i/d
Rate (Rs)

85.00 1

TOTAL MATERIAL 72.39

1,200.00 1
3.00
TOTAL LABOUR 8.11
19.50

108.93 Per Meter : Rs 357.27


7.35 Per Meter : Rs 24.11

Spec. No :
Unit (British) : Rft
: 2" i/d
Rate (Rs)
95.00 1
TOTAL MATERIAL 72.90

1,200.00 1
3.00
TOTAL LABOUR 7.60
19.50

120.88 Per Meter : Rs 396.47


7.35 Per Meter : Rs 24.11

15.6.1
(British) : No

Rate (Rs) Amount

23,000.00 1

TOTAL MATERIAL 76.70

1,200.00 1
1,250.00 1
3.00
TOTAL LABOUR 3.51

1,756.18 1
TOTAL EQUIPMENT 0.29
19.50

27,777.51 Cost Per No: 27,777.51


187.58 Cost Per No: 187.58
15.6.1
(British) : No

Rate (Rs) Amount

31,000.00 1

TOTAL MATERIAL 75.00

1,200.00 1
1,250.00 1
3.00
TOTAL LABOUR 3.37

1,756.18 1
TOTAL EQUIPMENT 2.12
19.50

38,281.90 Cost Per No: 38,281.90


187.58 Cost Per No: 187.58

15.6.1
(British) : No

Rate (Rs) Amount


42,000.00 1

TOTAL MATERIAL 75.64

1,200.00 1
1,250.00 1
3.00
TOTAL LABOUR 3.28

1,756.18 1
TOTAL EQUIPMENT 1.58
19.50

51,426.90 Cost Per No: 51,426.90


187.58 Cost Per No: 187.58

15.6.1
(British) : No

Rate (Rs) Amount

55,000.00 1

TOTAL MATERIAL 76.07

1,200.00 1
1,250.00 1
3.00
TOTAL LABOUR 3.21

1,756.18 1
TOTAL EQUIPMENT 1.21
19.50
66,961.90 Cost Per No: 66,961.90
187.58 Cost Per No: 187.58

Spec. No :
Unit (British) : No
Supply and Erection of AC ENERGY EFFICIENT LED LIGHT BULBS (7-10 W)
Rate (Rs)

500.00 1

TOTAL MATERIAL 67.32

1,200.00 1
3.00
TOTAL LABOUR 13.18
19.50

690.11 Cost Per No: 690.11


92.61 Cost Per No: 92.61

Spec. No :
Unit (British) : No
Supply and Erection of AC ENERGY EFFICIENT LED LIGHT BULBS (16-20 W)
Rate (Rs)

650.00 1

TOTAL MATERIAL 69.43

1,200.00 1
3.00
TOTAL LABOUR 11.07
19.50

869.36 Cost Per No: 869.36


92.61 Cost Per No: 92.61

Spec. No :
Unit (British) : No
Supply and Erection of AC ENERGY EFFICIENT LED LIGHT BULBS (21-30 W)
Rate (Rs)

800.00 1

TOTAL MATERIAL 70.81

1,200.00 1
3.00
TOTAL LABOUR 9.69
19.50

1,048.61 Cost Per No: 1,048.61


92.61 Cost Per No: 92.61

Spec. No :
Unit (British) : No
Supply and Erection of AC ENERGY EFFICIENT LED LIGHT BULBS (31-50 W)
Rate (Rs)

1,000.00 1

TOTAL MATERIAL 72.05

1,200.00 1
3.00
TOTAL LABOUR 8.45
19.50

1,287.61 Cost Per No: 1,287.61


92.61 Cost Per No: 92.61

Spec. No :
Unit (British) : No
Supply and Erection of DC ENERGY EFFICIENT LED LIGHT BULBS (51-100 W)
Rate (Rs)

2,000.00 1

TOTAL MATERIAL 74.68

1,200.00 1
3.00
TOTAL LABOUR 5.82
19.50

2,482.61 Cost Per No: 2,482.61


92.61 Cost Per No: 92.61

Spec. No : 26.34
Unit (British) : No
Supply and Erection of AC ENERGY EFFICIENT LED LIGHT BULBS (11-15 W)
Rate (Rs)

595.00 1

TOTAL MATERIAL 68.76


1,200.00 1
3.00
TOTAL LABOUR 11.74
19.50

803.63 Cost Per no: 803.63


92.61 Cost Per no: 92.61

26.10
(British) : Watt

Rate (Rs)

60.00 1

TOTAL MATERIAL 76.58

1,200.00 1
3.00
TOTAL LABOUR 3.92
19.50

72.58 Cost Per Watt: 72.58


0.88 Cost Per Watt: 0.88

26.10
(British) : Watt
Rate (Rs)

58.00 1

TOTAL MATERIAL 76.55

1,200.00 1
3.00
TOTAL LABOUR 3.95
19.50

70.19 Cost Per Watt: 70.19


0.88 Cost Per Watt: 0.88

26.41
(British) : No

Rate (Rs)

9,325.00 1

TOTAL MATERIAL 76.88

1,200.00 1
3.00
TOTAL LABOUR 3.62
19.50

11,235.98 Cost Per No: 11,235.98


92.61 Cost Per No: 92.61
26.41
(British) : No

Rate (Rs)

13,385.00 1

TOTAL MATERIAL 77.06

1,200.00 1
3.00
TOTAL LABOUR 3.44
19.50

16,087.68 Cost Per No: 16,087.68


92.61 Cost Per No: 92.61

26.41
(British) : No

Rate (Rs)

9,750.00 1

TOTAL MATERIAL 76.90

1,200.00 1
3.00
TOTAL LABOUR 3.60
19.50

11,743.86 Cost Per No: 11,743.86


92.61 Cost Per No: 92.61

26.41
(British) : No

Rate (Rs)

19,925.00 1

TOTAL MATERIAL 77.21

1,200.00 1
3.00
TOTAL LABOUR 3.29
19.50

23,902.98 Cost Per No: 23,902.98


92.61 Cost Per No: 92.61

26.41
(British) : No

Rate (Rs)
28,490.00 1

TOTAL MATERIAL 77.29

1,200.00 1
3.00
TOTAL LABOUR 3.21
19.50

34,138.16 Cost Per No: 34,138.16


92.61 Cost Per No: 92.61

26.42
(British) : No

Rate (Rs)

30,550.00 1

TOTAL MATERIAL 77.31

1,200.00 1
3.00
TOTAL LABOUR 3.19
19.50

36,599.86 Cost Per No: 36,599.86


92.61 Cost Per No: 92.61
26.43
(British) : No

Rate (Rs)

34,625.00 1

TOTAL MATERIAL 77.33

1,200.00 1
3.00
TOTAL LABOUR 3.17
19.50

41,469.48 Cost Per No: 41,469.48


92.61 Cost Per No: 92.61

26.44
(British) : No

Rate (Rs)

39,530.00 1

TOTAL MATERIAL 77.35

1,200.00 1
3.00
TOTAL LABOUR 3.15
19.50

47,330.96 Cost Per No: 47,330.96


92.61 Cost Per No: 92.61
Spec. No :
Unit (British) : AH
2 V VRLA GEL battery per AH
Rate (Rs)

258.00 1
TOTAL MATERIAL 76.43

1,200.00 1
3.00
TOTAL LABOUR 4.07
19.50

312.72 Cost Per AH: 312.72


4.41 Cost Per AH: 4.41

Spec. No :
Unit (British) : AH
2 V VRLA AGM Battery per AH
Rate (Rs)

242.00 1
TOTAL MATERIAL 76.36

1,200.00 1
3.00
TOTAL LABOUR 4.14
19.50

293.60 Cost Per AH: 293.60


4.41 Cost Per AH: 4.41
Spec. No :
Unit (British) : AH
2 V Lead Carbon Battery per AH
Rate (Rs)

274.00 1
TOTAL MATERIAL 76.49

1,200.00 1
3.00
TOTAL LABOUR 4.01
19.50

331.84 Cost Per AH: 331.84


4.41 Cost Per AH: 4.41

Spec. No :
Unit (British) : AH
2V OPzV battery per AH
Rate (Rs)

266.00 1
TOTAL MATERIAL 76.47

1,200.00 1
3.00
TOTAL LABOUR 4.03
19.50

322.28 Cost Per AH: 322.28


4.41 Cost Per AH: 4.41
Spec. No :
Unit (British) : AH
2V OPzS battery per AH
Rate (Rs)

200.00 1
TOTAL MATERIAL 76.13

1,200.00 1
3.00
TOTAL LABOUR 4.37
19.50

243.41 Cost Per AH: 243.41


4.41 Cost Per AH: 4.41

Spec. No :
Unit (British) : AH
Supply and Erection of 12 V Lithium LiFeP04 battery per AH
Rate (Rs)

56,220.00 1
TOTAL MATERIAL 75.88

1,200.00 1
3.00
TOTAL LABOUR 4.62
19.50

68,652.90 Cost Per AH: 68,652.90


1,470.00 Cost Per AH: 1,470.00
Spec. No :
Unit (British) : AH
2 V OPzV battery per AH
Rate (Rs)

80.70 1
TOTAL MATERIAL 76.36

1,200.00 1
3.00
TOTAL LABOUR 4.14
19.50

97.91 Cost Per ah: 97.91


1.47 Cost Per ah: 1.47

Spec. No :
Unit (British) : AH
2 V OPzS battery per AH
Rate (Rs)

68.40 1
TOTAL MATERIAL 76.16

1,200.00 1
3.00
TOTAL LABOUR 4.34
19.50

83.21 Cost Per ah: 83.21


1.47 Cost Per ah: 1.47
Spec. No :
Unit (British) : Rft
5 sq.mm flexible copper cable
Rate (Rs)

28.00 1

TOTAL MATERIAL 74.32

1,200.00 1
3.00
TOTAL LABOUR 6.18
19.50

34.93 Per Meter : Rs 114.57


1.47 Per Meter : Rs 4.82

Spec. No :
Unit (British) : Rft
Supply and Erection 1x4 sq.mm double insulated flexible copper cable
Rate (Rs)

42.00 1

TOTAL MATERIAL 75.35

1,200.00 1
3.00
TOTAL LABOUR 5.15
19.50
51.66 Per Meter : Rs 169.44
1.47 Per Meter : Rs 4.82

26.2, 26.43
(British) : Rft

Rate (Rs)

57.00 1

TOTAL MATERIAL 75.90

1,200.00 1
3.00
TOTAL LABOUR 4.60
19.50

69.59 Per Meter : Rs 228.24


1.47 Per Meter : Rs 4.82

Spec. No :
Unit (British) : Rft
0 sq.mm flexible copper cable
Rate (Rs)

88.00 1

TOTAL MATERIAL 76.46


1,200.00 1
3.00
TOTAL LABOUR 4.04
19.50

106.63 Per Meter : Rs 349.75


1.47 Per Meter : Rs 4.82

Spec. No :
Unit (British) : Rft

Rate (Rs)

137.00 1

TOTAL MATERIAL 76.94

1,000.00 1
3.00
TOTAL LABOUR 3.56
19.50

164.94 Per Meter : Rs 541.00


1.23 Per Meter : Rs 4.02

Spec. No :
Unit (British) : Rft

Rate (Rs)

195.00 1
TOTAL MATERIAL 77.10
1,000.00 1
3.00
TOTAL LABOUR 3.40
19.50

234.25 Per Meter : Rs 768.34


1.23 Per Meter : Rs 4.02

Spec. No :
Unit (British) : Rft
5 sq.mm Copper cable
Rate (Rs)

268.00 1

TOTAL MATERIAL 77.21

1,000.00 1
3.00
TOTAL LABOUR 3.29
19.50

321.49 Per Meter : Rs 1,054.47


1.23 Per Meter : Rs 4.02

Spec. No :
Unit (British) : Rft
5 sq.mm flexible copper cable
Rate (Rs)

51.50 1
TOTAL MATERIAL 75.74

1,200.00 1
3.00
TOTAL LABOUR 4.76
19.50

63.01 Per Meter : Rs 206.68


1.47 Per Meter : Rs 4.82

Spec. No :
Unit (British) : Rft
sq.mm flexible copper cable
Rate (Rs)

77.50 1

TOTAL MATERIAL 76.32

1,200.00 1
3.00
TOTAL LABOUR 4.18
19.50

94.08 Per Meter : Rs 308.59


1.47 Per Meter : Rs 4.82

Spec. No :
Unit (British) : Rft
sq.mm flexible copper cable
Rate (Rs)
108.00 1

TOTAL MATERIAL 76.65

1,200.00 1
3.00
TOTAL LABOUR 3.85
19.50

130.53 Per Meter : Rs 428.14


1.47 Per Meter : Rs 4.82

Spec. No :
Unit (British) : Rft
0 sq.mm flexible copper cable
Rate (Rs)

154.00 1

TOTAL MATERIAL 76.90

1,200.00 1
3.00
TOTAL LABOUR 3.60
19.50

185.50 Per Meter : Rs 608.44


1.47 Per Meter : Rs 4.82

Spec. No :
Unit (British) : Rft
6 sq.mm Copper cable
Rate (Rs)

320.00 1
TOTAL MATERIAL 77.21

1,200.00 1
3.00
TOTAL LABOUR 3.29
19.50

383.87 Per Meter : Rs 1,259.09


1.47 Per Meter : Rs 4.82

Spec. No :
Unit (British) : Rft
5sq.mm Copper cable
Rate (Rs)

450.00 1
TOTAL MATERIAL 77.29

1,200.00 1
3.00
TOTAL LABOUR 3.21
19.50

539.22 Per Meter : Rs 1,768.64


1.47 Per Meter : Rs 4.82

Spec. No :
Unit (British) : Rft
5 sq.mm Copper cable
Rate (Rs)

650.00 1
TOTAL MATERIAL 77.36

1,200.00 1
3.00
TOTAL LABOUR 3.14
19.50

778.22 Per Meter : Rs 2,552.56


1.47 Per Meter : Rs 4.82

Spec. No : 26.20
Unit (British) : Pair
4 connector (TUV Approved)
Rate (Rs)

187.50 1

TOTAL MATERIAL 64.57

1,200.00 1
3.00
TOTAL LABOUR 15.93
19.50

270.07 Cost Per Pair: 270.07


46.01 Cost Per Pair: 46.01

Spec. No :
Unit (British) : Pair
4 Branch connector
Rate (Rs)

900.00 1
TOTAL MATERIAL 74.40

1,200.00 1
3.00
TOTAL LABOUR 6.10
19.50

1,121.51 Cost Per Pair: 1,121.51


46.01 Cost Per Pair: 46.01

26.28
(British) : Per Watt

Rate (Rs)

64.36 1

TOTAL MATERIAL 76.08

1,200.00 1
3.00
TOTAL LABOUR 4.42
19.50

78.38 Cost Per Per Watt: 78.38


1.47 Cost Per Per Watt: 1.47
26.28
(British) : Per Watt

Rate (Rs)

33.30 1

TOTAL MATERIAL 74.80

1,200.00 1
3.00
TOTAL LABOUR 5.70
19.50

41.26 Cost Per Per Watt: 41.26


1.47 Cost Per Per Watt: 1.47

26.28
(British) : Per Watt

Rate (Rs)

21.12 1

TOTAL MATERIAL 73.33

1,200.00 1
3.00
TOTAL LABOUR 7.17
19.50

26.71 Cost Per per watt: 26.71


1.47 Cost Per per watt: 1.47

26.38
(British) : Per Watt

Rate (Rs)

12.95 1

TOTAL MATERIAL 70.93

1,200.00 1
3.00
TOTAL LABOUR 9.57
19.50

16.95 Cost Per Per Watt: 16.95


1.47 Cost Per Per Watt: 1.47

Spec. No : 26.28
Unit (British) : Per Watt
ff Grid Hybrid inverter
Rate (Rs)
per Watt 17.45 1

TOTAL MATERIAL 72.51

1,200.00 1
3.00
TOTAL LABOUR 7.99
19.50

22.32 Cost Per per watt: 22.32


1.47 Cost Per per watt: 1.47

Spec. No : 26.28
Unit (British) : Per Watt
n Grid Hybrid inverter
Rate (Rs)

Per Watt 39.89 1

TOTAL MATERIAL 75.24

1,200.00 1
3.00
TOTAL LABOUR 5.26
19.50

49.14 Cost Per per watt: 49.14


1.47 Cost Per per watt: 1.47

Spec. No : 26.37
Unit (British) : Per Watt
Supply and Erection of GRID TIE INVERTER (ON-Grid Inverter) (0-10 KW)
Unit Rate (Rs)

Watt 21.13 1

TOTAL MATERIAL 75.36

1,200.00 1
3.00
TOTAL LABOUR 5.14
19.50

25.99 Cost Per Per Watt: 25.99


0.74 Cost Per Per Watt: 0.74

Spec. No : 26.37
Unit (British) : Per Watt
Supply and Erection of GRID TIE INVERTER (ON-Grid Inverter) (10-20 KW)
Unit Rate (Rs)

Watt 19.50 1

TOTAL MATERIAL 75.19

1,200.00 1
3.00
TOTAL LABOUR 5.31
19.50

24.04 Cost Per Per Watt: 24.04


0.74 Cost Per Per Watt: 0.74
Spec. No : 26.37
Unit (British) : Per Watt
Supply and Erection of GRID TIE INVERTER (ON-Grid Inverter) (20-30 KW)
Unit Rate (Rs)

Watt 17.87 1

TOTAL MATERIAL 74.98

1,200.00 1
3.00
TOTAL LABOUR 5.52
19.50

22.09 Cost Per Per Watt: 22.09


0.74 Cost Per Per Watt: 0.74

26.37
(British) : Per Watt

Rate (Rs)

16.23 1

TOTAL MATERIAL 74.74

1,200.00 1
3.00
TOTAL LABOUR 5.76
19.50
20.13 Cost Per Per Watt: 20.13
0.74 Cost Per Per Watt: 0.74

Spec. No : 26.29
Unit (British) : No
Supply and Erection of dV /dT or Sine Filters 11 KW to 18.5 KW
Rate (Rs)

73,550.00 1

TOTAL MATERIAL 76.87

1,200.00 1
3.00
TOTAL LABOUR 3.63
19.50

88,627.25 Cost Per no: 88,627.25


735.00 Cost Per no: 735.00

26.29
(British) : No

Rate (Rs)

111,000.00 1

TOTAL MATERIAL 77.08


1,200.00 1
3.00
TOTAL LABOUR 3.42
19.50

133,380.00 Cost Per no: 133,380.00


735.00 Cost Per no: 735.00

26.23
(British) : No

Rate (Rs)

65,000.00 1

TOTAL MATERIAL 76.10

1,200.00 1
3.00
TOTAL LABOUR 4.40
19.50

79,145.00 Cost Per No: 79,145.00


1,470.00 Cost Per No: 1,470.00

26.23
(British) : No
Rate (Rs)

100,000.00 1

TOTAL MATERIAL 76.58

1,200.00 1
3.00
TOTAL LABOUR 3.92
19.50

120,970.00 Cost Per No: 120,970.00


1,470.00 Cost Per No: 1,470.00

26.23
(British) : No

Rate (Rs)

200,000.00 1

TOTAL MATERIAL 77.04

1,200.00 1
3.00
TOTAL LABOUR 3.46
19.50

240,470.00 Cost Per No: 240,470.00


1,470.00 Cost Per No: 1,470.00
26.23
(British) : No

Rate (Rs)

320,000.00 1

TOTAL MATERIAL 77.21

1,200.00 1
3.00
TOTAL LABOUR 3.29
19.50

383,870.00 Cost Per No: 383,870.00


1,470.00 Cost Per No: 1,470.00

26.24
(British) : No

Rate (Rs)

600,000.00 1

TOTAL MATERIAL 77.19

1,200.00 1
3.00
TOTAL LABOUR 3.31
19.50
719,940.00 Cost Per No: 719,940.00
2,940.00 Cost Per No: 2,940.00

Spec. No :
Unit (British) : No
Supply and Erection of AC ENERGY EFFICIENT CEILING FANS 56 inch, 50 W
Unit Rate (Rs)

No 4,668.00

TOTAL MATERIAL 75.37

1,200.00 1
3.00
TOTAL LABOUR 5.13
19.50

5,739.96 Cost Per No: 5,739.96


161.70 Cost Per No: 161.70

Spec. No :
Unit (British) : No
C CEILING FANS 48 inch 30-36 W
Rate (Rs)

3,700.00 1

TOTAL MATERIAL 74.83


1,200.00 1
3.00
TOTAL LABOUR 5.67
19.50

4,583.20 Cost Per No: 4,583.20


161.70 Cost Per No: 161.70

Spec. No :
Unit (British) : No
C PEDISTAL FANS 18 inch 18-30 W
Rate (Rs)

3,900.00 1

TOTAL MATERIAL 74.96

1,200.00 1
3.00
TOTAL LABOUR 5.54
19.50

4,822.20 Cost Per No: 4,822.20


161.70 Cost Per No: 161.70

15.6.6
(British) : Per Watt
Rate (Rs) Amount

17.03 1 Watt

TOTAL MATERIAL 72.40

1,200.00 1
3.00
TOTAL LABOUR 8.10
19.50

21.82 Cost Per Per Watt: 21.82


1.47 Cost Per Per Watt: 1.47

Spec. No :
Unit (British) : Watt
opper Conductor of 10 AWG
Rate (Rs)

7.00 1

TOTAL MATERIAL 66.16

1,200.00 1
3.00
TOTAL LABOUR 14.34
19.50

9.84 Cost Per Watt: 9.84


1.47 Cost Per Watt: 1.47
Spec. No : 15.12
Unit (British) : Watt
Supply and Erection of 1x1 ft 4mm Copper Earthing Plate
Unit Rate (Rs)

