Professional Documents
Culture Documents
IPC2022-86173 - Assessing Soil Corrosivity of Buried Structural Steel - Field Study
IPC2022-86173 - Assessing Soil Corrosivity of Buried Structural Steel - Field Study
IPC2022-86173 - Assessing Soil Corrosivity of Buried Structural Steel - Field Study
IPC2022
September 26 – September 30, 2022, Calgary, Alberta, Canada
IPC2022-86173
1 © 2022 by ASME
standards and provide guidance to future users, such as design
engineers and geotechnical service providers.
2.2 Analysis of Structural Steel Samples
Table 1 provides an overview of the structural steel samples
analyzed in this work, with additional details provided in
Appendix section 8.1. Structural components consisting of
I-beams, piles, pile caps, chance anchors, blowdown supports,
nuts/washers/bolts, and building support columns were Figure 1A: Meter Station F Figure 1B: Meter Station
examined. As indicated in Table 1, certain structures had samples as received G pit depth measurements
corrosion protection (e.g., cathodic protection, tape coating,
and/or paint coating). These aspects are taken into consideration Figure 1: Visual appearance of selected structural steel samples.
in the evaluation of the soil corrosivity model performance. The damage on the support columns exposed in the light
Table 1: Type and number of structural components analyzed industrial building was examined visually, but the columns were
from each site. not removed for detailed examination as described above
because they were being repaired in place. Metal loss
assessments were based on in-situ visual examination and the
site’s engineering report.
2.3 Soil Sampling and Measurements
Field measurements and sampling procedures were similar
from site to site, with slight variations to the procedure at Meter
Station G and the light industrial building. The general procedure
used at most sites is as follows:
• Soil measurements and soil samples were collected at a
depth of ~0.3 m [~ 1 ft] and ~1.0 m [~ 3.3 ft] (from ground
grade) and as close as possible to the structures of interest.
The soil samples were tested in the field and/or in the
laboratory for the physical and chemical parameters listed in
Table 2.
• Resistivity surveys were completed in the field using the
four pin Wenner method along a minimum of two transects
(e.g., north-south and east-west) and typically multiple pin
spacings at each site.
Electrical potential of the buried structural steel was
measured against copper-copper sulfate (Cu:CuSO4) reference
electrodes. In addition, a standard 1 cm 2 [0.155 in2] corrosion
coupon was temporarily installed at each site with initial and
Structural Steel Damage Assessment and final potential readings collected using Cu:CuSO4 reference
Corrosion Rate Calculations electrodes. Assessment of groundwater presence at steel burial
First, visual examination and photographs of the as-received depth was conducted through visual observations of groundwater
samples was conducted, as exemplified in Figure 1A. Then, seepage, soil sloughing, visible water in trenches/test pits
structures and areas of interest (i.e., with the greatest corrosion (presence of sump pumps, etc.), and by a desktop search for
damage), were identified for further analysis. The samples were shallow groundwater (<20 m depth) within 5 km of the site using
cut into subsamples and cleaned by sandblasting. A grid was then the Alberta Water Well Information Database (Government of
drawn on the area of interest and pit depth measurements were Alberta, 2021 [6].
taken in each square using an electronic pit depth gauge, as When groundwater was not observed during the field visit,
shown in Figure 1B. The deepest pit depth measured in each the desktop search provided data for a professional opinion on
square was recorded and the corrosion rate was calculated by whether groundwater presence is either temporary (i.e., seasonal
dividing the pit depth by the years in service. The average, presence), or never (i.e., always dry).
maximum, and minimum corrosion rates were reported. The Sulfide, pH, and oxidation reduction potential (ORP)
nominal thickness of the sample was determined by averaging measurements in the field were completed using calibrated
three sample thickness measurements. The average wall loss and electrodes in soil slurries prepared with deionized, de-
average remaining wall thickness were calculated using nominal oxygenated water following the U.S. EPA SW-846 Method
wall thickness and average pit depth measurements. 9045D [7]. Attempts to also measure these parameters in-situ by
pressing the electrodes into the soil were unsuccessful due to the
2 © 2022 by ASME
fragile electrode tips and poor soil contact. Electrical Excel using Microsoft Visual Basic for Applications (VBA)
conductivity and moisture content were measured in-situ using code. The tool consists of a data input tab and model output tabs.
pen-type sensors. Sulfate reducing bacteria were enumerated Once data is entered into the tab, it is run through a series of
semi-quantitatively using 3M Rapid Sulfate-Reducing Bacteria if/else statements to obtain the model results.
