Professional Documents
Culture Documents
Assessment of Rain Water Drainage System in 3 Roads in Khartoum
Assessment of Rain Water Drainage System in 3 Roads in Khartoum
Assessment of Rain Water Drainage System in 3 Roads in Khartoum
In 3 Roads In Khartoum
BY:
May, 2015
Acknowledgement
This thesis to obtain Master Degree in Civil Engineering, the
Building Technology Track, at The University of Khartoum. I have
been working on Master thesis from June, 2014 to April, 2015.
I
Abstract
The main objectives of this research to develop sustainable
rainwater drainage system, present planning and design guideline
for roads drainage system (case study) and emphasize the ability of
comprehensive and enlightened planning, design, review practices
to minimize and facilitate rainwater drainage system maintenance
and limit flooding of public and private property, both within the
catchment and downstream, to acceptable levels. Three roads were
randomly selected “Alshaheed Osama Almagbool, Alazhari
University, and Alferdos“ based on heavy traffic and severe water
effect. Drainage systems were designed geometrically, hydro-
logically and structurally. Geometrically; levels was recorded
transversely and longitudinally. They were modified in accordance
to direct the water off the road smoothly. Hydro-logically; In order
to obtain the design discharge catchment area was defined (using
GIS “Geographic Information system” and Google Earth).Runoff
coefficient for an area is governed by land use. The rational method
is used to predict the rain-fall flow. Outcome of the Hydrological
design is drain with an area of (1*0.6) m² for Elshaheed Osama
Elmagboul Road, (1*1.6) m² Alazhariy University Road and for
Alferdos Road drain is designed to come out with an area of
(1*1.9) m² after applying factor of safety (1.2) to the discharge.
Structurally, AASHTO” American Association of State Highway
and Transportation Officials”, LRFD” Load and Resistance Factor
II
Design” Bridge Design Specifications was used as a standard in
design of the box drains. On Elshaheed Osama Elmagboul Road,
the designed drain is reinforced with 6 bars with diameter of 12
mm in top, bottom and side-walls slabs (inside and outside, for
Alazhariy University Road, the reinforcement was 6 bars with
diameter of 12 mm in top and bottom (inside and outside). For
side-walls slabs 6 bars with 12 mm diameter (outside) and 9 bars
with diameter of 12 mm (inside) and Alferdos Road, the designed
drain is reinforced 6 bars with diameter of 12 mm in top slab
(inside and outside). For Alferdos Road the existing drainage
system has been redesigned whereas for the other two streets new
design has been adopted to meet the requirements.
III
المستخلص:
األهداف من هذه الدراسة هي إنشاء نظام تصريف يلبي كل متطلبات التصميم الجيد وذلك
بتوضيح خطوات منهجية إلنشاء مصرف كجزء ال يتجزأ من تصميم الطرق ,معتمدا
على الدراسات الحديثة و التجارب العملية السابقة لتفادي مشاكل التصريف و تقليل
تكاليف الصيانة فيما بعد ,و ذلك للمحافظة على األرواح البشرية و الممتلكات
الخاصة...ألخ.ثالثة طرق تم اختيارهاعشوائيا و هم الشهيد أسامة المقبول (لفة جنوب),
جامعة الزعيم األزهري و الفردوس بناءا على حركة المرور الكثيفة و تأثرها الكبير
بمياه األمطار .تم تصميم نظام التصريف هيدرولوجيا ,هندسيا و إنشائيا.هندسيا دونت
لتوجيه المياه قبالة الطريق مستويات األرض عرضيا وطوليا وتعديلها
بسالسة.هيدرولوجيااعتمدت الطريقة العقالنية ( )Rational Methodللتنبؤ بكمية
التصريف إليجاد مساحة المصرفلمساحةتجمعات المياه المحددة (باستخدام برنامجنظام
المعلومات الجغرافية" " GISوبرنامج ) .)Google Earthمعامل الجريان السطحي تم
إيجاده على أساس طبيعة المنطقة المحيطة و استخدامها.النتائج كانت مصرف بمساحة
( )6.0*1متر²لطريق الشهيد أسامة المقبول )1.1*1( ,متر ²لطريق جامعة األزهري
أما بالنسبة لطريق الفردوس المصرف صمم بمساحة ( )1.1*1متر ²و ذلك بعد تطبيق
معامل أمان ( )1.1على التصريف.إنشائياتم استخدامالجمعية األمريكية لمسؤولي الطرق
والمواصالت" ," AASHTOمعامل تصميم الحمل و المقاومة "" LRFDمواصفة
تصميم الجسور كمعيار أو مرجع لتصميم نظام التصريف.على طريق الشهيد أسامة
المقبول و طريق الفردوس المصرفين سلحا بعدد 0سيخات بقطر 11ملم في البالطة
العلوية والسفلية و البالطتين الجانبيتين من الداخل و الخارج ,لطريق جامعة األزهري
التسليح عدد 0سيخات بقطر 11ملم في البالطة العلوية و السفلية من الداخل و الخارج
أما البالطتين الجانبيتين فسلحت ب 0سيخات من الخارج و 9سيخات من الداخل بقطر
11ملم.
بالنسبة لطريق الفردوس تم إعادة تصميم نظام التصريف الموجود أما الطريقين اآلخرين
تم تصميم أنظمة جديدة لتلبية متطلبات التصميم المتكامل.
IV
ABBREVIATIONS:
AASHTO: American Association of State Highway and
Transportation Officials
DC: Self-Weight
V
LIST OF FIGURES:
Figure 1-1 Properties Damage .........................................................................3
Figure 2-1 Road cross section grading patterns used to control surface drainage
.......................................................................................................................7
Figure 2-5Traffic Traveling Parallel to Span (Less than 2 feet of fill) ............ 25
Figure 2-6 Traffic Traveling Parallel to Span (2 feet of fill or greater) ........... 26
Figure 2-7 Traffic Traveling Parallel to Span (2 feet of fill or greater showing
load projection overlap) ................................................................................ 27
Figure 3-6 Longitudinal Profile for Elshaheed Osama Almagbool Road ........ 37
VI
Figure 3-12Longitudinal Profile for Elferdos Road........................................ 43
Figure 4-3 The Existing Culvert and Road Surface DestressAlferdos Road ... 55
VII
LIST OF TABLES:
Table 2-1 General selection factors ............................................................... 10
Table 3-1 Design Data and water flow calculations Elshaheed Osama
Almagbool Road ........................................................................................... 46
Table 3-2 Manning equation trials Elshaheed Osama Almagbool Road ......... 46
Table 3-3 Drain Structural Design Results Elshaheed Osama Almagbool Road
..................................................................................................................... 47
Table 3-4 Design Data and Water Flow Calculations Alazhariy University
Road ............................................................................................................. 49
Table 3-6 Drain Structural Design Results Alazhariy University Road .......... 50
Table 3-7 Design Data and Water Flow Calculations Elferdos Road.............. 52
VII
I
TABLE OF CONTENT :
Acknowledgement ...................................................................... I
Abstract ...................................................................................... II
………………………………………………………المستخلص..………...………….…IV
ABBREVIATIONS…………………………………………………………..….………V
LIST OF FIGURES…………………………….……………….……………..………VI
LIST OF TABLES………………………………………………………………….….VIII
1 Introduction: ......................................................................... 1
1.1 Background ..................................................................................... 1
1.2 Problem Statement: ........................................................................ 2
1.3 Scope: ............................................................................................. 3
1.4 Objectives: ...................................................................................... 4
IX
2.3.1 Introduction: .......................................................................................... 13
2.3.2 Hydrology Design ................................................................................... 14
Runoff Coefficient ....................................................................................................... 16
Rainfall intensity.......................................................................................................... 18
Time of concentration ................................................................................................. 18
2.3.3 Permissible Velocities ............................................................................ 20
2.3.4 Structural and Configuration Requirements of Drains ............................ 20
4 Discussion: .......................................................................... 54
References………….……………………………………………………….…………63
APPENDICES:
X
APPENDIX (A): Cross sections profile along the Road.