No 2.00 1

TOTAL MATERIAL 48.44

1,200.00 1
3.00
TOTAL LABOUR 32.06
19.50

3.86 Cost Per Watt: 3.86


1.47 Cost Per Watt: 1.47

Spec. No : 0.00
Unit (British) : Watt
Supply and Erection of Stainless Steel Nuts and Bolts
Unit Rate (Rs)

Watt 2.00 1

TOTAL MATERIAL 48.44

1,200.00 1
3.00
TOTAL LABOUR 32.06
19.50
3.86 Cost Per Watt: 3.86
1.47 Cost Per Watt: 1.47

26.10
(British) : Watt

Rate (Rs)

4.00 1

TOTAL MATERIAL 59.62

1,200.00 1
3.00
TOTAL LABOUR 20.88
19.50

6.25 Cost Per Watt: 6.25


1.47 Cost Per Watt: 1.47

Spec. No : 26.17
Unit (British) : No
NVERTER BASED SPLIT AC (01 Ton)
Rate (Rs)

65,000.00 1
TOTAL MATERIAL 76.79
1,200.00 1
3.00
TOTAL LABOUR 3.71
19.50

78,410.00 Cost Per No: 78,410.00


735.00 Cost Per No: 735.00

Spec. No : 26.17
Unit (British) : No
NVERTER BASED SPLIT AC (1.5 Ton)
Rate (Rs)

70,000.00 1
TOTAL MATERIAL 76.84

1,200.00 1
3.00
TOTAL LABOUR 3.66
19.50

84,385.00 Cost Per No: 84,385.00


735.00 Cost Per No: 735.00

Spec. No : 26.17
Unit (British) : No
NVERTER BASED SPLIT AC (02 Ton)
Rate (Rs)

75,000.00 1
TOTAL MATERIAL 76.88
1,200.00 1
3.00
TOTAL LABOUR 3.62
19.50

90,360.00 Cost Per No: 90,360.00


735.00 Cost Per No: 735.00

Spec. No : 26.33
Unit (British) : No
Supply and Erection of SOLAR AUTO TRACKER for 3.6 KW installation
Rate (Rs)

223,800.00 1

TOTAL MATERIAL 77.09

1,200.00 1
3.00
TOTAL LABOUR 3.41
19.50

268,911.00 Cost Per No: 268,911.00


1,470.00 Cost Per No: 1,470.00

Spec. No :
Unit (British) : kW
Supply and Erection of PV MOUNTING FRAME WITH MANUAL TRAKERING
Rate (Rs)

24,461.00 1
TOTAL MATERIAL 77.38

1,200.00 1
3.00
TOTAL LABOUR 3.12
19.50

29,276.47 Cost Per kW: 29,276.47


45.57 Cost Per kW: 45.57

(British) : Each

Rate (Rs)

130.00 1
464.10 1
TOTAL MATERIAL 22.28

600.00 1
1,200.00 1
1,050.00 1
3.00
TOTAL LABOUR 58.22
19.50

514.67 Cost Per Each: 514.67


369.34 Cost Per Each: 369.34
(British) : Each

Rate (Rs)

130.00 1
30.00 1
TOTAL MATERIAL 13.39

1,200.00 1
1,050.00 1
3.00
TOTAL LABOUR 67.11
19.50

349.48 Cost Per Each: 349.48


290.33 Cost Per Each: 290.33

(British) : Rft

Rate (Rs)

2.00 1 RFT

TOTAL MATERIAL 21.12


600.00 1
1,200.00 1
3.00
TOTAL LABOUR 59.38
19.50

8.93 Per Meter : Rs 29.30


6.54 Per Meter : Rs 21.46

(British) : Sft

Rate (Rs)

Packet 464.10 1
TOTAL MATERIAL 18.59

600.00 1
1,050.00 1
3.00
TOTAL LABOUR 61.91
19.50

49.02 Per SQM : Rs 527.46


37.49 Per SQM : Rs 403.34

(British) : each
Rate (Rs) Amount

1,200.00 1
3.00
TOTAL LABOUR 80.50
19.50

147.00 Cost Per each: 147.00


147.00 Cost Per each: 147.00

(British) : Job

Rate (Rs) Amount

69.50 1 RFT

110.00 1 KG

TOTAL MATERIAL 45.89

1,200.00 1
1,050.00 1
3.00
TOTAL LABOUR 34.61
19.50
1,074.44 Cost Per Job: 1,074.44
444.68 Cost Per Job: 444.68

(British) : Job

Unit Rate (Rs)

No. 11,000.00 1
TOTAL MATERIAL 72.00

Day 600.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 8.50
19.50

14,174.00 Cost Per Job: 14,174.00


1,029.00 Cost Per Job: 1,029.00

(British) : Each

Rate (Rs) Amount


60.00 1 Each

TOTAL MATERIAL 14.70

850.00 1
1,200.00 1
3.00
TOTAL LABOUR 65.80
19.50

385.61 Cost Per Each: 385.61


313.91 Cost Per Each: 313.91

(British) : Each

Rate (Rs)

60.00 1 Each

TOTAL MATERIAL 12.65

850.00 1
1,200.00 1
3.00
TOTAL LABOUR 67.85
19.50

448.39 Cost Per Each: 448.39


376.69 Cost Per Each: 376.69

(British) : Each

Rate (Rs)

60.00 1 Each

TOTAL MATERIAL 12.36

850.00 1
1,200.00 1
3.00
TOTAL LABOUR 68.14
19.50

459.11 Cost Per Each: 459.11


387.41 Cost Per Each: 387.41
(British) : Each

Rate (Rs)

60.00 1 Each

TOTAL MATERIAL 10.00

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 70.50
19.50

567.83 Cost Per Each: 567.83


496.13 Cost Per Each: 496.13

(British) : Each

Rate (Rs)

60.00 1 Each
TOTAL MATERIAL 8.38

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 72.12
19.50

678.08 Cost Per Each: 678.08


606.38 Cost Per Each: 606.38

(British) : Each

Rate (Rs)

60.00 1 No

TOTAL MATERIAL 32.29

1,200.00 1
3.00
TOTAL LABOUR 48.21
19.50

174.60 Cost Per Each: 174.60


102.90 Cost Per Each: 102.90
(British) : Each

Rate (Rs)

9,500.00 1

TOTAL MATERIAL 74.27

600.00 1
1,050.00 1
3.00
TOTAL LABOUR 6.23
19.50

11,857.81 Cost Per Each: 11,857.81


505.31 Cost Per Each: 505.31

(British) : Each

Rate (Rs)

11,250.00 1

TOTAL MATERIAL 74.76


600.00 1
1,050.00 1
3.00
TOTAL LABOUR 5.74
19.50

13,949.06 Cost Per Each: 13,949.06


505.31 Cost Per Each: 505.31

(British) : Each

Rate (Rs)

5,500.00 1

TOTAL MATERIAL 72.09

600.00 1
1,050.00 1
3.00
TOTAL LABOUR 8.41
19.50

7,077.81 Cost Per Each: 7,077.81


505.31 Cost Per Each: 505.31

(British) : Each
Rate (Rs)

6,250.00 1

TOTAL MATERIAL 72.70

600.00 1
1,050.00 1
3.00
TOTAL LABOUR 7.80
19.50

7,974.06 Cost Per Each: 7,974.06


505.31 Cost Per Each: 505.31

(British) : H.P

Rate (Rs) Amount

650.00 1 HP

TOTAL MATERIAL 41.29

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 39.21
19.50
1,475.00 Cost Per H.P: 1,475.00
698.25 Cost Per H.P: 698.25

(British) : H.P

Rate (Rs) Amount

775.00 1 HP

TOTAL MATERIAL 41.86

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 38.64
19.50

1,734.63 Cost Per H.P: 1,734.63


808.50 Cost Per H.P: 808.50

(British) : H.P
Rate (Rs) Amount

650.00 1 HP

TOTAL MATERIAL 41.29

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 39.21
19.50

1,475.00 Cost Per H.P: 1,475.00


698.25 Cost Per H.P: 698.25

(British) : H.P

Rate (Rs)

775.00 1

TOTAL MATERIAL 41.86

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 38.64
19.50
1,734.63 Cost Per H.P: 1,734.63
808.50 Cost Per H.P: 808.50

Spec. No :
Unit (British) : Each
Coil for Ampere meter
Rate (Rs)

250.00 1
TOTAL MATERIAL 39.54

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 40.96
19.50

592.75 Cost Per Each: 592.75


294.00 Cost Per Each: 294.00

(British) : Job

Unit Rate (Rs)

Each 3,500.00 1
TOTAL MATERIAL 62.50

Day 600.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 18.00
19.50

5,211.50 Cost Per Job: 5,211.50


1,029.00 Cost Per Job: 1,029.00

(British) : Job

Unit Rate (Rs)

Each 5,600.00 1

TOTAL MATERIAL 63.82

Day 600.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 16.68
19.50

8,162.00 Cost Per Job: 8,162.00


1,470.00 Cost Per Job: 1,470.00
Spec. No :
Unit (British) : Each

Rate (Rs)

210.00 1
TOTAL MATERIAL 63.08

1,200.00 1
3.00
TOTAL LABOUR 17.42
19.50

309.75 Cost Per Each: 309.75


58.80 Cost Per Each: 58.80

Spec. No :
Unit (British) : Each
y size (Turbine/Submersible)
Rate (Rs)

4,500.00 1

TOTAL MATERIAL 68.38

1,200.00 1
3.00
TOTAL LABOUR 12.12
19.50

6,112.50 Cost Per Each: 6,112.50


735.00 Cost Per Each: 735.00
Spec. No :
Unit (British) : Set

Rate (Rs)

3,600.00 1
TOTAL MATERIAL 66.43

1,200.00 1
3.00
TOTAL LABOUR 14.07
19.50

5,037.00 Cost Per Set: 5,037.00


735.00 Cost Per Set: 735.00

Spec. No :
Unit (British) : Set

Rate (Rs)

320.00 1
TOTAL MATERIAL 56.36

1,200.00 1
3.00
TOTAL LABOUR 24.14
19.50

529.40 Cost Per Set: 529.40


147.00 Cost Per Set: 147.00
Spec. No :
Unit (British) : Rft
loumn Pipe Turbine
Rate (Rs)

490.00 1
TOTAL MATERIAL 48.07

1,200.00 1
3.00
TOTAL LABOUR 32.43
19.50

953.05 Per Meter : Rs 3,126.00


367.50 Per Meter : Rs 1,205.40

Spec. No :
Unit (British) : Rft

Rate (Rs)

380.00 1

TOTAL MATERIAL 47.50

1,200.00 1
3.00
TOTAL LABOUR 33.00
19.50

748.10 Per Meter : Rs 2,453.77


294.00 Per Meter : Rs 964.32
Spec. No :
Unit (British) : Job
Rewinding of Voltage Regulator complete in all respect: 3 coil
Rate (Rs)

13,800.00 1

TOTAL MATERIAL 71.30

1,200.00 1
3.00
TOTAL LABOUR 9.20
19.50

17,961.00 Cost Per Job: 17,961.00


1,470.00 Cost Per Job: 1,470.00

Spec. No :
Unit (British) : No.
Rewinding of Voltage Regulator coil complete in all respect:
Rate (Rs)

4,450.00 1

TOTAL MATERIAL 68.29

1,200.00 1
3.00
TOTAL LABOUR 12.21
19.50

6,052.75 Cost Per No.: 6,052.75


735.00 Cost Per No.: 735.00
Spec. No :
Unit (British) : Job
or point control machine
Rate (Rs)

3,580.00 1

TOTAL MATERIAL 66.38

1,200.00 1
3.00
TOTAL LABOUR 14.12
19.50

5,013.10 Cost Per Job: 5,013.10


735.00 Cost Per Job: 735.00

Spec. No :
Unit (British) : Job
or point control machine
Rate (Rs)

3,580.00 1

TOTAL MATERIAL 66.38

1,200.00 1
3.00
TOTAL LABOUR 14.12
19.50

5,013.10 Cost Per Job: 5,013.10


735.00 Cost Per Job: 735.00
Spec. No :
Unit (British) :
aft stainless steel
Unit Rate (Rs)

No 4,400.00

TOTAL MATERIAL

Day 1,200.00

TOTAL LABOUR

Rs. 6,140.00
Rs. 882.00

Spec. No :
Unit (British) : No.

Rate (Rs)

1,450.00 1
TOTAL MATERIAL 51.79

1,200.00 1
3.00
TOTAL LABOUR 28.71
19.50

2,614.75 Cost Per No.: 2,614.75


882.00 Cost Per No.: 882.00
Spec. No :
Unit (British) : No.
umn shaft Sleeve 20 to 30 mm
Rate (Rs)

590.00 1

TOTAL MATERIAL 59.38

1,200.00 1
3.00
TOTAL LABOUR 21.12
19.50

925.55 Cost Per No.: 925.55


220.50 Cost Per No.: 220.50

Spec. No :
Unit (British) : No.
pipe socket 3" to 6" i/d
Rate (Rs)

1,350.00 1

TOTAL MATERIAL 61.18

1,200.00 1
3.00
TOTAL LABOUR 19.32
19.50

2,054.25 Cost Per No.: 2,054.25


441.00 Cost Per No.: 441.00

Spec. No :
Unit (British) : No.

Rate (Rs)

1,150.00 1
TOTAL MATERIAL 50.93

1,200.00 1
3.00
TOTAL LABOUR 29.57
19.50

2,109.25 Cost Per No.: 2,109.25


735.00 Cost Per No.: 735.00

Spec. No :
Unit (British) : No.

Rate (Rs)

500.00 1

TOTAL MATERIAL 56.99

1,200.00 1
3.00
TOTAL LABOUR 23.51
19.50
818.00 Cost Per No.: 818.00
220.50 Cost Per No.: 220.50

Spec. No :
Unit (British) : No.

Rate (Rs)

25.00 1

TOTAL MATERIAL 43.83

1,200.00 1
3.00
TOTAL LABOUR 36.67
19.50

53.40 Cost Per No.: 53.40


23.52 Cost Per No.: 23.52

Spec. No :
Unit (British) : No.

Rate (Rs)

65.00 1
TOTAL MATERIAL 58.17

1,200.00 1
3.00
TOTAL LABOUR 22.33
19.50
104.13 Cost Per No.: 104.13
26.46 Cost Per No.: 26.46

Spec. No :
Unit (British) : No.

Rate (Rs)

80.00 1

TOTAL MATERIAL 16.81

1,050.00 1
3.00
TOTAL LABOUR 63.69
19.50

449.32 Cost Per No.: 449.32


353.72 Cost Per No.: 353.72

Spec. No :
Unit (British) : No.
le motor thrust bearing and disc
Rate (Rs)

9,750.00 1

TOTAL MATERIAL 69.97

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 10.53
19.50

12,937.50 Cost Per No.: 12,937.50


1,286.25 Cost Per No.: 1,286.25

(British) : Job

Rate (Rs)

3,350.00 1

TOTAL MATERIAL 64.50

600.00 1
1,050.00 1
3.00
TOTAL LABOUR 16.00
19.50

4,830.13 Cost Per Job: 4,830.13


826.88 Cost Per Job: 826.88

Spec. No :
Unit (British) : Job

Rate (Rs)
575.00 1

TOTAL MATERIAL 56.77

1,050.00 1
3.00
TOTAL LABOUR 23.73
19.50

944.38 Cost Per Job: 944.38


257.25 Cost Per Job: 257.25

Spec. No :
Unit (British) : Job

Rate (Rs)

550.00 1
TOTAL MATERIAL 54.58

1,050.00 1
3.00
TOTAL LABOUR 25.92
19.50

940.23 Cost Per Job: 940.23


282.98 Cost Per Job: 282.98

Spec. No :
Unit (British) : Pair
Rate (Rs)

100.00 1
TOTAL MATERIAL 59.62

600.00 1
3.00
TOTAL LABOUR 20.88
19.50

156.25 Cost Per Pair: 156.25


36.75 Cost Per Pair: 36.75

Spec. No :
Unit (British) : Job

Rate (Rs)

6,300.00 1
TOTAL MATERIAL 73.98

1,200.00 1
3.00
TOTAL LABOUR 6.52
19.50

7,896.00 Cost Per Job: 7,896.00


367.50 Cost Per Job: 367.50

Spec. No :
Unit (British) : Job
Rate (Rs)

7,820.00 1

TOTAL MATERIAL 73.55

1,200.00 1
3.00
TOTAL LABOUR 6.95
19.50

9,859.40 Cost Per Job: 9,859.40


514.50 Cost Per Job: 514.50

Spec. No :
Unit (British) : Job

Rate (Rs)

15,700.00 1

TOTAL MATERIAL 73.56

1,200.00 1
3.00
TOTAL LABOUR 6.94
19.50

19,790.50 Cost Per Job: 19,790.50


1,029.00 Cost Per Job: 1,029.00

Spec. No :
Unit (British) : Job

Rate (Rs)

3,025.00 1

TOTAL MATERIAL 70.51

1,200.00 1
3.00
TOTAL LABOUR 9.99
19.50

3,982.38 Cost Per Job: 3,982.38


367.50 Cost Per Job: 367.50

Spec. No :
Unit (British) : Job

Rate (Rs)

3,750.00 1

TOTAL MATERIAL 69.69

1,200.00 1
3.00
TOTAL LABOUR 10.81
19.50

4,995.75 Cost Per Job: 4,995.75


514.50 Cost Per Job: 514.50
Spec. No :
Unit (British) : Job

Rate (Rs)

4,200.00 1

TOTAL MATERIAL 64.58

1,200.00 1
3.00
TOTAL LABOUR 15.92
19.50

6,048.00 Cost Per Job: 6,048.00


1,029.00 Cost Per Job: 1,029.00

Spec. No :
Unit (British) : No.
(HT) Bush for 25 to 50 KVA
Rate (Rs)

1,300.00 1

TOTAL MATERIAL 63.41

1,050.00 1
3.00
TOTAL LABOUR 17.09
19.50

1,907.22 Cost Per No.: 1,907.22


353.72 Cost Per No.: 353.72
Spec. No :
Unit (British) : No.
mer L.T bush for 25 to 50 KVA
Rate (Rs)

1,550.00 1

TOTAL MATERIAL 55.87

1,200.00 1
3.00
TOTAL LABOUR 24.63
19.50

2,587.25 Cost Per No.: 2,587.25


735.00 Cost Per No.: 735.00

Spec. No :
Unit (British) : No.
er link of different KVS
Rate (Rs)

1,350.00 1

TOTAL MATERIAL 61.18

1,200.00 1
3.00
TOTAL LABOUR 19.32
19.50

2,054.25 Cost Per No.: 2,054.25


441.00 Cost Per No.: 441.00
Spec. No :
Unit (British) : No.
nit for 25 to 100 KVA
Rate (Rs)

1,150.00 1

TOTAL MATERIAL 50.93

1,200.00 1
3.00
TOTAL LABOUR 29.57
19.50

2,109.25 Cost Per No.: 2,109.25


735.00 Cost Per No.: 735.00

Spec. No :
Unit (British) : Liter

Rate (Rs)

175.00 1
TOTAL MATERIAL 52.36

1,200.00 1
3.00
TOTAL LABOUR 28.14
19.50

312.03 Cost Per Liter: 312.03


102.90 Cost Per Liter: 102.90
(British) : Job

Rate (Rs)

500.00 1 LS

3,600.00 1 No

TOTAL MATERIAL 59.95

1,200.00 1
3.00
TOTAL LABOUR 20.55
19.50

6,369.50 Cost Per Job: 6,369.50


1,470.00 Cost Per Job: 1,470.00

Spec. No :
Unit (British) : No.

Rate (Rs)

60.00 1

TOTAL MATERIAL 56.99

600.00 1
3.00
TOTAL LABOUR 23.51
19.50

98.16 Cost Per No.: 98.16


26.46 Cost Per No.: 26.46

Spec. No :
Unit (British) : Rft

Rate (Rs)

35.00 1
TOTAL MATERIAL 51.18

600.00 1
3.00
TOTAL LABOUR 29.32
19.50

63.88 Per Meter : Rs 209.51


22.05 Per Meter : Rs 72.32

Spec. No :
Unit (British) : No.

Rate (Rs)

1,100.00 1

TOTAL MATERIAL 68.20

1,200.00 1
3.00
TOTAL LABOUR 12.30
19.50

1,498.25 Cost Per No.: 1,498.25


183.75 Cost Per No.: 183.75

Spec. No :
Unit (British) : No.

Rate (Rs)

240.00 1
TOTAL MATERIAL 47.32

1,050.00 1
3.00
TOTAL LABOUR 33.18
19.50

474.34 Cost Per No.: 474.34


187.54 Cost Per No.: 187.54

Spec. No :
Unit (British) : Rft

Rate (Rs)

35.00 1

TOTAL MATERIAL 31.90


1,200.00 1
3.00
TOTAL LABOUR 48.60
19.50

103.12 Per Meter : Rs 338.25


61.30 Per Meter : Rs 201.06

Spec. No :
Unit (British) : No.

Rate (Rs)

700.00 1
TOTAL MATERIAL 63.82

600.00 1
3.00
TOTAL LABOUR 16.68
19.50

1,020.25 Cost Per No.: 1,020.25


183.75 Cost Per No.: 183.75

Spec. No :
Unit (British) : No.

