Professional Documents
Culture Documents
10 Control Schedule
10 Control Schedule
Project Management
Monitoring, Tracking and
Control
Monitoring and controlling processes overview
▪ Monitoring and controlling processes:
➢ Track, review, and orchestrate the progress and performance of the
project
➢ Identify any areas in which changes to the plan are required
➢ Initiate the required changes to the plan
Time
Cost Schedule Control
▪ As shown in Figure A [next slide], by adding the actual
progress curve to the baseline curve, you can now see the
current status versus the planned status which shows the
actual progress curve to be below the planned curve.
▪ If this represented dollars, we may falsely conclude that the
project is running under budget; Projects rarely run
significantly under budget.
▪ A more common reason for the actual curve to be below the
baseline is that the activities that should have been done
and thus the dollars or person hours / day that were planned
to be expended have not been.
▪ The schedule variance is depicted in Figure B below.
Cost Schedule Control
Progress
Cost Variance
Update
Date
Time
Figure A
Cost Schedule Control
Progress
Schedule Variance
Cost Variance
Update
Date
Time
Figure B
Cost Schedule Control
▪ To determine whether there has really been a progress schedule
variance, you need some additional information.
▪ Cost schedule control (CSC) comprises three basic measurements:
➢ budgeted cost of work scheduled (BCWS),
➢ budgeted cost of work performed (BCWP),
➢ and actual cost of work performed (ACWP)
▪ These measurements result in two variance values, schedule variance
and cost variance.
▪ The following Figure is a graphical representation of the three
measurements
▪ The figure shows a single activity that has a five-day duration and a
budget of $500. The budget is prorated over the five days at an average
daily value of $100.
Cost Schedule Control
5 days 5 days
5 days
Progress
Schedule
Variance
Cost
ACWP Variance
Time
Cost Schedule Control
▪ The CSC (EVA) can also be used to predict the future
status of a project.
▪ From the previous figure, By cutting the BCWS curve at the
height from the horizontal axis, which has been achieved by
the BCWP, and then pasting this curve on to the end of the
BCWP curve, you can extrapolate the completion of the
project. Note that this is based on using the original
estimates for the remaining work to be completed. And
doing the same for the ACWP.
Cost Schedule Control
Progress Schedule
Variance
Cost
ACWP Variance
Time
Cost Schedule Control
▪ The three basic indicators yield one additional level of
analysis for us.
▪ Schedule performance index (SPI) and Cost
performance index (CPI) are a further refinement. They
are computed as follows:
» SPI = BCWP / BCWS
» CPI = BCWP / ACWP
Cost Schedule Control
▪ Schedule performance index. The schedule performance
index (SPI) is a measure of how close the project is to
performing work as it was actually scheduled.
▪ If we are ahead of schedule, BCWP will be greater than
BCWS, and therefore the SPI will be greater than 1. On the
other hand, an SPI below 1 would indicate that the work
performed was less than the work scheduled.
Cost Schedule Control
▪ Cost performance index. The cost performance index
(CPI) is a measure of how close the project is to spending
on the work performed to what was planned to have been
spent. If you are spending less on the work performed than
was budgeted, the CPI will be greater than 1. if not, and you
are spending more than was budgeted for the work
performed, then the CPI will be less than 1.
▪ Some managers may prefer this type of analysis. Any value
less than 1 is undesirable; any value over 1 is good.
Earned Value Analysis
To summarize
▪ 3 major components
➢ BCWS: Budgeted Cost of Work Scheduled
» Now called “Planned Value” (PV)
» “Yearned”
» How much work should be done?
➢ BCWP: Budgeted Cost of Work Performed
» Now called “earned value” (EV)
» “Earned”
» How much work is done?
» BCWS * % complete
➢ ACWP: Actual Cost of Work Performed
» Now called “Actual Cost” (AC)
» “Burned”
» How much did the work done cost?
Derived EVA Variances
▪ SV: Schedule Variance
➢ BCWP – BCWS
➢ Planned work vs. work completed
▪ CV: Cost Variance
➢ BCWP – ACWP
➢ Budgeted costs vs. actual costs
▪ Negatives are termed ‘unfavorable’
▪ Can be plotted on ‘spending curves’
➢ Cumulative cost (Y axis) vs. Time (X axis)
➢ Typically in an ‘S’ shape
▪ “What is the project status?”
