Cement
S.No Description Unit Qty Sand (Cft) Crush (Cft) Bricks (No.) Steel (Ton)
(Bags)
3 P.C.C and R.C.C (1:2:4) with 1% steel Cft 100.00 17.600 44.00 88.00 0.222
6 RCC Slab 5" thick(1:2:4) with 1% steel Sft 100 7.33 18.33 36.66 92.6 Kg
D Misc.
25 Bitumen