Rate (Rs)

1,480.00 1
TOTAL MATERIAL 70.37
600.00 1
3.00
TOTAL LABOUR 10.13
19.50

1,952.35 Cost Per No.: 1,952.35


183.75 Cost Per No.: 183.75

Spec. No :
Unit (British) : Job
column pipe of various size
Rate (Rs)

200.00 1

TOTAL MATERIAL 16.58

1,050.00 1
3.00
TOTAL LABOUR 63.92
19.50

1,139.38 Cost Per Job: 1,139.38


900.38 Cost Per Job: 900.38

(British) : Rft

Rate (Rs)
56.00 1

TOTAL MATERIAL 46.39

1,200.00 1
3.00
TOTAL LABOUR 34.11
19.50

112.93 Per Meter : Rs 370.41


46.01 Per Meter : Rs 150.92

(British) : Rft

Rate (Rs)

45.00 1

TOTAL MATERIAL 42.24

1,200.00 1
3.00
TOTAL LABOUR 38.26
19.50

99.79 Per Meter : Rs 327.30


46.01 Per Meter : Rs 150.92
(British) : Rft

Rate (Rs)

90.00 1

TOTAL MATERIAL 42.27

1,200.00 1
3.00
TOTAL LABOUR 38.23
19.50

199.43 Per Meter : Rs 654.11


91.88 Per Meter : Rs 301.35

(British) : Rft

Rate (Rs)

100.00 1

TOTAL MATERIAL 44.29

1,200.00 1
3.00
TOTAL LABOUR 36.21
19.50

211.38 Per Meter : Rs 693.31


91.88 Per Meter : Rs 301.35
(British) : Rft

Rate (Rs)

87.00 1

TOTAL MATERIAL 41.62

1,200.00 1
3.00
TOTAL LABOUR 38.88
19.50

195.84 Per Meter : Rs 642.36


91.88 Per Meter : Rs 301.35

(British) : Rft

Rate (Rs)

280.00 1

TOTAL MATERIAL 55.28


1,200.00 1
3.00
TOTAL LABOUR 25.22
19.50

472.49 Per Meter : Rs 1,549.75


137.89 Per Meter : Rs 452.27

(British) : Rft

Rate (Rs)

205.00 1
TOTAL MATERIAL 50.03

1,200.00 1
3.00
TOTAL LABOUR 30.47
19.50

382.86 Per Meter : Rs 1,255.78


137.89 Per Meter : Rs 452.27

(British) : Rft
Rate (Rs)

155.00 1
TOTAL MATERIAL 44.90

1,200.00 1
3.00
TOTAL LABOUR 35.60
19.50

323.11 Per Meter : Rs 1,059.80


137.89 Per Meter : Rs 452.27

(British) : Hr

Rate (Rs)

350.00 1

TOTAL MATERIAL 42.97

1,200.00 1
1,050.00 1
3.00
TOTAL LABOUR 37.53
19.50

762.78 Cost Per Hr: 762.78


344.53 Cost Per Hr: 344.53
Spec. No :
Unit (British) : Per Job
Disconnection of Illegal water connection, complete in all respects
Rate (Rs)

850.00 1
1,200.00 1
3.00
TOTAL LABOUR 80.50
19.50

1,057.79 Cost Per Per Job: 1,057.79


1,057.79 Cost Per Per Job: 1,057.79

6.1
(British) : Per Job

Rate (Rs)

1,200.00 1
600.00 1
3.00
TOTAL LABOUR 80.50
19.50

315.09 Cost Per Per Job: 315.09


315.09 Cost Per Per Job: 315.09
Spec. No :
Unit (British) : Each

Rate (Rs)

9,900.00 1,000 No
TOTAL MATERIAL 16.72

1,200.00 1
600.00 1
3.00
TOTAL LABOUR 63.78
19.50

55.93 Cost Per Each: 55.93


44.10 Cost Per Each: 44.10

Spec. No :
Unit (British) : Each
Repairing corners of bridges & other hydraulic masonry works
Rate (Rs)

1,200.00 1
600.00 1
3.00
TOTAL LABOUR 80.50
19.50

551.25 Cost Per Each: 551.25


551.25 Cost Per Each: 551.25
10.9
(British) : Sft

Rate (Rs)

550.00 1
40.00 1
TOTAL MATERIAL 23.27

10.00 1

TOTAL EQUIPMENT 54.23


19.50

17.08 Per SQM : Rs 183.74


0.00 Per SQM : Rs 0.00

10.9
(British) : 100 Sft

Rate (Rs)

550.00 1
40.00 1
TOTAL MATERIAL 34.14

10.00 1

TOTAL EQUIPMENT 43.36


19.50

21.36 Per SQM : Rs 2.30


0.00 Per SQM : Rs 0.00

Spec. No :
Unit (British) : 100 Sft
nts of stone masonry (old work)
Rate (Rs)

600.00 1
600.00 1
3.00
TOTAL LABOUR 80.50
19.50

918.75 Per SQM : Rs 98.86


918.75 Per SQM : Rs 98.86

Spec. No :
Unit (British) : 100 Sft
nts of brick masonry (old work)
Rate (Rs)

600.00 1
600.00 1
3.00
TOTAL LABOUR 80.50
19.50

551.25 Per SQM : Rs 59.31


551.25 Per SQM : Rs 59.31
Spec. No :
Unit (British) : Each

Rate (Rs)

476.00 1
TOTAL MATERIAL 48.35

1,200.00 1
850.00 1
3.00
TOTAL LABOUR 32.15
19.50

920.40 Cost Per Each: 920.40


351.58 Cost Per Each: 351.58

Spec. No :
Unit (British) : Each

Rate (Rs)

550.00 1
2,600.00 100 Cft
3,438.00 100 Cft
TOTAL MATERIAL 25.37

1,200.00 1
600.00 1
3.00
TOTAL LABOUR 55.13
19.50

88.12 Cost Per Each: 88.12


59.76 Cost Per Each: 59.76

12.19.20
(British) : Each

Rate (Rs)

400.00 1
1.20 1
TOTAL MATERIAL 65.45

1,200.00 1
3.00
TOTAL LABOUR 15.05
19.50

578.48 Cost Per Each: 578.48


91.88 Cost Per Each: 91.88

12.19.20
(British) : Each

Rate (Rs)

280.00 1
1.20 1
TOTAL MATERIAL 61.40

1,200.00 1
3.00
TOTAL LABOUR 19.10
19.50

433.65 Cost Per Each: 433.65


91.88 Cost Per Each: 91.88

12.19.20
(British) : Each

Rate (Rs)

120.00 1
1.20 1
TOTAL MATERIAL 48.58

1,200.00 1
3.00
TOTAL LABOUR 31.92
19.50

242.45 Cost Per Each: 242.45


91.88 Cost Per Each: 91.88

12.19.20
(British) : Each
Rate (Rs)

30.00 1
0.80 1
TOTAL MATERIAL 24.56

1,200.00 1
3.00
TOTAL LABOUR 55.94
19.50

133.46 Cost Per Each: 133.46


91.88 Cost Per Each: 91.88

12.19.20
(British) : Each

Rate (Rs)

25.00 1
0.80 1
TOTAL MATERIAL 21.61

1,200.00 1
3.00
TOTAL LABOUR 58.89
19.50

126.53 Cost Per Each: 126.53


91.88 Cost Per Each: 91.88
12.19.20
(British) : Each

Rate (Rs)

80.00 1
6.00 1
TOTAL MATERIAL 47.07

1,200.00 1
3.00
TOTAL LABOUR 33.43
19.50

230.50 Cost Per Each: 230.50


91.88 Cost Per Each: 91.88

12.19.20
(British) : Each

Rate (Rs)

60.00 1
6.00 1
TOTAL MATERIAL 42.27

1,200.00 1
3.00
TOTAL LABOUR 38.23
19.50

199.43 Cost Per Each: 199.43


91.88 Cost Per Each: 91.88

12.19.20
(British) : Each

Rate (Rs)

50.00 1
6.00 1
TOTAL MATERIAL 40.00

1,200.00 1
3.00
TOTAL LABOUR 40.50
19.50

187.48 Cost Per Each: 187.48


91.88 Cost Per Each: 91.88

12.19.20
(British) : Each
Rate (Rs)

120.00 1
1.20 1
TOTAL MATERIAL 23.08

1,200.00 1
3.00
TOTAL LABOUR 57.42
19.50

519.50 Cost Per Each: 519.50


367.50 Cost Per Each: 367.50

Spec. No :
Unit (British) : Each
Removing and Fixing new approved section hook and eye : Brass 6"
Rate (Rs)

600.00 1
TOTAL MATERIAL 68.89

1,200.00 1
3.00
TOTAL LABOUR 11.61
19.50

808.88 Cost Per Each: 808.88


91.88 Cost Per Each: 91.88

Spec. No :
Unit (British) : Each
Removing and Fixing new approved section hook and eye : Brass 4"
Rate (Rs)

350.00 1
TOTAL MATERIAL 63.82

1,200.00 1
3.00
TOTAL LABOUR 16.68
19.50

510.13 Cost Per Each: 510.13


91.88 Cost Per Each: 91.88

12.19.20
(British) : Each

Rate (Rs)

175.00 1
TOTAL MATERIAL 54.25

1,200.00 1
3.00
TOTAL LABOUR 26.25
19.50

301.00 Cost Per Each: 301.00


91.88 Cost Per Each: 91.88
12.19.20
(British) : Each

Rate (Rs)

150.00 1
TOTAL MATERIAL 51.67

1,200.00 1
3.00
TOTAL LABOUR 28.83
19.50

271.13 Cost Per Each: 271.13


91.88 Cost Per Each: 91.88

Spec. No :
Unit (British) : Each
m door closer of approved quality
Rate (Rs)

2,500.00 1

TOTAL MATERIAL 74.81

1,200.00 1
3.00
TOTAL LABOUR 5.69
19.50

3,097.75 Cost Per Each: 3,097.75


110.25 Cost Per Each: 110.25
12.2
(British) : Each

Rate (Rs)

5,000.00 1
137.80 1
8.57 1
TOTAL MATERIAL 59.15

1,200.00 1
3.00
TOTAL LABOUR 21.35
19.50

304.54 Cost Per Each: 304.54


73.50 Cost Per Each: 73.50

Spec. No :
Unit (British) : Each
Removing & refixing cleats with brass hooks for roof ventilators
Rate (Rs)

5,000.00 1
137.80 1
182.00 1
TOTAL MATERIAL 58.88

1,200.00 1
3.00
TOTAL LABOUR 21.62
19.50
300.26 Cost Per Each: 300.26
73.50 Cost Per Each: 73.50

Spec. No : 12.2
Unit (British) : Each
or stops of 1.5" dia rubber block
Rate (Rs)

596.00 1
TOTAL MATERIAL 76.23

1,200.00 1
3.00
TOTAL LABOUR 4.27
19.50

724.42 Cost Per Each: 724.42


12.20 Cost Per Each: 12.20

Spec. No : 12.2
Unit (British) : Each
hook with clamps for doors
Rate (Rs)

148.00 1
TOTAL MATERIAL 75.84

1,200.00 1
3.00
TOTAL LABOUR 4.66
19.50
180.83 Cost Per Each: 180.83
3.97 Cost Per Each: 3.97

Spec. No : 12.1
Unit (British) : Each

Rate (Rs)

5,000.00 1
82.00 1
TOTAL MATERIAL 75.93

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 4.57
19.50

17,656.76 Cost Per Each: 17,656.76


367.50 Cost Per Each: 367.50

Spec. No : 4.1
Unit (British) : Rft

Rate (Rs)

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 80.50
19.50
36.82 Per Meter : Rs 120.78
36.82 Per Meter : Rs 120.78

Spec. No :
Unit (British) : 100 Sft
woodwork/steel with paint remover
Rate (Rs)

210.00 1
TOTAL MATERIAL 18.29

850.00 1
3.00
TOTAL LABOUR 62.21
19.50

270.99 Per SQM : Rs 29.16


208.25 Per SQM : Rs 22.41

Spec. No :
Unit (British) : 100 Sft
ters of old paints from woodwork
Rate (Rs)

600.00 1
3.00
TOTAL LABOUR 80.50
19.50

307.23 Per SQM : Rs 33.06


307.23 Per SQM : Rs 33.06
Spec. No :
Unit (British) : 100 Sft
Scraping, brushing and removing old paint, from metal surface
Rate (Rs)

600.00 1
3.00
TOTAL LABOUR 80.50
19.50

1,470.00 Per SQM : Rs 158.17


1,470.00 Per SQM : Rs 158.17

Spec. No : 13.3
Unit (British) : 100 Sft
Burning off or rubbing down with pumice stone, old paint from wood work
Rate (Rs)

146.60 1
TOTAL MATERIAL 29.47

600.00 1
850.00 1
3.00
TOTAL LABOUR 51.03
19.50

1,590.95 Per SQM : Rs 171.19


995.31 Per SQM : Rs 107.10
Spec. No : 13.3
Unit (British) : 100 Sft
oda,old paint from wood work
Rate (Rs)

165.00 1
TOTAL MATERIAL 16.72

600.00 1
3.00
TOTAL LABOUR 63.78
19.50

466.09 Per SQM : Rs 50.15


367.50 Per SQM : Rs 39.54

Spec. No :
Unit (British) : 100 Sft

Rate (Rs)

600.00 1
3.00
TOTAL LABOUR 80.50
19.50

735.00 Per SQM : Rs 79.09


735.00 Per SQM : Rs 79.09
Spec. No : 13.1
Unit (British) : 100 Sft
from barrage gates
Rate (Rs)

289.00 1
TOTAL MATERIAL 51.73

600.00 1
3.00
TOTAL LABOUR 28.77
19.50

260.88 Per SQM : Rs 28.07


88.20 Per SQM : Rs 9.49

Spec. No :
Unit (British) : 100 Sft
paint from barrage headworks
Rate (Rs)

289.00 1
TOTAL MATERIAL 38.03

600.00 1
3.00
TOTAL LABOUR 42.47
19.50

356.43 Per SQM : Rs 38.35


183.75 Per SQM : Rs 19.77
Spec. No :
Unit (British) : 100 Sft

Rate (Rs)

289.00 1
TOTAL MATERIAL 10.72

600.00 1
3.00
TOTAL LABOUR 69.78
19.50

1,275.18 Per SQM : Rs 137.21


1,102.50 Per SQM : Rs 118.63

Spec. No :
Unit (British) : 100 Sft

Rate (Rs)

289.00 1
TOTAL MATERIAL 8.33

600.00 1
3.00
TOTAL LABOUR 72.17
19.50

1,642.68 Per SQM : Rs 176.75


1,470.00 Per SQM : Rs 158.17
Spec. No :
Unit (British) : 100 Sft

Rate (Rs)

289.00 1
TOTAL MATERIAL 15.04

600.00 1
3.00
TOTAL LABOUR 65.46
19.50

907.68 Per SQM : Rs 97.67


735.00 Per SQM : Rs 79.09

Spec. No :
Unit (British) : 100 Sft
r or rolled steel beams
Rate (Rs)

111.82 1
TOTAL MATERIAL 5.92

600.00 1
3.00
TOTAL LABOUR 74.58
19.50

397.16 Per SQM : Rs 42.73


367.50 Per SQM : Rs 39.54
Spec. No :
Unit (British) : Each
nkha poles, including fixing hooks
Rate (Rs)

130.00 1
401.22 1
TOTAL MATERIAL 7.86

600.00 1
3.00
TOTAL LABOUR 72.64
19.50

203.99 Cost Per Each: 203.99


183.75 Cost Per Each: 183.75

13.9
(British) : Job

Rate (Rs)

130.00 1
401.22 1
TOTAL MATERIAL 35.27

1,200.00 1
3.00
TOTAL LABOUR 45.23
19.50

186.75 Cost Per Job: 186.75


102.90 Cost Per Job: 102.90
13.1 , 13.9
(British) : Job

Rate (Rs)

130.00 1
401.22 1
TOTAL MATERIAL 26.02

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 54.48
19.50

913.04 Cost Per Job: 913.04


611.52 Cost Per Job: 611.52

13.1 , 13.9
(British) : 100 RFT

Rate (Rs)

130.00 1
401.22 1
TOTAL MATERIAL 43.90

1,200.00 1
3.00
TOTAL LABOUR 36.60
19.50

1,671.89 Per Meter : Rs 54.84


735.00 Per Meter : Rs 24.11

13.1 , 13.9
(British) : 100 RFT

Rate (Rs)

130.00 1
401.22 1
TOTAL MATERIAL 41.25

1,200.00 1
3.00
TOTAL LABOUR 39.25
19.50

3,102.10 Per Meter : Rs 101.75


1,470.00 Per Meter : Rs 48.22

13.1 , 13.9
(British) : 100 RFT
Rate (Rs)

130.00 1
401.22 1
TOTAL MATERIAL 39.01

1,200.00 1
3.00
TOTAL LABOUR 41.49
19.50

4,853.33 Per Meter : Rs 159.19


2,440.20 Per Meter : Rs 80.04

13.1 , 13.9
(British) : Job

Rate (Rs)

130.00 1
401.22 1
TOTAL MATERIAL 57.14

1,200.00 1
3.00
TOTAL LABOUR 23.36
19.50

164.85 Cost Per Job: 164.85


44.10 Cost Per Job: 44.10
3.9.3
(British) : 100 Sft

Rate (Rs)

600.00 1
3.00
TOTAL LABOUR 80.50
19.50

367.50 Per SQM : Rs 39.54


367.50 Per SQM : Rs 39.54

16.9
(British) : 100 Rft

Rate (Rs) Amount

550.00 1
2,600.00 100 Cft
TOTAL MATERIAL 13.82

1,200.00 1
600.00 1
600.00 1
600.00 1
3.00
TOTAL LABOUR 58.99

700.00 1

TOTAL EQUIPMENT 7.69


19.50

4,294.25 Per Meter : Rs 140.85


3,123.75 Per Meter : Rs 102.46

3.9.3
(British) : 100 Sft

Rate (Rs) Amount

600.00 1
3.00
TOTAL LABOUR 80.50
19.50

735.00 Per SQM : Rs 79.09


735.00 Per SQM : Rs 79.09

3.9.3 , 16.4.7
(British) : 100 Sft
Rate (Rs) Amount

Cft 2,600.00 100 Cft


Cft 3,290.00 100 Cft
Kg 85.50 1
No 112.00 1
TOTAL MATERIAL 52.37

Day 600.00 1
3.00
TOTAL LABOUR 22.79

Hour 1,210.00 1

Hour 400.00 1
Hour 471.80 1
TOTAL EQUIPMENT 5.33
19.50

6,074.24 Per SQM : Rs 653.59


1,580.25 Per SQM : Rs 170.03

3.9.3 , 16.4.7
(British) : 100 Sft

Rate (Rs) Amount

Cft 3,438.00 100 Cft


Kg 85.50 1
No 112.00 1
Cft 375.00 100 Cft
TOTAL MATERIAL 55.77

Day 600.00 1
3.00
TOTAL LABOUR 19.28

Hour 1,210.00 1

Hour 400.00 1
Hour 471.80 1
TOTAL EQUIPMENT 5.46
19.50

8,064.09 Per SQM : Rs 867.70


1,727.25 Per SQM : Rs 185.85

3.9.3 , 16.4.7
(British) : 100 Sft

Unit Rate (Rs)

Cft 3,438.00
Kg 85.50 1
No 112.00 1
Cft 70.00
TOTAL MATERIAL 54.15

Day 600.00 1
3.00
TOTAL LABOUR 18.95

Hour 1,210.00 1

Hour 400.00 1
Hour 471.80 1
TOTAL EQUIPMENT 7.39
19.50

10,328.15 Per SQM : Rs 1,111.31


2,168.25 Per SQM : Rs 233.30

3.9.3
(British) : 100 Sft

Rate (Rs)

9.14 1
165.00 1
TOTAL MATERIAL 23.93

600.00 1
850.00 1
3.00
TOTAL LABOUR 56.57
19.50

470.50 Per SQM : Rs 50.63


327.69 Per SQM : Rs 35.26

3.9.3
(British) : 100 Sft
Rate (Rs)

600.00 1
3.00
TOTAL LABOUR 80.50
19.50

367.50 Per SQM : Rs 39.54


367.50 Per SQM : Rs 39.54

16.9
(British) : 100 Sft

Rate (Rs) Amount

18.38 1 Kg
112.00 1 No
3,100.00 100 Cft

2,410.00 100 Cft

70.18 1 Kg

TOTAL MATERIAL 48.15

600.00 1
600.00 1
3.00
TOTAL LABOUR 32.35
19.50

6,287.78 Per SQM : Rs 676.56


2,418.15 Per SQM : Rs 260.19
Spec. No :
Unit (British) : Rft
ulling out & refitting
Rate (Rs)

600.00 1
1,050.00 1
3.00
TOTAL LABOUR 80.50
19.50

73.13 Per Meter : Rs 239.87


73.13 Per Meter : Rs 239.87

Spec. No :
Unit (British) : kg
: With plastic cane.
Rate (Rs)

310.00 1
TOTAL MATERIAL 12.58

1,000.00 1
3.00
TOTAL LABOUR 67.92
19.50

1,747.84 Cost Per kg: 1,747.84


1,470.00 Cost Per kg: 1,470.00
Spec. No :
Unit (British) : kg
: With willow cane.
Rate (Rs)

750.00 1
TOTAL MATERIAL 62.32

1,000.00 1
3.00
TOTAL LABOUR 18.18
19.50

2,145.97 Cost Per kg: 2,145.97


428.75 Cost Per kg: 428.75

4.1
(British) : Ton

Rate (Rs)

600.00 1
3.00
TOTAL LABOUR 80.50
19.50

167.58 Cost Per Ton: 167.58


167.58 Cost Per Ton: 167.58
12.14
(British) : Sft

Rate (Rs)