XI
Chapter One Introduction
1 Introduction:
1.1 Background
Drainage is the natural or artificial removal of surface and sub-surface
water from an area. The most important part in infrastructure is the
1
Chapter One Introduction
2
Chapter One Introduction
The main reason of all those problems is the poor water drainage
system design which is mainly due to inadequate drainage capacity
(geometric) or weak drainage structure (structural). Both geometric
and structural problems will be investigated in this study.
1.3 Scope:
Describe the procedure recommended for the selection and design of
drainage system components in order to direct rainwater off the road.
Guidelines contained in this research have been developed from a
comprehensive review of basic design technology as contained in
3
Chapter One Introduction
1.4 Objectives:
1. To develop sustainable rainwater drainage system.
2. To present planning and design guideline for roads drainage
system (case study).
3. To emphasize the ability of comprehensive and enlightened
planning, design, and review practices to minimize and facilitate
rainwater drainage system maintenance.
4. To limit flooding of public and private property, both within the
catchment and downstream, to acceptable levels.
4
Chapter Two Literature Review
2 Literature Review:
2.1 Introduction
The planning and design of road drainage infrastructure can be quite
complicated and involves the consideration of a diverse set of data in
order to develop the most appropriate drainage solution for a project.
Collaborative planning by a group of professionals with
complementary skills is often a productive way to identify all aspects,
issues, functional requirements, expectations, demands, constraints,
risks and possible costs to be considered in a project.(Reeves 2010)
Geometric
Geographic
Environmental
Crossing type
Maintenance
Safety
Staged construction of road
2.2.1 Geometric Considerations:
There are two aspects of geometric that must be considered in the
drainage design for a road project. Some parts or components of these
aspects may in turn become design controls. The first aspect deals with
geometry of the stream and the second aspect deals with the geometry
of the road-stream crossing.(Reeves 2010)
5
Chapter Two Literature Review
channel shape.
6
Chapter Two Literature Review
Figure 2-1 Road cross section grading patterns used to control surface drainage
7
Chapter Two Literature Review
of the state may not be suitable in other areas. This is also true for
prevention of erosion.(Reeves 2010)
Bridges
Culverts
Floodways
8
Chapter Two Literature Review
Flood discharge
Stream channel conditions and topography
Afflux constraints
Debris properties
Scour risk
Road alignment
Level of serviceability
9
Chapter Two Literature Review
Navigation
Soil conditions
Culvert types:
Box culverts and slab deck culverts provide for a greater waterway
area at shallow depths, while pipes need to flow at a greater depth
before the maximum flow capacity is reached. The use of pipes
however does tend to spread the flow to a greater extent, which is
often desirable for consideration of concentration of flow and risk of
scour. (Reeves 2010)
10
Chapter Two Literature Review
11
Chapter Two Literature Review
Reinforced concrete
Are the most type common used. This is primarily due to products
availability, strength, serviceability, durability and overall cost
(design, construction and operation).
Fibre reinforced
12
Chapter Two Literature Review
13
Chapter Two Literature Review
Within a project, the design criteria will vary in accordance with road
type and whether the design relates to cross drainage, surface drainage,
urban drainage, or construction phase drainage, including erosion and
sediment control.
Usually the design discharge is used to provide the size of the drainage
structure and the level of the road. The design discharge is expressed
as a flow rate, usually as cubic meters per second (m3/s), and is
14
Chapter Two Literature Review
Basic Formulations:
The idea behind the Rational Method is that for a spatially and
temporally uniform rainfall intensity i which continues indefinitely,
the runoff at the outlet of a catchment will increase until the time of
concentration tc, when the whole catchment is contributing flows to
the outlet. The peak runoff is given by the following expression:
Q= k *C* I* A
Where:
15
Chapter Two Literature Review
infiltration.
Q= k * I * j* A j
Runoff Coefficient
16
Chapter Two Literature Review
soil, vegetation cover, the duration and intensity of rainfall, and the
antecedent moisture conditions, etc.
17
Chapter Two Literature Review
Rainfall intensity
tc is the time for a drop of water to flow from the remotest point in the
catchment to its outlet. For an urban drainage system,
tc = to + tf
tf=
Where: to = inlet time (time taken for flow from the remotest point to
reach the most upstream point of the urban drainage system) Table
below shows the Recommended Standard Inlet Times. (Reevs, 2010)
Table 2-3 Recommended Standard Inlet Times
tf = flow time
Lj = length of jth reach of drain
Vj = flow velocity in jth reach of drain
18
Chapter Two Literature Review
Manning’s Equation:
Where:
V = velocity in pipe (m/s);
R = hydraulic radius of pipe flowing full (m);
S = slope of energy line or hydraulic gradient (m/m);
n = Manning’s roughness coefficient for pipe. Table 2-5 shows “n”
Values.
19
Chapter Two Literature Review
Asphalt 0.016
Brass 0.011
Brick 0.015
Canvas 0.012
20
Chapter Two Literature Review
2.3.4.1 Loads
Self-Weight (DC)
The self-weight of the top slab must be resisted by the top slab. The
benefit of axial compression from the self-weight of the top slab
and walls is not included in the analysis. The top slab, wall, and all
haunch weights are applied to the bottom slab as an upward reaction
from the soil in an equivalent uniform pressure. The bottom slab
weight is not applied in the model because its load is assumed to be
directly resisted by the soil. (LRFD Bridge Design Manual 2013)
The design fill height is measured from the top surface of the top slab
to the top of the roadway or fills. The design fill height is denoted by
the abbreviations of H or DE depending on the equation used. Earth
vertical loads refer to soil and pavement loads above the culvert and in
adjacent regions slightly outside the span of the culvert based on the
soil-structure interaction factor. Culvert walls are assumed to be
frictionless, so no vertical component of the earth horizontal resultant
force is considered. (LRFD Bridge Design Manual, 2013)
21
Chapter Two Literature Review
Fe = 1+0.20*
Where:
For design and analysis purposes, the equivalent fluid method is used.
