Professional Documents
Culture Documents
S03 Earthworks
S03 Earthworks
S03 Earthworks
SECTION 3: EARTHWORKS
TABLE OF CONTENTS
CONTENTS PAGE
i
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
ii
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
iii
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
SECTION 3: EARTHWORKS
3.1.1 Definition
(a) 'Topsoil' shall mean the top layer of soil that can support
vegetation, and shall include all turf which is not acceptable for
turfing under Clause 3.14.
(b) 'Suitable Material' shall comprise all earth and rock materials
which are not classified as 'Unsuitable Material' as defined below,
which are capable of being compacted in the manner specified in
Clause 3.8 of the Specifications, whether obtained from within or
outside the Site and which meets specific requirements for
incorporation in the works as specified in the contract.
S3-1
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(e) 'Rock Fill' shall be clean, hard, durable, well graded rock from
approved sources. Not more than 5% by weight of rock fill shall
consist of pieces heavier than 1700kg and not more than 20%
shall consist of pieces heavier than 700kg. The material shall not
have more than 10% by weight of particles passing a 75.4mm BS
sieve.
S3-2
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(a) The Contractor shall employ only such plant and working methods
which are suited to the materials to be handled. He shall be
responsible for maintaining the nature of all suitable material, so
that when it is placed and compacted it remains suitable as
defined above.
S3-3
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(d) When the Contractor disposes of any material outside the reserve,
he shall be fully and solely responsible for the expenses incurred
and any legal consequences.
(h) Unless otherwise specified, turf not required for relaying and all
top soil shall be removed from areas of cuttings and
embankments and, unless surplus to requirements, stockpiled for
re-use for the soiling of slopes, berms, verges and central
reserves, and for the provision of beds for the cultivation of trees
and shrubs. The storage of stripped topsoil shall be to a maximum
height of 2 metres, and shall on no account be consolidated or
trafficked by heavy machinery. The storage of topsoil shall be kept
completely separate from that of stored subsoil. The mounds shall
be hydroseeded in accordance with the specification for
hydroseeding, and the grass fertilized and maintained throughout
the period of storage. The topsoil shall be kept free of noxious
weeds by removing seedheads before maturity and by the use of
S3-4
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(i) The Contractor shall make his own arrangements for stockpiling of
top soil and/or suitable material, and for the provision of sites for
the purpose. No excavated material shall be stockpiled within the
Site without the approval of the S.O..
3.2.1 General
S3-5
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(b) Where permission has been granted for the use of explosives for
the execution of the work, the Contractor shall be solely
responsible for obtaining the necessary licenses for the
procurement, possession, transport, storage and handling of
explosives, and for ensuring the validity of such licenses at all
relevant times. Before starting work, the Contractor shall satisfy
the S.O. that all the required permits are in order and that this
category of work is adequately covered by the policies of
insurance.
S3-6
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(b) All relevant security regulations dealing with the storage, handling
and transport of explosives shall be complied with.
S3-7
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(e) The Contractor shall submit in writing his blasting proposals to the
S.O. for approval at least 48 hours before an initial blast and at
least 24 hours before any subsequent blasts.
3.2.4 Monitoring
(b) Trial blast tests shall be carried out for controlled perimeter
blasting and bulk blasting techniques to test the drilling accuracy
necessary to achieve the required sound uniform surfaces to the
completed excavations, and to test the efficacy of the blasting
arrangements.
S3-8
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(d) The requirements for the trial blasts shall be as specified in this
Clause for the final slopes.
(e) The resultant trial faces shall be fully exposed, all loose rock
scaled, and the faces evaluated by the S.O. before controlled
perimeter blasting of the design slopes commences.
(f) Further trials will be required if the S.O. considers the resultant
faces to be unsatisfactory.
3.2.6 Pre-Splitting
(a) Controlled perimeter blasting at the final rock slope surface shall
be carried out using the pre-splitting technique, unless the S.O.
permits otherwise.