5,000.00 1
137.80 1
179.00 1
TOTAL MATERIAL 68.75

1,200.00 1
3.00
TOTAL LABOUR 11.75
19.50

159.16 Per SQM : Rs 1,712.59


18.38 Per SQM : Rs 197.72

12.25.1.3
(British) : Sft

Rate (Rs)

5,000.00 1
137.80 1
132.00 1
494.00 1
TOTAL MATERIAL 70.91

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 9.59
19.50

25.37 Per SQM : Rs 272.94


2.20 Per SQM : Rs 23.73

Spec. No :
Unit (British) : Each

Rate (Rs)

600.00 1
3.00
TOTAL LABOUR 80.50
19.50

551.25 Cost Per Each: 551.25


551.25 Cost Per Each: 551.25

Spec. No :
Unit (British) : Cft
ncluding disposal of waste
Rate (Rs)

600.00 1
3.00
TOTAL LABOUR 80.50
19.50

69.09 Per CUM : Rs 2,439.89


69.09 Per CUM : Rs 2,439.89

13.1.5
(British) : Sft

Rate (Rs)

556.74 1
TOTAL MATERIAL 52.02

1,200.00 1
3.00
TOTAL LABOUR 28.48
19.50

54.97 Per SQM : Rs 591.44


18.38 Per SQM : Rs 197.72

12.15
(British) : Each

Rate (Rs)
132.00 1
53.00 1
TOTAL MATERIAL 46.73

1,200.00 1
3.00
TOTAL LABOUR 33.77
19.50

456.02 Cost Per Each: 456.02


183.75 Cost Per Each: 183.75

12.2 , 12.14
(British) : Sft

Rate (Rs)

5,000.00 1
137.80 1
179.00 1
TOTAL MATERIAL 62.89

1,200.00 1
3.00
TOTAL LABOUR 17.61
19.50

76.42 Per SQM : Rs 822.31


14.70 Per SQM : Rs 158.17
4.1 ,12.12
(British) : Sft

Rate (Rs)

60.00 1
TOTAL MATERIAL 31.00

1,200.00 1
3.00
TOTAL LABOUR 49.50
19.50

181.95 Per SQM : Rs 1,957.78


110.25 Per SQM : Rs 1,186.29

4.1 ,12.12
(British) : Sft

Rate (Rs)

26.40 1
TOTAL MATERIAL 17.58

1,200.00 1
3.00
TOTAL LABOUR 62.92
19.50

141.80 Per SQM : Rs 1,525.75


110.25 Per SQM : Rs 1,186.29
4.1 ,12.12
(British) : Sft

Rate (Rs)

20.00 1
TOTAL MATERIAL 14.09

1,200.00 1
3.00
TOTAL LABOUR 66.41
19.50

134.15 Per SQM : Rs 1,443.45


110.25 Per SQM : Rs 1,186.29

12.28
(British) : Rft

Rate (Rs)

137.80 1
20.33 1
346.00 1
556.74 1
TOTAL MATERIAL 42.29
1,200.00 1
1,200.00 1
3.00
TOTAL LABOUR 38.21
19.50

590.58 Per Meter : Rs 1,937.11


271.95 Per Meter : Rs 892.00

Spec. No : 12.26
Unit (British) : Each
of aluminium windows
Unit Rate (Rs)

Day 600.00 2
Day 1,200.00 1
3.00
TOTAL LABOUR 80.50
19.50

826.88 Cost Per Each: 826.88


826.88 Cost Per Each: 826.88

12.26
(British) : Sft

Rate (Rs)

132.00 1
231.00 1
53.00 1
TOTAL MATERIAL 58.81

1,200.00 1
3.00
TOTAL LABOUR 21.69
19.50

89.72 Per SQM : Rs 965.42


22.05 Per SQM : Rs 237.26

12.25.1.3
(British) : Sft

Rate (Rs)

19.12 1
137.80 1
132.00 1
494.00 1
62.00 1
TOTAL MATERIAL 10.78

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 69.72
19.50

127.62 Per SQM : Rs 1,373.17


110.25 Per SQM : Rs 1,186.29
(British) : Each

Rate (Rs)

132.00 1
100.00 1
80.00 1
21.18 1
TOTAL MATERIAL 59.70

600.00 1
850.00 1
3.00
TOTAL LABOUR 20.80
19.50

474.25 Cost Per Each: 474.25


111.02 Cost Per Each: 111.02

Spec. No :
Unit (British) : Sft

Rate (Rs)

118.40 1
5,000.00 1
137.80 1
132.00 1
494.00 1
26.07 1
37.00 1
150.00 1
64.00 1
80.00 1
TOTAL MATERIAL 43.39

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 37.11
19.50

74.11 Per SQM : Rs 797.39


33.08 Per SQM : Rs 355.89

Spec. No :
Unit (British) :

Unit Rate (Rs)

Day 600.00
Day 600.00

TOTAL LABOUR

Hour 1,245.26
Hour 3,828.00
Hour 1,758.00
Hour 1,500.00
Hour 625.00
Hour 1,500.00

Hour 3,200.00

TOTAL EQUIPMENT 76.05


19.50

9,505.67 Per CUM : Rs 335.69


182.13 Per CUM : Rs 6.43
12.25
(British) : Sft

Rate (Rs)

5,000.00 1
48.95 1
137.80 1
217.50 1
182.00 1
TOTAL MATERIAL 50.54

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 29.96
19.50

779.72 Per SQM : Rs 8,389.80


275.63 Per SQM : Rs 2,965.73

11.1.2.4
(British) : 100 Sft

Rate (Rs)
600.00 100 Sft
20,844.72 100 Cft

TOTAL MATERIAL 29.36

1,200.00 1
600.00 1
600.00 1
3.00
TOTAL LABOUR 51.14
19.50

4,395.84 Per SQM : Rs 472.99


2,756.25 Per SQM : Rs 296.57

12.2.1.5,
12.2.1.7,
(British) : Each 12.2.1.8,
12.2.1.9
xisting opening including embedding chowkat in

Rate (Rs)

550.00 1
2,600.00 100 Cft
3,438.00 100 Cft
TOTAL MATERIAL 60.38

1,200.00 1
600.00 1
3.00
TOTAL LABOUR 20.12
19.50
237.98 Cost Per Each: 237.98
53.58 Cost Per Each: 53.58

4.5.6, 4.4.5
(British) : Sft

Rate (Rs)

16,712.36 100 Cft

TOTAL MATERIAL 2.82

1,200.00 1
600.00 1
3.00
TOTAL LABOUR 77.68
19.50

94.35 Per SQM : Rs 1,015.19


90.99 Per SQM : Rs 979.08

12.4.1.3
(British) : Cft
Rate (Rs)

5,000.00 1
556.74 1
TOTAL MATERIAL 74.67

600.00 1
1,200.00 1
1,200.00 1
3.00
TOTAL LABOUR 5.83
19.50

6,283.38 Per CUM : Rs 221,895.80


235.20 Per CUM : Rs 8,306.02

11.2.2
(British) : 100 Sft

Rate (Rs) Amount

600.00 1
600.00 1
3.00
TOTAL LABOUR 80.50
19.50

431.74 Per SQM : Rs 46.46


431.74 Per SQM : Rs 46.46
11.5
(British) : Sft

Rate (Rs) Amount

600.00 1
3.00
TOTAL LABOUR 80.50
19.50

0.88 Per SQM : Rs 9.49


0.88 Per SQM : Rs 9.49

11.8.2
(British) : Sft

Rate (Rs) Amount

346.00 1
TOTAL MATERIAL 50.26

600.00 1
3.00
TOTAL LABOUR 30.24
19.50

3.09 Per SQM : Rs 33.22


1.10 Per SQM : Rs 11.86

13.9
(British) : Sft

Unit Rate (Rs)

Ltr 401.22 1
TOTAL MATERIAL 17.44

Day 600.00 1
Day 1,200.00 1
3.00
TOTAL LABOUR 63.06
19.50

9.34 Per SQM : Rs 100.48


7.28 Per SQM : Rs 78.30

12.19.26
(British) : Rft

Rate (Rs)
5,000.00 1
TOTAL MATERIAL 61.44

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 19.06
19.50

93.19 Per Meter : Rs 305.66


19.70 Per Meter : Rs 64.61

12.19.26
(British) : Rft

Rate (Rs)

0.75 1
50.00 1
80.00 1
TOTAL MATERIAL 69.79

1,200.00 1
3.00
TOTAL LABOUR 10.71
19.50

128.61 Per Meter : Rs 421.84


13.08 Per Meter : Rs 42.91
12.19.26
(British) : Rft

Rate (Rs)

6.00 1
50.00 1
80.00 1

TOTAL MATERIAL 70.25

1,200.00 1
3.00
TOTAL LABOUR 10.25
19.50

136.68 Per Meter : Rs 448.30


13.08 Per Meter : Rs 42.91

12.19.26
(British) : Rft

Rate (Rs) Amount

6.00 1
155.00 1
24.00 1
200.00 1
4.31 1
250.00 1
TOTAL MATERIAL 71.92

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 8.58
19.50

891.29 Per Meter : Rs 2,923.41


65.64 Per Meter : Rs 215.28

12.19.26
(British) : Rft

Rate (Rs)

6.00 1
155.00 1
24.00 1
200.00 1
4.31 1
250.00 1
TOTAL MATERIAL 71.92

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 8.58
19.50

891.29 Per Meter : Rs 2,923.41


65.64 Per Meter : Rs 215.28
12.18
(British) : Each

Rate (Rs)

132.00 1
375.00 1
TOTAL MATERIAL 43.62

1,200.00 1
3.00
TOTAL LABOUR 36.88
19.50

829.06 Cost Per Each: 829.06


367.50 Cost Per Each: 367.50

12.18
(British) : Each

Rate (Rs)

132.00 1
1,200.00 1
TOTAL MATERIAL 62.36

1,200.00 1
3.00
TOTAL LABOUR 18.14
19.50
1,844.52 Cost Per Each: 1,844.52
367.50 Cost Per Each: 367.50

12.18
(British) : Each

Rate (Rs)

132.00 1
2,000.00 1

TOTAL MATERIAL 67.65

1,200.00 1
3.00
TOTAL LABOUR 12.85
19.50

2,829.19 Cost Per Each: 2,829.19


367.50 Cost Per Each: 367.50

12.2.1.14
(British) : Each

Rate (Rs)
132.00 1
5,000.00 1

TOTAL MATERIAL 69.41

1,200.00 1
3.00
TOTAL LABOUR 11.09
19.50

6,889.26 Cost Per Each: 6,889.26


735.00 Cost Per Each: 735.00

12.19.18
(British) : Each

Rate (Rs)

132.00 1
375.00 1
TOTAL MATERIAL 55.82

1,200.00 1
3.00
TOTAL LABOUR 24.68
19.50

645.31 Cost Per Each: 645.31


183.75 Cost Per Each: 183.75
12.19.25
(British) : Each

Rate (Rs)

155.00 1
1.20 1
TOTAL MATERIAL 45.75

1,200.00 1
3.00
TOTAL LABOUR 34.75
19.50

331.71 Cost Per Each: 331.71


137.89 Cost Per Each: 137.89

12.19.25
(British) : Each

Rate (Rs)

300.00 1
0.75 1
TOTAL MATERIAL 56.58

1,200.00 1
3.00
TOTAL LABOUR 23.92
19.50

501.76 Cost Per Each: 501.76


137.89 Cost Per Each: 137.89

12.19.6
(British) : Each

Rate (Rs)

430.00 1 No

1.20 1 No

TOTAL MATERIAL 63.46

1,200.00 1
3.00
TOTAL LABOUR 17.04
19.50

646.27 Cost Per Each: 646.27


119.51 Cost Per Each: 119.51

12.19.6
(British) : Each

Rate (Rs)
625.00 1 No

1.20 1 No

TOTAL MATERIAL 65.20

1,200.00 1
3.00
TOTAL LABOUR 15.30
19.50

906.78 Cost Per Each: 906.78


147.00 Cost Per Each: 147.00

12.19.6
(British) : Each

Rate (Rs)

0.80 1
195.00 1

TOTAL MATERIAL 52.28

1,200.00 1
3.00
TOTAL LABOUR 28.22
19.50

361.14 Cost Per Each: 361.14


119.51 Cost Per Each: 119.51
12.19.6
(British) : Each

Rate (Rs)

0.80 1
245.00 1

TOTAL MATERIAL 52.51

1,200.00 1
3.00
TOTAL LABOUR 27.99
19.50

448.38 Cost Per Each: 448.38


147.00 Cost Per Each: 147.00

12.19.7
(British) : Each

Rate (Rs)

0.75 1
8.57 1
TOTAL MATERIAL 11.00

1,200.00 1
3.00
TOTAL LABOUR 69.50
19.50
426.77 Cost Per Each: 426.77
367.50 Cost Per Each: 367.50

12.19.7
(British) : Each

Rate (Rs)

17.14 1
0.80 1
TOTAL MATERIAL 18.32

1,200.00 1
3.00
TOTAL LABOUR 62.18
19.50

478.52 Cost Per Each: 478.52


367.50 Cost Per Each: 367.50

12.19.5
(British) : Each

Rate (Rs)
125.00 1 No

4.80 1 No

TOTAL MATERIAL 51.91

1,200.00 1
3.00
TOTAL LABOUR 28.59
19.50

328.46 Cost Per Each: 328.46


110.25 Cost Per Each: 110.25

12.19.5
(British) : Each

Rate (Rs)

4.80 1
350.00 1

TOTAL MATERIAL 65.46

1,200.00 1
3.00
TOTAL LABOUR 15.04
19.50

578.96 Cost Per Each: 578.96


91.88 Cost Per Each: 91.88
12.19.5
(British) : Each

Rate (Rs)

60.00 1 No

1.00 1 No

TOTAL MATERIAL 34.44

1,200.00 1
3.00
TOTAL LABOUR 46.06
19.50

196.29 Cost Per Each: 196.29


110.25 Cost Per Each: 110.25

12.19.5
(British) : Each

Rate (Rs)

1.00 1
50.00 1

TOTAL MATERIAL 35.07

1,200.00 1
3.00
TOTAL LABOUR 45.43
19.50

165.97 Cost Per Each: 165.97


91.88 Cost Per Each: 91.88

12.19.8
(British) : Each

Rate (Rs)

1.00 1
80.00 1
TOTAL MATERIAL 41.40

1,200.00 1
3.00
TOTAL LABOUR 39.10
19.50

194.65 Cost Per Each: 194.65


91.88 Cost Per Each: 91.88

12.19.8
(British) : Each
Rate (Rs)

1.00 1
70.00 1
TOTAL MATERIAL 35.48

1,200.00 1
3.00
TOTAL LABOUR 45.02
19.50

201.07 Cost Per Each: 201.07


110.25 Cost Per Each: 110.25

12.19.8
(British) : Each

Rate (Rs)

1.00 1
50.00 1
TOTAL MATERIAL 29.73

1,200.00 1
3.00
TOTAL LABOUR 50.77
19.50

177.17 Cost Per Each: 177.17


110.25 Cost Per Each: 110.25
12.19.10
(British) : Each

Rate (Rs)

0.75 1
50.00 1
TOTAL MATERIAL 32.62

1,200.00 1
3.00
TOTAL LABOUR 47.88
19.50

157.00 Cost Per Each: 157.00


91.88 Cost Per Each: 91.88

12.19.10
(British) : Each

Rate (Rs)

0.75 1
80.00 1
TOTAL MATERIAL 41.40

1,200.00 1
3.00
TOTAL LABOUR 39.10
19.50

194.65 Cost Per Each: 194.65


91.88 Cost Per Each: 91.88

12.19.10
(British) : Each

Rate (Rs)

0.75 1
120.00 1
TOTAL MATERIAL 49.01

1,200.00 1
3.00
TOTAL LABOUR 31.49
19.50

246.03 Cost Per Each: 246.03


91.88 Cost Per Each: 91.88

12.19.10
(British) : Each

Rate (Rs)

0.75 1
280.00 1
TOTAL MATERIAL 61.33

1,200.00 1
3.00
TOTAL LABOUR 19.17
19.50

431.85 Cost Per Each: 431.85


91.88 Cost Per Each: 91.88

12.19.10
(British) : Each

Rate (Rs)

0.75 1
340.00 1
TOTAL MATERIAL 63.69

1,200.00 1
3.00
TOTAL LABOUR 16.81
19.50

505.35 Cost Per Each: 505.35


91.88 Cost Per Each: 91.88

12.19.10
(British) : Each
Rate (Rs)

0.75 1
500.00 1
TOTAL MATERIAL 67.55

1,200.00 1
3.00
TOTAL LABOUR 12.95
19.50

700.13 Cost Per Each: 700.13


91.88 Cost Per Each: 91.88

12.19.10
(British) : Each

Rate (Rs)

0.75 1
60.00 1
TOTAL MATERIAL 35.83

1,200.00 1
3.00
TOTAL LABOUR 44.67
19.50

168.95 Cost Per Each: 168.95


91.88 Cost Per Each: 91.88
12.19.10
(British) : Each

Rate (Rs)

0.75 1
80.00 1
TOTAL MATERIAL 41.06

1,200.00 1
3.00
TOTAL LABOUR 39.44
19.50

192.85 Cost Per Each: 192.85


91.88 Cost Per Each: 91.88

12.19.10
(British) : Each

Rate (Rs)

0.75 1
120.00 1
TOTAL MATERIAL 48.36

1,200.00 1
3.00
TOTAL LABOUR 32.14
19.50

240.65 Cost Per Each: 240.65


91.88 Cost Per Each: 91.88

12.19.18
(British) : Each

Rate (Rs)

0.75 1
350.00 1
TOTAL MATERIAL 63.99

1,200.00 1
3.00
TOTAL LABOUR 16.51
19.50

516.40 Cost Per Each: 516.40


91.88 Cost Per Each: 91.88

12.19.18
(British) : Each
Rate (Rs)

0.75 1
280.00 1
TOTAL MATERIAL 61.37

1,200.00 1
3.00
TOTAL LABOUR 19.13
19.50

432.75 Cost Per Each: 432.75


91.88 Cost Per Each: 91.88

12.19.18
(British) : Each

Rate (Rs)

0.75 1
200.00 1
TOTAL MATERIAL 56.76

1,200.00 1
3.00
TOTAL LABOUR 23.74
19.50

337.15 Cost Per Each: 337.15


91.88 Cost Per Each: 91.88
12.19.18
(British) : Each

Rate (Rs)

0.75 1
180.00 1
TOTAL MATERIAL 55.17

1,200.00 1
3.00
TOTAL LABOUR 25.33
19.50

313.25 Cost Per Each: 313.25


91.88 Cost Per Each: 91.88

12.19.18
(British) : Each

Rate (Rs)

0.80 1
40.00 1
TOTAL MATERIAL 29.30

1,200.00 1
3.00
TOTAL LABOUR 51.20
19.50

146.37 Cost Per Each: 146.37


91.88 Cost Per Each: 91.88

12.19.18
(British) : Each

Rate (Rs)

0.80 1
35.00 1
TOTAL MATERIAL 27.22

1,200.00 1
3.00
TOTAL LABOUR 53.28
19.50

140.39 Cost Per Each: 140.39


91.88 Cost Per Each: 91.88

12.19.18
(British) : Each

Rate (Rs)

0.80 1
30.00 1
TOTAL MATERIAL 24.95

1,200.00 1
3.00
TOTAL LABOUR 55.55
19.50

134.42 Cost Per Each: 134.42


91.88 Cost Per Each: 91.88

12.19.18
(British) : Each

Rate (Rs)

0.80 1
25.00 1
TOTAL MATERIAL 22.46

1,200.00 1
3.00
TOTAL LABOUR 58.04
19.50

128.44 Cost Per Each: 128.44


91.88 Cost Per Each: 91.88

12.19.18
(British) : Each
Rate (Rs) Amount

80.00 1
6.00 1
TOTAL MATERIAL 47.07

1,200.00 1
3.00
TOTAL LABOUR 33.43
19.50

230.50 Cost Per Each: 230.50


91.88 Cost Per Each: 91.88

12.19.18
(British) : Each

Rate (Rs) Amount

6.00 1
70.00 1
TOTAL MATERIAL 45.39

1,200.00 1
3.00
TOTAL LABOUR 35.11
19.50

218.55 Cost Per Each: 218.55


91.88 Cost Per Each: 91.88

12.19.18
(British) : Each

Rate (Rs) Amount

6.00 1
60.00 1
TOTAL MATERIAL 43.51

1,200.00 1
3.00
TOTAL LABOUR 36.99
19.50

206.60 Cost Per Each: 206.60


91.88 Cost Per Each: 91.88

12.19.18
(British) : Each

Rate (Rs) Amount


6.00 1
50.00 1
TOTAL MATERIAL 41.40

1,200.00 1
3.00
TOTAL LABOUR 39.10
19.50

194.65 Cost Per Each: 194.65


91.88 Cost Per Each: 91.88

Spec. No :
Unit (British) : Job

Rate (Rs)

500.00 1

TOTAL MATERIAL 48.44

1,200.00 1
3.00
TOTAL LABOUR 32.06
19.50

965.00 Cost Per job: 965.00


367.50 Cost Per job: 367.50

Spec. No :
Unit (British) : Job
Gas charging for 2.0 Ton Split AC with R410 or equivalent gas
Rate (Rs)

4,000.00 1

TOTAL MATERIAL 72.09

1,200.00 1
3.00
TOTAL LABOUR 8.41
19.50

5,147.50 Cost Per job: 5,147.50


367.50 Cost Per job: 367.50

Spec. No :
Unit (British) : Job

Rate (Rs)