The maximum for lateral earth pressure on the walls based on at rest
pressure.
22
Chapter Two Literature Review
Water (WA)
The approximate strip method is used for design with the 1 foot wide
design strip oriented parallel to the span. The design live loads applied
to the top slabs of box culverts include the HL-93 truck and tandem
loads for box culverts of any span length.
Design box culverts for a single loaded lane with a multiple presence
factor of 1.2. MnDOT investigated several live load cases with
several box culvert spans at different fill heights and found the live
load intensity of 2 lanes with a MPF of 1.0 controlled over a single
23
Chapter Two Literature Review
lane with a multiple presence factor of 1.2 at fill heights of 6.5 feet and
greater. However, the maximum live load intensity increase as a
percentage of the total load is very small. Based on these findings and
the commentary in AASHTO Article C12.11.2.1, multiple loaded
lanes are not considered in box culvert design. (AASHTO LRFD
BRIDGE DESIGN SPECIFICATIOPNS, 2012)
The dynamic load allowance (IM) for culverts and other buried
structures reduced based on the depth of fill over the culvert.
AASHTO LRFD requires that IM be considered for fill heights of up
to 8 ft. The equation to calculate the dynamic load allowance is as
follows:
Where:
24
Chapter Two Literature Review
E = 96 + 1.44 S
Where:
LLDF = 1.15, factor for distribution of live load through depth of fill
25
Chapter Two Literature Review
26
Chapter Two Literature Review
Figure 2-7 Traffic Traveling Parallel to Span (2 feet of fill or greater showing load
projection overlap)
27
Chapter Two Literature Review
Load Combinations
28
Chapter Two Literature Review
Use a value of 1.0 for all load modifiers (η) for box culvert
design, except for earth EV and EH loads, EV & EH where η R =
1.05 is used due to the lack of redundancy. (AASHTO LRFD
BRIDGE DESIGN SPECIFICATIOPNS, 2012)
29
Chapter Two Literature Review
2.3.4.4 Flexure
Flexural reinforcement is designed for positive and negative
moment at all design locations. The flexural resistance factor, f, is 1.0
for precast concrete.
30
Chapter Two Literature Review
Shear in Slabs of Box Culverts with Less Than 2 Feet of Fill and
Walls of Box Culverts at All Fill Heights
For top slabs of boxes with less than 2 feet of fill and walls of
boxes at all fill heights calculate the shear resistance using the
greater of that computed using the “Simplified Procedure for Non-
pre-stressed Sections” given in AASHTO LRFD Article 5.8.3.4.1
and the “General Procedure ” given in AASHTO Article 5.8.3.4.2.
(AASHTO LRFD BRIDGE DESIGN SPECIFICATIOPNS, 2012)
For top and bottom slabs of boxes with 2 feet of fill or greater
calculate the shear resistance using the shear provisions specific to
slabs of box culverts.
2.3.4.9 Fatigue
Fatigue is not considered in the design of buried structures.
31
Chapter Three Work Done and Results
Three roads were randomly selected based on heavy traffic and severe
water effect.
3.1.2 Elshaheed Osama Almagbool Road:
Connecting Elengaz and Almaoona main Roads- Khartoum North.
32
Chapter Three Work Done and Results
3.1.4 AlferdosRoad:
Connecting Alseteen and EbaidKhatim main Roads- Khartoum.
33
Chapter Three Work Done and Results
The selected sites were visited, to record the road existing levels
readings using Theodolite Device.
Each Road was divided into sections were located at which five points
were defined, distributed across the road section in arrangement: one
in the middle, two at the side edges and two outside the road width.
The longitudinal profile obtained from the points at the middle in each
section along the Road. The first middle point was recorded as a
benchmark for the other points.
34
Chapter Three Work Done and Results
35
Chapter Three Work Done and Results
The site visit shows serious damage on the street’s pavements and
irregular levels.
36
Chapter Three Work Done and Results
1.5
0.5
0
0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400
-0.5
-1
-1.5
-2
-2.5
-3
37
Chapter Three Work Done and Results
3.2.3 Alazhariy University Road:
38
Chapter Three Work Done and Results
1.0 Km length was divided into 50 meter intervals for the first 5
sections, and 60 meter for the rest starting from Almaoona to Alsaid
Ali Road. At the Road terminal joining the main road two points at the
middle with 20 meter distance from the last section was recorded.
(Appendix (1))
39
Chapter Three Work Done and Results
Ground Level
1.5
0.5
0
0 100 200 300 400 500 600 700 800 900 1000
-0.5
-1
-1.5
-2
40
Chapter Three Work Done and Results
3.2.4 AlferdosRoad:
41
Chapter Three Work Done and Results
42
Chapter Three Work Done and Results
3
Longitudinal Profile Level Elferdos Road
Ground Level
2.5
1.5
0.5
0
0 150 300 450 600 750 900 1050 1200 1350 1500 1650 1800 1950
-0.5
-1
-1.5
-2
-2.5
-3
43
Chapter Three Work Done and Results
44
Chapter Three Work Done and Results
3.3.1.1 Geometric Design For The longitudinal slope Elshaheed Osama Almagbool Road:
1.5
0.5
0
