LIFTING PLAN CHECKLIST AND METHOD STATEMENT

(MOBILE CRANES)

FOR

UPLIFTING AND REMOVAL OF 4 X 23000 LITER AND


1 X46000 LITER TANKS
Site or Contract: Managed or Contract lift:

Task description: Installation of 4x 23000-liter and 1x 46000-liter tanks

Date planned for lift:

SECTION A: PRE-PLANNING

1. The load to be lifted. 3x 46000 liter Underground Storage Tank


Size 1x 23000 liter Underground Storage Tank
Shape All tanks have lifting hooks.
Lifting eyes, lifting points The tanks are cylindrical in shape with a manhole
Centre of gravity and stability located in the center of the tank, and no shift in the
center of gravity is expected during the lifting operation
Location.

2. Access route for crane and space The crane shall be parked inside the redzone at the
available at planned operating stockpile area
position.
3. Crane position before, during and (See sketch plan on the following page)
after the lift.
4. Maximum load to be lifted in tons. 5 Tons

5. Lifting accessories and attachments. Crane Hook and Lifting chains/slings all weigh 0,2 tons
Specify their weight if not included
above.
6. Expected operating radius in meters. 16m maximum operating radius

7. Lift height required, in meters. 8m maximum lifting height

8. Presence of overhead cables and None


other hazards that could affect the
lifting operation.
9. Ground conditions - foundations, The ground has a high water table which has, overtime,
made-up ground, impact loading, affected the stability of the soil
etc.
10. Crane configuration and (See sketch plan on the following page)
arrangements for erection and
dismantling
11. Crane to be used and configuration A Tadano Faun 70 ton mobile crane shall be used to
execute the lifting.

12. Maximum permissible motion


speeds, acceleration, and N/A
deceleration
13. Other factors considered. Coordination of loading times to be firmed up with
McDonalds.

14. Exclusion Zone The Tank farm will be barricaded and treated as an
exclusion zone during the lifting operation. And only the
certified riggers and operators will have access.

Sketch plan.

Site access for trucks and position of crane before, during the lifting operation.

Completed by: on date


SECTION B: CRANE ON SITE
To be completed by the appointed person in control of the lifting operation before the lift begins.

Crane Details

Make and Model: Tadano Faun ATS70 -4 Size: 70 ton

Identification No: TBA

Hire Company:

SWL Indicator Functional?

Weekly Inspection Book in Cab?


Is the crane of the correct size and type?
Driver, Operator Details
Certificate no:
Crane Position
Adequate and suitable base? All outriggers fully extended?
Adequate packing under
Position of outriggers satisfactory?
outriggers?
Lifting Gear
Endless Round Sling -
Type Shackles - Identification No
Crane Hook -
SWL 11,52 tons Test Certificate in place No
Visual Check
(i.e., general condition)
Can the lift proceed in safety?
Comments;

Completed by on-
SECTION C: METHOD STATEMENT & AUTHORISATION OF LIFTING
OPERATION

Task to be carried out. Installation of underground storage tanks


Where the work is expected to take
more than a day specify the
N/A
configuration of the crane at the end
of each day’s work.

Explain the control measures


required to eliminate or minimize Refer to the Attached scope of Work and Excavation Plan
risk to those involved.

Explain the steps required to


eliminate risk to other people e.g., Refer to the attached Traffic Control Plan
road closures and segregation zones.

Crane – Competencies, Load Certificates, Outriggers


operational, Disk is current, no oil leaks on the vehicle.
Site - Ensure sufficient space for parking, lifting, and
loading. No overhead services or structures. No
Pre work checks of crane, site, and
underground services that are affected by the plant.
load.
Load – Check that lifting hooks are sound. Ensure that the
tanks are empty of all product/liquid. Ensure that measures
to control fumes are in place.

Task allocation to named people;


 Appointed person in control
of lifting operation.
 Crane supervisor.
 Crane operator.
 Slingers – signalers.
 Others
Confirmation of load details; weight,
5,5m x 2.55m; 5 tons
dimensions, CoG.
Lifting points and lifting method - Lifting Points are the tank hooks.
including accessories to be used and - Mobile crane shall be used for lifting the tanks.
their configuration. - Accessories to be used for the lifting are shackles,
slings and crane hooks.
The tanks are supplied with tank hooks, Tanks are fitted
Pickup and landing points
with speed frames as landing points.
Height and radius of lift 8m, 16m
Model and configuration of crane. Tadano Faun ATS70 -4
Configuration of outriggers and The crane is supplied with 4 outriggers, 2 in the front and 2
ground supports in the back.

Overhead and underground hazards None Identified

Sequence of lifting operations  Establish site (Deliver Crane and all components).
 Park the delivery truck in the lifting zone.
 Ensure that all pre-lifting checks (Safety and
technical are performed).
 Install correct sling, tackles and hooks as required.
 Connect the hooks to the lifting eyes of the tank.
 Ensure clear communication between the rigging
team and the crane operator.
 Issue instruction to lift.
 Lift tank off delivery truck and set it in the
appropriate position in the tank pit.
Control measures to eliminate or
minimize risk. Permit and Work Clearance form will be prepared on the
day of the lift.

Environmental limitations – wind The lift will take place in the month of Sept. The lifting
speed, sea state etc. operation shall consider the effect of wind during the lift.

Access to attach and remove slings Steps shall be built into the excavation to allow for safe
and lifting accessories. access into the excavation by personnel.
- Ensure that that tanks are emptied of all water,
- Ensure that all chains/slings are of equal length.
Measures to ensure that the load - Ensure that all chains/slings are equal strength.
remains stable once slings and - Ensure that all necessary load certificates are in
attachments have been removed. place.
- Operators and riggers shall consider the wind speed
and direction when lifting.
Work in the excavation shall be treated as working at
Arrangements for working at height heights. Riggers shall have working at heights training and
and rescue plans – if applicable. fall arrest systems shall be used while working in the
excavation.
Method of communication e.g., hand Radio and Hand Signals shall be used for communication
signals, radio, etc. between the riggers and crane operators.

PROVISION OF AUTHORITY -
Authorisation commences

Authorisation issued by
Name
Signature

The person giving this authorisation confirms that the operator, slingers, signalers, supervisors and
others involved in this lifting operation have taken part in a team briefing at which this method
statement was explained and they were given all necessary information and made aware of
specific hazards i.e. position of load, loads to be lifted, any excavation, soft ground, overhead
cables, etc.

Accepted by Crane Driver


Name

Signature

THIS AUTHORISATION IS VALID UNTIL -