(c) The average spacing and charges per hole shall be determined by
the Contractor, who shall carry out trial pre-splitting blast tests for
S3-9
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(d) Before commencing the trial pre-splitting and bulk blasts, the
Contractor shall submit to the S.O. details of his proposals
including the following data.
iv. Diameter, spacing burden and depth for main bulk blast
holes.
S3-10
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
ii. At least 60 per cent of the drill hole traces in any panel are
visible in the final rock surface, distributed uniformly after
scaling down of all loose rock.
(f) Drill holes shall generally not be more than 50mm from the true
location at the top of the hole and shall generally not diverge from
the required line by more than 150mm in 10 metres. The diameter
of the holes shall not be less than 60mm nor greater than 80mm.
No subgrade drilling shall be permitted.
S3-11
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
The Contractor shall, where ordered by the S.O., provide access to the
rock slopes for the S.O.. Access shall consist of a rigid temporary
structure that will allow the S.O. to examine safely all parts of the rock
slopes during the trial stages and the pre-splitting works for the final rock
slope.
Where the S.O. may wish to carry out additional inspection of the area of
the slope from which rock or other materials have been removed, the
Contractor shall re-erect or repair the access to allow the additional
inspection to take place where required by the S.O..
The Contractor shall make due allowances in his programming for the
time required to erect and maintain access to the rock slopes.
3.2.8 Safety
S3-12
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
S3-13
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(g) Drilling rigs for shot holes shall be of the hydraulic type fitted with
efficient silencers and means of dust suppression.
(a) The pump truck from which any explosives are dispensed into the
drilled holes shall be equipped with an accurate flow meter or
similar measurement/recording device in order to accurately
monitor and control the volume of explosives dispensed at each
position.
(c) After a charge has been wired and tested, a gunny sack shall be
placed over the charged hole; a blasting mat shall then be placed
on top of the gunny sack and a sand bag placed on the blasting
mat.
S3-14
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(d) Where the relevant authorities allow the use of slurry explosives in
order, to prevent seepage of slurry into rock cracks and fissures in
drilled holes, fast cross-linking fluids shall be introduced into the
slurry mix to speed the jelling process and to reduce its viscosity.
The Contractor's proposals in this respect shall be subject to the
approval of the S.O., and shall be modified as Site conditions
dictate. A full tubular steel and wire mesh "roofover" shall be
required to all areas where the Contractor elects to use slurry mix
explosives, unless otherwise approved by the S.O..
(a) The Contractor shall adopt a method of working such that at any
time controlled perimeter blasting operations, including the drilling
of perimeter holes, do not advance by more than one panel ahead
of bulk blasting operations and more than two panels ahead of
mucking operations to remove all blasted materials from the
perimeter face, unless specially approved by the S.O., in order
that adjustments to drilling, charging and detonation can be made,
appropriate to the conditions being encountered.
(b) The S.O. shall only approve a variation to the above procedure
subsequent to the Contractor demonstrating the success of his
working procedure in relevant rock conditions.
(c) Mucking out to the perimeter faces shall be carried out carefully
from the perimeter line.
S3-15
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
The drill holes within the buffer zone shall not be larger than
50mm diameter, and the spacings, burdens (which shall not
exceed the hole spacing) and charge per hole in the zone shall be
suitably reduced to avoid excessive blast damage to the final face.
No subgrade drilling shall be allowed in the holes above the
berms.
S3-16
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(d) Any excavation below the formation level tolerance limit specified
in Clause 3.9 shall be made good by backfilling with suitable
material of similar characteristics to that removed, compacted in
accordance with Clause 3.8.
S3-17
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(f) Constructional traffic shall not use the surface of the bottom of a
cutting unless the cutting is in rock or the Contractor maintains the
level of the bottom surface at least 300mm above formation level.