0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400
-0.5
-1
-1.5
-2
-2.5
-3
45
Chapter Three Work Done and Results
Table 3-1 Design Data and water flow calculations Elshaheed Osama Almagbool
Road
B d a p R S Qcal Qact Vo
1 0.413 0.413 1.826 0.2261774 0.001 0.3232151 0.3236 0.783516
1 0.44 0.441 1.96 0.225 0.001 0.3522827 0.3452 0.784465
A = Q/V=0.42/0.78 =0.53 m²
1*0.53 Area
Total depth = d + FB
46
Chapter Three Work Done and Results
Table 3-3 Drain Structural Design Results Elshaheed Osama Almagbool Road
47
Chapter Three Work Done and Results
3.3.2.1 Geometric Design For The Longitudinal Slope Alazhariy University Road:
0.5
0
0 100 200 300 400 500 600 700 800 900 1000
-0.5
-1
-1.5
-2
48
Chapter Three Work Done and Results
Table 3-4 Design Data and Water Flow Calculations Alazhariy University Road
to(5- tc=to+ I C=
L(m) v(m/S) v(m/min) tf(min) A(km²) Q(m³/s)
10)min tf (mm/hr) 0.5 K
8 1000 0.70 42.00 23.81 31.81 8.00 0.7817 0.5 0.278 0.8693
8 1000 0.87 52.16 19.17 27.17 9.00 0.7817 0.5 0.278 0.9779
8 1000 0.65 39.12 25.56 33.56 8.00 0.7817 0.5 0.278 0.8693
8 1000 0.98 59.07 16.93 24.93 10.00 0.7817 0.5 0.278 1.0866
8 1000 1.03 61.57 16.24 24.24 11.50 0.7817 0.5 0.278 1.2495
8 1000 1.18 70.81 14.12 22.12 13.50 0.7817 0.5 0.278 1.4669
8 1000 1.08 64.68 15.46 23.46 12.00 0.7817 0.5 0.278 1.3039
8 1000 1.06 63.50 15.75 23.75 11.00 0.7817 0.5 0.278 1.1952
B d a p R S Qcal Qact Vo
1 1 1 3 0.333333 0.001 1.013 0.8693 0.86925
1 1.5 1.5 4 0.375 0.001 1.64 0.9779 0.65193
1 0.883 0.883 2.766 0.319233 0.001 0.87 0.8693 0.98442
1 1.0588 1.0588 3.1176 0.339620 0.001 1.087 1.0866 1.02622
1 1.0588 1.0588 3.1176 0.339620 0.001 1.087 1.2495 1.18015
1 1.3608 1.3608 3.7216 0.365649 0.001 1.467 1.4669 1.07793
1 1.232 1.232 3.464 0.355658 0.001 1.30 1.3039 1.06
1 1.146 1.146 3.292 0.34 0.001 1.196 1.1952 1.04
A = Q/V=1.44/1.04 =1.38 m²
1*1.38 Area
Total depth = d + FB
49
Chapter Three Work Done and Results
50
Chapter Three Work Done and Results
3.3.3 AlferdosRoad:
1.5
0.5
0
0 150 300 450 600 750 900 1050 1200 1350 1500 1650 1800 1950
-0.5
-1
-1.5
-2
-2.5
-3
51
Chapter Three Work Done and Results
to(5-
tf(min I ∑A(
10)mi L(m) v(m/S) v(m/min) tc=to+tf C Q(m³/s)
) (mm/hr) Km²)
n K
8 1800 0.70 42.00 42.86 50.86 6.00 1.259 0.5 0.278 1.0500
8 1800 1.02 61.17 29.43 37.43 8.00 1.259 0.5 0.278 1.4000
8 1800 1.07 64.37 27.96 35.96 8.50 1.259 0.5 0.278 1.4875
B d a p R S Qcal Qact Vo
1 1.03 1.03 3.06 0.33660131 0.001 1.050726852 1.0500 1.0194233
1 1.305 1.305 3.61 0.36149584 0.001 1.396115855 1.4000 1.0728031
1 1.377 1.377 3.754 0.36680874 0.001 1.487541632 1.4875 1.0802531
A = Q/V=1.8/1.08 =1.67 m²
(1*1.67) Area
Total depth = d + FB
52
Chapter Three Work Done and Results
53
Chapter Four Discussion
4 Discussion:
Generally, most of Khartoum State roads faced rain water drainage
problems in the past rainy seasons. This study is about to analyze
some of these problems to come out with the proper solution by taking
three streets as a case study (present planning and design guideline for
road drainage system).
Figure 4-1 Cracking and Non uniformityy of Levels Elshaheed Osama Elmagboul
Road
54
Chapter Four Discussion
Figure 4-3 The Existing Culvert and Road Surface DestressAlferdos Road
55
Chapter Four Discussion
fall intensity is obtained for two years retaining period from previous
study and experience of engineers. The rational method is used to
predict the rain-fall flow. Outcome of the Hydrological design is
culvert with an area of (1*0.6) m² and (1*1.6) m² respectively after
applying factor of safety (1.2) to the discharge. For Alferdos Road
culvert is designed to come out with an area of (1*1.9) m² whereas the
existing area (from east to west, at Ebaid-Khatim, the culvert starts
with two boxes of areas (0.77*1.31 m² and 0.77*1.21), then one box
(1.64*0.81) and ends to khor at Alseteen Road).
56
Chapter Four Discussion
57
Chapter Four Discussion
58
Chapter Four Discussion
For bottom slab the steel area provided is 792 mm²; 7 bars with 12
mm diameter (inside) and 678.6 mm² area; 6 bars with diameter of 12
mm (outside).
For side-walls slabs the steel area provided is 1131mm²; 10 bars with
12 mm diameter (inside) and 678.6 mm² area; 6 bars with diameter of
12 mm (outside).
59
Chapter Five Conclusion and Recommendations
60
Chapter Five Conclusion and Recommendations
61
Chapter Five Conclusion and Recommendations
5.2 Recommendations
1. Due to by-time accumulated soil, embankment at the road two
sides’ terminal, the rainwater is stored on the pavement surface. In
such case Gullies are recommended to take rainwater away from the
road into the drainage system.
Figure 5-4 Gully at the side of a road Figure 5-5 Gully at the middle of a road
62
Chapter Five Conclusion and Recommendations
63
Refrences:n.d.
64
Appendix (A)
Elshaheed Osama:
Original Cross-Sectional Levels:
Existing Road Levels (Based on site survey)
x1 x2
0.25
x1 0.25
x2
0.05 0.05
-0.15 0.0 1.0 2.0 3.0 4.0 5.0 -0.15 0.0 1.0 2.0 3.0 4.0 5.0
-0.35 -0.35
-0.55 -0.55
-0.75 -0.75
-0.95 -0.95
-1.15 -1.15
-1.35 -1.35
.
