QUOTATION

Project : Supply & Install of Partition Wall & Ceiling at Flavor & Packaging Area Date : December 14, 2021
Location : #9001 GP Dr. Natividad St., Ibayo-Tipas, Taguig City Owner : Regent Foods Corp

SCOPE OF WORKS QTY UNIT PRICE REMARKS


I. Detail Design of Partition Wall 1 Lot ₱0.00 FREE
1.0 Design of Wall Footing
2.0 Design of Lintel Beam
3.0 Design of Wall Partition & Ceiling

II. Footing 37.2 cu.m ₱467,530


1.0 Excavation
2.0 Rebar Works
3.0 Concreting

III. CHB Wall Partition 705.6 sq.m ₱391,344


a. CHB LAYING 1.20m Ht.
1.0 CHB 5"
2.0 Reinforced Steel Bar Ø10mm Grade 33
3.0 Cement
4.0 Sand
5.0 GI wire #16
b. PLASTERING WORKS
1.0 Cement
2.0 Sand
c. Lintel Beam
1.0 Cement
2.0 Sand

IV Dry Wall Partition 637.92 sq.m ₱879,264


1.0 3" x 3" Square Tube
2.0 Metal Tracks & Studs
3.0 Ficem Board 4.5mm thk.
4.0 Blind Rivet & Metal Screw
5.0 Mesh Tape
6.0 Boral Jointing Compound
7.0 Concrete Nail 1"

V. Ceiling Works 552.25 sq.m ₱690,313


1.0 Carrying Channel
2.0 Wall Angle
3.0 Metall Furring
4.0 Ficem Board 3.5mm thk.
5.0 Blind Rivet & Metal Screw
6.0 Mesh Tape

VI. Painting Works 2175.29 sq.m ₱978,881


1.0 Partition Wall
2.0 Ceiling

TOTAL ₱3,407,331
12% VAT ₱408,880
TOTAL CONTRACT PRICE ₱3,816,210

Term of Payment 30% Down Payment, 70% Progress Billing


Validity Offer This expires 30 days from the date hereof and subject for confirmation afterwards
Warranty One year Warranty
Duration 40 Working Days

Prepared By:
ALVIN L. CALUSA
Contractor