Any damage to the subgrade arising from such use of the surface
shall be made good by the Contractor at his own expense with
material having the same characteristics as the material which has
been damaged. From the time the Contractor begins to trim the
remaining material to formation level on any given area, the
movement and use of constructional plant thereon other than that
used to complete this operation shall be in accordance with the
requirements of Clause 3.
(a) Where any material below the natural ground level under
embankments, under culvert bedding, or below formation level in
cuttings is required to be excavated, the resultant excavation shall
be backfilled with suitable material deposited in layers of thickness
appropriate to the compaction plant to be used, and compacted in
the manner specified for the forming of embankments. Except that
where in these circumstances such backfill has to be deposited
below standing water, it shall be material as described in Clause
3.22.
(b) If, after the removal of material as specified in Clause 3.4, the
Contractor allows the material so exposed to reach a condition
where compaction of backfill in accordance with Clause 3.8 is
S3-18
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(a) The sides of pits and trenches shall be adequately supported at all
times. Except where otherwise described in the Specifications, or
shown on the Drawings or agreed with the S.O., they shall not be
battered.
(b) Trenches and pits shall be kept free of water in accordance with
Clause 3.10.
(c) The bottoms of all excavations shall be formed to the lines and
levels shown on the Drawings. Any pockets of soft material or
loose rock in the bottoms of pits and trenches shall be removed,
and the resulting cavities and any large fissures filled with
concrete 15/20 to Section 11 of the Specification. After the
placing of any specified blinding concrete, no trimming of the side
faces shall be carried out for 24 hours.
(d) All excavated materials from trenches and pits not required for
backfilling shall be disposed of immediately in accordance with the
requirements of Clause 3.1.
(e) The Contractor shall at his own expense make good with suitable
material as defined in Clause 3.1, or concrete 15/20 to Section 11
of the Specification, as directed by the S.O.:
S3-19
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
Unless otherwise specified, all backfill for foundation pits and trenches
shall consist of suitable material as defined in Clause 3.1, deposited and
compacted by approved plant in accordance with Clause 3.8. Timber
sheeting and other excavation supports shall be carefully removed as the
backfilling proceeds, except where they are specified to be left in position.
However, the removal of such supports shall not relieve the Contractor of
his responsibilities for the stability of the Works.
S3-20
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
S3-21
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
S3-22
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
3
(h) Isolated boulders up to 0.10m in size may be incorporated in
earth embankments at the discretion of the S.O. provided that the
specified compaction requirements are met. No stone exceeding
0.02m3 shall be placed less than 0.5 metres below formation level
of carriageways or hard shoulders.
S3-23
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(l) In areas of shallow filling where the ground level is less than
300mm below formation level, traffic shall not use the surface
unless the Contractor brings up and maintains the surface level at
least 300mm above formation level. Any damage to the subgrade
arising from such use shall be made good by the Contractor at his
own expense with material having the same characteristics as the
damaged material.
(n) Joints in the geotextile filter fabric laid perpendicular to the centre-
line of the embankment shall have a minimum overlap of
1000mm, or where laid under water 1500mm. Overlap sideways
(longitudinal direction of road) shall be 1000mm if joints are not
stitched. The geotextile shall be suitably held in position until
covered by the drainage layer material. Stitching or stapling of the
fabric shall be allowed with the prior approval of the S.O. where
this can be proven to be a viable alternative to lapping. Any
damage to the fabric shall be repaired by patching with the same
fabric ensuring a minimum 1000mm overlap fully around the
S3-24
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(b) The Contractor shall submit to the S.O. for approval his proposals
for the compaction of each main type of material to be used in the
embankments. These shall include proposals for the type of plant,
the number of passes and the loose depth for each material. The
Contractor shall carry out compaction trials together with any
necessary laboratory investigations, as required by the S.O., using
the procedures proposed by the Contractor, and shall satisfy the
S.O. that all the specified requirements regarding compaction can
be achieved. Compaction trials with the main types of
embankment material likely to be encountered shall be completed
before the works with the corresponding materials will be allowed
to commence.