At 0 m At 60 m
0.25
x3 x3 x4 x4
0.25
0.05
0.05
-0.15 0.0 1.0 2.0 3.0 4.0 5.0 -0.15 0.0 1.0 2.0 3.0 4.0 5.0
-0.35 -0.35
-0.55 -0.55
-0.75 -0.75
-0.95 -0.95
-1.15 -1.15
-1.35 -1.35
At 120 m At 180 m
x5 x6
x5 x6
0.25 0.25
0.05 0.05
-0.15 0.0 1.0 2.0 3.0 4.0 5.0 -0.15 0.0 1.0 2.0 3.0 4.0 5.0
-0.35 -0.35
-0.55 -0.55
-0.75 -0.75
-0.95 -0.95
-1.15 -1.15
-1.35 -1.35
At 240 m At 300 m
x7 x7 x8 x8
0.25 0.25
0.05 0.05
-0.15 0.0 1.0 2.0 3.0 4.0 5.0 -0.15 0.0 1.0 2.0 3.0 4.0 5.0
-0.35 -0.35
-0.55 -0.55
-0.75 -0.75
-0.95 -0.95
-1.15 -1.15
-1.35
-1.35
At 360 m At 420 m
x9 x9 x10 x10
0.25 0.25
0.05 0.05
-0.15 0.0 1.0 2.0 3.0 4.0 5.0 6.0 -0.15 0.0 1.0 2.0 3.0 4.0 5.0
-0.35 -0.35
-0.55 -0.55
-0.75 -0.75
-0.95 -0.95
-1.15 -1.15
-1.35 -1.35
At 480 m At 540 m
At 600 m At 660 m
x13
x13 x14 x14
0.25 0.25
0.05 0.05
-0.15 0.0 1.0 2.0 3.0 4.0 5.0 -0.15 0.0 1.0 2.0 3.0 4.0 5.0
-0.35 -0.35
-0.55 -0.55
-0.75 -0.75
-0.95 -0.95
-1.15 -1.15
-1.35 -1.35
At 720 m At 780 m
At 840 m At 900 m
x17 x18
x17 x18
0.25 0.25
0.05 0.05
-0.15 0.0 1.0 2.0 3.0 4.0 5.0 -0.15 0.0 1.0 2.0 3.0 4.0 5.0
-0.35 -0.35
-0.55 -0.55
-0.75 -0.75
-0.95 -0.95
-1.15 -1.15
-1.35 -1.35
At 960 m At 1020m
x19 x19
x20 x20
0.25 0.25
0.05 0.05
-0.15 0.0 1.0 2.0 3.0 4.0 5.0 -0.15 0.0 1.0 2.0 3.0 4.0 5.0
-0.35 -0.35
-0.55 -0.55
-0.75 -0.75
-0.95 -0.95
-1.15 -1.15
-1.35 -1.35
At 1080 m At 1140 m
x22
x22 x21 x21
0.25 0.25
0.05 0.05
-0.15 0.0 1.0 2.0 3.0 4.0 5.0 -0.15 0.0 1.0 2.0 3.0 4.0 5.0
-0.35 -0.35
-0.55 -0.55
-0.75 -0.75
-0.95 -0.95
-1.15 -1.15
-1.35 -1.35
At 1200 m
At 1260 m
x23 x23
0.25
0.05
-0.15 0.0 1.0 2.0 3.0 4.0 5.0
-0.35
-0.55
-0.75
-0.95
-1.15
-1.35
At 1320 m
1x
X1 x2 x2
4.5 4.5
3.5 3.5
2.5 2.5
1.5 1.5
0.5 0.5
0.5- -0.5
0.0 1.0 2.0 3.0 4.0 5.0 0.0 1.0 2.0 3.0 4.0 5.0
1.5- -1.5
2.5- -2.5
3.5- -3.5
4.5- -4.5
5.5- -5.5
6.5- -6.5
At 0 m At 50 m
x3 x4
x3 x4
4.5 4.5
3.5 3.5
2.5 2.5
1.5 1.5
0.5 0.5
-0.5 -0.5
0.0 1.0 2.0 3.0 4.0 5.0 0.0 1.0 2.0 3.0 4.0 5.0
-1.5 -1.5
-2.5 -2.5
-3.5 -3.5
-4.5 -4.5
-5.5 -5.5
-6.5 -6.5
At 100 m At 150 m
x5 x5
x6 x6
4 4
2.5 2.5
1 1
-0.5 -0.5
0.0 1.0 2.0 3.0 4.0 5.0 0.0 1.0 2.0 3.0 4.0 5.0
-2 -2
-3.5 -3.5
-5 -5
-6.5 -6.5
At 200 m At 260 m
x7 x7 x8 x8
4.5 4.5
3.5 3.5
2.5 2.5
1.5 1.5
0.5 0.5
-0.5 -0.5
0.0 1.0 2.0 3.0 4.0 5.0 0.0 1.0 2.0 3.0 4.0 5.0
-1.5 -1.5
-2.5 -2.5
-3.5 -3.5
-4.5 -4.5
-5.5 -5.5
-6.5 -6.5
At 320 m At 380 m
x10
x9 x9 x10
4.5 4.5
3.5 3.5
2.5 2.5
1.5 1.5
0.5 0.5
-0.5 -0.5
0.0 1.0 2.0 3.0 4.0 5.0 0.0 1.0 2.0 3.0 4.0 5.0
-1.5 -1.5
-2.5 -2.5
-3.5 -3.5
-4.5 -4.5
-5.5 -5.5
-6.5 -6.5
At 440 m At 500 m
x11
x11 x12 x12
4.5 4.5
3.5 3.5
2.5 2.5
1.5 1.5
0.5 0.5
-0.5 -0.5
0.0 1.0 2.0 3.0 4.0 5.0 0.0 1.0 2.0 3.0 4.0 5.0
-1.5 -1.5
-2.5 -2.5
-3.5 -3.5
-4.5 -4.5
-5.5 -5.5
-6.5 -6.5
At 560 m At 620 m
x14
x13 x13 x14
4.5 4.5
3.5 3.5
2.5 2.5
1.5 1.5
0.5 0.5
-0.5 -0.5
0.0 1.0 2.0 3.0 4.0 5.0 0.0 1.0 2.0 3.0 4.0 5.0
-1.5 -1.5
-2.5 -2.5
-3.5 -3.5
-4.5 -4.5
-5.5 -5.5
-6.5 -6.5
At 680 m At 740 m
x15
x15 x16 x16
4.5 4.5
3.5 3.5
2.5 2.5
1.5 1.5
0.5 0.5
-0.5 -0.5
0.0 1.0 2.0 3.0 4.0 5.0 0.0 1.0 2.0 3.0 4.0 5.0
-1.5 -1.5
-2.5 -2.5
-3.5 -3.5
-4.5 -4.5
-5.5 -5.5
-6.5 -6.5
At 800 m At 860 m
x17
4.5
3.5
2.5
1.5
0.5
-0.5
0.0 1.0 2.0 3.0 4.0 5.0
-1.5
-2.5 x17
-3.5
-4.5
-5.5
-6.5
At 920 m
Cross sections profile along the Street
Alferdos Road:
Original Cross-Sectional Levels:
Existing Road Levels (Based on site survey)
x1
0
x1 x2 x2
0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0 -0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6 -1.6
At 0 m At 60 m
x4
x3 x3 x4
0 0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6 -1.6
At 120 m At 180 m
0
x5 x5
x6 x6
0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6
-1.6
At 240 m At 300 m
x7 x7
x8 x8
0 0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0 -0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6 -1.6
At 360 m At 420 m
x9 x9 x10 x10
0 0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0 6.0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6 -1.6
At 480 m At 540 m
x11
0
x11 x12 x12
0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6 -1.6
At 600 m At 660 m
x13 x13
0
x14 x14
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6 -1.6
At 720 m At 780 m
x16
x15 x15 x16
0
0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6 -1.6
At 840 m At 900 m
x17
x17 x18 x18
0 0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0 -0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6 -1.6
At 960 m At 1020 m
x20
x19 x19
x20
0 0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0 -0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6 -1.6
