Chapter 3 Southwestern University
Chapter 3 Southwestern University
How
long is the project expected to take?
A B E F
I L
G H
C
D
K
J
Expected Time = (A+4M+B) / 6
A 30
B 60
C 55
D 65
E 30
F .1
G 30
H 20
I 30
J 10
K .1
L 30
2. What is the probability of finishing in 270 days?
Project Variance ((b- a)/6)^2
A 11.11
C 69.44
D 136.11
G 2.78
H 11.11
I 44.44
L 44.44
Total 319.43
This study source was downloaded by 100000807919769 from CourseHero.com on 09-17-2022 06:38:59 GMT -05:00
https://www.coursehero.com/file/42046654/Chapter-3-Southwestern-University-docx/
Z= (270-260)/ 17.8726= .5595
Probability = 71.21%
3. If it is necessary to crash to 250 or 240 days, how would Hill do so, and at what costs?