20SP-010-BA-6180-00005 - 01E - IFR - Method Statement For Interconnection - Code-3
20SP-010-BA-6180-00005 - 01E - IFR - Method Statement For Interconnection - Code-3
METHOD STATEMENT
FOR INTERCONNECTION
Rooftop Solar Project On-Grid
Project 800,06 KWp PT. Shell
Manufacturing Indonesia
Originating Company PT. Shell Manufacturing Indonesia
Method Statement for
Document Title Interconnection
Originator / Author BS
Next revision please change the cover page as standard from KOM reference
Please update based on Comment result, Resubmit to 02E Re-Issue For Review (IFR)
Digitally signed
by Rezki Al
Khairi
Date: 2022.06.21
20:43:21 +07'00'
1.1. Purpose
The purpose of this method statement is to describe the method of work in the installation of
solar PV in PT Shell LOBP Marunda.
1.2. Scope
Scope of work:
- Installation Pv Module rooftop new filling, staging
3. EQUIPMENT
Equipment will be used for this activity as below:
No Description Spec / Type Unit Quantity
1 Allen Key Set 1
2 Hand tools Set 1
3 Press Schoen Set 1
4 Cable Cutter Set 1
general comment :
follow5 comment
Megger Insulation
on Tester Set 1
others6 document
Clamp Meter Set 1
All Equipment and Tools Inspection should be done before mobilization to site,
certificate and function shall have valid certificate.
4. MANPOWER PLANNING
Manpower Planning proposed by Cleantech Solar (PT. Sedayu) for Interconnection in Shell LOBP
Marunda.
1. Ensure that all safety precautions and recommendations outlined in the risk assessments
have been applied
2. Make sure all personnel including third parties are safety inducted prior to site entry
3. Make sure operators are qualified, hold license for machine operation and trained in the
maintenance of machinery
4. Provide First Aid Facility on working site in case of minor injury treatment
5. Arrange for all personnel the pertinent Personal Protective Equipment (PPE) including
safety helmet, safety boots, ear/eye protector, dust mask, gloves and reflective vest.
6. Place warning signs, barricades, lighting or fences at relevant location such as excavation
location, crossing roads and crossing ditch, demolition areas
7. Arrange with the owners, subcontractor or third parties like U/G cables, pipe lines to make
secure to use.
8. Ensure safe access to the right way and maintain the permanent and temporary access
roads in a good condition during construction activities
9. Check, cover and secure all materials debris prior to its movements outside the site
10. Monitoring regularly by security team that no unauthorized person entry to construction
site.
11. Ambulance and first Aider shall be ready near the location.
12. All personnel have additional training regarding snake awareness and the first aid
13. Pest control will be screening area from bee, snake and controlled
14. Provide Competence certificate for working at height
8. SITE DISTURBANCE
1. Ensure that the site kept in tidy condition at all the times and that all the waste generated by
the works is cleared from the site to disposal area.
2. Do not burn combustible material arising from clearance on site without the written
consent.
3. Switch off all vehicle engines when not in use to minimize combustion emissions
4. Collect and disposed used chemicals and engine oils in appropriate containers, prohibiting
its discharge to land or surface waters