IM-09-A1 General Insp Checklist
IM-09-A1 General Insp Checklist
IM-09-A1 General Insp Checklist
Name of Project :
Job No. :
Area Inspected :
Inspected By :
Date :
Sl.
Activities Observation Measures
No.
PILING WORK
1 Condition of tripod and its stability
2 Condition of wire ropes, D shackles, Bulldog
Grips etc.
3 Removal of loose earth, slush etc.
4 Entry in register, details of periodical checking
& maintenance
5 Guards for rotating parts of machines
EXCAVATION
1 Verification of underground electrical cable
2 Condition of storing material
3 Cutting earth from top & ensuring no
undercutting
4 Storing of material from the edge of excavated
pit 5' or half of the depth whichever is more
5 Barricade / Fencing/ Displaying of danger sign,
warning sign by way of red flag / tape / light
etc.
6 Provision of dewatering facilities
7 Provision for ladders for deep trench
8 Stability of nearby structure
9 Avoid traffic movement, piling work in the
vicinity
DEMOLITION
Page 1 of 6
Sl.
Activities Observation Measures
No.
BLASTING
1 Blasting record incorporating number of holes
made / type of explosive used / firing pattern
and sequence with date & time of blast
2 Handling of explosives by licensed blaster
3 Intensity of the charge calculated before use
4 Before drilling presence of unfired explosives
checked
5 Blasting is carried out only during lean hours
say lunch / night hours
6 Standard warning signal / all clear signal
before and after firing is ensured
7 Competent persons equipped with red flags
are posted at possible approaches to stop
traffic and by-passers
GROUND SURFACES
1 Ground level , no soft spot
2 Footing timber level adequately supported
3 No Unauthorised entry
SCAFFOLDS
1 Base plate level
2 Spindle jack vertical
3 Standard plumb (vertical tubes), no damage
4 Ledgers level (horizontal tubes), no damage
5 Diagonal bracing, secure and not missing
6 Lock pin in place and secure
7 Support from permanent structure
Page 2 of 6
Sl.
Activities Observation Measures
No.
LADDERS
1 Placed on level ground
2 Position at an angle of 1:4
3 Adequately secured
4 No damage, check welds
5 Extend 4 rungs above stepping off point
6 Uniform and proper spacing of rung
WORKING PLATFORM
1 Should not be less than 600 mm wide
2 Guard rails adequate check
i) Top rail at least 910 mm height
ii) No gap greater than 470 mm
3 Boards free of defects check
i) No gaps
ii) Adequate supports
iii) No risk of trips
iv) Properly secured / tied
PPE
1 Helmet and footwear worn
2 Safety harnesses as required and secured
above shoulder level
3 Use of safety harnesses while working at
height
4 Safety Goggles during welding / gas cutting /
grinding etc.
5 Condition / Maintenance of safety appliances
6 Use of body guards, gloves etc.
MEANS OF ACCESS
1 Platform, toe board and railings
2 Scaffolding - its condition and Maintenance
3 Staircase and railing
4 Ladder & fixing
5 Safe access to and from means of access
Page 4 of 6
Sl.
Activities Observation Measures
No.
ELECTRICAL WORKS
HOUSEKEEPING
1 Material stacking and storing
2 Working / moving area clean
3 Access / Main Approach / Passages free form
obstacles
4 Cordoning / covering of pit, vat, machine
foundation etc.
5 Displaying of Red Flags / Tape / light.
6 Removal of unwanted materials like excavated
earth debris etc.
ROAD SAFETY
Page 5 of 6
Sl.
Activities Observation Measures
No.
MISCELLANEOUS
1 First Aid box with proper medicine and its
maintenance
2 Validity date of medicine
3 Illumination
4 EHS boards and promotional materials
i) Posters
ii) Stickers
5 Arrangement of drinking water and sanitation
6 Provision of emergency vehicle
Page 6 of 6