S3-25
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
iii. At least 90% of the maximum dry density for the rest of the
embankment. The soaked CBR value of the subgrade to a
depth of 900mm beneath the final formation level shall be
not less than 5%
S3-26
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(f) The S.O. may at any time carry out field density tests on material
which he considers has been inadequately compacted. If the test
results confirm that compaction is inadequate, then the Contractor
shall carry out such further work as the S.O. may decide is
required to achieve the specified requirements.
(h) Each layer in rock fill embankments shall be spread and levelled in
accordance with Clause 3.7, and systematically compacted by at
least 12 passes of a towed vibratory roller with a static load per
metre width of roll of at least 1,800kg, or a grid roller with a load
per metre width of roll of at least 8,000kg, or other approved plant
until there is no visible movement of the rockfill under the
equipment. Compaction shall be carried out in a longitudinal
direction along the embankment and shall begin at the outer
edges and progress towards the centre.
S3-27
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(c) The forming and compaction of embankments and other earth fills
using wet materials shall comply with the requirements of Clause
3.7 and 3.8 generally except where supplemented or modified by
this clause.
(d) The Contractor shall submit to the S.O. for approval his proposals
for the excavation of wet materials and the forming and
compaction of embankments and other earth fills using such
materials. These shall include proposals for the type of plant to be
used, measures for drying at source, measures for keeping the
earthworks free of water, methods of deposition and spreading
including the loose depth of deposition, procedures for aeration
and drying for moisture reduction and compaction of the wet
material including the number of passes to achieve the specified
compaction requirement.
(e) The Contractor shall carry out trial excavation, deposition and
compaction together with any necessary laboratory investigations
and monitoring as required by the S.O. using the procedures
proposed by the Contractor, and shall satisfy the S.O. that all the
specified requirements regarding compaction can be achieved.
The Contractor shall demonstrate the effectiveness of his
proposals to the satisfaction of the S.O. before the works with the
wet materials will be allowed to commence.
S3-28
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(j) All wet materials used for forming embankments and as filling
elsewhere shall be compacted as soon as practicable after
deposition by appropriate compaction plant which may include
pad-foot or sheep-foot compactors. The Contractor may carry out
compaction at moisture content outside the limits specified in
Clause 3.8 provided the compaction trials shall establish that all
S3-29
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
ii. One test per 500 sq.m for each layer of compacted
material elsewhere.
iii. cease work on the material until its condition is such that it
can be compacted as described in Clause 3.8 and
subclauses (j) and (k) of this clause.
S3-30
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(n) 600mm thick sand drainage layers extending through the full width
of the embankments shall be provided at every 5m vertical
intervals for dissipation of compaction pore pressures. These shall
be deposited in layers, each not exceeding 300mm loose depth
and each layer shall be lightly compacted.
(o) Upon completion of the embankment to its full width and formation
level, the embankment shall be allowed to rest for a minimum
period of three months prior to commencement of formation
preparation and laying of subballast and ballast.
S3-31
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(c) Compaction and forming of each lift shall be carried out as follows:
S3-32
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
Field density tests shall be carried out after (iv) to check for
compliance with the requirements for compaction given in Clause
3.8 of the Specifications.
(d) The Contractor shall carry out trial deposition and compaction
together with any necessary laboratory investigations and
monitoring to establish the loose depth of each layer, the no. of
passes and procedure for breaking up and compaction as
required under subclauses 3.8.2 (c) (ii) and the no. of passes for
compaction as required under subclause 3.8.2 (c) (iv) before the
work with soft rockfill will be allowed to commence.
(e) Detailed monitoring of the trials shall be carried out and recorded.
These shall include:
S3-33
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(a) Preparation of the formation in cuts shall be carried out only after
completion of any specified subgrade drainage, filter drains, piped
drains, services and ducts, and, unless otherwise agreed by the
S.O., immediately prior to laying the separation geotexile and sand
layer. The sequence of operations shall be as follows.