400.00 1

TOTAL MATERIAL 44.29

1,200.00 1
3.00
TOTAL LABOUR 36.21
19.50

845.50 Cost Per job: 845.50


367.50 Cost Per job: 367.50
Spec. No :
Unit (British) : Job

Rate (Rs)

600.00 1

TOTAL MATERIAL 31.00

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 49.50
19.50

1,819.50 Cost Per job: 1,819.50


1,102.50 Cost Per job: 1,102.50

Spec. No :
Unit (British) : Job
Supply and Replacement of compressor for 1.5 Ton Split AC
Rate (Rs)

13,000.00 1

TOTAL MATERIAL 71.56

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 8.94
19.50

16,858.00 Cost Per job: 16,858.00


1,323.00 Cost Per job: 1,323.00
Spec. No :
Unit (British) : Job
Supply and Replacement of compressor for 2.0 Ton Split AC
Rate (Rs)

16,000.00 1

TOTAL MATERIAL 72.60

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 7.90
19.50

20,443.00 Cost Per job: 20,443.00


1,323.00 Cost Per job: 1,323.00

Spec. No :
Unit (British) : Job
Supply and Replacement of compressor for 1.5 T Window AC
Rate (Rs)

13,000.00 1

TOTAL MATERIAL 72.48

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 8.02
19.50

16,637.50 Cost Per job: 16,637.50


1,102.50 Cost Per job: 1,102.50
Spec. No :
Unit (British) : Job
Supplay and Replacement of compressor for 2.0 T Window AC
Rate (Rs)

16,000.00 1

TOTAL MATERIAL 73.37

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 7.13
19.50

20,222.50 Cost Per job: 20,222.50


1,102.50 Cost Per job: 1,102.50

Spec. No :
Unit (British) : Job
pressor for Electric Water Cooler
Rate (Rs)

9,500.00 1

TOTAL MATERIAL 75.13

1,200.00 1
3.00
TOTAL LABOUR 5.37
19.50
11,720.00 Cost Per job: 11,720.00
367.50 Cost Per job: 367.50

Spec. No :
Unit (British) : Job
Gas charging for 1.5 Ton Split AC with R410 or equivalent gas
Rate (Rs)

3,500.00 1

TOTAL MATERIAL 71.38

1,200.00 1
3.00
TOTAL LABOUR 9.12
19.50

4,550.00 Cost Per job: 4,550.00


367.50 Cost Per job: 367.50

Spec. No :
Unit (British) : Job
Gas changing for 1.5 Ton Window AC with R410 or equivalent gas
Rate (Rs)

3,500.00 1

TOTAL MATERIAL 71.38

1,200.00 1
3.00
TOTAL LABOUR 9.12
19.50

4,550.00 Cost Per job: 4,550.00


367.50 Cost Per job: 367.50

Spec. No :
Unit (British) : Job
Gas changing for 2.0 Ton Window AC with R410 or equivalent gas
Rate (Rs)

4,000.00 1

TOTAL MATERIAL 72.09

1,200.00 1
3.00
TOTAL LABOUR 8.41
19.50

5,147.50 Cost Per job: 5,147.50


367.50 Cost Per job: 367.50

Spec. No :
Unit (British) : Job
Gas charging for Electric Water Cooler with R410 or equivalent gas
Rate (Rs)

3,500.00 1

TOTAL MATERIAL 71.38


1,200.00 1
3.00
TOTAL LABOUR 9.12
19.50

4,550.00 Cost Per job: 4,550.00


367.50 Cost Per job: 367.50

Spec. No :
Unit (British) : Job
Gas charging for floor stand AC unit with R410 or equivalent gas
Rate (Rs)

4,000.00 1

TOTAL MATERIAL 71.10

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 9.40
19.50

5,221.00 Cost Per job: 5,221.00


441.00 Cost Per job: 441.00

Spec. No :
Unit (British) : Job
Repairing of PC Circuit Board complete for Split AC unit
Unit Rate (Rs)

1 No 3,500.00 1
TOTAL MATERIAL 70.27

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 10.23
19.50

4,623.50 Cost Per job: 4,623.50


441.00 Cost Per job: 441.00

Spec. No :
Unit (British) : Job
Supply and replacement of PC Circuit Board complete for Split AC unit
Rate (Rs)

3,000.00 1

TOTAL MATERIAL 69.20

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 11.30
19.50

4,026.00 Cost Per job: 4,026.00


441.00 Cost Per job: 441.00
Spec. No :
Unit (British) : Job
of Sensor for Split AC unit
Rate (Rs)

900.00 1
TOTAL MATERIAL 55.36

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 25.14
19.50

1,516.50 Cost Per job: 1,516.50


441.00 Cost Per job: 441.00

Spec. No :
Unit (British) : Job
of running capacitor
Rate (Rs)

500.00 1
TOTAL MATERIAL 52.36

1,200.00 1
3.00
TOTAL LABOUR 28.14
19.50

891.50 Cost Per job: 891.50


294.00 Cost Per job: 294.00
Spec. No :
Unit (British) : Job
Supply and Replacement of Insulation Copper pipe for Split AC unit
Rate (Rs)

300.00 1

TOTAL MATERIAL 55.36

1,200.00 1
3.00
TOTAL LABOUR 25.14
19.50

505.50 Cost Per job: 505.50


147.00 Cost Per job: 147.00

Spec. No :
Unit (British) : No
Remote Control for Split AC unit
Rate (Rs)

1,500.00 1

TOTAL MATERIAL 77.50


19.50

1,792.50 Cost Per no: 1,792.50


0.00 Cost Per no: 0.00

Spec. No :
Unit (British) : Job
Supply and fixing of drain pipe flexible for outdoor unit of split AC
Rate (Rs)

30.00 1

TOTAL MATERIAL 25.83

1,200.00 1
3.00
TOTAL LABOUR 54.67
19.50

109.35 Cost Per job: 109.35


73.50 Cost Per job: 73.50

Spec. No :
Unit (British) : Job
motor for outdoor unit of split AC
Rate (Rs)

1,500.00 1

TOTAL MATERIAL 66.81

1,200.00 1
3.00
TOTAL LABOUR 13.69
19.50

2,086.50 Cost Per job: 2,086.50


294.00 Cost Per job: 294.00
Spec. No :
Unit (British) : Job
motor for window AC unit
Rate (Rs)

1,500.00 1

TOTAL MATERIAL 69.20

1,200.00 1
3.00
TOTAL LABOUR 11.30
19.50

2,013.00 Cost Per job: 2,013.00


220.50 Cost Per job: 220.50

Spec. No :
Unit (British) : Job
motor for Electric Water Cooler
Rate (Rs)

1,500.00 1

TOTAL MATERIAL 69.20

1,200.00 1
3.00
TOTAL LABOUR 11.30
19.50

2,013.00 Cost Per job: 2,013.00


220.50 Cost Per job: 220.50
Spec. No :
Unit (British) : Job
Supply and fixing of steel bracket with rawal bolt best quality for AC
Rate (Rs)

1,000.00 1

TOTAL MATERIAL 69.20

1,200.00 1
3.00
TOTAL LABOUR 11.30
19.50

1,342.00 Cost Per job: 1,342.00


147.00 Cost Per job: 147.00

Spec. No :
Unit (British) : Job
/76 - 3 core wire for split AC
Rate (Rs)

80.00 1

TOTAL MATERIAL 53.45

1,200.00 1
3.00
TOTAL LABOUR 27.05
19.50

139.70 Cost Per job: 139.70


44.10 Cost Per job: 44.10
Spec. No :
Unit (British) : Job

Rate (Rs)

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 80.50
19.50

551.25 Cost Per job: 551.25


551.25 Cost Per job: 551.25

Spec. No :
Unit (British) : Job

Rate (Rs)

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 80.50
19.50

551.25 Cost Per job: 551.25


551.25 Cost Per job: 551.25
Spec. No :
Unit (British) : Job

Rate (Rs)

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 80.50
19.50

882.00 Cost Per job: 882.00


882.00 Cost Per job: 882.00

Spec. No :
Unit (British) : Job

Rate (Rs)

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 80.50
19.50

1,102.50 Cost Per job: 1,102.50


1,102.50 Cost Per job: 1,102.50

Spec. No :
Unit (British) : Job
ontact relay for split AC complete
Rate (Rs)

3,500.00 1

TOTAL MATERIAL 74.93

1,200.00 1
3.00
TOTAL LABOUR 5.57
19.50

4,329.50 Cost Per job: 4,329.50


147.00 Cost Per job: 147.00

16.8.16
(British) : Each

Rate (Rs)

83.00 1
9.14 1
186.00 1
TOTAL MATERIAL 60.77

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 19.73
19.50

434.08 Cost Per Each: 434.08


95.55 Cost Per Each: 95.55
Spec. No :
Unit (British) : 100 No.
or levelling 1.5" square 6" long
Rate (Rs)

1,333.33 1
TOTAL MATERIAL 70.07

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 10.43
19.50

5,620.43 Cost Per 100 No.: 5,620.43


551.25 Cost Per 100 No.: 551.25

Spec. No :
Unit (British) : 100 No.
Supplying wooden pegs for alignment, 2" to 3" square, 9" long
Rate (Rs)

1,333.33 1
TOTAL MATERIAL 70.40

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 10.10
19.50

8,240.48 Cost Per 100 No.: 8,240.48


771.75 Cost Per 100 No.: 771.75
Spec. No : 14.7.3
Unit (British) : Rft
Fixing enamelled iron gauges flush with masonry including cost of hooks
Rate (Rs)

23.00 1
TOTAL MATERIAL 10.27

1,200.00 1
600.00 1
3.00
TOTAL LABOUR 70.23
19.50

105.91 Per Meter : Rs 347.39


92.17 Per Meter : Rs 302.31

Spec. No :
Unit (British) : Each
Supply & fix boundry pillars in position, including digging pits
Rate (Rs)

550.00 1
2,600.00 100 Cft
3,438.00 100 Cft
TOTAL MATERIAL 24.72

600.00 1
3.00
TOTAL LABOUR 55.78
19.50

535.44 Cost Per Each: 535.44


367.50 Cost Per Each: 367.50
16.8.9
(British) : Each

Rate (Rs)

550.00 1
2,600.00 100 Cft
3,438.00 100 Cft
110.00 1
129.00 1
130.00 1
TOTAL MATERIAL 49.01

600.00 1
1,200.00 1
3.00
TOTAL LABOUR 31.49
19.50

767.66 Cost Per Each: 767.66


286.65 Cost Per Each: 286.65

Spec. No :
Unit (British) : Rft
a pressure pipe in ordinary soil
Rate (Rs)

600.00 1
600.00 1
3.00
TOTAL LABOUR 80.50
19.50

107.68 Per Meter : Rs 353.18


107.68 Per Meter : Rs 353.18

Spec. No :
Unit (British) : Rft
pressure pipe in clay
Rate (Rs)

600.00 1
600.00 1
3.00
TOTAL LABOUR 80.50
19.50

218.66 Per Meter : Rs 717.21


218.66 Per Meter : Rs 717.21

Spec. No :
Unit (British) : Rft
a pressure pipe in shingle
Rate (Rs)

600.00 1
600.00 1
3.00
TOTAL LABOUR 80.50
19.50
328.18 Per Meter : Rs 1,076.42
328.18 Per Meter : Rs 1,076.42

Spec. No :
Unit (British) : Each

Rate (Rs)

600.00 1
3.00
TOTAL LABOUR 80.50
19.50

294.00 Cost Per Each: 294.00


294.00 Cost Per Each: 294.00

Spec. No :
Unit (British) : 100 Sft

Rate (Rs)

100.00 1
TOTAL MATERIAL 8.16

850.00 1
3.00
TOTAL LABOUR 72.34
19.50

1,160.75 Per SQM : Rs 124.90


1,041.25 Per SQM : Rs 112.04
Spec. No :
Unit (British) : Each

Rate (Rs)

100.00 1
TOTAL MATERIAL 9.29

850.00 1
3.00
TOTAL LABOUR 71.21
19.50

509.57 Cost Per Each: 509.57


449.82 Cost Per Each: 449.82

Spec. No :
Unit (British) : Each
Napkins / Dusters etc
Rate (Rs)

100.00 1
TOTAL MATERIAL 12.20

850.00 1
3.00
TOTAL LABOUR 68.30
19.50

77.55 Cost Per Each: 77.55


65.60 Cost Per Each: 65.60
Spec. No :
Unit (British) : Each

Rate (Rs)

47.00 1
TOTAL MATERIAL 39.28

600.00 1
3.00
TOTAL LABOUR 41.22
19.50

367.97 Cost Per Each: 367.97


183.75 Cost Per Each: 183.75

Spec. No :
Unit (British) : Per Gallon
per gallon capacity
Unit Rate (Rs)

kg 100.00 1
Ltr 40.00 1
TOTAL MATERIAL 57.57

Day 600.00 1
3.00
TOTAL LABOUR 22.93
19.50

1.68 Cost Per Per Gallon: 1.68


0.44 Cost Per Per Gallon: 0.44

(British) : Each

Rate (Rs)

80.00 1
TOTAL MATERIAL 14.01

600.00 1
3.00
TOTAL LABOUR 66.49
19.50

134.88 Cost Per Each: 134.88


110.98 Cost Per Each: 110.98

Spec. No :
Unit (British) : 100 Cft

Rate (Rs)

11.00 1
TOTAL MATERIAL 63.62

600.00 1
3.00
TOTAL LABOUR 16.88
19.50

1,608.50 Per CUM : Rs 568.04


294.00 Per CUM : Rs 103.83

3.11
(British) : per spray

Rate (Rs)

2,000.00 1

TOTAL MATERIAL 74.25

850.00 1
3.00
TOTAL LABOUR 6.16

85.00 1

TOTAL EQUIPMENT 0.10


19.50

2,497.30 Cost Per per spray: 2,497.30


104.13 Cost Per per spray: 104.13

3.11.4
(British) : 100 Sft
Rate (Rs)

7.00 1

TOTAL MATERIAL 74.66

850.00 1
3.00
TOTAL LABOUR 4.58

85.00 1

TOTAL EQUIPMENT 1.26


19.50

868.73 Per SQM : Rs 93.47


18.12 Per SQM : Rs 1.95

3.11.4
(British) : 100 Sft

Rate (Rs) Amount

9.00 1

TOTAL MATERIAL 75.28

850.00 1
3.00
TOTAL LABOUR 4.24

85.00 1
TOTAL EQUIPMENT 0.99
19.50

1,107.73 Per SQM : Rs 119.19


18.12 Per SQM : Rs 1.95

16.8.11
(British) : Rft

Rate (Rs)

120.00 1 Kg
167.00 1 Kg
91.60 1 Doz
40.00 1 Kg
27,789.20 100 Cft

TOTAL MATERIAL 23.55

600.00 1
1,050.00 1
3.00
TOTAL LABOUR 56.95
19.50

493.04 Per Meter : Rs 1,617.18


345.82 Per Meter : Rs 1,134.28
16.8.11
(British) : Rft

Rate (Rs)

120.00 1 Kg
167.00 1 Kg
91.60 1 Doz
40.00 1 Kg
27,789.20 100 Cft

18,006.74 100 Cft 37.08

TOTAL MATERIAL 28.07

600.00 1
1,050.00 1
3.00
TOTAL LABOUR 52.43
19.50

537.35 Per Meter : Rs 1,762.50


345.82 Per Meter : Rs 1,134.28

(British) : Sft
Rate (Rs) Amount

56.82 1

TOTAL MATERIAL 63.30

850.00 1
3.00
TOTAL LABOUR 17.20
19.50

83.52 Per SQM : Rs 898.66


15.62 Per SQM : Rs 168.06

Spec. No :
Unit (British) : 100 Sft
Making notice board 1/2" thick of c/s mortar 1:3 with 2"x1/2" beading
Rate (Rs)

550.00 1
2,600.00 100 Cft
TOTAL MATERIAL 30.64

1,200.00 1
600.00 1
3.00
TOTAL LABOUR 49.86
19.50

3,009.80 Per SQM : Rs 323.85


1,837.50 Per SQM : Rs 197.72
Spec. No :
Unit (British) : Each

Rate (Rs)

55.00 1
56.00 1
57.00 1
TOTAL MATERIAL 62.60

800.00 1
3.00
TOTAL LABOUR 17.90
19.50

249.76 Cost Per Each: 249.76


49.00 Cost Per Each: 49.00

Spec. No :
Unit (British) : Per Cut

Rate (Rs)

1,200.00 1
3.00
TOTAL LABOUR 80.50
19.50

117.60 Cost Per Per Cut: 117.60


117.60 Cost Per Per Cut: 117.60
Spec. No :
Unit (British) : Per Cut
" Dia upto 4" dia
Unit Rate (Rs)

Days 1,200.00 1
3.00
TOTAL LABOUR 80.50
19.50

221.97 Cost Per Per Cut: 221.97


221.97 Cost Per Per Cut: 221.97

7.17
(British) : 100 Sft

Rate (Rs)

3.23 1
TOTAL MATERIAL 33.31

600.00 1
3.00
TOTAL LABOUR 47.19
19.50

956.53 Per SQM : Rs 102.92


551.25 Per SQM : Rs 59.31
(British) : Sft

Rate (Rs)

550.00 1
2,600.00 1
1,600.00 1
60.00 1
90.00 1
8.40 1
240.00 1
TOTAL MATERIAL 65.88

1,200.00 1
600.00 1
630.00 1
3.00
TOTAL LABOUR 14.62
19.50

690.49 Per SQM : Rs 7,429.63


105.69 Per SQM : Rs 1,137.22

(British) : 100 Sft

Rate (Rs)
130.00 1
508.00 1
TOTAL MATERIAL 43.05

1,200.00 1
3.00
TOTAL LABOUR 37.45
19.50

1,076.36 Per SQM : Rs 115.82


485.10 Per SQM : Rs 52.20

(British) : Each

Rate (Rs)

550.00 1
2,600.00 1
120.00 1
TOTAL MATERIAL 24.24

1,200.00 1
600.00 1
850.00 1
3.00
TOTAL LABOUR 13.19

800.00 1
TOTAL EQUIPMENT 43.07
19.50
6,040.52 Cost Per Each: 6,040.52
811.56 Cost Per Each: 811.56

(British) : Each

Rate (Rs)

550.00 1
2,600.00 1
120.00 1
TOTAL MATERIAL 22.89

1,200.00 1
600.00 1
850.00 1
3.00
TOTAL LABOUR 14.83

800.00 1
TOTAL EQUIPMENT 42.77
19.50

5,911.77 Cost Per Each: 5,911.77


921.81 Cost Per Each: 921.81
(British) : Rft

Rate (Rs)

600.00 1
600.00 1
3.00
TOTAL LABOUR 13.69

2,250.00 1

TOTAL EQUIPMENT 66.81


19.50

3,129.75 Per Meter : Rs 10,265.58


441.00 Per Meter : Rs 1,446.48

(British) : Rft
Rate (Rs)

600.00 1
600.00 1
3.00
TOTAL LABOUR 18.00

2,250.00 1

TOTAL EQUIPMENT 62.50


19.50

3,350.25 Per Meter : Rs 10,988.82


661.50 Per Meter : Rs 2,169.72

(British) : Rft
Rate (Rs)

600.00 1
600.00 1
3.00
TOTAL LABOUR 11.30

3,000.00 1

TOTAL EQUIPMENT 69.20


19.50

4,026.00 Per Meter : Rs 13,205.28


441.00 Per Meter : Rs 1,446.48

(British) : Rft

Rate (Rs)

600.00 1
600.00 1
3.00
TOTAL LABOUR 11.51

3,500.00 1

TOTAL EQUIPMENT 68.99


19.50

4,711.70 Per Meter : Rs 15,454.38


529.20 Per Meter : Rs 1,735.78

(British) : Rft

Rate (Rs)

600.00 1
600.00 1
3.00
TOTAL LABOUR 11.83

3,500.00 1
TOTAL EQUIPMENT 68.67
19.50

4,733.75 Per Meter : Rs 15,526.70


551.25 Per Meter : Rs 1,808.10

(British) : Acre

Rate (Rs)

850.00 1
2,500.00 1
5,000.00 1
3.00
TOTAL LABOUR 59.94

5,000.00 1

TOTAL EQUIPMENT 20.56


19.50

458.83 Cost Per ha: 458.83


339.33 Cost Per ha: 458.83
Amount

78,000.00

% 78,000.00

Day 1,920.00
Day 1,360.00
Day 1,920.00
Day 1,920.00
% 213.60
% 7,333.60
% 16,598.40
Amount

55,000.00

% 55,000.00

Day 1,680.00
Day 1,190.00
Day 1,680.00
Day 1,680.00
% 186.90
% 6,416.90
% 11,939.85
Amount

44,600.00

% 44,600.00

Day 1,440.00
Day 1,020.00
Day 1,440.00
Day 1,440.00
% 160.20
% 5,500.20
% 9,738.30
Amount

38,500.00

% 38,500.00

Day 960.00
Day 680.00
Day 960.00
Day 960.00
% 106.80
% 3,666.80
% 8,201.70
Amount

37,000.00

% 37,000.00

Day 720.00
Day 510.00
Day 720.00
Day 720.00
% 80.10
% 2,750.10
% 7,735.65

Amount

34,500.00
% 34,500.00

Day 480.00
Day 340.00
Day 480.00
Day 480.00
% 53.40
% 1,833.40
% 7,074.60

Amount

315,000.00

% 315,000.00

Day 2,400.00
Day 2,400.00
Day 1,700.00
Day 2,400.00
% 267.00
% 9,167.00
% 63,160.50

Amount

294,000.00

% 294,000.00

Day 2,160.00
Day 2,160.00
Day 1,530.00
Day 2,160.00
% 240.30
% 8,250.30
% 58,891.95
Amount