At 1080 m At 1140 m
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6 -1.6
At 1200 m At 1260 m
0
x23 x23 x24 x24
0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6 -1.6
At 1320 m At 1380 m
x25 x25
x26 x26
0 0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0 -0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6
-1.6
At 1440 m At 1500
x27 x27 x28 x28
0 0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0 -0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6 -1.6
At 1560 m At 1620 m
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6 -1.6
At 1680 m At 1740 m
Cross sections profile along the Street
Appendix (B)
Modified Cross-Sectional Slope
Elshaheed Osama AlmagboolRoad:
Geometric design For the Cross-Sectional Levels:
Existing Road Levels (Based on site survey)
1x 1new x2 new 2
0.25 0.25
0.05 0.05
0.15- 0.0 1.0 2.0 3.0 4.0 5.0 -0.15 0.0 1.0 2.0 3.0 4.0 5.0
0.35- -0.35
0.55- -0.55
0.75- -0.75
0.95- -0.95
1.15- -1.15
1.35- -1.35
At 0 m At 60 m
x4 new 4
x3 new 3
0.25 0.25
0.05 0.05
-0.15 0.0 1.0 2.0 3.0 4.0 5.0 -0.15 0.0 1.0 2.0 3.0 4.0 5.0
-0.35 -0.35
-0.55 -0.55
-0.75 -0.75
-0.95 -0.95
-1.15 -1.15
-1.35 -1.35
At 120 m At 180 m
x5 new 5 x6 new 6
0.25 0.25
0.05 0.05
-0.15 0.0 1.0 2.0 3.0 4.0 5.0 -0.15 0.0 1.0 2.0 3.0 4.0 5.0
-0.35 -0.35
-0.55 -0.55
-0.75 -0.75
-0.95 -0.95
-1.15 -1.15
-1.35 -1.35
At 240 m At 300 m
x7 new 7 x8 new 8
0.25 0.25
0.05 0.05
-0.15 0.0 1.0 2.0 3.0 4.0 5.0 -0.15 0.0 1.0 2.0 3.0 4.0 5.0
-0.35 -0.35
-0.55 -0.55
-0.75 -0.75
-0.95 -0.95
-1.15 -1.15
-1.35 -1.35
At 360 m At 420 m
x9 new 9
x10 new 10
0.25
0.25
0.05
0.05
-0.15 0.0 1.0 2.0 3.0 4.0 5.0 6.0 -0.15 0.0 1.0 2.0 3.0 4.0 5.0
-0.35 -0.35
-0.55 -0.55
-0.75 -0.75
-0.95 -0.95
-1.15 -1.15
-1.35 -1.35
At 480 m At 540 m
x11 new 11 x12 new 12
0.25 0.25
0.05 0.05
-0.15 0.0 1.0 2.0 3.0 4.0 5.0 -0.15 0.0 1.0 2.0 3.0 4.0 5.0
-0.35 -0.35
-0.55 -0.55
-0.75 -0.75
-0.95 -0.95
-1.15 -1.15
-1.35 -1.35
At 600 m At 660 m
x13 new 13 x14 new 14
0.25 0.25
0.05 0.05
-0.15 0.0 1.0 2.0 3.0 4.0 5.0 -0.15 0.0 1.0 2.0 3.0 4.0 5.0
-0.35 -0.35
-0.55 -0.55
-0.75 -0.75
-0.95 -0.95
-1.15 -1.15
-1.35 -1.35
At 720 m At 780 m
At 840 m At 900 m
x18
x17 new 17 new 18
0.25 0.25
0.05 0.05
-0.15 0.0 1.0 2.0 3.0 4.0 5.0 -0.15 0.0 1.0 2.0 3.0 4.0 5.0
-0.35 -0.35
-0.55 -0.55
-0.75 -0.75
-0.95 -0.95
-1.15 -1.15
-1.35 -1.35
At 960 m At 1020 m
0.05 0.05
-0.15 0.0 1.0 2.0 3.0 4.0 5.0 -0.15 0.0 1.0 2.0 3.0 4.0 5.0
-0.35 -0.35
-0.55 -0.55
-0.75 -0.75
-0.95 -0.95
-1.15 -1.15
-1.35 -1.35
At 1080 m At 1140 m
x21 new 21 x22 new 22
0.25 0.25
0.05 0.05
-0.15 0.0 1.0 2.0 3.0 4.0 5.0 -0.15 0.0 1.0 2.0 3.0 4.0 5.0
-0.35 -0.35
-0.55 -0.55
-0.75 -0.75
-0.95 -0.95
-1.15 -1.15
-1.35 -1.35
At 1200 m At 1260 m
x23 new 23
0.25
0.05
-0.15 0.0 1.0 2.0 3.0 4.0 5.0
-0.35
-0.55
-0.75
-0.95
-1.15
-1.35
At 1320 m
x1 new 1 x2 new 2
4.5 4.5
3.5 3.5
2.5 2.5
1.5 1.5
0.5 0.5
-0.5 -0.5
0.0 1.0 2.0 3.0 4.0 5.0 0.0 1.0 2.0 3.0 4.0 5.0
-1.5 -1.5
-2.5 -2.5
-3.5 -3.5
-4.5 -4.5
-5.5 -5.5
-6.5 -6.5
At 0 m At 50 m
x3 new 3 x4 new 4
4.5 4.5
3.5 3.5
2.5 2.5
1.5 1.5
0.5 0.5
-0.5 -0.5
-1.5 0.0 1.0 2.0 3.0 4.0 5.0
-1.5 0.0 1.0 2.0 3.0 4.0 5.0
-2.5 -2.5
-3.5 -3.5
-4.5 -4.5
-5.5 -5.5
-6.5 -6.5
At 100 m At 150 m
x5 new 5 x6 new 6
4.5 4.5
3.5 3.5
2.5 2.5
1.5 1.5
0.5 0.5
-0.5 -0.5
0.0 1.0 2.0 3.0 4.0 5.0 0.0 1.0 2.0 3.0 4.0 5.0
-1.5 -1.5
-2.5 -2.5
-3.5 -3.5
-4.5 -4.5
-5.5 -5.5
-6.5 -6.5
At 200 m At 260 m
x7 new 7 x8 new 8
4.5 4.5
3.5 3.5
2.5 2.5
1.5 1.5
0.5 0.5
-0.5 -0.5
0.0 1.0 2.0 3.0 4.0 5.0 0.0 1.0 2.0 3.0 4.0 5.0
-1.5 -1.5
-2.5 -2.5
-3.5 -3.5
-4.5 -4.5
-5.5 -5.5
-6.5 -6.5
At 320 m At 380 m
x9 new 9 x10 new 10
4.5 4.5
3.5 3.5
2.5 2.5
1.5 1.5
0.5 0.5
-0.5 -0.5
0.0 1.0 2.0 3.0 4.0 5.0 0.0 1.0 2.0 3.0 4.0 5.0
-1.5 -1.5
-2.5 -2.5
-3.5 -3.5
-4.5 -4.5
-5.5 -5.5
-6.5 -6.5
At 440 m At 500 m
x12 new 12
x11 new 11
4.5 4.5
3.5 3.5
2.5 2.5
1.5 1.5
0.5 0.5
-0.5 -0.5
0.0 1.0 2.0 3.0 4.0 5.0 0.0 1.0 2.0 3.0 4.0 5.0
-1.5 -1.5
-2.5 -2.5
-3.5 -3.5
-4.5 -4.5
-5.5 -5.5
-6.5 -6.5
At 560 m At 620 m
x13 new 13 x14 new 14
4.5 4.5
3.5 3.5
2.5 2.5
1.5 1.5
0.5 0.5
-0.5 -0.5
0.0 1.0 2.0 3.0 4.0 5.0 0.0 1.0 2.0 3.0 4.0 5.0
-1.5 -1.5
-2.5 -2.5
-3.5 -3.5
-4.5 -4.5
-5.5 -5.5
-6.5 -6.5
At 680 m At 740 m
x15 x16
new 15 4.5
4.5
3.5 3.5
2.5 2.5
1.5 1.5
0.5 0.5
-0.5 -0.5
0.0 1.0 2.0 3.0 4.0 5.0 0.0 1.0 2.0 3.0 4.0 5.0
-1.5 -1.5
-2.5 -2.5
-3.5 -3.5
-4.5 -4.5
-5.5 -5.5
-6.5 -6.5
At 800 m At 860 m
x17 new 17
4.5
3.5
2.5
1.5
0.5
-0.5
0.0 1.0 2.0 3.0 4.0 5.0
-1.5
-2.5
-3.5
-4.5
-5.5
-6.5
At 920 m
x1 new 1 x2 new 2
