Professional Documents
Culture Documents
MIP17-MS-1018 Method Statement For Installation of Sheet Pipling - Rev.0
MIP17-MS-1018 Method Statement For Installation of Sheet Pipling - Rev.0
MIP17-MS-1018 Method Statement For Installation of Sheet Pipling - Rev.0
Page 1 of 10
COMPANY LSTK CONTRACTOR:
Branch of Sinopec
Saudi
International
Arabian Oil
Petroleum Services
Company
Corp
Project:
CONTRACT No# 6600044545
MIP PKG 17 RAS TANURA AREA PIPELINE
BI No. 10-09004-0003
METHOD OF STATEMENT FOR INSTALLATION OF SHEET
Document title:
PIPLING
BI-10-09004-0003
Page 2 of 22
MIP17-MS-1018 REV.00
COMPANY LSTK CONTRACTOR:
Branch of Sinopec
Saudi
International
Arabian Oil
Petroleum Services
Company
Corp
Project:
CONTRACT No# 6600044545
MIP PKG 17 RAS TANURA AREA PIPELINE
BI No. 10-09004-0003
METHOD OF STATEMENT FOR INSTALLATION OF SHEET
Document title:
PIPLING
Table of Contents
1. PURPOSE...................................................................................................................................................................4
2. SCOPE OF WORK....................................................................................................................................................4
3. DEFINITIONS............................................................................................................................................................4
4. REFERENCES...........................................................................................................................................................5
5. RESPONSIBILTY......................................................................................................................................................5
6. METHODOLOGY.....................................................................................................................................................6
7. SAFETY REQUIREMENTS..................................................................................................................................10
8. JOB SAFETY ANALYSIS......................................................................................................................................10
Page 3 of 22
MIP17-MS-1018 REV.00
COMPANY LSTK CONTRACTOR:
Branch of Sinopec
Saudi
International
Arabian Oil
Petroleum Services
Company
Corp
Project:
CONTRACT No# 6600044545
MIP PKG 17 RAS TANURA AREA PIPELINE
BI No. 10-09004-0003
METHOD OF STATEMENT FOR INSTALLATION OF SHEET
Document title:
PIPLING
1. PURPOSE
The purpose of this Method Statement is to provide the work methods for installation of
Sheet Pile (SP) to augment the capacity of already installed Fabricated anchor block
(1.2m wide x 2m long x 2m deep) and associated works to hold the machine in place for
pulling of 30” dia TNJ-1 pipeline at KM67+337.
This method statement ensure that the processes involved in the drilling technique are
efficiently executed by eliminating possible errors.
2. SCOPE OF WORK
This scope of works describes the specific work required to be implemented for
installation of sheet piling under "MIP PKG 17 Ras Tanura Area Pipeline Project". This
method statement applies to the required materials and equipment used for Sheet Piling
technique. It defines the responsibilities for planning and execution of Sheet Piling to
augment the capacity of already installed fabricated anchor block to facilitate completion
of pipe pilling of 30” carrier pipe at 30” TNJ-1 pipeline KM67+337.
3. DEFINITIONS
4. REFERENCES
5. RESPONSIBILTY
HDD Project Manager is the person has the overall responsibility and accountability for
the Sheet Piling operation.
Page 5 of 22
MIP17-MS-1018 REV.00
COMPANY LSTK CONTRACTOR:
Branch of Sinopec
Saudi
International
Arabian Oil
Petroleum Services
Company
Corp
Project:
CONTRACT No# 6600044545
MIP PKG 17 RAS TANURA AREA PIPELINE
BI No. 10-09004-0003
METHOD OF STATEMENT FOR INSTALLATION OF SHEET
Document title:
PIPLING
Site engineer is responsible to ensure the Crossing crew understands the traffic
Management and Control Plan, ensure all required permits are in place, and the
requirement of safe work.
QC Inspector is responsible to cover all site activities in accordance with the approved
Project Quality Plan as approved by Saudi Aramco.
QC Supervisor is to ensure all Inspection Procedures reporting, and acceptance will be
adhered to QC site Team as per Saudi Aramco policy be always in contact with the
Saudi Aramco QC Division responsible for the project.
HDD Project Coordinator is responsible for coordination with various departments and
client through commencement till the Project Completion.
Safety officer in-charge on the area will conduct daily safety inspection on the work
area to ensure that all workers are in compliance of the safety.
6. METHODOLOGY
6.1 General
This Method Statement is based on the sheet piling execution process as described below,
Section 6.3.
In some circumstances activities or stages may not be applicable. It may also be necessary
to add activities or stages, depending on either internal or customer requirements or
Contract agreement.
Based on the Project, an execution team consists of the Project Leader, Supervisor,
Operator, Gang Leader and labor.
