Project Name : EPCC Contract for Processing of Sludge from WWTP in DCU at SR2 TOCO Reference No.

:T2102070100
Client : OQ Refinery Rev : 0
Location : Sohar DATE : 5 APRIL 2021

EQUIPMENT DEPLOYMENT SCHEDULE

TOTAL
SR. DESCRIPTION PEAK M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16
MM
Jul-21 Aug-21 Sep-21 Oct-21 Nov-21 Dec-21 Jan-22 Feb-22 Mar-22 Apr-22 May-22 Jun-22 Jul-22 Aug-22 Sep-22 Oct-22

1
A TRANSPORT & EQUIPMENT (TOCO)
1 TRANSPORT & GENERAL 1 1
SALOON CAR 1 12 1 1 1 1 1 1 1 1 1 1 1 1 1 1
PICK-UP 2 12 1 1 1 2 2 2 2 1
BUS 25 SEATER 2 12 1 1 1 2 2 2 2 1
BUS 66 SEATER 2 12 1 1 1 2 2 2 2 1
CANTER - 3T- DOUBLE CABIN W/HAIB 1 8 1 1 1 1 1 1 1 1

2 EQUIPMENT WORKS 1 1
AIR COMPRESSOR 300 ~ 450 CFM 1 1 1
FORKLIFTER 5 TON 1 1 1
CRANE 50 TON 1 1 1
CRANE 450 TONS 1 0.5 1

3 PIPING WORKS (FAB & ERECTION) 1 1


AIR COMPRESSOR 300 ~ 450 CFM 2 11.0 1 1 1 2 2 1 1 1 1
TRAILER FLAT BED 40 FT 1 4.8 0.3 0.3 0.3 1 1 1 1
WELDING GENERATOR DIESEL 400 AMP 6 30.0 2 4 4 6 6 4 2 2
POWER GENERATOR 50 KVA 1 5.0 1 1 1 1 1
WINCH WITH PULLEY & MAN BASKET 2 4.0 2 2
CRANE 30 TON 1 8.0 1 1 1 1 1 1 1 1
WATER TANKER 1 1.0 1
VACCUM TANKER 1 1.0 1

4 E&I WORKS 1
MANLIFT 1 1.0 1
TOTAL TRANSPORT & EQUIPMENT (TOCO) 127 1 1 1 1 1 1 9 11 11 19 22 21 16 10 1
B TRANSPORT & EQUIPMENT - SUBCONTRACTORS
1

1 SCAFFOLDING/PAINTING 1 1
CANTER - 3T- DOUBLE CABIN W/HAIB 1 2 1 1
AIR COMPRESSOR 350 CFM 1 2 1 1
200 LTR BLASTING POT / POWER GUN 1 2 1 1
AIRLEES SPRAY MACHINE/CONVENTIONAL SPRAY GUN 1 2 1 1

2 CIVIL & STUCTURAL WORKS 1 1


Crane 30 Tons 1 3 1 1 1
Tipper-18m³ 1 3 1 1 1
Shovel 1 3 1 1 1
Plate compactor 1 1 1
Concrete Mixer 1 3 1 1 1
BOOM TRUCK 1 3 1 1 1
TRAILER 1 2 1 1
Project Name : EPCC Contract for Processing of Sludge from WWTP in DCU at SR2 TOCO Reference No. :T2102070100
Client : OQ Refinery Rev : 0
Location : Sohar DATE : 5 APRIL 2021

EQUIPMENT DEPLOYMENT SCHEDULE

TOTAL
SR. DESCRIPTION PEAK M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16
MM
Jul-21 Aug-21 Sep-21 Oct-21 Nov-21 Dec-21 Jan-22 Feb-22 Mar-22 Apr-22 May-22 Jun-22 Jul-22 Aug-22 Sep-22 Oct-22
TOTAL TRANSPORT & EQUIPMENT- SUBCONTRACTORS 27 5 6 7 4 4

TOTAL "A + B" = 154 1 1 1 1 1 1 14 17 18 19 22 21 20 14 1