Equipment Deployment Schedule
:T2102070100
Client : OQ Refinery Rev : 0
Location : Sohar DATE : 5 APRIL 2021
TOTAL
SR. DESCRIPTION PEAK M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16
MM
Jul-21 Aug-21 Sep-21 Oct-21 Nov-21 Dec-21 Jan-22 Feb-22 Mar-22 Apr-22 May-22 Jun-22 Jul-22 Aug-22 Sep-22 Oct-22
1
A TRANSPORT & EQUIPMENT (TOCO)
1 TRANSPORT & GENERAL 1 1
SALOON CAR 1 12 1 1 1 1 1 1 1 1 1 1 1 1 1 1
PICK-UP 2 12 1 1 1 2 2 2 2 1
BUS 25 SEATER 2 12 1 1 1 2 2 2 2 1
BUS 66 SEATER 2 12 1 1 1 2 2 2 2 1
CANTER - 3T- DOUBLE CABIN W/HAIB 1 8 1 1 1 1 1 1 1 1
2 EQUIPMENT WORKS 1 1
AIR COMPRESSOR 300 ~ 450 CFM 1 1 1
FORKLIFTER 5 TON 1 1 1
CRANE 50 TON 1 1 1
CRANE 450 TONS 1 0.5 1
4 E&I WORKS 1
MANLIFT 1 1.0 1
TOTAL TRANSPORT & EQUIPMENT (TOCO) 127 1 1 1 1 1 1 9 11 11 19 22 21 16 10 1
B TRANSPORT & EQUIPMENT - SUBCONTRACTORS
1
1 SCAFFOLDING/PAINTING 1 1
CANTER - 3T- DOUBLE CABIN W/HAIB 1 2 1 1
AIR COMPRESSOR 350 CFM 1 2 1 1
200 LTR BLASTING POT / POWER GUN 1 2 1 1
AIRLEES SPRAY MACHINE/CONVENTIONAL SPRAY GUN 1 2 1 1
TOTAL
SR. DESCRIPTION PEAK M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16
MM
Jul-21 Aug-21 Sep-21 Oct-21 Nov-21 Dec-21 Jan-22 Feb-22 Mar-22 Apr-22 May-22 Jun-22 Jul-22 Aug-22 Sep-22 Oct-22
TOTAL TRANSPORT & EQUIPMENT- SUBCONTRACTORS 27 5 6 7 4 4