Measurement Bill No.

02 - Works executed from 1st July 22 to 30th Sep 22 | Date - 1st Oct 22
BIM Services - Techture
Upto Date Status Upto Previous Staus This Bill Status
ITEM ITEM DESCRIPTION UNIT QTY. RATE
Completion Amount Completion Amount Completion Amount

Development of BIM Execution Plan


1 (BEP) based on Owner's BIM Manual and Sum 1 100,000
setting up project as per specifications

A Submission 30% 30,000 30.00% 30,000.00 30.00% 30,000.00 0.00% -


B Approval 30% 30,000 30.00% 30,000.00 30.00% 30,000.00 0.00% -
C Progress 40% 40,000 40.00% 40,000.00 40.00% 40,000.00 0.00% -

Site Topography Model - Incorporating


2 outputs of drone scan and GRP for Sum 1 200,000
project boundary. Exclusive of one-time
laser scan and GPR for project boundary

A Submission 30% 60,000 30.00% 60,000.00 30.00% 60,000.00 0.00% -


B Approval 30% 60,000 30.00% 60,000.00 30.00% 60,000.00 0.00% -
C Progress 40% 80,000 40.00% 80,000.00 40.00% 80,000.00 0.00% -

Drone based 3D mesh creation for


3 project Right of Way to map existing Sum 1 400,000
conditions over ground
A Submission 30% 120,000 30.00% 120,000.00 30.00% 120,000.00 0.00% -
B Approval 30% 120,000 30.00% 120,000.00 30.00% 120,000.00 0.00% -
C Progress 40% 160,000 40.00% 160,000.00 40.00% 160,000.00 0.00% -

Ground Penetrating Radar (GPR) Survey


4 up to the required depth to identify Km 18.1 80,000
utilities and obstructions below ground
within project boundary

A Submission 30% 434,400 26.52% 384,000.00 26.52% 384,000.00 0.00% -


B Approval 30% 434,400 26.52% 384,000.00 26.52% 384,000.00 0.00% -
C Progress 40% 579,200 35.36% 512,000.00 35.36% 512,000.00 0.00% -

LOD 300 BIM Model - for Architecture,


Civil and MEP.
5 Inclusive of Clash Detection and Services
Coordination
Sabarmati Station
Architectural Model as per Tender
Drawings on Submission Sum 1 1,040,000 100.00% 1,040,000.00 50.00% 520,000.00 50.00% 520,000.00

Structural Model as per Tender Drawings Sum 1 520,000 100.00% 520,000.00 100.00% 520,000.00 0.00% -
5A on Submission
MEP Model as per Tender Drawings on
Submission Sum 1 520,000 0.00% - 0.00% - 0.00% -

Coordinated Model as per Tender


Drawings on Submission Sum 1 520,000 0.00% - 0.00% - 0.00% -

Ahmedabad Station
Architectural Model as per Tender
Drawings on Submission Sum 1 880,000 100.00% 880,000.00 50.00% 440,000.00 50.00% 440,000.00

Structural Model as per Tender Drawings


on Submission Sum 1 440,000 100.00% 440,000.00 100.00% 440,000.00 0.00% -
5B
MEP Model as per Tender Drawings on Sum 1 440,000 0.00% - 0.00% - 0.00% -
Submission
Coordinated Model as per Tender
Drawings on Submission Sum 1 440,000 0.00% - 0.00% - 0.00% -

Creation of LOD 300 BIM Model for


6 viaduct portion as per tender drawings Sum 1 1,000,000

A Submission 70% 700,000 85.00% 595,000.00 75.00% 525,000.00 10.00% 70,000.00


B Approval 30% 300,000 85.00% 255,000.00 75.00% 225,000.00 10.00% 30,000.00

Extraction of Detailed Design drawings –


7 Civil and Arch
Upto 200 sheets Nos. 1 300,000 0.00% 0.00% 0.00% 0.00% 0.00% -

Extra Sheets Nos. 1 4,000 per sheet


(Rate Only)

Execution Stage Updates


Construction stage updates in BIM
Model
Updating the model at the execution
stage as per site changes. Inclusive of
8 Clash Detection and Coordination,
incorporation of RFIs, Site Instructions,
Engineers Instructions etc. and support
in the project construction duration for
required updates.

