Contents
1. Work Safety Instruction ......................................................................................................................................4
WARNING!!
Please read the safety instructions before installing,
using or maintaining the solar power plant system.
❖ All personnel are required to wear Personal Protective Equipment (PPE) when carrying
out operations and maintenance work
❖ The system contains sophisticated electronic equipment and must be installed and
maintained by qualified and experienced electricians. Every question about the system
must be referred to the supplier of goods.
❖ Every maintenance and installation of the system must refer to national or
international electricity regulations.
❖ All precautions relating to the installation and operation of electrical voltage equipment
must be observed when installing the system. These include considerations for cable
insulation, access to bare conductors, grounding, and protection from moisture.
❖ Do not operate the equipment or system if the lid and inverter are still open.
❖ After the system has been turned off the possibility of an electric current is still present
in the inverter, therefore make sure that all equipment has been disconnected from the
electrical connection.
❖ Do not operate inverters and electrical panels under ambient conditions that are not
recommended.
❖ Do not expose the inverter and all electrical panels to rain, snow, water spray or dust.
To reduce the risk of danger, do not install inverters and electrical panels close to water
leaks, and leave the panel rooms with sufficient air ventilation.
❖ To avoid the risk of fire and electric shock, ensure that the cables are in good condition
and accordance with the recommended size, do not operate the system if there are
damaged or out of standard cable sizes.
❖ This system contains elements that can cause sparks, to avoid fire or explosion do not
place flammable objects close to the panel.
JOB NO :
DOC NO : EPTI-OM-MS-01
METHOD STATEMENT
REV : 00
PAGE : 5 of 18
2. Scope of Work
Scope of Work and Schedule for this Preventive Maintenance work are stated in the Annex 1
and Annex 2 attached to PO and Master Agreement.
The checklist form has to be filled for reporting purpose, accompanied by documentation to
support the report. The checklist form is stated in Annex D on the Master Agreement.
3. PV Module Cleaning
Cleaning solar panels help ensure solar installations generate optimal electricity. Most solar
PV module have been designed for easy installation and minimal maintenance, however,
dust, pollen, leaves and other contaminants often find their way onto the panel and soil the
surface. To overcome this, solar PV module are manufactured so that normal and regular
levels of rainfall will clean them naturally if installed at a sufficient angle.
a b c
JOB NO :
DOC NO : EPTI-OM-MS-01
METHOD STATEMENT
REV : 00
PAGE : 6 of 18
a b
c d
e
JOB NO :
DOC NO : EPTI-OM-MS-01
METHOD STATEMENT
REV : 00
PAGE : 9 of 18
❖ Termographic Inspection
a. Make sure all personnel follow Working at Height instruction
b. Turn on the thermal camera to see if there are any hotspots
To turn on the camera, push and hold MENU button for 2 seconds. A start-up
screen shows on the display and an indicator bar shows the status, see Figure
below. The indication bar increases on power up and decreases on power down.
After the start-up screen, the Product is ready to use. To turn off the camera, push
and hold MENU button for 2 seconds. The Auto Off feature turns off the Product
after 10 minutes of inactivity.
f. Connect the MC4 probe of the PV tester to MC4 connector of the string
g. Press RPE and Auto button to turn on the PV Tester
h. Press VISO and select 1000V
i. Press Auto button and wait for the result
j. Press Save button to save the measurement result
Step 2 If the solar inverter is not shut down due to a fault, send a shutdown
command on the SUN2000 app, SmartLogger, or management system. If the
solar inverter has shut down due to a fault, go to the next step.
Step 3 Turn off the AC switch between the solar inverter and the power grid.
Step 4 Measure the DC current of each PV input string using a clamp meter that is set
to the DC position.
- If the current is less than or equal to 0.5 A, go to the next step.
- If the current is higher than 0.5 A, wait until the solar irradiance decreases and the
PV string current decreases below 0.5 A at night, and then go to the next step.
Step 5 Open the maintenance compartment door, install a support bar, and use a
multimeter to measure the voltage between the AC terminal block and the
ground. Ensure that the AC side of the solar inverter is disconnected.
Step 6 Turn off all DC input switches of the solar inverter.
❖ Annual Maintenance
a. All personnel have to wear standard PPE during the work period
b. Carry out all steps from quarterly maintenance
c. Check the earth pit resistance of entire plant
d. Fill out the relevant form
d. Take a picture for documentation and fill out the checklist form
❖ Quarterly Maintenance
a. All personnel have to wear standard PPE before doing the work
b. Carry out all steps from monthly maintenance procedure
c. Visually check the relay status and auxiliary supply status
d. Visually check all MCCB and Isolator terminal for any abnormality
e. Check LT Panel earthing connection
f. Clean LT panel with a dry microfiber cloth
g. Fill out the checklist form
JOB NO :
DOC NO : EPTI-OM-MS-01
METHOD STATEMENT
REV : 00
PAGE : 16 of 18
❖ Half-Yearly Maintenance
a. All personnel have to wear standard PPE before doing the work
b. Carry out all steps from quarterly maintenance procedure
c. Check MCCB operating mechanism and trip mechanism condition
d. Fill out the checklist form
❖ Annual Maintenance
a. All personnel have to wear standard PPE before doing the work
b. Carry out all steps from half-yearly maintenance procedure
c. Carry out torque check of all busbar joints
d. Carry out torque check of all the bolts in the panels
e. Check the ACB terminals push and trip and operating conditions
f. Check the flexible joint between bus bar and main terminal
g. Check connection conductors, main circuit terminals, and current carrying
parts for heat discoloration
h. Remove arc chamber and check it for foreign object or dust accumulation,
deformation, cracks, chips and other damage. If foreign matter or dust is
accumulated, use vacuum cleaner to remove foreign matter of dust and wipe
off with dry, clean cloth
i. Carry out energy meter calibration
j. VCB inspections and testing, relays and operations for relay mechanism etc.
k. Check SHT mounting screws for looseness. If loose, retighten
l. Fill out the checklist form
❖ FMC Hospital
Emergency Contact : 0251-8665-000