S3-34
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
iii. The soaked CBR of the material for the top 300mm
beneath the final formation to be scarified and compacted
to the requirements of the preceeding subclause (ii), shall
be not less than 5%. If the in-situ material complies with
this requirement, then the in-situ material can be used for
forming the top 300mm in accordance with subclause (ii).
Otherwise the Contractor shall dispose of the excavated
300mm material and replace with suitable material
complying with the CBR requirements.
S3-35
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
directed by the S.O., make good at his own expense the surface
by recompaction before laying the geotextile and sand layer.
(a) The Contractor shall arrange for the rapid dispersal of water shed
on to the earthworks or completed formation during construction,
or which enters the earthworks from any source. When practicable
the water shall be discharged into the permanent outfall for the
pipe drainage system. The Contractor shall provide adequate
means of trapping silt in temporary drainage systems discharging
into permanent drainage systems. The arrangements shall be
made in respect of all earthworks, including excavation, whether
for pipe trenches, foundations or cuttings.
(c) In pumping out excavations and in any lowering of the water table
the Contractor shall pay due regard to the stability of all structures.
3.11 Topsoil
S3-36
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(b) Topsoil shall consist of friable surface soil free from detrimental
amounts of subsoil, hard clay, gravel and stones, noxious weeds,
refuse or other foreign materials.
(e) Spreading of topsoil shall not be done when the ground or topsoil
is excessively wet or in any condition detrimental to the work.
S3-37
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
iii. the types of grass and legume (if any) and strains of seed
to be used, and the function, root and growth
characteristics of each type.
vi. the type of mulch to be used and its method and rate of
application.
S3-38
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(d) The Contractor shall ensure that even growth is achieved on all
hydroseeded areas, and that adequate fertilization and watering is
undertaken to ensure even germination and establishment of the
grass. Any areas which fail to show successful germination within
one month of hydroseeding, as determined by the S.O., shall be
re-hydroseeded.
S3-39
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
3.14 Turfing
(c) Turf shall be delivered to Site within 36 hours of being cut, and
when stored turves shall be stacked grass to grass to a maximum
height of 1.0m. Turf stored on Site for a period of more than 48
hours shall not be used without the approval of the S.O..
(d) The prepared areas shall be close turfed, with turves laid to a well
bonded pattern with no gaps between the turves, and lightly
beaten. Alternatively, where indicated on the Drawings, the
prepared areas shall be spot turfed with turves set at 500mm
centres in lines spaced 500mm apart. The turves in alternating
lines shall be staggered to give a diagonal pattern.
(f) During the currency of the Contract, the Contractor shall mow,
with cutting blades set 40mm above ground, those areas which
have been turfed. The first and subsequent mowings shall be
carried out when the grass has reached 75 - 100mm high, or at a
time to be agreed with the S.O., and the grassed areas shall be
cleared of all grass cuttings.
S3-40
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
3.15 Watercourses
(c) The beds and sloping sides of watercourses shall, where shown
on the Drawings, be protected against the action of water by
mortared stone pitching, or mortared pre-cast concrete blocks, or
cast in situ concrete, forming a flat or curved surface as indicated.
Stones for mortared stone pitching shall be roughly dressed
square. No stone shall be less than 250mm in depth nor 0.03
cubic metre in volume. Mortared stone pitching shall be laid in
accordance with the details shown on the Drawings.
S3-41
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(b) The maximum particle size of the material shall be 100mm, and at
least 90% shall pass the 75mm BS sieve, and not more than 10%
shall pass the 75m BS sieve.