➢ You can use variances to answer this
Derived EVA Ratios
▪ SPI: Schedule Performance Index
➢ BCWP / BCWS
▪ CPI: Cost Performance Index
➢ BCWP / ACWP
▪ Problems in project if either of these less than 1 (or 100%)
Earned Value Analysis
▪ Other Derived Values
➢ BAC: Budget At Completion
» Sum of all budgets (BCWS). Your original budget.
➢ EAC: Estimate At Completion
» Forecast total cost at completion
» EAC = ((BAC – BCWP)/CPI) + ACWP
» Unfinished work divided by CPI added to sunk cost
» If CPI < 1, EAC will be > BAC
➢ CR: Critical Ratio
» SPI x CPI
» CR = 1: everything on track
» CR > .9 and CR < 1.2 ok
» Can be charted
Earned Value Analysis
▪ BCWS
➢ Use ‘loaded labor’ rates if possible
» Direct pay + overhead
▪ Remember it’s an aggregate figure
➢ May hide where the problem lies
➢ Beware of counterbalancing issues
» Over in one area vs. under in another
Earned Value Analysis
▪ Benefits
➢ Consistent unit of measure for total progress
➢ Consistent methodology
» Across cost and completed activity
» Apples and apples comparisons
➢ Ability to forecast cost & schedule
➢ Can provide warnings early
▪ Success factors
➢ A full WBS is required (all scope)
➢ Beware of GIGO: Garbage-in, garbage-out
▪ FYI: MS Project supports EVA (see reading list)
Three Fundamental Values
• BCWS (PV)
– The budgeted cost of work scheduled
• ACWP (AC)
– The actual cost of work performed
• BCWP (EV)
– The budgeted cost of work performed
BCWS
The budgeted cost of tasks as scheduled in the project
plan, based on the costs of resources (resources: The
people, equipment, and material that are used to
complete tasks in a project) assigned to those tasks, plus
any fixed costs (fixed cost: A set cost for a task that
remains constant regardless of the task duration or the
work performed by a resource.)
For example, the total planned budget for a 4-day task is
$100 and it starts on a Monday. If the status date is set
to the following Wednesday, the BCWS is $75
ACWP
• The actual cost (actual cost: The cost that has actually been
incurred to date for a task, resource, or assignment. For
example, if the only resource assigned to a task gets paid
$20 per hour and has worked for two hours, the actual cost
to date for the task is $40.)
• For resources, the total amount of work to which a
resource is assigned for all tasks. Work is different from task
duration. For example, if the 4-day task actually incurs a
total cost of $35 during each of the first 2 days, the ACWP
for this period is $70 (but the BCWS is still $75).
BCWP
• The value of the work performed by the status
date, measured in currency. This is literally the
value earned by the work performed and is called
the budgeted cost of work performed (BCWP).
• For example, if after 2 days 60% percent of the
work on a task has been completed, you might
expect to have spent 60 percent of the total task
budget, or $60
Earned Value Measure
• Cost variance (CV) – The difference between the
budgeted cost of work performed [BCWP] on a task
and the actual cost of work performed [ACWP]
CV = BCWP – ACWP
– If the CV is positive, the cost is currently under the
budgeted amount; if the CV is negative, the task is
currently over budget
– For example, the status date is set to the following
Wednesday, the BCWS is $75, the ACWP for this period is
$70, and the BCWP is $60. In that case, the task's CV is
-$10.
Schedule variance (SV)
• The difference between the budgeted cost of
work performed [BCWP] and the budgeted
cost of work scheduled [BCWS]
SV = BCWP – BCWS
– the difference between the current progress and
the scheduled progress of a task, in terms of cost
(the formula SV = BCWP - BCWS). In the example
above, the task's SV is -$15.
The cost performance index (CPI)
• Ratio of budgeted costs of work performed to
actual costs of work performed
CPI = BCWP / ACWP
• The cumulative CPI [sum of the BCWP for all tasks
divided by the sum of the ACWP for all tasks] can
be used to predict whether a project will go over
budget
• In the example above, the task's CPI is about .86,
or 86 percent
The schedule performance index (SPI)
• The ratio of the budgeted cost of work
performed [BCWP] to the budgeted cost of work
scheduled (BCWS), which is often used to
estimate the project completion date. calculated
as :
SPI = BCWP/BCWS
– the ratio of work performed to work scheduled (the
formula SPI = BCWP / BCWS). In the example above,
the task's SPI is .80, or 80 percent.
The task to complete performance index (TCPI)
• The ratio of the work remaining to be done to funds remaining to
be spent, as of the status date