262,000.00

% 262,000.00

Day 1,920.00
Day 1,920.00
Day 1,360.00
Day 1,920.00
% 213.60
% 7,333.60
% 52,478.40
Amount

174,000.00

% 174,000.00

Day 1,680.00
Day 1,680.00
Day 1,190.00
Day 1,680.00
% 186.90
% 6,416.90
% 35,144.85
Amount

169,000.00

% 169,000.00

Day 1,440.00
Day 1,440.00
Day 1,020.00
Day 1,440.00
% 160.20
% 5,500.20
% 33,996.30

Amount
161,000.00

% 161,000.00

Day 960.00
Day 960.00
Day 680.00
Day 960.00
% 106.80
% 3,666.80
% 32,089.20

Amount

157,000.00
% 157,000.00

Day 480.00
Day 480.00
Day 340.00
Day 480.00
% 53.40
% 1,833.40
% 30,962.10

Amount

213,000.00

% 213,000.00

Day 2,280.00
Day 2,280.00
Day 1,615.00
Day 2,280.00
% 253.65
% 8,708.65
% 43,183.73

Amount

207,000.00

% 207,000.00

Day 2,160.00
Day 2,160.00
Day 1,530.00
Day 2,160.00
% 240.30
% 8,250.30
% 41,926.95
Amount

190,000.00

% 190,000.00

Day 1,920.00
Day 1,920.00
Day 1,360.00
Day 1,920.00
% 213.60
% 7,333.60
% 38,438.40
Amount

176,000.00

% 176,000.00

Day 1,680.00
Day 1,680.00
Day 1,190.00
Day 1,680.00
% 186.90
% 6,416.90
% 35,534.85
Amount

163,500.00

% 163,500.00

Day 1,440.00
Day 1,440.00
Day 1,020.00
Day 1,440.00
% 160.20
% 5,500.20
% 32,923.80

Amount

155,000.00
% 155,000.00

Day 960.00
Day 960.00
Day 680.00
Day 960.00
% 106.80
% 3,666.80
% 30,919.20

Amount

152,000.00

% 152,000.00
Day 720.00
Day 720.00
Day 510.00
Day 720.00
% 80.10
% 2,750.10
% 30,160.65

Amount

148,000.00

% 148,000.00

Day 480.00
Day 480.00
Day 340.00
Day 480.00
% 53.40
% 1,833.40
% 29,207.10

Amount

325,000.00

% 325,000.00

Day 2,400.00
Day 2,400.00
Day 1,700.00
Day 2,400.00
% 267.00
% 9,167.00
% 65,110.50
Amount

320,000.00

% 320,000.00

Day 2,160.00
Day 2,160.00
Day 1,530.00
Day 2,160.00
% 240.30
% 8,250.30
% 63,961.95
Amount

270,000.00

% 270,000.00

Day 1,920.00
Day 1,920.00
Day 1,360.00
Day 1,920.00
% 213.60
% 7,333.60
% 54,038.40
Amount

164,000.00

% 164,000.00

Day 1,680.00
Day 1,680.00
Day 1,190.00
Day 1,680.00
% 186.90
% 6,416.90
% 33,194.85

Amount
152,000.00

% 152,000.00

Day 1,440.00
Day 1,440.00
Day 1,020.00
Day 1,440.00
% 160.20
% 5,500.20
% 30,681.30

Amount

150,000.00
% 150,000.00

Day 960.00
Day 960.00
Day 680.00
Day 960.00
% 106.80
% 3,666.80
% 29,944.20

Amount

147,000.00

% 147,000.00

Day 480.00
Day 480.00
Day 340.00
Day 480.00
% 53.40
% 1,833.40
% 29,012.10

Amount

227,000.00

% 227,000.00

Day 2,280.00
Day 2,280.00
Day 1,615.00
Day 2,280.00
% 253.65
% 8,708.65
% 45,913.73
Amount

215,000.00

% 215,000.00

Day 2,160.00
Day 2,160.00
Day 1,530.00
Day 2,160.00
% 240.30
% 8,250.30
% 43,486.95
Amount

190,000.00

% 190,000.00

Day 1,920.00
Day 1,920.00
Day 1,360.00
Day 1,920.00
% 213.60
% 7,333.60
% 38,438.40
Amount

151,000.00

% 151,000.00

Day 1,680.00
Day 1,680.00
Day 1,190.00
Day 1,680.00
% 186.90
% 6,416.90
% 30,659.85

Amount

145,000.00
% 145,000.00

Day 1,440.00
Day 1,440.00
Day 1,020.00
Day 1,440.00
% 160.20
% 5,500.20
% 29,316.30

Amount

141,000.00

% 141,000.00
Day 960.00
Day 960.00
Day 680.00
Day 960.00
% 106.80
% 3,666.80
% 28,189.20

Amount

138,000.00

% 138,000.00

Day 480.00
Day 480.00
Day 340.00
Day 480.00
% 53.40
% 1,833.40
% 27,257.10

Amount

135,000.00

% 135,000.00

Day 480.00
Day 480.00
Day 340.00
Day 480.00
% 53.40
% 1,833.40
% 26,672.10
Amount

404,000.00

% 404,000.00

Day 2,640.00
Day 2,640.00
Day 1,870.00
Day 2,640.00
% 293.70
% 10,083.70
% 80,689.05
Amount

397,000.00

% 397,000.00

Day 2,520.00
Day 2,520.00
Day 1,785.00
Day 2,520.00
% 280.35
% 9,625.35
% 79,237.27
Amount

349,000.00

% 349,000.00

Day 2,280.00
Day 2,280.00
Day 1,615.00
Day 2,280.00
% 253.65
% 8,708.65
% 69,703.73
Amount

220,000.00

% 220,000.00

Day 2,040.00
Day 2,040.00
Day 1,445.00
Day 2,040.00
% 226.95
% 7,791.95
% 44,375.18

Amount

209,000.00
% 209,000.00

Day 1,440.00
Day 1,440.00
Day 1,020.00
Day 1,440.00
% 160.20
% 5,500.20
% 41,796.30

Amount

198,000.00
% 198,000.00

Day 960.00
Day 960.00
Day 680.00
Day 960.00
% 106.80
% 3,666.80
% 39,304.20

Amount

193,000.00

% 193,000.00

Day 480.00
Day 480.00
Day 340.00
Day 480.00
% 53.40
% 1,833.40
% 37,982.10

Amount

304,000.00

% 304,000.00

Day 2,400.00
Day 1,500.00
Day 1,700.00
Day 2,400.00
% 240.00
% 8,240.00
% 60,840.00
Amount

295,000.00

% 295,000.00

Day 2,160.00
Day 2,160.00
Day 1,530.00
Day 2,160.00
% 240.30
% 8,250.30
% 59,086.95
Amount

265,000.00

% 265,000.00

Day 1,920.00
Day 1,920.00
Day 1,360.00
Day 1,920.00
% 213.60
% 7,333.60
% 53,063.40
Amount

216,000.00

% 216,000.00

Day 1,680.00
Day 1,680.00
Day 1,190.00
Day 1,680.00
% 186.90
% 6,416.90
% 43,334.85

Amount

196,000.00
% 196,000.00

Day 1,440.00
Day 1,440.00
Day 1,020.00
Day 1,440.00
% 160.20
% 5,500.20
% 39,261.30

Amount

178,000.00

% 178,000.00
Day 1,200.00
Day 1,200.00
Day 850.00
Day 1,200.00
% 133.50
% 4,583.50
% 35,577.75

Amount

174,000.00

% 174,000.00

Day 960.00
Day 960.00
Day 680.00
Day 960.00
% 106.80
% 3,666.80
% 34,624.20
Amount

170,000.00

% 170,000.00

Day 480.00
Day 480.00
Day 340.00
Day 480.00
% 53.40
% 1,833.40
% 33,497.10
25.3 , 25.4

Amount

Day 13.80
Day 2.81
Day 1.98
% 0.56
% 19.14
% 3.62

25.3 , 25.4

Amount

Day 4.80
Day 0.68
Day 0.48
% 0.18
% 6.14
% 1.16
Amount

Day 36.00
Day 8.50
Day 6.00
% 1.52
% 52.02
% 9.85

25.3 , 25.4

Amount

Day 4,500.00
Day 300.00
% 144.00
% 4,944.00
% 936.00
25.3 , 25.4

Amount

Day 300.00
Day 262.50
% 16.88
% 579.38
% 109.69

25.3 , 25.4

Amount

Day 510.00
% 15.30
% 525.30
% 99.45
Amount

Day 45.00
Day 3.00
Day 15.00

% 1.89
% 64.89
% 12.29

Amount

Day 6.90
Day 0.48
% 0.22
% 7.60
% 1.44
Amount

Kg 110,000.00
% 110,000.00

Day 48,000.00
Day 4,800.00
% 1,584.00
% 54,384.00
% 31,746.00

Amount

Pkt 928.20
Kg 110,000.00
% 110,928.20

Day 3,000.00
Day 5,250.00
% 247.50
% 8,497.50
% 23,239.75
Amount

Day 3,809.40
Day 4,761.75

% 257.13
% 8,828.28
% 1,671.37

Amount

Day 4.80
Day 8.40
% 0.40
% 13.60
% 2.57

25.3 , 25.4

Amount

Day 9,120.00
Day 3,360.00
% 374.40
% 12,854.40
% 2,433.60

Amount

Day 696.00
Day 42.00
% 22.14
% 760.14
% 143.91

Amount

Day 324.00
Day 42.00
% 10.98
% 376.98
% 71.37

25.3.2, 25.3.5
, 25.3.6

Amount

Kg 81.40
% 81.40

Day 21.00
Day 73.50
Day 29.75
% 3.73
% 127.98
% 40.10

25.3.2, 25.3.3,
25.4.21 25.4.17

Amount

Day 100.02
Day 125.03

% 6.75
% 231.80
% 43.88

25.3.2, 25.3.3,
25.4.21 25.4.17

Amount

Day 150.00
Day 187.50

% 10.13
% 347.63
% 65.81

25.3.2, 25.3.3,
25.4.21 25.4.17

Amount

Day 49.98
Day 62.48

% 3.37
% 115.83
% 21.93

25.3.2, 25.3.3,
25.4.21 25.4.17

Amount

Kg 1,148.59
% 1,148.59

Day 85.74
Day 107.18

% 5.79
% 198.70
% 261.59

25.4.2.3

Amount

Day 40.02
Day 12.52

% 1.58
% 54.12
% 10.25
Amount

Day 24.00
Day 1.88

% 0.78
% 26.65
% 5.05

25.4.5

Amount

Day 3.00
Day 3.75

% 0.20
% 6.95
% 1.32

25.4.2.2 ,
Amount

Day 8.34
Day 10.43

% 0.56
% 19.33
% 3.66

Amount

Day 30.00
Day 5.25
Day 3.75

% 1.17
% 40.17
% 7.61

25.4.2.2 ,
Amount

Day 19.98
Day 20.04
Day 12.52

% 1.58
% 54.12
% 10.25

25.4.2.2 ,

Amount

Day 10.02
Day 12.52

% 0.68
% 23.22
% 4.40

25.4.2.2
Amount

Kg 44.66
% 44.66

Day 199.98
Day 249.97

% 13.50
% 463.45
% 96.45

25.4.4, 25.4.8,
25.4.9 ,
25.4.13

Amount

Kg 1.86
% 1.86

Day 29.19
Day 16.68
% 1.38
% 47.25
% 9.31
25.4.4, 25.4.8,
25.4.9 ,
25.4.13

Amount

Kg 0.65
% 0.65

Day 7.98
Day 15.96
% 0.72
% 24.66
% 4.80

41.57
14.44
635.80
5.62

9.65

% 707.09

Day 195.20
Day 130.13
Day 158.01
% 14.50
% 497.84
% 232.13

41.57
14.44
717.20
5.62

9.65

% 788.49

Day 195.20
Day 130.13
Day 158.01
% 14.50
% 497.84
% 248.01
693.60
171.84
41.57
24.07
5.62

9.65

% 946.36

Day 195.20
Day 111.54
Day 120.33
% 12.81
% 439.88
% 267.82
Amount

Kg 5.36
Kg 345.40
% 350.76

Day 52.50
Day 30.00
Day 30.00

% 3.38
% 115.88
% 90.34

Amount

Kg 500.52
Rft 45.00
% 545.52

Day 21.25
Day 42.00
Day 52.50
% 3.47
% 119.22
% 128.95

Amount

42.23
85.00

% 127.23

Day 10.50
Day 20.00
% 0.92
% 31.42
% 30.76
Amount

Ltr 20.06
Sft 525.00
% 545.06

Day 67.91
Day 48.12
Day 83.89
Day 59.92

% 7.80
% 267.65
% 156.96

Amount

Ltr 20.06
Sft 165.00
No 9.50
% 194.56
Day 8.50
Day 6.00
Day 10.50
Day 7.50

% 0.98
% 33.48
% 44.28

Amount

Kg 198.06
% 198.06

Day 24.00
Day 12.00
Day 2.63
% 1.16
% 39.78
% 46.15
Amount

Kg 145.25
Ltr 18.05
RFT 132.95
Pack 4.32
% 300.57

Day 12.00
Day 18.00
Day 12.00
Day 42.00
Day 24.00
Day 24.00

% 3.96
% 135.96
% 84.35

Amount

KG 9.60
Pack 24.78
RFT 55.00
% 89.38

Day 67.20
Day 30.00
% 2.92
% 100.12
% 36.38

Amount

Ltr 70.82
SFT 35.00
SFT 437.00
% 542.82

Day 6.00
Day 12.00
Day 10.50
% 0.86
% 29.36
% 111.41
Amount

Ltr 70.82
SFT 40.00
SFT 437.00
% 547.82

Day 6.00
Day 12.00
Day 10.50
% 0.86
% 29.36
% 112.38
Amount

Ltr 70.82
SFT 48.00
SFT 437.00
% 555.82

Day 6.00
Day 12.00
Day 10.50
% 0.86
% 29.36
% 113.94

Amount
Ltr 70.82
SFT 55.00
SFT 437.00
% 562.82

Day 6.00
Day 12.00
Day 10.50
% 0.86
% 29.36
% 115.31

Amount

Ltr 70.82
SFT 62.50
SFT 437.00
% 570.32

Day 6.00
Day 12.00
Day 10.50
% 0.86
% 29.36
% 116.77
Amount

Ltr 94.41
SFT 55.00
SFT 35.00
SFT 437.00
% 621.41

Day 6.00
Day 15.00
Day 10.50
% 0.95
% 32.45
% 127.32
Amount

Ltr 94.41
SFT 55.00
SFT 35.00
SFT 437.00
% 621.41

Day 6.00
Day 15.00
Day 10.50
% 0.95
% 32.45
% 127.32

Amount

Ltr 94.41
SFT 55.00
SFT 48.00
SFT 437.00
% 634.41

Day 6.00
Day 15.00
Day 10.50
% 0.95
% 32.45
% 129.85
Amount

Ltr 94.41
SFT 55.00
SFT 55.00
SFT 437.00
% 641.41

Day 6.00
Day 15.00
Day 10.50
% 0.95
% 32.45
% 131.22
Amount

Ltr 94.41
SFT 55.00
SFT 62.50
SFT 437.00
% 648.91

Day 6.00
Day 15.00
Day 10.50
% 0.95
% 32.45
% 132.68

Amount

Kg 360.00
Sft 60.00
% 420.00

Day 300.00
Day 187.50

% 14.63
% 502.13
% 176.96
1 Ltr 140.47
1 Kg 709.69
1 No 13.50
1 Rft 90.00
60.40 % 953.65

1 Day 90.00
1 Day 45.00
1 Day 78.75
1 Day 56.25

3.00 % 8.10
20.10 % 278.10
19.50 % 238.61

Per Meter : Rs 4,822.80


Per Meter : Rs 1,084.86

25.7.4
Amount

Bag 6.43
0.04
0.13
Kg 18.99
Ltr 42.81
Kg 33.55
% 101.95

Day 18.36
Day 9.18
Day 5.52
Day 16.07
Day 9.18
% 1.75
% 60.05
% 31.25

Amount

Bag 2.64
0.02
0.05
Kg 25.30
Ltr 42.81
Kg 46.97
% 117.79

Day 18.24
Day 11.88
Day 5.52
Day 17.64
Day 9.12
% 1.87
% 64.27
% 35.14

Amount

Kg 549.77
Ltr 25.08
Pack 46.41
Ltr 13.58
No 6.31
No 10.00

% 651.15

Day 46.86
Day 18.72
Day 16.38
Day 32.87
% 3.44
% 118.27
% 149.37
Amount

Kg 292.13
Kg 27.70
Ltr 14.32
Pack 58.01
Ltr 5.21
No 8.55

Doz 8.84
No 4.71
% 419.49

Day 5.34
Day 21.48
Day 56.28
Day 37.49
% 3.62
% 124.20
% 105.31
Amount

Kg 292.13
Kg 10.77
Ltr 11.15
Pack 58.01
Ltr 4.06
Kg 157.32
No 1.83
No 7.44
% 542.71