3.20 Instrumentation
3.20.1 General
(b) The Contractor shall be responsible for and shall follow the
instructions of the manufacturer in the installation, calibration and
testing of all measuring instruments and equipment, which shall
be carried out under the direct supervision of the Engineer. The
Contractor shall inform the S.O. at least 2 days prior to
S3-42
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(b) The top end of the PVC riser pipe shall have a screw connection
to enable extension of the pipe above ground level;
(c) The length and outlet diameter of the ceramic piezometer tip shall
be a minimum of 210mm and 50mm respectively. The minimum
internal diameter of the riser pipe shall be 14mm;
(d) All connections between piezometer tip and riser pipe and
between different lengths of riser pipes shall be by use of PVC
connectors designed to ensure perfect sealings against leakage.
(e) An electrical dip meter which actuates when in contact with water
shall be supplied for use as a read out device.
S3-43
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
and 3.2mm outer diameter nylon tubes, one black and one white
and covered with a polythene sheath 1mm think.
3.20.4 Inclinometers
S3-44
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(c) The completed inclinometer tube shall extend above the existing
ground or finished embankment level. The top of the tube shall be
fitted with a lockable top cap assembly. Heavy compaction
equipment shall not approach within 1.5m of inclinometer tubes.
S3-45
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
S3-46
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
All instruments shall be protected against damage over the period of the
Contract. Instruments damaged during the above period shall be
immediately replaced by the Contractor.
S3-47
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
3.20.12 Personnel
S3-48
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(b) Material complying with the requirements for the gravel drainage
layer of Clause 3.23 shall be placed to form a gravel drainage
layer of the specified thickness, as shown on the Drawings. No
constructional plant shall be allowed to travel directly over the
geotextile layer, where provided, until a sufficient thickness of
material has been placed to prevent damage to the geotextile and
to avoid heave of the foundation soil.
S3-49
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(d) Surcharge shall be removed only with the approval of the S.O.,
and such removal shall be carried out in accordance with the
method and procedure stated on the Drawings.
(a) This work shall consist of the construction of selected fill capping
layers by furnishing, placing, compacting and shaping selected
materials from approved sources in accordance with the
Specifications, to the lines, levels, grades, dimensions and cross-
sections shown on the Drawings.
(c) The material shall have a 10% fines value of 50 kN or more when
tested in accordance with BS 812, except that samples shall be
soaked in water at room temperature for 48 hours before testing
without having been oven dried.
(d) The material shall be laid in layers not greater than 300mm loose
depth, and care shall be taken to prevent segregation of the
material.
S3-50
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
BS Sieve Percentage by
Size Weight Passing
500 mm 100
10 mm 0 - 100
5 mm 0 - 100
2 mm 0 - 100
600 m 0 - 50
75 m 0-5
3.23.1 General
Free Draining Material for drainage layers, etc. shall consist of hard,
clean, crushed rock, gravel or sand having a grading within the limits
specified below. The aggregate crushing value of the material when
tested in accordance with BS 812 shall not exceed 30 per cent.
S3-51
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
3.23.2 Grading
(b) The moisture content versus dry density curve shall be determined
by BS 1377-4:1990 Clause 3 for each sample.
S3-52
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(b) The moisture content versus dry density curve shall be determined
by BS 1377 – 4: 1990 Clause 3 for each sample.
S3-53
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
3.25.1 General
Rock stabilization works on final excavated rock slopes shall include, but
not be limited to: breaking up and removing loose or overhanging rocks,
supporting loose rocks with dowels or bolts, providing masonry infill or
buttresses, or reinforced concrete supports, securing loose areas with
sprayed concrete (reinforced with mesh or plain), infilling joints with
mortar, removing soft material and backfilling with concrete, and providing
adequate drainage measures. Typical details of these items are shown on
the Drawings.
The Contractor shall inspect provide access to rock slopes. Access shall
consist of a rigid temporary structure that will allow personnel to inspect
examine safely all parts of the rock slopes.
S3-54
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
ii. flush out hole with water until return water is clear
(b) The Contractor shall provide all torque wrenches, jacks and other
equipment required to install and test the bolts.
S3-55
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(c) The Contractor shall submit to the S.O. for approval the details of
the bolts and fixtures, together with the proposed method of
installation and testing of the rock bolts.
