CHOLOCAL CUMBRAY PEDREGAL

MATERIAL SOLICITADO POR C/BAÑO


54 61 162
LADRILLO 18 HUECOS 480.00 25920.00 29280.00 77760.00
CEMENTO 12.00 648.00 732.00 1944.00
FIERRO 3/8 3.00 162.00 183.00 486.00
FIERRO 1/4 3.00 162.00 183.00 486.00
ALAMBRE N° 16 0.50 27.00 30.50 81.00
ALAMBRE N° 8 0.75 40.50 45.75 121.50
CLAVOS 2 1/2 0.15 8.10 9.15 24.30
CLAVOS DE 2 0.15 8.10 9.15 24.30
YESO 0.10 5.40 6.10 16.20
ARENA GRUESA 0.95 51.30 57.95 153.90
GRAVILLA 3/4 0.90 48.60 54.90 145.80
PIEDRA BASE 0.30 16.20 18.30 48.60
ARENA FINA 0.50 27.00 30.50 81.00
HORMIGON 0.25 13.50 15.25 40.50
INODORO 1.00 54.00 61.00 162.00
LAVATORIO DE 23"X18" 1.00 54.00 61.00 162.00
DUCHA CROMADA 1.00 54.00 61.00 162.00
SUMIDERO CROMADO DE 2" 1.00 54.00 61.00 162.00
BIODIGESTOR 1.00 54.00 61.00 162.00

NOTA SE HA PROGRAMADO LA ENTREGA DE 10 BAÑOS POR SEMANA


CONSTANCIA CRUZ BLANCA CATHUAY
69 108 115 569
33120.00 51840.00 55200.00 273.12 MILLAR
828.00 1296.00 1380.00 6828.00 BOL
207.00 324.00 345.00 1707.00 VARILLA
207.00 324.00 345.00 1707.00 VARILLA
34.50 54.00 57.50 284.50 KG
51.75 81.00 86.25 426.75 KG
10.35 16.20 17.25 85.35 KG
10.35 16.20 17.25 85.35 KG
6.90 10.80 11.50 56.90 BOL
65.55 102.60 109.25 540.55 M3
62.10 97.20 103.50 512.10 M3
20.70 32.40 34.50 170.70 M3
34.50 54.00 57.50 284.50 M3
17.25 27.00 28.75 142.25 M3
69.00 108.00 115.00 569.00 UNID
69.00 108.00 115.00 569.00 UNID
69.00 108.00 115.00 569.00 UNID
69.00 108.00 115.00 569.00 UNID
69.00 108.00 115.00 569.00 UNID
PEDIDO DE MATERIALES PARA RESERVORIO Y CAPTACIONES

CEMENTO 600 BOL


ARENA GRUESA 60 M3
PIEDRA DE 1/2 60 M4
PIEDRA BASE 30 M5
ARENA FINA 15 M6
FIERRO DE 1/2 145 VAR
FIERRO DE 3/8 240 VAR
ALAMBRE N° 16 100 KG
ALAMBRE N° 08 150 KG
CLAVOS DE 4" 80 KG
CLAVOS DE 3" 80 KG
CLAVOS DE 2 1/2 40 KG
CLAVOS DE 2 40 KG
YESO 15 BOL
ALAMBRE DE PUAS 6 ROLLOS
PLASTICO PARA CUBRIR CEMENTO 80 MTS