Day 33.36
Day 58.32
Day 16.68
Day 58.38
Day 29.19
% 5.88
% 201.81
% 144.04

Amount

Rft 230.00
% 230.00

Day 82.50
Day 144.38
Day 82.50
% 9.28
% 318.66
% 105.18

ft 900.00

% 900.00

Day 120.00
Day 131.25
% 7.54
% 258.79
% 224.49
Amount

Day 300.00
% 9.00
% 309.00
% 58.50

Amount

Kg 145.00

% 145.00

Day 45.60
Day 21.00
% 2.00
% 68.60
% 41.26
Amount

No 500.00

% 500.00

Day 78.00
% 2.34
% 80.34
% 112.71

25.7.4

Amount

Each 100.00

% 100.00

Day 30.00
% 0.90
% 30.90
% 25.35
Amount

Kg 110.00
% 110.00

Day 21.00
Day 12.00
% 0.99
% 33.99
% 27.89

Amount

Kg 209.00
Kg 114.00

% 323.00
Day 240.00
% 7.20
% 247.20
% 109.79

Amount

kg 40.12
sft 300.00
% 340.12

Day 72.00
Day 84.00
% 4.68
% 160.68
% 96.74
Amount

Packet 2.92
% 2.92

Day 12.48
Day 17.53
% 0.90
% 30.92

hr 10.43
% 10.43
% 8.46

Amount

Each 9,000.00

% 9,000.00

Day 600.00
Day 2,100.00
% 81.00
% 2,781.00
% 2,281.50
Amount

1.60
13.80
19.14
89.57
104.99
41.70

% 270.80

Day 12.00
Day 8.34
Day 23.63
Day 139.97
% 5.52
% 189.45
% 88.67
Amount

140.00

150.00

% 290.00

Day 519.84
Day 82.50
Day 48.00
% 19.51
% 669.85
% 183.37

Amount

Sft 110.00
% 110.00

Day 48.00
Day 84.00
% 3.96
% 135.96
% 47.19

Packet 5.15
Rft 81.40

Rft 92.40

Rft 58.00

kg 10.38
Sft 110.00
% 357.34

Day 6.66
Day 11.65
% 0.55
% 18.86
% 73.25
Packet 5.15
Rft 96.20

Rft 96.80

Rft 121.80

kg 10.38
sft 100.00
% 430.34

Day 6.66
Day 11.65
% 0.55
% 18.86
% 87.49
Pkt 23.20
Rft 185.00

Rft 140.80

Rft 243.60

KG 27.50
sft 100.00
% 720.10

Day 6.60
Day 11.55
% 0.54
% 18.69
% 143.96

Amount
17.09
5.94
180.46

110.00

% 313.49

Day 1.56
Day 24.12
Day 2.73
Day 1.15
% 0.89
% 30.45
% 66.90

Amount

Bag 2.20
0.16
0.55
Kg 24.40

Kg 27.48
Kg 125.00
% 179.79

Day 12.00
Day 12.00
Day 10.50
% 1.04
% 35.54
% 41.79

Amount

Bag 2.20
0.16
0.55
Kg 24.40

Kg 27.48
Kg 60.00
% 114.79

Day 12.00
Day 12.00
Day 10.50
% 1.04
% 35.54
% 29.11
Amount

Kg 24.40

Kg 27.48
Kg 13.20
Kg 125.00
% 190.08

Day 12.00
Day 12.00
Day 10.50
% 1.04
% 35.54
% 43.79
Amount

Kg 24.40

Kg 27.48
Kg 13.20
Kg 60.00
% 125.08

Day 12.00
Day 12.00
Day 10.50
% 1.04
% 35.54
% 31.12

Amount

Job 12.35
Pack 58.01
Rft 161.76
Sft 150.00

No. 10.00
No. 9.53
No. 5.00
% 406.66

Day 5.40
Day 43.20
Day 56.70
% 3.16
% 108.46
% 99.83

No 26,000.00

% 26,000.00

Day 300.00
% 9.00
% 309.00

Hour 1,756.18
% 1,756.18
% 5,470.96
No 24,000.00

% 24,000.00

Day 212.50
Day 300.00
% 15.38
% 527.88

Hour 1,756.18
% 1,756.18
% 5,122.39
Amount

No 37,000.00

% 37,000.00

Day 280.50
Day 396.00
% 20.30
% 696.80

Hour 1,756.18
% 1,756.18
% 7,689.37

Amount

No 35,000.00
% 35,000.00

Day 280.50
Day 396.00
% 20.30
% 696.80

Hour 1,756.18
% 1,756.18
% 7,299.37

Amount

No 50,000.00

% 50,000.00

Day 425.00
Day 600.00
% 30.75
% 1,055.75

Hour 1,756.18
% 1,756.18
% 10,292.33
Amount

No 48,000.00

% 48,000.00

Day 425.00
Day 600.00
% 30.75
% 1,055.75

Hour 1,756.18
% 1,756.18
% 9,902.33

26.2.4

Amount

Rft 65.00
% 65.00

Day 6.00
% 0.18
% 6.18
% 13.85

15.2.4

Amount

Rft 85.00

% 85.00

Day 6.00
% 0.18
% 6.18
% 17.75

15.2.4

Amount
Rft 95.00
% 95.00

Day 6.00
% 0.18
% 6.18
% 19.70

No 23,000.00

% 23,000.00

Day 75.00
Day 78.13
% 4.59
% 157.72

Hour 87.81
% 87.81
% 4,531.98
No 31,000.00

% 31,000.00

Day 75.00
Day 78.13
% 4.59
% 157.72

Hour 878.09
% 878.09
% 6,246.09
No 42,000.00

% 42,000.00

Day 75.00
Day 78.13
% 4.59
% 157.72

Hour 878.09
% 878.09
% 8,391.09

No 55,000.00

% 55,000.00

Day 75.00
Day 78.13
% 4.59
% 157.72

Hour 878.09
% 878.09
% 10,926.09
15.6.1

Amount

No 500.00

% 500.00

Day 75.60
% 2.27
% 77.87
% 112.24

15.6.1

Amount

No 650.00

% 650.00

Day 75.60
% 2.27
% 77.87
% 141.49

26.6.1

Amount

No 800.00

% 800.00

Day 75.60
% 2.27
% 77.87
% 170.74

26.6.1

Amount

No 1,000.00

% 1,000.00

Day 75.60
% 2.27
% 77.87
% 209.74

15.6.1

Amount

No 2,000.00

% 2,000.00

Day 75.60
% 2.27
% 77.87
% 404.74

Amount

No 595.00

% 595.00
Day 75.60
% 2.27
% 77.87
% 130.77

Amount

Watt 60.00

% 60.00

Day 0.72
% 0.02
% 0.74
% 11.84
Amount

Watt 58.00

% 58.00

Day 0.72
% 0.02
% 0.74
% 11.45

Amount

No 9,325.00

% 9,325.00

Day 75.60
% 2.27
% 77.87
% 1,833.12
Amount

No 13,385.00

% 13,385.00

Day 75.60
% 2.27
% 77.87
% 2,624.82

Amount

No. 9,750.00

% 9,750.00

Day 75.60
% 2.27
% 77.87
% 1,915.99

Amount

No. 19,925.00

% 19,925.00

Day 75.60
% 2.27
% 77.87
% 3,900.12

Amount
No 28,490.00

% 28,490.00

Day 75.60
% 2.27
% 77.87
% 5,570.29

Amount

No. 30,550.00

% 30,550.00

Day 75.60
% 2.27
% 77.87
% 5,971.99
Amount

No 34,625.00

% 34,625.00

Day 75.60
% 2.27
% 77.87
% 6,766.62

Amount

No 39,530.00

% 39,530.00

Day 75.60
% 2.27
% 77.87
% 7,723.09
26.60

Amount

AH 258.00
% 258.00

Day 3.60
% 0.11
% 3.71
% 51.01

25.50

Amount

AH 242.00
% 242.00

Day 3.60
% 0.11
% 3.71
% 47.89
26.70

Amount

AH 274.00
% 274.00

Day 3.60
% 0.11
% 3.71
% 54.13

26.80

Amount

AH 266.00
% 266.00

Day 3.60
% 0.11
% 3.71
% 52.57
26.80

Amount

AH 200.00
% 200.00

Day 3.60
% 0.11
% 3.71
% 39.70

26.90

Amount

AH 56,220.00
% 56,220.00

Day 1,200.00
% 36.00
% 1,236.00
% 11,196.90
26.80

Amount

AH 80.70
% 80.70

Day 1.20
% 0.04
% 1.24
% 15.97

26.80

Amount

AH 68.40
% 68.40

Day 1.20
% 0.04
% 1.24
% 13.57
26.2, 26.43

Amount

Rft 28.00

% 28.00

Day 1.20
% 0.04
% 1.24
% 5.69

26.2, 26.43

Amount

Rft 42.00

% 42.00

Day 1.20
% 0.04
% 1.24
% 8.42
Amount

Rft 57.00

% 57.00

Day 1.20
% 0.04
% 1.24
% 11.35

26.2, 26.43

Amount

Rft 88.00

% 88.00
Day 1.20
% 0.04
% 1.24
% 17.39

26.2, 26.43

Amount

Rft 137.00

% 137.00

Day 1.00
% 0.03
% 1.03
% 26.91

26.2, 26.43

Amount

Rft 195.00
% 195.00
Day 1.00
% 0.03
% 1.03
% 38.22

26.2, 26.43

Amount

Rft 268.00

% 268.00

Day 1.00
% 0.03
% 1.03
% 52.46

26.2, 26.43

Amount

Rft 51.50
% 51.50

Day 1.20
% 0.04
% 1.24
% 10.28

26.2, 26.43

Amount

Rft 77.50

% 77.50

Day 1.20
% 0.04
% 1.24
% 15.35

26.2, 26.43

Amount
Rft 108.00

% 108.00

Day 1.20
% 0.04
% 1.24
% 21.29

26.2, 26.43

Amount

Rft 154.00

% 154.00

Day 1.20
% 0.04
% 1.24
% 30.26

26.2, 26.43
Amount

Rft 320.00
% 320.00

Day 1.20
% 0.04
% 1.24
% 62.63

26.2, 26.43

Amount

Rft 450.00
% 450.00

Day 1.20
% 0.04
% 1.24
% 87.98

26.2, 26.43
Amount

Rft 650.00
% 650.00

Day 1.20
% 0.04
% 1.24
% 126.98

Amount

Pair 187.50

% 187.50

Day 37.56
% 1.13
% 38.69
% 43.89

26.20
Amount

Pair 900.00
% 900.00

Day 37.56
% 1.13
% 38.69
% 182.82

Amount

Watt 64.36

% 64.36

Day 1.20
% 0.04
% 1.24
% 12.78
Amount

Watt 33.30

% 33.30

Day 1.20
% 0.04
% 1.24
% 6.73

Amount

per 21.12
Watt

% 21.12

Day 1.20
% 0.04
% 1.24
% 4.35

Amount

Per 12.95
Watt

% 12.95

Day 1.20
% 0.04
% 1.24
% 2.76

Amount
per 17.45
Watt
% 17.45

Day 1.20
% 0.04
% 1.24
% 3.64

Amount

Per 39.89
Watt
% 39.89

Day 1.20
% 0.04
% 1.24
% 8.01
Amount

Watt 21.13

% 21.13

Day 0.60
% 0.02
% 0.62
% 4.24

Amount

Watt 19.50

% 19.50

Day 0.60
% 0.02
% 0.62
% 3.92
Amount

Watt 17.87

% 17.87

Day 0.60
% 0.02
% 0.62
% 3.60

Amount

Watt 16.23

% 16.23

Day 0.60
% 0.02
% 0.62
% 3.28
Amount

No 73,550.00

% 73,550.00

Day 600.00
% 18.00
% 618.00
% 14,459.25

Amount

No 111,000.00

% 111,000.00
Day 600.00
% 18.00
% 618.00
% 21,762.00

Amount

No 65,000.00

% 65,000.00

Day 1,200.00
% 36.00
% 1,236.00
% 12,909.00
Amount

No 100,000.00

% 100,000.00

Day 1,200.00
% 36.00
% 1,236.00
% 19,734.00

Amount

No 200,000.00

% 200,000.00

Day 1,200.00
% 36.00
% 1,236.00
% 39,234.00
Amount

No 320,000.00

% 320,000.00

Day 1,200.00
% 36.00
% 1,236.00
% 62,634.00

Amount

No 600,000.00

% 600,000.00

Day 2,400.00
% 72.00
% 2,472.00
% 117,468.00
26.13

Amount

1 No 4,668.00

% 4,668.00

Day 132.00
% 3.96
% 135.96
% 936.00

26.15

Amount

No 3,700.00

% 3,700.00
Day 132.00
% 3.96
% 135.96
% 747.24

26.16

Amount

No 3,900.00

% 3,900.00

Day 132.00
% 3.96
% 135.96
% 786.24
17.03

% 17.03

Day 1.20
% 0.04
% 1.24
% 3.55

15.1.2

Amount

Watt 7.00

% 7.00

Day 1.20
% 0.04
% 1.24
% 1.60
Amount

No 2.00

% 2.00

Day 1.20
% 0.04
% 1.24
% 0.62

Amount

Watt 2.00

% 2.00

Day 1.20
% 0.04
% 1.24
% 0.62
Amount

Watt 4.00

% 4.00

Day 1.20
% 0.04
% 1.24
% 1.01

Amount

No 65,000.00
% 65,000.00
Day 600.00
% 18.00
% 618.00
% 12,792.00

Amount

No 70,000.00
% 70,000.00

Day 600.00
% 18.00
% 618.00
% 13,767.00

Amount

No 75,000.00
% 75,000.00
Day 600.00
% 18.00
% 618.00
% 14,742.00

Amount

No 223,800.00

% 223,800.00

Day 1,200.00
% 36.00
% 1,236.00
% 43,875.00

26.34

Amount

kW 24,461.00
% 24,461.00

Day 37.20
% 1.12
% 38.32
% 4,777.15

Amount

Kg 52.00
Pack 69.62
% 121.62

Day 42.00
Day 144.00
Day 115.50
% 9.05
% 310.55
% 82.51
Amount

Kg 39.00
Pack 10.50
% 49.50

Day 132.00
Day 105.00
% 7.11
% 244.11
% 55.87

Amount

2.00

% 2.00
Day 2.34
Day 3.00
% 0.16
% 5.50
% 1.43

Amount

Packet 9.65
% 9.65

Day 8.76
Day 21.84
% 0.92
% 31.52
% 7.85
Day 120.00
% 3.60
% 123.60
% 23.40

417.00

110.00

% 527.00

Day 300.00
Day 63.00
% 10.89
% 373.89
% 173.55
Amount

No. 11,000.00
% 11,000.00

Day 300.00
Day 540.00
% 25.20
% 865.20
% 2,308.80
60.00

% 60.00

Day 106.25
Day 150.00
% 7.69
% 263.94
% 61.67

Amount

60.00

% 60.00

Day 127.50
Day 180.00
% 9.23
% 316.73
% 71.66

Amount

60.00

% 60.00

Day 106.25
Day 210.00
% 9.49
% 325.74
% 73.37
Amount

60.00

% 60.00

Day 165.00
Day 240.00
% 12.15
% 417.15
% 90.68

Amount

60.00
% 60.00

Day 255.00
Day 240.00
% 14.85
% 509.85
% 108.23

Amount

60.00

% 60.00

Day 84.00
% 2.52
% 86.52
% 28.08
Amount

No. 9,500.00

% 9,500.00

Day 150.00
Day 262.50
% 12.38
% 424.88
% 1,932.94

Amount

No. 11,250.00

% 11,250.00
Day 150.00
Day 262.50
% 12.38
% 424.88
% 2,274.19

Amount

No. 5,500.00

% 5,500.00

Day 150.00
Day 262.50
% 12.38
% 424.88
% 1,152.94
Amount

No. 6,250.00

% 6,250.00

Day 150.00
Day 262.50
% 12.38
% 424.88
% 1,299.19

650.00

% 650.00

Day 150.00
Day 420.00
% 17.10
% 587.10
% 237.90
775.00

% 775.00

Day 180.00
Day 480.00
% 19.80
% 679.80
% 279.83
650.00

% 650.00

Day 150.00
Day 420.00
% 17.10
% 587.10
% 237.90

Amount

HP 775.00

% 775.00

Day 180.00
Day 480.00
% 19.80
% 679.80
% 279.83
Amount

Each 250.00
% 250.00

Day 60.00
Day 180.00
% 7.20
% 247.20
% 95.55

Amount

Each 3,500.00
% 3,500.00

Day 240.00
Day 600.00
% 25.20
% 865.20
% 846.30

Amount

Each 5,600.00

% 5,600.00

Day 300.00
Day 900.00
% 36.00
% 1,236.00
% 1,326.00
Amount

Each 210.00
% 210.00

Day 48.00
% 1.44
% 49.44
% 50.31

Amount

Each 4,500.00

% 4,500.00

Day 600.00
% 18.00
% 618.00
% 994.50
Amount

Each 3,600.00
% 3,600.00

Day 600.00
% 18.00
% 618.00
% 819.00

Amount

Each 320.00
% 320.00

Day 120.00
% 3.60
% 123.60
% 85.80
Amount

Rft 490.00
% 490.00

Day 300.00
% 9.00
% 309.00
% 154.05

Amount

Rft 380.00

% 380.00

Day 240.00
% 7.20
% 247.20
% 120.90
Amount

Job 13,800.00

% 13,800.00

Day 1,200.00
% 36.00
% 1,236.00
% 2,925.00

Amount

No. 4,450.00

% 4,450.00

Day 600.00
% 18.00
% 618.00
% 984.75
Amount

Job 3,580.00

% 3,580.00

Day 600.00
% 18.00
% 618.00
% 815.10

Amount

Job 3,580.00

% 3,580.00

Day 600.00
% 18.00
% 618.00
% 815.10
No.

Amount

1 No 4,400.00

66.60 % 4,400.00

1 Day 720.00
3.00 % 21.60
13.90 % 741.60
19.50 % 998.40

Cost Per No.: 6,140.00


Cost Per No.: 882.00

Amount

No 1,450.00
% 1,450.00

Day 720.00
% 21.60
% 741.60
% 423.15
Amount

No 590.00

% 590.00

Day 180.00
% 5.40
% 185.40
% 150.15

Amount

No 1,350.00

% 1,350.00

Day 360.00
% 10.80
% 370.80
% 333.45
Amount

No 1,150.00
% 1,150.00

Day 600.00
% 18.00
% 618.00
% 341.25

Amount

No 500.00

% 500.00

Day 180.00
% 5.40
% 185.40
% 132.60
Amount

No 25.00

% 25.00

Day 19.20
% 0.58
% 19.78
% 8.62

Amount

No 65.00
% 65.00

Day 21.60
% 0.65
% 22.25
% 16.89
Amount

LS 80.00

% 80.00

Day 288.75
% 8.66
% 297.41
% 71.91

Amount

No 9,750.00

% 9,750.00

Day 150.00
Day 900.00
% 31.50
% 1,081.50
% 2,106.00

Amount

per set 3,350.00

% 3,350.00

Day 150.00
Day 525.00
% 20.25
% 695.25
% 784.88

Amount
No 575.00

% 575.00

Day 210.00
% 6.30
% 216.30
% 153.08

Amount

per set 550.00


% 550.00

Day 231.00
% 6.93
% 237.93
% 152.30
Amount

Pair 100.00
% 100.00

Day 30.00
% 0.90
% 30.90
% 25.35

Amount

No 6,300.00
% 6,300.00

Day 300.00
% 9.00
% 309.00
% 1,287.00
Amount

No 7,820.00

% 7,820.00

Day 420.00
% 12.60
% 432.60
% 1,606.80

Amount

No 15,700.00

% 15,700.00

Day 840.00
% 25.20
% 865.20
% 3,225.30
Amount

No 3,025.00

% 3,025.00

Day 300.00
% 9.00
% 309.00
% 648.38

Amount

No 3,750.00

% 3,750.00

Day 420.00
% 12.60
% 432.60
% 813.15
Amount

No 4,200.00

% 4,200.00

Day 840.00
% 25.20
% 865.20
% 982.80

Amount

No 1,300.00

% 1,300.00

Day 288.75
% 8.66
% 297.41
% 309.81
Amount

No 1,550.00

% 1,550.00

Day 600.00
% 18.00
% 618.00
% 419.25

Amount

No 1,350.00

% 1,350.00

Day 360.00
% 10.80
% 370.80
% 333.45
Amount

No 1,150.00

% 1,150.00

Day 600.00
% 18.00
% 618.00
% 341.25

Amount

No 175.00
% 175.00

Day 84.00
% 2.52
% 86.52
% 50.51
Amount

500.00

3,600.00

% 4,100.00

Day 1,200.00
% 36.00
% 1,236.00
% 1,033.50

Amount

No 60.00

% 60.00

Day 21.60
% 0.65
% 22.25
% 15.91

Amount

Rft 35.00
% 35.00

Day 18.00
% 0.54
% 18.54
% 10.34

Amount

No 1,100.00

% 1,100.00

Day 150.00
% 4.50
% 154.50
% 243.75

Amount

No 240.00
% 240.00

Day 153.09
% 4.59
% 157.68
% 76.65

Amount

Rft 35.00

% 35.00
Day 50.04
% 1.50
% 51.54
% 16.58

Amount

No 700.00
% 700.00

Day 150.00
% 4.50
% 154.50
% 165.75

Amount

No 1,480.00
% 1,480.00
Day 150.00
% 4.50
% 154.50
% 317.85

Amount

No 200.00

% 200.00

Day 735.00
% 22.05
% 757.05
% 182.33

Amount
Rft 56.00

% 56.00

Day 37.56
% 1.13
% 38.69
% 18.24

Amount

Rft 45.00

% 45.00

Day 37.56
% 1.13
% 38.69
% 16.10
Amount

Rft 90.00

% 90.00

Day 75.00
% 2.25
% 77.25
% 32.18

Amount

Rft 100.00

% 100.00

Day 75.00
% 2.25
% 77.25
% 34.13
Amount

Rft 87.00

% 87.00

Day 75.00
% 2.25
% 77.25
% 31.59

Amount

Rft 280.00

% 280.00
Day 112.56
% 3.38
% 115.94
% 76.55

Amount

Rft 205.00
% 205.00

Day 112.56
% 3.38
% 115.94
% 61.92
Amount

Rft 155.00
% 155.00

Day 112.56
% 3.38
% 115.94
% 52.17

Amount

Hr 350.00

% 350.00

Day 150.00
Day 131.25
% 8.44
% 289.69
% 123.09
Amount

Day 263.50
Day 600.00
% 25.91
% 889.41
% 168.38

Amount

Day 171.48
Day 85.74
% 7.72
% 264.94
% 50.16
7.2.1.4

Amount

9.90
% 9.90

Day 24.00
Day 12.00
% 1.08
% 37.08
% 8.95

Amount

Day 300.00
Day 150.00
% 13.50
% 463.50
% 87.75
Amount

Bag 3.85
Bag 0.44
% 4.29

Sft 10.00

% 10.00
% 2.79

Amount

Bag 6.88
Bag 1.00
% 7.88

Sft 10.00

% 10.00
% 3.49
7.1.14

Amount

Day 600.00
Day 150.00
% 22.50
% 772.50
% 146.25

7.1.14

Amount

Day 300.00
Day 150.00
% 13.50
% 463.50
% 87.75
Amount

LS 476.00
% 476.00

Day 168.00
Day 119.00
% 8.61
% 295.61
% 148.79

Amount

Bag 16.50
2.08
5.16
% 23.74

Day 30.00
Day 18.78
% 1.46
% 50.24
% 14.14
Amount

No 400.00
No 7.20
% 407.20

Day 75.00
% 2.25
% 77.25
% 94.03

Amount

No 280.00
No 6.00
% 286.00

Day 75.00
% 2.25
% 77.25
% 70.40

Amount

No 120.00
No 6.00
% 126.00

Day 75.00
% 2.25
% 77.25
% 39.20
Amount

No 30.00
No 4.80
% 34.80

Day 75.00
% 2.25
% 77.25
% 21.41

Amount

No 25.00
No 4.00
% 29.00

Day 75.00
% 2.25
% 77.25
% 20.28
Amount

No 80.00
No 36.00
% 116.00

Day 75.00
% 2.25
% 77.25
% 37.25

Amount

No 60.00
No 30.00
% 90.00

Day 75.00
% 2.25
% 77.25
% 32.18

Amount

No 50.00
No 30.00
% 80.00

Day 75.00
% 2.25
% 77.25
% 30.23
Amount

No 120.00
No 7.20
% 127.20

Day 300.00
% 9.00
% 309.00
% 83.30

12.19.20

Amount

No 600.00
% 600.00

Day 75.00
% 2.25
% 77.25
% 131.63

12.19.20
Amount

No 350.00
% 350.00

Day 75.00
% 2.25
% 77.25
% 82.88

Amount

No 175.00
% 175.00

Day 75.00
% 2.25
% 77.25
% 48.75
Amount

No 150.00
% 150.00

Day 75.00
% 2.25
% 77.25
% 43.88

12.19.22

Amount

No 2,500.00

% 2,500.00

Day 90.00
% 2.70
% 92.70
% 505.05
Amount

Cft 176.50
Kg 8.27
No 8.57
% 193.34

Day 60.00
% 1.80
% 61.80
% 49.40

12.2

Amount

Cft 5.00
Kg 2.76
No 182.00
% 189.76

Day 60.00
% 1.80
% 61.80
% 48.70
Amount

No 596.00
% 596.00

Day 9.96
% 0.30
% 10.26
% 118.16

Amount

No 148.00
% 148.00

Day 3.24
% 0.10
% 3.34
% 29.49
Amount

Cft 12,500.00
No 1,968.00
% 14,468.00

Day 60.00
Day 240.00
% 9.00
% 309.00
% 2,879.76

Amount

Day 10.02
Day 20.04
% 0.90
% 30.96
% 5.86
13.3.1

Amount

Litre 52.50
% 52.50

Day 170.00
% 5.10
% 175.10
% 43.39

13.3.1

Amount

Day 250.80
% 7.52
% 258.32
% 48.91
13.3.1

Amount

Day 1,200.00
% 36.00
% 1,236.00
% 234.00

Amount

Ltr 498.44
% 498.44

Day 600.00
Day 212.50
% 24.38
% 836.88
% 255.63
Amount

Kg 82.50
% 82.50

Day 300.00
% 9.00
% 309.00
% 74.59

13.1.5

Amount

Day 600.00
% 18.00
% 618.00
% 117.00
Amount

Doz 144.50
% 144.50

Day 72.00
% 2.16
% 74.16
% 42.22

13.1.5

Amount

Doz 144.50
% 144.50

Day 150.00
% 4.50
% 154.50
% 57.43
13.1.5

Amount

Doz 144.50
% 144.50

Day 900.00
% 27.00
% 927.00
% 203.68

13.1.5

Amount

Doz 144.50
% 144.50

Day 1,200.00
% 36.00
% 1,236.00
% 262.18
Amount

Doz 144.50
% 144.50

Day 600.00
% 18.00
% 618.00
% 145.18

Amount

Ltr 24.82
% 24.82

Day 300.00
% 9.00
% 309.00
% 63.34
Amount

No 1.69
Ltr 15.25
% 16.94

Day 150.00
% 4.50
% 154.50
% 32.55

Amount

No 15.60
Ltr 54.57
% 70.17

Day 84.00
% 2.52
% 86.52
% 30.06
Amount

No 15.60
Ltr 236.72
% 252.32

Day 300.00
Day 199.20
% 14.98
% 514.18
% 146.55

Amount

No 222.30
Ltr 561.71
% 784.01

Day 600.00
% 18.00
% 618.00
% 269.88

Amount

No 222.30
Ltr 1,143.48
% 1,365.78

Day 1,200.00
% 36.00
% 1,236.00
% 500.33
Amount

No 334.23
Ltr 1,685.12
% 2,019.35

Day 1,992.00
% 59.76
% 2,051.76
% 782.21

Amount

No 20.80
Ltr 80.24
% 101.04

Day 36.00
% 1.08
% 37.08
% 26.72
Amount

Day 300.00
% 9.00
% 309.00
% 58.50

Bag 577.50
52.00
% 629.50

Day 1,200.00
Day 600.00
Day 150.00
Day 600.00
% 76.50
% 2,626.50

Hour 350.00

% 350.00
% 688.25

Day 600.00
% 18.00
% 618.00
% 117.00
65.00
329.00
Kg 2,907.00
No 112.00
% 3,413.00