This execution team shall discuss formally the scope of work, project details as well as
review any critical safety issues that may be relevant, this will be discussed on-site prior to
job commencement.
Page 6 of 22
MIP17-MS-1018 REV.00
COMPANY LSTK CONTRACTOR:
Branch of Sinopec
Saudi
International
Arabian Oil
Petroleum Services
Company
Corp
Project:
CONTRACT No# 6600044545
MIP PKG 17 RAS TANURA AREA PIPELINE
BI No. 10-09004-0003
METHOD OF STATEMENT FOR INSTALLATION OF SHEET
Document title:
PIPLING
Project Leader shall ensure, prior to Sheet Piling operation, the availability of resources and
equipment required for the execution.
Page 7 of 22
MIP17-MS-1018 REV.00
COMPANY LSTK CONTRACTOR:
Branch of Sinopec
Saudi
International
Arabian Oil
Petroleum Services
Company
Corp
Project:
CONTRACT No# 6600044545
MIP PKG 17 RAS TANURA AREA PIPELINE
BI No. 10-09004-0003
METHOD OF STATEMENT FOR INSTALLATION OF SHEET
Document title:
PIPLING
Surveyor shall locate the area with the center line using a thread rope to control
the straightness & vertically on the position
Page 8 of 22
MIP17-MS-1018 REV.00
COMPANY LSTK CONTRACTOR:
Branch of Sinopec
Saudi
International
Arabian Oil
Petroleum Services
Company
Corp
Project:
CONTRACT No# 6600044545
MIP PKG 17 RAS TANURA AREA PIPELINE
BI No. 10-09004-0003
METHOD OF STATEMENT FOR INSTALLATION OF SHEET
Document title:
PIPLING
6.3.5 Documentation:
Project Leader Supervisor shall prepare the Daily Progress Report on daily basis
detailing the project status and hindrances to the main Contractor
The Daily Progress report summary is then submitted to the PLD Manager to
review and comment.
After Completion of Project Execution, Project Leader shall intimate Project Coordinator
for processing the Work Progress Certificate.
Where appropriate the execution team shall discuss any lessons learned after Project
completion and record in Project Close-out Sheet, to avoid repetition of faults made
during the project.
Where appropriate, the main Contractor shall be asked to complete a customer
feedback form to gauge their overall satisfaction
Page 9 of 22
MIP17-MS-1018 REV.00
COMPANY LSTK CONTRACTOR:
Branch of Sinopec
Saudi
International
Arabian Oil
Petroleum Services
Company
Corp
Project:
CONTRACT No# 6600044545
MIP PKG 17 RAS TANURA AREA PIPELINE
BI No. 10-09004-0003
METHOD OF STATEMENT FOR INSTALLATION OF SHEET
Document title:
PIPLING
7. SAFETY REQUIREMENTS
Obtain the work permit according to GI 2100. All the approved documents such as
MOS, JSA, and HIP etc. must be present and available at site.
PPE requirements and usage (e.g., face shield, ear plugs, etc.) shall be in compliance
with the CSM 1-3 Personal Protective Equipment (PPE).
All safety precautionary signboards must be visibly posted, and barricades install to
ensure that only authorized personnel are within the affected area.
Pre-Excavation checklist will be conducted and provision of excavation protection such
as shoring /sloping according to soil condition, if required as per Excavation and
Shoring guide 06-002-2008.
Hand tools and power tools must be inspected, and color coded by a competent person
prior to use in site.
Electrical cables must be free from damaged and competent electrician name and
contact numbers be posted in the area.
The work shall be executed in accordance with the approved Job Safety Analysis
(JSA).
Inspected UL/FM fire extinguisher must be readily available in the area.
Personnel must have familiar about the requirements of all job activities.
Page 10 of 22
MIP17-MS-1018 REV.00
COMPANY LSTK CONTRACTOR:
Branch of Sinopec
Saudi
International
Arabian Oil
Petroleum Services
Company
Corp
Project:
CONTRACT No# 6600044545
MIP PKG 17 RAS TANURA AREA PIPELINE
BI No. 10-09004-0003
METHOD OF STATEMENT FOR INSTALLATION OF SHEET
Document title:
PIPLING
Note:
1. This JSA is applicable only to same situation/activity, any changes, or additional prior to activity should be
reported to supervisors immediately.
