Professional Documents
Culture Documents
IPC 2022 Paper - Subsurface Drainage For Pipelines Geohazard
IPC 2022 Paper - Subsurface Drainage For Pipelines Geohazard
IPC 2022 Paper - Subsurface Drainage For Pipelines Geohazard
IPC2022
September 26-30, 2022, Calgary, Alberta, Canada
IPC2022-87107
Effectiveness of Subsurface Drainage for Mitigation of Landslides Affecting
Pipelines
Keywords: landslide, subsurface drainage, slope stability • Improving drainage inside the pipe trench to enhance
the trench stability
1. INTRODUCTION • Improving surface drainage by diverting the water away
from the pipeline ROW
There are about 2.5 million miles of pipeline in the United • Monitoring the pipeline or landslide using geotechnical
States with half of the pipelines built more than 50 years ago. instruments, such as inclinometers and strain gauges
Pipelines are buried in soil. Soil or ground movement around the
pipe can induce external stress or strain on the pipe that may have If other mitigation measures have been implemented on the
not been accounted for at the time of design. These external slope or around the pipe in the past, the design and construction
forces from ground movement have a higher likelihood of of the subsurface drainage system must consider how best to
occurring in the landslide-susceptible area of the United States. minimize disturbance to existing systems. Although, subsurface
drainage improves ground stability, it cannot always stabilize the
1 © 2022 by ASME
landslide by itself. Subsurface drainage can be implemented drainage might not be effective. For example, if the landslide is
along with other mitigation measures, such as landslide about 500 feet wide and subsurface drainage is installed only
stabilization, as a long-term mitigation approach to reduce the within a 35-foot ROW, the effectiveness of the drainage system
potential need for future mitigations. on landslide stability is considerably limited, or even ineffective.
That said, the drainage system within the ROW can,
2. DESIGN CONSIDERATIONS nevertheless, improve the geotechnical stability of the pipeline
trench.
Although subsurface drainage can be simple, there are
several factors to be considered before designing the system.
These considerations are pertinent to the characteristics and
geotechnical stability of the landslide. For most pipelines in the
United States, subsurface drainage is implmented within the
pipeline ROW, which limits the area where the system can be
installed.
2 © 2022 by ASME
FIGURE 2: LOCATION OF PIPELINE ROW AND SUBSURFACE DRAINAGE COMPARED TO BOUNDARY OF LANDSLIDE
Local and Global Stability: When excavating in a landslide- In order to develop an effective improvement to the
prone area, an engineer needs to evaluate the geotechnical landslide stability, a proper geotechnical analysis is required. We
stability of the drainage trench and the overall geotechnical conducted several parametric studies for seepage and slope
stability of the slope or the existing landslide before any stability analyses to develop design charts that can be used to
excavation starts. Also, the additional loading from stockpiles conduct a preliminary evaluation of subsurface drainage for
and construction equipment should be considered in these various site conditions. Although the design charts proposed in
stability evaluations. this paper help with preliminary evaluations, the charts do not
Various factors affect the geotechnical stability analyses, eliminate the need for a full geotechnical design of subsurface
and, among those factors, the condition of the groundwater is drainage.
essential. Because the groundwater table can fluctuate from
precipitation; the drainage system should be constructed during 3.1 Simplified Model
the dry season when groundwater levels are lower and the soil is
drier. If needed, temporary shoring should be installed. If For the parametric study of the effectiveness of subsurface
installing a drainage system could exacerbate the overall stability drainage on the potential field change in the slope, we modeled
of the slope, it should be avoided or be conducted in combination the problem (schematized in Figure 4) using the following
with other mitigation measures. parameters:
(1) the slope of the ground surface (S, %)
Soil Stockpile: Additional loads from soil stockpiled during (2) length of landslide (L, ft)
excavation might result in other instabilities; therefore, the (3) the slip surface at depth of D (ft)
location of the soil stockpile should be planned before the (4) a steady-state groundwater table and parallel to the
excavation begins. slope at depth of W (ft) below the ground surface
(5) the soil is homogeneous with a hydraulic conductivity
Presence of other Pipelines or Structures: Stress-relief of 10-7 ft/s
excavation can increase the probability of destabilizing the (6) the average groundwater drop after installation of
upslope areas. This is even more critical when other pipelines, subsurface drainage is W (ft)
infrastructure, or structures are located upslope of the excavated (7) subsurface drainage is installed to a depth of 8 ft from
area. the groundwater table
3 © 2022 by ASME
(a) (b)
FIGURE 3: POTENTIAL LOCATIONS OF SUBSURFACE DRAINAGE IN PIPELINE ROW (A) PERPENDICULAR AND (B)
PARALLEL TO LANDSLIDE
4 © 2022 by ASME
parameters along the slip surfaces to obtain a factor of safety of require different subsurface drainage systems. This study mainly
1.0. focuses on subsurface drain systems that are lateral or oblique to
the pipeline. Examples of this type of subsurface drain within the
Table 1: SUMMARY OF GEOTECHNICAL PARAMETERS FOR ROW and parallel to the pipeline (Figure 5). To estimate the
MODELS groundwater drawdown for the actual sites, we conducted 2D
Undrained seepage analyses for three representative sites with overall slope
Friction Hydraulic percentages of 15%, 30%, and 45%. The results of seepage
Soil Unit Shear
Angle Conductivity
Layer Weight Strength analyses for these cases are presented in Figure 6 to Figure 8.