(d) The holes for the rock bolts shall be drilled using rotary or rotary
percussive equipment.
(e) The diameter of the drill hole shall be such as to permit free entry
of the rock bolt with any required protection.
The diameter of the hole shall also be compatible with the grout,
and if appropriate the rock bolt manufacturer's recommendation
for the drill hole diameter.
(f) The completed drill hole shall be cleared of all drill cuttings using a
high pressure air and water jet, which shall be inserted to the
bottom of the hole and withdrawn slowly as often as necessary
until the drill hole is deemed to be.
For drill holes inclined downward into the rock, the hole shall be
cleaned and the water removed immediately prior to the
installation of the rock bolt.
S3-56
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(g) The rock bolt shall be fitted and centrally located by means of
spacers to ensure that the bolt is centred in the hole over the fixed
and free anchorage lengths.
The spacers shall be of a form which permits the free flow of grout
and minimizes potential debonding at the grout/bolt interface in
the fixed anchorage length.
(h) The installation procedure of the rock bolt shall be such that all
voids within the drill hole are filled with grout for corrosion
protection purposes.
The annulus around the installed rock bolt after centering the bolt
in the drill hole shall be filled with cement grout injected under
pressure through a plastic tube extending to the base of the drill
hole to ensure that all air and water is displaced by the grout. An
air-bleed tube shall be provided for the grouting of the annulus
around the rock bolt.
(i) Water Tightness Tests shall be carried out in drill holes prior to
the installation of rock bolts, to determine the likelihood of grout
loss along the fixed anchorage length.
(j) Bearing plates or anchor plates for rock bolts shall be seated
either on an epoxy or cement mortar bed, which shall be prepared
after the rock surface has been trimmed and cleaned to a plane
normal to the bolt axis.
(k) The rock bolts shall be stressed to the design ultimate load.
S3-57
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
2
has attained strength of 25N/mm as demonstrated by
compression tests on cube samples of the grout.
(m) After the Acceptance Test has been carried out and the installed
rock bolt is accepted, the concrete cap to the bolt shall be cast
and the bolt shall be designated by a unique number permanently
marked into the cap.
(n) The Contractor shall submit to the S.O. a full report on each rock
bolt. This shall include details of the bolt, its installation, and the
results of all tests required under this Clause.
(o) The Contractor shall install trial rock bolts and carry out Pull Out
Tests and Proving Tests prior to installation of any permanent rock
bolts.
These Pull Out Tests and Proving Tests shall demonstrate that
the Contractor's equipment and proposed method of working are
consistent with the requirements of this Clause, especially in
respect of the method of installation, determination of the
anchorage length, and attaining the required working load for the
rock bolt.
The trial rock bolts for the Pull Out Test shall be tested to
destruction and the mode of failure recorded.
The trial rock bolts for the Proving Tests shall be proof loaded to
1.5 times the design working load prior to lock-off at the working
S3-58
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
load. The Proving Tests shall be carried out after the rock bolt Pull
Out Tests, and shall be similar in nature to the Acceptance Test.
ii. The test load Pt shall equal 1.5 Pw. The bolt shall be
loaded incrementally to Pt and the deformation measured
at loads of Po (datum), 0.5 Pw, 0.8 Pw and Pt.
iii. Upon reaching load Pt the load shall be held constant while
the change in deformation is observed over the following
time intervals (et = elastic extension under load Pt - Po) :
S3-59
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
iv. The bolt shall be unloaded in steps to the datum load Po,
the deformation being measured at the intermediate loads
given above and at load Po.
v. The lock-off load Pl shall equal 1.1 Pw. The bolt shall be
reloaded from Po to P1, the deformation recorded at load
P1 and the bolt locked off.
(q) Water Tightness Tests shall be carried out in drill holes prior to the
installation of rock bolts, to determine the likelihood of grout loss
around the fixed anchorage length.