2. Concurrence of competent person is needed with signature.
3. Safety Officer and Site supervisor from construction must monitor, control and supervise the work.
4. Approved JSA shall be on site prior to the construction.
5. Subject to changes, if deemed required.
6. Method Statement to be explained to all employees and it must be made available at the site.
7. JSA to be made available at the site and Job Specific Hazards and Control Measures to be clearly communicated to
all personnel involved in the job
8. Toolbox meeting to be done by the crew before work starts.
9. Site Supervisor shall be available at the site. Ensure appropriate control measures are implemented in the site.
10. Emergency Contact Numbers to be made visible on the site and at the Temporary shelter.
11. First Aid Box must be made available at the area.
12. First Aider with valid ID must be assign on site.
Page 12 of 22
MIP17-MS-1018 REV.00
COMPANY LSTK CONTRACTOR:
Branch of Sinopec
Saudi
International
Arabian Oil
Petroleum Services
Company
Corp
Project:
CONTRACT No# 6600044545
MIP PKG 17 RAS TANURA AREA PIPELINE
BI No. 10-09004-0003
METHOD OF STATEMENT FOR INSTALLATION OF SHEET
Document title:
PIPLING
Page 15 of 22
MIP17-MS-1018 REV.00
COMPANY LSTK CONTRACTOR:
Branch of Sinopec
Saudi
International
Arabian Oil
Petroleum Services
Company
Corp
Project:
CONTRACT No# 6600044545
MIP PKG 17 RAS TANURA AREA PIPELINE
BI No. 10-09004-0003
METHOD OF STATEMENT FOR INSTALLATION OF SHEET
Document title:
PIPLING
Page 16 of 22
MIP17-MS-1018 REV.00
COMPANY LSTK CONTRACTOR:
Branch of Sinopec
Saudi
International
Arabian Oil
Petroleum Services
Company
Corp
Project:
CONTRACT No# 6600044545
MIP PKG 17 RAS TANURA AREA PIPELINE
BI No. 10-09004-0003
METHOD OF STATEMENT FOR INSTALLATION OF SHEET
Document title:
PIPLING
Page 18 of 22
MIP17-MS-1018 REV.00
COMPANY LSTK CONTRACTOR:
Branch of Sinopec
Saudi
International
Arabian Oil
Petroleum Services
Company
Corp
Project:
CONTRACT No# 6600044545
MIP PKG 17 RAS TANURA AREA PIPELINE
BI No. 10-09004-0003
METHOD OF STATEMENT FOR INSTALLATION OF SHEET
Document title:
PIPLING
5.4. Failure of Vibro 5.4.1. Vibro hammer should have 3rd party certificate
hammer and with certified operator.
hydraulic hose 5.4.2. Daily and monthly inspection of gears and
equipment.
5.4.3. Workers should keep safe distance from the
hammering machine.
5.4.4. Hydraulic hose should be inspected for any
leaks/damages on daily basis
5.4.5. At a minimum, hard hats, safety glasses and
safety shoes shall be worn in SA restricted areas
and project work sites. Additional PPE shall be
selected and used based upon the results of a
documented PPE needs analysis,
5.5. Noise 5.5.1. Ample supplies of approved hearing protection
(e.g., earplugs) shall be provided at the job site
Page 19 of 22
MIP17-MS-1018 REV.00
COMPANY LSTK CONTRACTOR:
Branch of Sinopec
Saudi
International
Arabian Oil
Petroleum Services
Company
Corp
Project:
CONTRACT No# 6600044545
MIP PKG 17 RAS TANURA AREA PIPELINE
BI No. 10-09004-0003
METHOD OF STATEMENT FOR INSTALLATION OF SHEET
Document title:
PIPLING
Emergency
Emergency Response Procedure Office/Name Designation Number
1. Dial 911 from the nearest Saudi Aramco
telephone or from your mobile (03- N/A 911
Telephone
6730911). Northern Area 013-673-0911
2. When reporting an emergency Aramco (RT) Tanajib 013 378 0911
speak slowly, calmly, distinctly, in Emergency Khursaniyah 013 679 0911
a clear voice and give information
in the following sequence: Contractor Site 0503910052
3. States there is an emergency or Supervisor
disaster at your location and Contractor Site 0559693988
specify your location. Safety Supervisor
4. Tell Your Name_____ and your
Badge # ______.
5. Tell about emergency or
disaster like you see a fire, car
accident, major injury, etc. at the
following location: _________.
6. Inform that there are _______
(number of) people requiring
medical assistance / attention.
7. Repeat the above Information
and answer questions.
8. Do not hang up until the
Page 21 of 22
MIP17-MS-1018 REV.00
COMPANY LSTK CONTRACTOR:
Branch of Sinopec
Saudi
International
Arabian Oil
Petroleum Services
Company
Corp
Project:
CONTRACT No# 6600044545
MIP PKG 17 RAS TANURA AREA PIPELINE
BI No. 10-09004-0003
METHOD OF STATEMENT FOR INSTALLATION OF SHEET
Document title:
PIPLING
Page 22 of 22
MIP17-MS-1018 REV.00