Materials Quantity Material Cost Labor Cost Project Cost

Drywall
1. 6mm Shera Fiber 90 pcs 76,500 45,900 122,400
Cement Board
2. Metal Stud, Tracks. 145 pcs 17,400 10,440 27,840
Furring
3. Consumables 1 lot 7000 7000
(Cutting Disc, Blind
Rivets, Screws)
Subtotal: 157,240
Ceiling
1. Metal Furring 400 pcs 54,000 32,400
2. Wall Angle 68 pcs 6,460 3,876
3. Carrying Channel 200 Pcs 21,600 12,960
4. Consumables 1 lot 12,000 12,000
(Screws, w clip rod)
Subtotal: 143,296
Floor
a. 50 x 50 cm floor 745 pcs 77,400 46,440 123,840
Carpet (BPO Used
but good as new)
1. Consumables 7 gallons 9940 5,964 9,940
(Adhesive)
b. Polishing of
Cement Floor
1. Cement 20 bags 5000 3,000 8000
2. Concrete Sealer 10 gallons 9000 5,400 14,400
3. Consumables 1 lot 10,000 6,000 16,000
(Poloshing Disc,
Thinner Agent)
Subtotal: 178,144
Painting Works
1. Skim Coat (Super 35 bags 21,000 12,600 33,600
Fine)
2. Flat Latex White 8 pails 28,000 16,800 44,800
3. Semi Gloss White 6 pails 24,000 14,400 38,400
4. Consumables 1 lot 18,000 10,800 28,800
Subtotal: 145,600
Electrical
Relocation of 1 LOT 40,000
Lights and New
Installation of
Roughing Ins
Subtotal: 40,000
Mobilization, Deliveries, Overhead Supervision and Staging
1. Mobilization 1 LOT 10,0000 10,000
2. Scaffolds, Lumbers, 1 LOT 15,000 15,000
GI Pipes Erection
3. Overhead 1 LOT 25,000 25,000
Supervision
5. Deliveries 1 LOT 5000 5000
Subtotal: 55,000
Grand Total: 719,280
****Notes: Quotation is valid 7 days upon receipt****

Hoping to be your Design and Build Partner soon.

Thank you so much for your business

Sincerely,

___________________________________