S3-60
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
Should the fixed anchorage length fail the test, the fixed
anchorage length shall be waterproofed by preliminary grouting,
redrilled, and another Water Tightness Test carried out. This
procedure shall be repeated until the water loss is within the
specified limit of 50 litres.
A full record of the Water Tightness Tests and any grouting and
redrilling shall be kept and forwarded to the S.O. prior to bolt
installation, in a format approved by the S.O..
3.25.6 Buttresses
S3-61
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(b) The Contractor shall remove all vegetation from joints, and the
joints shall be sealed with a 1:2 cement/ sand mortar.
(a) The plant used for sprayed concrete shall be of the dry mix
delivery type with water added at the nozzle, and shall be
S3-62
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(b) Before sprayed concrete is used, the Contractor shall submit his
mix design for approval, and shall demonstrate the process that
he will use by spraying trial panels to prove the suitability of the
plant, the materials and the operators to be used. The trial panels
shall consist of two types:
Cores cut from trial panels shall be used to determine the density
that can be achieved and the tolerance within which the density
can be maintained. Tests shall be made to determine the average
percentage of rebound for concrete of various thicknesses. The
results of the rebound tests shall be used in calculations of the
cement content of the applied concrete. The Contractor shall
provide two copies of the results of all tests to the S.O. Once the
trial panels have been approved, the Contractor shall not alter the
mix or means of application without the S.O.'s written consent.
(d) All materials used shall comply with and shall be stored tested and
used in accordance with the provisions of the relevant Clauses in
the Specifications. The Contractor shall ensure that a sufficient
S3-63
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(e) The moisture content of the mix before use shall not exceed 10%,
the remaining water being added at the instant of application. The
air and water supply, the rate of application, and all other factors
affecting the quality of the work shall be adjusted by the operator
so as to produce dense concrete with no sloughing. No mix shall
be used more than two hours after any water has been added to
it. Rebound material shall not be reused and shall be removed
within 8 hours of spraying.
(g) 50mm diameter drainage holes shall be formed with PVC pipes at
2 metre centres in each direction.
S3-64
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
Six cores shall be cut from each panel, three of which shall be
crushed at 7 days and three at 28 days. Cores shall not be taken
within 125mm of the edges of the panel. Prior to crushing the
density of each core shall be measured. The minimum equivalent
cube strengths of the cores shall be:
at 7 days - 10 MPa
at 28 days - 20 MPa.
S3-65
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(b) The protective screen shall be of the chain-link steel net type, and
shall not be subject to unravelling when individual links are
broken.
(c) The protective screen shall generally be fixed over the final rock
face in the following manner:
i. Drill 50mm diameter holes in the rock along the top of the
rock face at 1000mm centres to 1500mm depth.
S3-66
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
vii. Rock bolts are to be used to tie down bottom and side
edges and general areas. Line wires in vertical joints are to
pass under the anchor plates.
(a) This work shall consist of drilling drain holes into rock slopes shall
include installing small diameter perforated pipes wrapped in filter
fabric in the drain holes.
(b) The drain holes shall be drilled at an upward angle into the rock
slope using casing to support the hole, unless otherwise agreed
by the S.O..
(c) The drain holes shall be lined with 75mm diameter perforated
uPVC pipes, or perforated steel pipes wrapped in geotextile filter
fabric to Clause 23.3 of the Specification. Perforated steel pipes
shall have a bituminous coating inside and out. The casing where
S3-67
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
The Contractor shall cut back or gouge out weak zones from rock joints.
The resulting voids shall be filled with Class 25/20 concrete to the
agreement of the S.O..
(a) Grout used in connection with rock bolts and dowels shall comply
with the following requirements:
S3-68
Revised on 30 Sept. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
iv. The cube strength of the grout shall not be less than
2
30N/mm at 28 days.
v. The water for mixing shall not contain oil, organic matter,
or other substances harmful to cement grout, and shall be
in accordance with Appendix A of BS 3148.
S3-69
Revised on 30 Sept. 2011