(SRB) Detection Pouches. Laboratory analyses were completed
Table 3: Comparison of approach, outcome, and data
by ALS Environmental laboratories in Edmonton.
requirements of the industry guidelines (first published in
Table 2: Field and laboratory measurements of soil properties. Beauregard and Mah, 2020) [5]
DIN50929- ANSI/ AASHTO
3:2018-03 AWWA R27-01 [1]
[2] C105/A21.5
[3]
Intended structures Buried Ductile iron Steel pilings
pipelines pipe for for non-marine
and water and applications
structural wastewater
components
Approach
Point-based criteria ✓ ✓ -
Decision tree - - ✓
Table of corrosion rates ✓ - -
Outcome
Qualitative Soil Corrosivity ✓ ✓ ✓
Rating
Estimated Soil Corrosion Rate ✓ - -
Recommended Mitigation - ✓ ✓
Model Input
Electrical and electrochemical properties
Resistivity ✓ ✓ ✓
Oxidation Reduction Potential - ✓ -
(ORP)
Structure to Soil Potential ✓ - -
The soil sample from Meter Station G was analyzed in the Physical soil characteristics
laboratory only. The soil sample consisted of a mixture of soil Soil Texture, Type and/or ✓ - ✓
Composition
collected at various locations on-site as well as soil recovered Soil Compaction - - -
from the received steel structures. Mixing these soil samples was
necessary to obtain the required volume for analysis. The soil Soil Homogeneity ✓ - ✓
analysis was conducted approximately eight months after field Presence and location of soil water
sampling due to limitations of the original soil sample volume. Ground Water Level at Buried ✓ - ✓
Position
Soil samples from the light industrial building were Moisture Content ✓ - -
analyzed in the field and in the lab. Fewer properties were
measured in the field; only the electrical potential of the Drainage - ✓ -
structure, moisture content of the soil, and SRB concentration Soil water chemistry
were measured. The laboratory analysis was consistent with that pH ✓ ✓ ✓
performed for other sites. As requested by the laboratory, gravel, Sulphate Concentration ✓ - -
which made up a large proportion of the soil matrix, was sifted Sulphide Concentration ✓ ✓ -
from the soil prior to sending samples for analysis.
Chloride Concentration ✓ - -
2.4 Soil Corrosivity Analysis
Alkaline buffering capacity ✓ - -
The soil properties were analyzed to assess local soil
corrosivity using the AASHTO R27-01 [1], DIN 50929-3 [2] and Acid buffering capacity ✓ - -
ANSI/AWWA C105/A21.5 [3] standards. While the aim of these
standards is similar, their approach, outcome, and input data 3. RESULTS
requirements differ, as summarized in Table 3 and described in 3.1 Structural Steel Damage and Corrosion Rate
further detail in Beauregard and Mah (2020) [5]. Observations
A Microsoft Excel-based tool was developed to efficiently
The corrosion rates and metal loss measured on each sample
analyze field and laboratory soil measurements within the
are reported in the Appendix 8, section 8.2. For most of the
corrosion models mentioned above. The tool was developed in
3 © 2022 by ASME
buried steel samples collected at the decommissioned facilities, [86 ohm-in] to 342 ohm-cm [135 ohm-in]) and high amounts of
the damage manifested itself as relatively small areas of minor sulphide (6.2 and 4.0 mmol/kg [2.81 and 1.81 mmol/lb]), sulfate
general metal loss. The Meter Station F I-beam sample Figure (9.8 and 27.4 mmol/kg [4.45 and 12.43 mmol/lb]) and neutral
2A) showed the highest metal loss of the buried components at salts (13.9 and 33.1 mmol/kg [6.30 and 15.01 mmol/lb]). The soil
meter stations. Even so, there remained significant wall matrix consisted of medium to coarse grain particles (including
thickness on the I-beam (> 86 % wall thickness). The structural gravel) which increased the prediction of the corrosion rate.