For 34 Months from July 22 - 7th Month


- Rs. 88,235 per month Nos. 1 3,000,000 8.82% 264,705.00 0.00% - 8.82% 264,705.00

9 Creation of Reinforcement Model


A Sabarmati Station Sum 1 800,000
Submission 400,000 5.00% 20,000.00 0.00% - 5.00% 20,000.00
Approval 400,000 0.00% - 0.00% - 0.00% -
B Ahmedabad Station Sum 1 600,000
Submission 300,000 10.00% 30,000.00 0.00% - 10.00% 30,000.00
Approval 300,000 0.00% - 0.00% - 0.00% -
C Viaduct Portion Sum 1 600,000
Submission 300,000 20.00% 60,000.00 0.00% - 20.00% 60,000.00
Approval 300,000 0.00% - 0.00% - 0.00% -
Extraction of Detailed Design drawings – 4,500 per sheet
10 Reinf Nos. 1 (Rate Only)
Submission 60% 2,700
Approval 40% 1,800

11 As-built model Sum 1 180,000


A Submission 90,000 0.00% - 0.00% - 0.00% -
B Approval 90,000 0.00% - 0.00% - 0.00% -

12 Asset Data Incorporation Sum 1 120,000


On Completion 120,000 0.00% - 0.00% - 0.00% -

1,000 per sheet


13 Generation of As-built sheets Nos. 1 (Rate only)

14 Deployment of Site BIM Coordinator (1 Nos. Per 120,000 4.84 580,800.00 2.23 267,600.00 2.61 313,200.00
No.) Month

Deployment of Site BIM Engineer (2.


15 Nos.-Arch Nos. Per 90,000 6.19 557,100.00 3.25 292,500.00 2.94 264,600.00
Month
& MEP)

16 BIM based Quantity Estimation and Sum 1 500,000


BOQs
A Submission as per Tender Set 250,000 80.00% 200,000.00 0.00% - 80.00% 200,000.00
B Submission as per GFC Set 250,000 0.00% - 0.00% - 0.00% -

Generation of Planned 4D Simulation


17 and subsequent updating of Planned vs. Sum 1 1,000,000
Actual 4D simulation
A Submission 60% 600,000 70.00% 420,000.00 0.00% - 70.00% 420,000.00
B Approval 40% 400,000 0.00% - 0.00% - 0.00% -

Addition of cost-based S-Curves for


18 major construction elements like Sum 1 450,000
concrete, reinforcement, brickwork etc.

A Submission 225,000 0.00% - 0.00% - 0.00% -


B Approval 225,000 0.00% - 0.00% - 0.00% -

Generation of Progress Dashboards


19 based on information received from Sum 1 450,000
client's planning team
A Submission 225,000 0.00% - 0.00% - 0.00% -
B Approval 225,000 0.00% - 0.00% - 0.00% -
Total INR 15,948,000 7,842,605.00 5,210,100.00 2,632,505.00
Remark

100% Complete. Report Attached

100% Complete. Report Attached

100% Complete. Report Attached

16 km of 18.1 km complete

100% Complete. Report Attached

100% Complete. Report Attached

100% Complete. Report Attached

100% Complete. Report Attached

85% Complete. Report Attached


85% Complete. Report Attached

Rs. 88235 for 3 Months - July 22, Aug 22


and Sep 22

5% Complete. Report Attached

10% Complete. Report Attached

20% Complete. Report Attached


1st to 31st July 22 - 0.87 Month
1st to 31st Aug 22 - 0.94 Month
1st to 30th Sep 22 - 0.80 Month
Abhay Malik - Timesheet Attached

1st to 31st July 22 - 0.94 Month


1st to 31st Aug 22 - 1 Month
1st to 30th Sep 22 - 1 Month
Rutwik Patel - Timesheet Attached

80% Complete. Report Attached

70% Complete. Report Attached