Day 1,290.00
% 38.70
% 1,328.70

Hour 202.07

Hour 66.80
Hour 78.79
% 347.66
% 984.88

893.88
Kg 3,693.60
No 224.00
18.75
% 4,830.23

Day 1,410.00
% 42.30
% 1,452.30

Hour 274.67

Hour 90.80
Hour 107.10
% 472.57
% 1,309.00

Amount

100 Cft 1,306.44


Kg 4,360.50
No 336.00
100 Cft 5.25
% 6,008.19

Day 1,770.00
% 53.10
% 1,823.10

Hour 476.74

Hour 157.60
Hour 185.84
% 820.18
% 1,676.68

Amount

Rft 45.26
Kg 74.25
% 119.51

Day 72.00
Day 195.50
% 8.03
% 275.53
% 75.47
Amount

Day 300.00
% 9.00
% 309.00
% 58.50

171.49
112.00
620.00

229.29

2,105.40

% 3,238.18

Day 1,824.00
Day 150.00
% 59.22
% 2,033.22
% 1,016.38
Amount

Day 7.20
Day 52.50
% 1.79
% 61.49
% 11.64

Amount

Kg 232.50
% 232.50

Day 1,200.00
% 36.00
% 1,236.00
% 279.34
Amount

Kg 1,437.00
% 1,437.00

Day 350.00
% 10.50
% 360.50
% 348.47

Amount

Day 136.80
% 4.10
% 140.90
% 26.68
Amount

Dft 105.00
Kg 11.02
Kg 1.79
% 117.81

Day 15.00
% 0.45
% 15.45
% 25.90

Amount

Cft 18.00
Kg 0.03
Kg 0.12
Doz 1.24
% 19.38

Day 0.48
Day 1.32
% 0.05
% 1.85
% 4.13

14.5.6

Amount

Day 450.00
% 13.50
% 463.50
% 87.75

14.5.6

Amount

Day 56.40
% 1.69
% 58.09
% 11.00

Amount

Ltr 30.62
% 30.62

Day 15.00
% 0.45
% 15.45
% 8.90

Amount
Kg 15.84
Rft 212.00
% 227.84

Day 150.00
% 4.50
% 154.50
% 73.68

Amount

Cft 25.00
Kg 9.65
Kg 17.00
% 51.65

Day 12.00
% 0.36
% 12.36
% 12.41
Amount

Sft 60.00
% 60.00

Day 90.00
% 2.70
% 92.70
% 29.25

Amount

Sft 26.40
% 26.40

Day 90.00
% 2.70
% 92.70
% 22.70
Amount

Sft 20.00
% 20.00

Day 90.00
% 2.70
% 92.70
% 21.45

Amount

Kg 9.65
No 81.32
Doz 8.65
Ltr 167.02
% 266.64
Day 120.00
Day 102.00
% 6.66
% 228.66
% 95.28

Amount

Day 375.00
Day 300.00
% 20.25
% 695.25
% 131.63

Amount

Pkt 1.32
Ltr 2.31
Rft 53.00
% 56.63

Day 18.00
% 0.54
% 18.54
% 14.55

Amount

Sft 3.82
Kg 0.99
Pkt 3.54
1 Doz 4.94
No 1.24
% 14.53

Day 30.00
Day 60.00
% 2.70
% 92.70
% 20.38
Amount

Kg 9.24
Kg 50.00
No 160.00
Rft 84.72
% 303.96

Day 37.50
Day 53.13
% 2.72
% 93.34
% 76.94

12.1 , 12.2

Amount

kg 0.18
Cft 5.00
Kg 0.99
Pkt 3.54
Doz 8.84
No 1.86
No 3.96
1 No 1.80
Sft 7.04
No 1.12
% 34.34

Day 9.00
Day 18.00
% 0.81
% 27.81
% 11.96

16.9.5
1000 Cft

Amount

1 Day 74.34
1 Day 74.34
3.00 % 4.46
4.45 % 153.14

1 Hour 462.74
1 Hour 1,422.48
1 Hour 435.46
1 Hour 2,787.15
1 Hour 154.81
1 Hour 557.40

1 Hour 1,982.08

% 7,802.12
% 1,550.41
Amount

Cft 250.00
sft 48.95
Kg 5.79
No 26.10
No 91.00
% 421.84

Day 75.00
Day 150.00
% 6.75
% 231.75
% 126.13

Amount
120.00
1,252.04

% 1,372.04

Day 1,200.00
Day 750.00
Day 300.00
% 67.50
% 2,317.50
% 706.30

Amount

Bag 72.60
12.95
68.76
% 154.31

Day 15.84
Day 27.90
% 1.31
% 45.05
% 38.62
Amount

2.81

% 2.81

Day 28.56
Day 45.72
% 2.23
% 76.51
% 15.03
Amount

Cft 5,000.00
Ltr 61.24
% 5,061.24

Day 118.08
Day 54.12
Day 19.80
% 5.76
% 197.76
% 1,024.38

Day 316.14
Day 36.30
% 10.57
% 363.01
% 68.73
Day 0.72
% 0.02
% 0.74
% 0.14

Doz 1.66
% 1.66

Day 0.90
% 0.03
% 0.93
% 0.50

Amount

Ltr 1.73
% 1.73

Day 1.98
Day 3.96
% 0.18
% 6.12
% 1.49

Amount
Cft 61.50
% 61.50

Day 8.04
Day 8.04
% 0.48
% 16.56
% 15.13

Amount

No 0.96
Rft 50.00
No 45.71
% 96.68

Day 10.68
% 0.32
% 11.00
% 20.93
Amount

No 7.71
Rft 50.00
No 45.71

% 103.43

Day 10.68
% 0.32
% 11.00
% 22.25

No 7.71
Rft 155.00
No 77.14
No 285.72
No 4.62
No 160.72
% 690.92

Day 10.74
Day 42.84
% 1.61
% 55.19
% 145.18

Amount

No 7.71
Rft 155.00
No 77.14
No 285.72
No 4.62
No 160.72
% 690.92

Day 10.74
Day 42.84
% 1.61
% 55.19
% 145.18
Amount

Kg 11.25
No 375.00
% 386.25

Day 300.00
% 9.00
% 309.00
% 133.82

Amount

Kg 36.00
No 1,200.00
% 1,236.00

Day 300.00
% 9.00
% 309.00
% 299.52
Amount

Kg 59.99
No 2,000.00

% 2,059.99

Day 300.00
% 9.00
% 309.00
% 460.20

Amount
Kg 150.00
No 5,000.00

% 5,150.00

Day 600.00
% 18.00
% 618.00
% 1,121.25

Amount

Kg 11.25
No 375.00
% 386.25

Day 150.00
% 4.50
% 154.50
% 104.57
Amount

No 155.00
No 7.20
% 162.20

Day 112.56
% 3.38
% 115.94
% 53.58

Amount

No 300.00
No 4.50
% 304.50

Day 112.56
% 3.38
% 115.94
% 81.33
Amount

430.00

10.80

% 440.80

Day 97.56
% 2.93
% 100.49
% 104.98

Amount
625.00

10.80

% 635.80

Day 120.00
% 3.60
% 123.60
% 147.38

Amount

No 7.20
No 195.00

% 202.20

Day 97.56
% 2.93
% 100.49
% 58.45
Amount

No 7.20
No 245.00

% 252.20

Day 120.00
% 3.60
% 123.60
% 72.58

Amount

No 6.75
No 42.85
% 49.60

Day 300.00
% 9.00
% 309.00
% 68.17
Amount

No 85.70
No 7.20
% 92.90

Day 300.00
% 9.00
% 309.00
% 76.62

Amount
125.00

57.60

% 182.60

Day 90.00
% 2.70
% 92.70
% 53.16

Amount

No 57.60
No 350.00

% 407.60

Day 75.00
% 2.25
% 77.25
% 94.11
Amount

60.00

12.00

% 72.00

Day 90.00
% 2.70
% 92.70
% 31.59

Amount

No 12.00
No 50.00

% 62.00

Day 75.00
% 2.25
% 77.25
% 26.72

Amount

No 6.00
No 80.00
% 86.00

Day 75.00
% 2.25
% 77.25
% 31.40
Amount

No 6.00
No 70.00
% 76.00

Day 90.00
% 2.70
% 92.70
% 32.37

Amount

No 6.00
No 50.00
% 56.00

Day 90.00
% 2.70
% 92.70
% 28.47
Amount

No 4.50
No 50.00
% 54.50

Day 75.00
% 2.25
% 77.25
% 25.25

Amount

No 6.00
No 80.00
% 86.00

Day 75.00
% 2.25
% 77.25
% 31.40
Amount

No 9.00
No 120.00
% 129.00

Day 75.00
% 2.25
% 77.25
% 39.78

Amount

No 4.50
No 280.00
% 284.50

Day 75.00
% 2.25
% 77.25
% 70.10

Amount

No 6.00
No 340.00
% 346.00

Day 75.00
% 2.25
% 77.25
% 82.10
Amount

No 9.00
No 500.00
% 509.00

Day 75.00
% 2.25
% 77.25
% 113.88

Amount

No 4.50
No 60.00
% 64.50

Day 75.00
% 2.25
% 77.25
% 27.20
Amount

No 4.50
No 80.00
% 84.50

Day 75.00
% 2.25
% 77.25
% 31.10

Amount

No 4.50
No 120.00
% 124.50

Day 75.00
% 2.25
% 77.25
% 38.90

Amount

No 5.25
No 350.00
% 355.25

Day 75.00
% 2.25
% 77.25
% 83.90
Amount

No 5.25
No 280.00
% 285.25

Day 75.00
% 2.25
% 77.25
% 70.25

Amount

No 5.25
No 200.00
% 205.25

Day 75.00
% 2.25
% 77.25
% 54.65
Amount

No 5.25
No 180.00
% 185.25

Day 75.00
% 2.25
% 77.25
% 50.75

Amount

No 5.60
No 40.00
% 45.60

Day 75.00
% 2.25
% 77.25
% 23.52
Amount

No 5.60
No 35.00
% 40.60

Day 75.00
% 2.25
% 77.25
% 22.54

Amount

No 5.60
No 30.00
% 35.60

Day 75.00
% 2.25
% 77.25
% 21.57

Amount

No 5.60
No 25.00
% 30.60

Day 75.00
% 2.25
% 77.25
% 20.59
No 80.00
No 36.00
% 116.00

Day 75.00
% 2.25
% 77.25
% 37.25

No 36.00
No 70.00
% 106.00

Day 75.00
% 2.25
% 77.25
% 35.30
No 36.00
No 60.00
% 96.00

Day 75.00
% 2.25
% 77.25
% 33.35
No 36.00
No 50.00
% 86.00

Day 75.00
% 2.25
% 77.25
% 31.40

Amount

Job 500.00

% 500.00

Day 300.00
% 9.00
% 309.00
% 156.00
Amount

1 Job 4,000.00

% 4,000.00

Day 300.00
% 9.00
% 309.00
% 838.50

Amount

Job 400.00

% 400.00

Day 300.00
% 9.00
% 309.00
% 136.50
Amount

Job 600.00

% 600.00

Day 300.00
Day 600.00
% 27.00
% 927.00
% 292.50

Amount

1 No 13,000.00

% 13,000.00

Day 360.00
Day 720.00
% 32.40
% 1,112.40
% 2,745.60
Amount

1 No 16,000.00

% 16,000.00

Day 360.00
Day 720.00
% 32.40
% 1,112.40
% 3,330.60

Amount

1 No 13,000.00

% 13,000.00

Day 300.00
Day 600.00
% 27.00
% 927.00
% 2,710.50
Amount

1 No 16,000.00

% 16,000.00

Day 300.00
Day 600.00
% 27.00
% 927.00
% 3,295.50

Amount

1 No 9,500.00

% 9,500.00

Day 300.00
% 9.00
% 309.00
% 1,911.00
Amount

1 Job 3,500.00

% 3,500.00

Day 300.00
% 9.00
% 309.00
% 741.00

Amount

1 Job 3,500.00

% 3,500.00

Day 300.00
% 9.00
% 309.00
% 741.00

Amount

1 Job 4,000.00

% 4,000.00

Day 300.00
% 9.00
% 309.00
% 838.50

Amount

1 Job 3,500.00

% 3,500.00
Day 300.00
% 9.00
% 309.00
% 741.00

Amount

1 Job 4,000.00

% 4,000.00

Day 120.00
Day 240.00
% 10.80
% 370.80
% 850.20

Amount

1 No 3,500.00
% 3,500.00

Day 120.00
Day 240.00
% 10.80
% 370.80
% 752.70

Amount

1 No 3,000.00

% 3,000.00

Day 120.00
Day 240.00
% 10.80
% 370.80
% 655.20
Amount

1 No 900.00
% 900.00

Day 120.00
Day 240.00
% 10.80
% 370.80
% 245.70

Amount

1 No 500.00
% 500.00

Day 240.00
% 7.20
% 247.20
% 144.30
Amount

1 No 300.00

% 300.00

Day 120.00
% 3.60
% 123.60
% 81.90

Amount

1 No 1,500.00

% 1,500.00
% 292.50
Amount

1 No 30.00

% 30.00

Day 60.00
% 1.80
% 61.80
% 17.55

Amount

1 No 1,500.00

% 1,500.00

Day 240.00
% 7.20
% 247.20
% 339.30
Amount

1 No 1,500.00

% 1,500.00

Day 180.00
% 5.40
% 185.40
% 327.60

Amount

1 No 1,500.00

% 1,500.00

Day 180.00
% 5.40
% 185.40
% 327.60
Amount

1 No 1,000.00

% 1,000.00

Day 120.00
% 3.60
% 123.60
% 218.40

Amount

1 No 80.00

% 80.00

Day 36.00
% 1.08
% 37.08
% 22.62
Amount

Day 150.00
Day 300.00
% 13.50
% 463.50
% 87.75

Amount

Day 150.00
Day 300.00
% 13.50
% 463.50
% 87.75
Amount

Day 240.00
Day 480.00
% 21.60
% 741.60
% 140.40

Amount

Day 300.00
Day 600.00
% 27.00
% 927.00
% 175.50
Amount

1 No 3,500.00

% 3,500.00

Day 120.00
% 3.60
% 123.60
% 705.90

Amount

No 83.00
Sft 14.29
No 186.00
% 283.29

Day 30.00
Day 48.00
% 2.34
% 80.34
% 70.45
16.8.16

Amount

Cft 4,241.99
% 4,241.99

Day 150.00
Day 300.00
% 13.50
% 463.50
% 914.94

16.8.16

Amount

Cft 6,249.98
% 6,249.98

Day 150.00
Day 480.00
% 18.90
% 648.90
% 1,341.60
Amount

No 11.50
% 11.50

Day 50.16
Day 25.08
% 2.26
% 77.50
% 16.91

16.8.14

Amount

Bag 98.23
11.60
30.71
% 140.53

300.00
% 9.00
% 309.00
% 85.90
Amount

Bag 166.21
19.65
51.95
kg 4.40
sft 30.32
No 130.00
% 402.52

Day 180.00
Day 54.00
% 7.02
% 241.02
% 124.12

24.3.4, 24.3.5

Amount

Day 69.60
Day 18.30
% 2.64
% 90.54
% 17.14

24.3.4, 24.3.5

Amount

Day 160.20
Day 18.30
% 5.36
% 183.85
% 34.81

24.3.4, 24.3.5

Amount

Day 249.60
Day 18.30
% 8.04
% 275.94
% 52.24
Amount

Day 240.00
% 7.20
% 247.20
% 46.80

Amount

kg 100.00
% 100.00

Day 850.00
% 25.50
% 875.50
% 185.25
Amount

kg 50.00
% 50.00

Day 367.20
% 11.02
% 378.22
% 81.35

Amount

kg 10.00
% 10.00

Day 53.55
% 1.61
% 55.16
% 12.39
Amount

Rft 154.16
% 154.16

Day 150.00
% 4.50
% 154.50
% 59.31

Amount

kg 1.00
Ltr 0.04
% 1.04

Day 0.36
% 0.01
% 0.37
% 0.27
Amount

pkt 20.00
% 20.00

Days 90.60
% 2.72
% 93.32
% 21.57

Amount

Cft 1,100.00
% 1,100.00

Day 240.00
% 7.20
% 247.20
% 261.30

Amount

Job 2,000.00

% 2,000.00

Day 85.00
% 2.55
% 87.55

Day 2.66

% 2.66
% 407.09
Amount

Sft 700.00

% 700.00

Day 14.79
% 0.44
% 15.23

Hour 11.81

% 11.81
% 141.69

Sft 900.00

% 900.00

Day 14.79
% 0.44
% 15.23

Hour 11.81
% 11.81
% 180.69

Amount

0.52
14.55
25.14
3.30
79.70

% 123.20

Day 158.82
Day 123.48
% 8.47
% 290.77
% 79.07
Amount

0.52
14.55
25.14
3.30
79.70

% 160.28

Day 158.82
Day 123.48
% 8.47
% 290.77
% 86.30
Sft 56.82

% 56.82

Day 12.75
% 0.38
% 13.13
% 13.57

Amount

Bag 825.00
156.00
% 981.00

Day 900.00
Day 600.00
% 45.00
% 1,545.00
% 483.80
Amount

Sft 55.00
No 56.00
No 57.00
% 168.00

Day 40.00
% 1.20
% 41.20
% 40.56

24.3.6.4

Amount

Days 96.00
% 2.88
% 98.88
% 18.72
24.3.6.4

Amount

Days 181.20
% 5.44
% 186.64
% 35.33

Amount

Sft 339.15
% 339.15

Day 450.00
% 13.50
% 463.50
% 153.88
Amount

bag 2.14
Cft 50.44
cft 68.64
Sft 42.86
kg 1.29
No 84.00
Sft 240.00
% 489.37

Day 32.16
Day 42.84
Day 11.28
% 2.59
% 88.87
% 112.25

Amount
No 32.50
Ltr 462.28
% 494.78

Day 396.00
% 11.88
% 407.88
% 173.70

Amount

Bag 16.50
100 Cft 130.00
Kg 1,429.20
% 1,575.70

Day 300.00
Day 150.00
Day 212.50
% 19.88
% 682.38

Day 2,800.00
% 2,800.00
% 982.45
Amount

Bag 16.50
100 Cft 130.00
Kg 1,309.20
% 1,455.70

Day 300.00
Day 240.00
Day 212.50
% 22.58
% 775.08

Day 2,720.00
% 2,720.00
% 961.00
Amount

Day 240.00
Day 120.00
% 10.80
% 370.80

Rft 2,250.00

% 2,250.00
% 508.95
Amount

Day 420.00
Day 120.00
% 16.20
% 556.20

Rft 2,250.00

% 2,250.00
% 544.05
Amount

Day 240.00
Day 120.00
% 10.80
% 370.80

Rft 3,000.00

% 3,000.00
% 655.20

Amount

Day 288.00
Day 144.00
% 12.96
% 444.96

Rft 3,500.00

% 3,500.00
% 766.74

Amount

Day 300.00
Day 150.00
% 13.50
% 463.50

Rft 3,500.00
% 3,500.00
% 770.25

Amount

Day 102.00
Day 100.00
Day 75.00
% 8.31
% 285.31

Day 100.00

% 100.00
% 73.52