(deg) (ft/s)
(psf)
Landslide
105 - Var* 1x10-7
Soil
Stable
115 1500 - 1x10-7
Soil
Drainage
135 - 40 1
Material
*Back-calculated for the factor of safety of 1.0.
𝐹𝐹𝐹𝐹𝑑𝑑 (1)
𝐸𝐸 = � − 1� × 100
𝐹𝐹𝐹𝐹𝑖𝑖
Where, 𝐹𝐹𝐹𝐹𝑖𝑖 is the initial factor of safety which is equal to 1 for FIGURE 5: EXAMPLE OF SUBSURFACE DRAINAGE SYSTEM
WITHIN THE ROW
all models (i.e., the landslide is marginally stable), 𝐹𝐹𝐹𝐹𝑑𝑑 is a factor
of safety for the model after lowering the groundwater due to the
As shown in Figure 6 to Figure 8, the drop in the groundwater
effect of a subsurface drainage system.
table is nonlinear along the boundary of the landslide. The drop
in the groundwater table within the landslide can be calculated
4. RESULTS AND DISCUSSION
using a simplified approach.
Figures 9 and 10 show the examples for calculating the drop
4.1 Estimation of Drop in Groundwater
in groundwater table for the landslide with a length of 100 feet
and slope of 15% with two different locations of the pipeline
The effectiveness of subsurface drainage to improve the
ROW and subsurface drain. In Case 1, the subsurface drain is in
geotechnical stability of a landslide is greatly related to the
the upper portion of the slope. In Case 2, the subsurface drainage
capability of the subsurface drainage system to lower the
is at the toe of the landslide. As shown, the drop in the
groundwater table. This section provides a chart and method to
groundwater table is estimated to be an average of 3.7 feet for
estimate the average drop in the groundwater table within a
Case 1 and 2.8 feet for Case 2.
landslide.
The direction of landslide movement can be lateral, axial, or
oblique to the pipeline. These various landslide directions
5 © 2022 by ASME
FIGURE 6: SEEPAGE ANALYSES FOR 15% SLOPE
6 © 2022 by ASME
FIGURE 8: SEEPAGE ANALYSES FOR 45% SLOPE
7 © 2022 by ASME
FIGURE 10: EXAMPLE OF ESTIMATED AVERAGE DROP IN GROUNDWATER LEVEL (CASE 2)
8 © 2022 by ASME
110% 110%
Length = 100 ft Slope 15% Length = 185 ft Slope 15%
100% Water Drop = 6 ft
100% Water Drop = 6 ft
Slope 30% Slope 30%
90% 90%
Slope 45% Slope 45%
Drainage Effectiveness
Drainage Effectiveness
80% Slope 60% 80% Slope 60%
70% 70%
60% 60%
FS = 1.5 FS = 1.5
50% 50%
40% 40%
30% 30%
20% 20%
10% 10%
0% 0%
3 3 3 3 9 ft 13 ft 17 ft 21 ft
Depth of Landslide Depth of Landslide
110% 110%
Length = 100 ft Slope 15% Length = 185 ft Slope 15%
100% 100%
Water Drop = 3 ft Slope 30% Water Drop = 3 ft Slope 30%
90% 90%
Slope 45% Slope 45%
Drainage Effectiveness
Drainage Effectiveness
80% Slope 60% 80% Slope 60%
70% 70%
60% 60%
FS = 1.5 FS = 1.5
50% 50%
40% 40%
30% 30%
20% 20%
10% 10%
0% 0%
9 ft 13 ft 17 ft 21 ft 9 ft 13 ft 17 ft 21 ft
Depth of Landslide Depth of Landslide
110% 110%
Slope 15% Slope 15%
100% Length = 100 ft 100% Length = 185 ft
Water Drop = 1 ft Slope 30% Water Drop = 1 ft
Slope 30%
90% 90%
Slope 45% Slope 45%
Drainage Effectiveness
Drainage Effectiveness
9 © 2022 by ASME
110% square error (RMSE) and determination coefficient (R2),
Length = 270 ft Slope 15% respectively, given by Equations 2 and 3.
100%
Water Drop = 6 ft Slope 30%
90%
Slope 45%
Drainage Effectiveness
10 © 2022 by ASME
Figure 12 provides the measured versus predicted strength to estimate the effectiveness of subsurface drainage systems in
values based on the GEP models developed in this study. The landslide projects. For instance, if there is a landslide with a
statistical parameters and performance measures for each subset length of 120 feet, depth of 10 feet, and slope of 20%, and the
of models are also provided in Table 2. Smith recommended that proposed subsurface drainage system was capable to reduce the
for a coefficient of determination of |𝑅𝑅2| > 0.8, a strong groundwater table to 3 feet below the initial groundwater table,
correlation exists between the input and output layers of the the effectiveness of this subsurface drainage system can be
models [5]. The proposed GEP models in this section showed estimated to be 55% (i.e., the factor of safety of landslide is 1.55
acceptable prediction capability as the correlation coefficient for for post drainage condition) based on Equation 5.
the developed model is more than 0.80 as indicated in Table 2.
The RMSE is also within the acceptable range for the developed 6. SUMMARY
model.
A subsurface drainage system is a widely used mitigation
110% strategy to slow down the likelihood of landslide movement in
Training pipeline projects. The subsurface drainage system s commonly
100%
Validation designed to lower the groundwater table within the landslide and
90% Linear (Line of Equality) to improve the geotechnical stability of the landslide. This paper
80% discussed the design consideration for subsurface drainage
Predicted Effectiveness
11 © 2022 by ASME