Western Region MIS 28-09-2022

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 6

Total LED Lights

Sl. No. Phase ULB Name Vendor Installation till now

1 Phase-IV Ladnun Florida 3790


2 Phase-IV Merta City Eon 4631
3 Phase-IV Baggar HQ Lamp 1676
4 Phase-IV Surajgarh HQ Lamp 1754
5 Phase-IV Chirawa Florida 2693
6 Phase-IV Deshnok Surya Roshni 954
7 Phase-IV Nokha Surya Roshni 5854
8 Phase-IV Mundwa Eon 1581
9 Phase-IV Degana Florida 2074
10 Phase-IV Udaipurwati HQ Lamp 3034
11 Phase-IV Parbatsar Florida 1504
12 Phase-IV Mukundgarh HQ Lamp 1688
13 Phase-IV Khetri Florida 977
15 Phase-IV Kuchera Eon 1774
16 Phase-IV Nawa Florida 1916
SLNP, Rajasthan - Daily LED M
LED Complaints Status As O

Total Total Complaint Today


Total Rectified Rectified
Complaint till Complaint till ULB & Vendor Total Today
now EESL CHS Night
now Register/ Portal Patrolling Complaint
Tollfree Today
3460 3365 0 0 0 0 0
4724 4591 0 0 2 2 2
4060 4043 0 0 5 5 5
3522 3517 0 0 5 5 6
4151 4085 0 0 10 10 4
3214 3214 0 0 0 0 0
8281 8274 0 0 7 7 9
2235 2179 0 0 4 4 0
3953 3752 0 0 3 3 0
6369 6352 2 0 5 7 6
1720 1706 0 0 2 2 4
4462 4446 0 0 7 7 7
1099 1074 0 0 0 0 0
2258 2157 0 0 12 12 0
1692 1565 0 0 0 0 3
jasthan - Daily LED Maintenance Report
omplaints Status As On:- 28-Sep-2022

Pending Pending
Complaints Complaints Rectified complaints complaints Total Pending
Rectified in Less in More than 48 (Less than 48 (more than 48 Complaints
than 48 hours hours
hours) hours)

0 0 3 92 95
2 0 2 131 133
2 3 17 0 17
6 0 5 0 5
2 2 10 56 66
0 0 0 0 0
9 0 7 0 7
0 0 8 48 56
0 0 7 194 201
0 6 17 0 17
2 2 2 12 14
7 0 16 0 16
0 0 5 20 25
0 0 14 87 101
0 3 0 127 127
Complaints pending at
Reason of Pending Complaints ULB end (Not included in Reason of Pending
EESL Side total pending Complaints ULB Side
complaints)

Adequate stock not available 0


Adequate stock not available 28 Underground cable issue
Maintenance team working slow 0
0
Adequate stock not available 0
0
0
Adequate stock not available 0
Adequate stock not available 50 Line fault issue
Maintenance team working slow 0
Maintenance team working slow 0
13 infrastructure issue
Adequate stock not available 0
Adequate stock not available 12 infrastructure issue
Adequate stock not available 0
Maintenance
Team Deployed

1 team 95 0
1 team 133 0
1 team 17 0
1 team 5 0
1 team 66 0
1 team 0 0
3 team 7 0
1 team 56 0
1 team 201 0
1 team 17 0
1 team 14 0
1 team 16 0
1 team 25 0
1 team 101 0
1 team 127 0
2009
1309
0.651568

You might also like