0 0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0 -0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1
-1
-1.2
-1.2
-1.4
-1.4
-1.6
-1.6
At 0 m At 60 m
x3 new 3 x4 new 4
0 0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6 -1.6
At 120 m At 180 m
x5 new 5 x6 new 6
0 0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6 -1.6
At 240 m At 300 m
x7 x8 new 8
new 7
0 0
0.0 1.0 2.0 3.0 4.0 5.0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0 -0.2
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6 -1.6
At 360 m At 420 m
x9 new 9 x10 new 10
0 0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0 6.0 -0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6 -1.6
At 480 m At 540 m
x11 new 11 x12 new 12
0 0
0.0 1.0 2.0 3.0 4.0 5.0 0.0 1.0 2.0 3.0 4.0 5.0
-0.2 -0.2
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6 -1.6
At 600 m At 660 m
x13 new 13 x14 new 14
0 0
0.0 1.0 2.0 3.0 4.0 5.0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0 -0.2
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6 -1.6
At 720 m At 780 m
x15 new 15 x16 new 16
0 0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6 -1.6
At 840 m At 900 m
x17 new 17 x18 new 18
0 0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.2
0.0 1.0 2.0 3.0 4.0 5.0
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6 -1.6
At 960 m At 1020 m
x19 new 19 x20 new 20
0
0
0.0 1.0 2.0 3.0 4.0 5.0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.2
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6 -1.6
At 1080 m At 1140 m
x21 new 21 x22 new 22
0 0
0.0 1.0 2.0 3.0 4.0 5.0 0.0 1.0 2.0 3.0 4.0 5.0
-0.2 -0.2
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6 -1.6
At 1200 m At 1260 m
x23 new 23 x24 new 24
0 0
0.0 1.0 2.0 3.0 4.0 5.0 0.0 1.0 2.0 3.0 4.0 5.0
-0.2 -0.2
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6 -1.6
At 1320 m At 1380 m
x25 new 25 x26
0 new 26
0
0.0 1.0 2.0 3.0 4.0 5.0
-0.2 -0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6 -1.6
At 1440 m At 1500 m
x27 new 27 x28 new 28
0 0
-0.2 0.0 1.0 2.0 3.0 4.0 5.0 -0.2 0.0 1.0 2.0 3.0 4.0 5.0
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6 -1.6
At 1560 m At 1620 m
x29 new 29 x30 new 30
0 0
0.0 1.0 2.0 3.0 4.0 5.0
-0.2 -0.2 0.0 1.0 2.0 3.0 4.0 5.0 6.0
-0.4 -0.4
-0.6 -0.6
-0.8 -0.8
-1 -1
-1.2 -1.2
-1.4 -1.4
-1.6 -1.6
At 1680 m At 1740 m
LOAD SUMMARY
WEIGHT OF THE WALLS 21.34615 KN/m
EARTH PRESSURE ON WALLS
TOP MAXIMUM 6.406726 KN/m
MINIMUM 3.203363 KN/m
BOTTOM MAXIMUM 32.03363 KN/m
MINIMUM 16.01681 KN/m
LIVE LOAD SURCHARGE
TOP 21.55969 KN/m
BOTTOM 26.50781 KN/m
HYDROSTATIC PRESSURE 4.527692 KN/m
UNIFORM LOAD ON ROOF EV 8.397525 KN/m
LIVE
LOAD 137.3387 KN/m
K=rise/span*(Tt/Ts)³= 0.6
K1=K+1= 1.6
K2=K+2= 2.6
K3=K+3= 3.6
K4=4*K+9= 11.4
K5=2*K+3= 4.2
K6=K+6= 6.6
K7=2*K+7= 8.2
K8=3*K+8= 9.8
ANALYSIS
WEIGHT OF THE WALLS
MOMENTS
Ma=Mab=w*span²*k/(12*k1*k3)= 0.185296 KN.m
Mc=-(k5/k)*Ma= -1.29708 KN.m
Mcd=w*span²/8-Mc= 1.371194 KN.m
Mac=(Ma+Mc)/2= -0.55589 KN.m
HYDROSTATIC PRESSURE
Ma=w*rise²*k*k7/(60*k1*k3)= 0.023204 KN.m
Mc=(k8/k7)*Ma= 0.027732 KN.m
Mac=(Ma+Mc)/2-(w*rise²/16)= -0.0764 KN.m
UNIFORM LOAD ON ROOF EV
Ma=Mc=-w*span²/(12*k1)= -0.43737 KN.m
Mab=Mcd=(w*span²/8)-Ma= 0.61232 KN.m
LIVE LOAD
Ma=Mc=-w*span²/(12*k1)= -7.15305 KN.m
Mab=Mcd=(w*span²/8)-Ma= 10.01428 KN.m
EARTH PRESSURE ON WALLS
MAXIMUM
RECTANGULAR
Ma=Mc=-w*rise²*k/(12*k1)= -0.07208 KN.m
Mac=w*rise²/8 – Ma= 0.216227 KN.m
TRIANGULAR
Ma=-w*rise²*k*k7/(60*k1*k3)= -0.13134 KN.m
Mc=(k8/k7)*Ma= -0.15696 KN.m
Mac=(1/16)*rise²*w-(Ma+Mc)/2= 0.432454 KN.m
MINIMUM
RECTANGULAR
Ma=Mc=-w*rise²*k/(12*k1)= -0.03604 KN.m
Mac=w*rise²/8 – Ma= 0.108113 KN.m
TRIANGULAR
Ma=-w*rise²*k*k7/(60*k1*k3)= -0.06567 KN.m
Mc=(k8/k7)*Ma= -0.07848 KN.m
Mac=(1/16)*rise²*w-(Ma+Mc)/2= 0.216227 KN.m
LIVE LOAD SURCHARGE
RECTANGULAR
Ma=Mc=-w*rise²*k/(12*k1)= -0.24255 KN.m
Mac=w*rise²/8 – Ma= 0.727639 KN.m
TRIANGULAR
Ma=-w*rise²*k*k7/(60*k1*k3)= -0.02536 KN.m
Mc=(k8/k7)*Ma= -0.03031 KN.m
Mac=(1/16)*rise²*w-(Ma+Mc)/2= 0.0835 KN.m
DESIGN
Determine the required area of flexural
reinforcement
the resistance force ɸ, for flexure is 1.0 for precast box
culverts
Mu=ɸ*Mn=ɸ*As*fy+(d-a/2)
the depth of the compression
block is
a=As*fy/(0.85*fc'*b)
substituting for "a" in the 1st
equation
Mu=ɸ*Mn=ɸ*As*fy+(d-As*fy/(0.85*2*fc'*b))
ɸ=1 fy=280N/mm² b=1m fc=28N/mm²
Mu=1*As*280+(d-As*280/(1.7*28*1000))
1.647*As²-
280*As*d+Mu=0
As=(280*d-√(78400*d²-6.588*Mu))/3.294
Sidewall
d=thickness-cover-ø/2
ø=bar diameter=12mm
d 244 mm
Referring to table 2 the peak moment for tension on the outside face
is 21.845KN.m (top strength Ia).
-
M peak 15.53836067 KN.m
As 228.6958684 mm²/m 339.3 As PROVIDED
The peak moment for tension on the inside face is 1.46 KN.m
As 21.38104398 mm²/m 113.1 As PROVIDED
Top slab
d 244 mm
peak moment for tension on the outside -13.6404 KN.m
As 200.6250438 mm²/m 339.3 As PROVIDED
peak moment for tension on the intside 18.52845 KN.m
As 272.9975934 mm²/m 452.4 As PROVIDED
Bottom
slab
D= 244 mm
peak moment for tension on the outside -15.5384 KN.m
As= 228.6958684 mm²/m 339.3 As PROVIDED
peak moment for tension on the intside 20.00437 KN.m
As= 294.9004459 mm²/m 452.4 As PROVIDED
s≤(700* γe/(βs*fss))-2*dc
γe= 0.75 (exposure factor)
Top slab:
for the top slab the governing service limit state moment is 15.8 KN.m .
take s 250 mm 9.84 inch
dc= cover +dw/2 56 mm 2.2 inch
βs 1.327868852
fss 27.7647732 ksi 191.2993 N/mm²
0.6*fy 216
fss≤ 0.1*fy use 191.3 N/mm²
j=0.74|+0.1*(e/d) 1.8059492
take 'j' = 0.9
i=1/(1-
(j*d/e)) 1.0922179
Bottom slab :
for the top slab the governing service limit state moment is 15.8 KN.m .
take s 250 mm 9.84 inch
dc= cover +dw/2 56 mm 2.2 inch
βs 1.327868852
fss 27.7647732 ksi 191.2993 N/mm²
0.6*fy 216
fss≤ 0.1*fy use 191.3 N/mm²
j=0.74+0.1*(e/d) 1.6219838
take 'j' = 0.9
i=1/(1-
(j*d/e)) 1.1136387
fs=(Ms+Ns*(d-
h/2))/(As*j*i*d) 112.5759 N/mm² <191.3 N/mm²
Good
Side wall
for the top slab the governing service limit state moment is 15.8 KN.m .
take s 250 mm 9.84 inch
dc= cover +dw/2 56 mm 2.2 inch
βs 1.327868852
fss 27.7647732 ksi 191.2993 N/mm²
0.6*fy 216
fss≤ 0.1*fy use 191.3 N/mm²
find the actual stress provided in the steel:
e=Ms/Ns+d-h/2 413.61975 mm
i=1/(1-
(j*d/e)) 2.1576659
fs=(Ms+Ns*(d-
h/2))/(As*j*i*d) 74.78886 N/mm² <191.3 N/mm²
Good
where:
c=As*fy/(0.85*fc*β1*b)
fc 28 N/mm² 4.061 ksi
β1=0.85-0.05*(fc-4.0) 0.84695
Sidewall
Outside
face
c 6.0597071 mm
c/d 0.0248349 OK
Top slab
Outside
face
c 8.0796094 mm
c/d 0.0331132 OK
Bottom slab
Outside
face
c 8.0796094 mm
c/d 0.0331132 OK
**ρ=As/Ac <0.018
Sidewall
Ac=b*d 1000*244= 244000 mm²
ρ 0.001390574 OK
Top slab
ρ 0.001854098 OK
Bottom
slab
ρ 0.001854098 OK
CHECK SHEAR
Sidewall
Vu= 39.57249656 KN
with assosiated moment
Mu= 15.53836 KN.m
the nominal shear resistance without the presence of shear reinforcement is given by:
Vr=ɸ*Vn
where:
Vn=Lesser
of 0.25*fc*bv*dv
or
Vc= 0.0316*β*√fc*bv*dv
bv is the assumed member width
dv is the effective shear depth calculated as:
a=As*fy/(0.85*fc*b) 9.07563 mm
dv=max(0.72h,0.9d,d-a/2)
0.72h 216 mm
0.9d 219.6 mm
max d-a/2 239.46218 mm √
Sxe=239.4622 mm
ɛs=(Mu/dv+0.5Nu+Vu)/(Es*As)= 0.0008707
Top slab
Vu= 30.72537722 KN
with assosiated moment Mu= 2.344416 KN.m
the nominal shear resistance without the presence of shear reinforcement is given
by:
Vr=ɸ*Vn
where:
Vn=Lesser of 0.25*fc*bv*dv
or
Vc= 0.0316*β*√fc*bv*dv
bv is the assumed member width
dv is the effective shear depth calculated as:
a=As*fy/(0.85*fc*b) 9.07563 mm
dv=max(0.72h,0.9d,d-a/2)
0.72h= 15522.975 mm
0.9d= 219.6 mm
max d-a/2= 239.46218 mm √
Sxe=239.462 mm
ɛs=(Mu/dv+0.5Nu+Vu)/(Es*As)= 0.0005121
where the magnitude of the moment 'Mu' is not to be less than:
β=(4.8/(1+750*ɛs))*(51/(39+sxe))
β= 3.652253224
Vc= 146.2392396 KN
Vn= 1676.235294 KN
Bottom slab
Vu= 39.57249656 KN
with assosiated moment Mu= 15.53836 KN.m
the nominal shear resistance without the presence of shear reinforcement is given
by:
Vr=ɸ*Vn
where:
Vn=Lesser of 0.25*fc*bv*dv
or
Vc= 0.0316*β*√fc*bv*dv
bv is the assumed member width
dv is the effective shear depth calculated as:
a=As*fy/(0.85*fc*b) 9.07563 mm
dv=max(0.72h,0.9d,d-a/2)
0.72h= 216 mm
0.9d= 219.6 mm
max d-a/2= 239.46218 mm √
Sxe=239.4622 mm
ɛs=(Mu/dv+0.5Nu+Vu)/(Es*As)= 0.0008705
β=(4.8/(1+750*ɛs))*(51/(39+sxe))
β= 3.058273257
Vc= 122.4557905 KN
Vn= 1676.235294 KN