beams in the light industrial building were more heavily The results also demonstrate that the DIN 50929-3 [2] model
corroded and in one location a through hole was observed typically provides the most conservative assessment, which is
(Figure 2B). The range of sample metal loss and corrosion rates consistent with the case studies presented by Beauregard and
are presented in Table 4 by the two broad structure types Mah (2020) [5].
investigated (i.e., the buried structural steel samples from
decommissioned facilities and the structural supports in the light
industrial building). The corrosion rates are compared to rates
reported in literature for different corrosion mechanisms (Figure
3). The measured corrosion rates generally fall within the lower
to mid-range of those reported in literature except for the rate
associated with the through hole in the structural beam of the
light industrial area. Interestingly, Figure 3 shows that many
samples without CP (e.g., piles, I-beams) have a large range in
corrosion rate, with some lower than those from samples with CP
(e.g., blowdown stack supports).
4 © 2022 by ASME
Table 5: Heat map of the general corrosivity of soil samples corrosion rate measurements, taken on either side of the same
assessed using different models. I-beam sample from Meter Station F were higher than those
anticipated by the models (by a factor of ~1.4 in the AASHTO
R27-01 [1] model and ~1.8 in the DIN 50929-3:2018 [2] model).
When considering the implication of this result, it is important to
note that the measured corrosion rates are themselves
conservative compared to the actual general corrosion rate. The
measured corrosion rates are representative of a relatively
localized area and are calculated based on the average of the
deepest measurements in the grid. Further, the results are within
the tolerance given in the DIN 50929-3:2018 [2] standard (factor
of two). Therefore, this result should not discount the otherwise
conservative model performance.
5 © 2022 by ASME
be drawn from the insight gained from this work. Specifically, in/yr]). Therefore, a soil corrosion assessment is required to
guidance on the use of laboratory or field measurement determine a reasonable corrosion rate for design purposes. For
techniques can be drawn from comparing the data collected from soils assessed using the AASHTO R27-01 [1] model as having
both settings, as summarized in Table 8. ‘not significant corrosion’, the value of 0.0254 mm/yr [0.001
in/yr], first proposed by Durr and Beavers (1998) [9], could be
Table 7: Measured corrosion rate observed compared to soil
adopted as a threshold since it was conservative for most steel
prediction model rates.
samples examined in this study. For finer corrosion rate
resolution, the corrosion rates proposed in DIN 50929-3:2018 [2]
could also be adopted, since they too tend to overestimate the
measured corrosion rates. They also provide rates for high
corrosion, which are not explicitly provided by Durr and Beavers
(1998) [9]. The statistical analysis of the measured corrosion
rates presented in Table 7 can also be used to guide decisions
about corrosion rates used in a design. When adopting these
values, conservatism is also established since it is assumed that
the structure corrodes uniformly when in fact the corrosion
observed is non-uniform with many sections of lower damage.
6 © 2022 by ASME
application, inspector cost and coordination, field coating to components would likely justify the upfront soil corrosivity
touch up field weld locations and general repairs. Further, there assessment costs.
are indirect costs from scheduling and material requirements for
fabrication and field coating. In addition, there are internal costs 5. CONCLUSION
associated with documenting and storing the inspection and
testing records for the coating application. The work demonstrates that AASHTO R27-01 [1], DIN
On the other hand, conducting a soil corrosivity assessment 50929-3 [2] and ANSI/AWWA C105/A21.5 [3] standards can be
to determine the need to coat a structure would result in a practically used in the field to provide a conservative soil
relatively small cost increase to current geotechnical analysis corrosivity assessment. The models tend to overpredict corrosion
while offering the potential to save on the coating costs described rates at locations assessed to have low or medium soil corrosivity
above. The costs associated with a soil corrosivity assessment while accurately identifying locations of high soil corrosivity
would include: where additional corrosion protection would be warranted.
Companies wishing to adopt these standards into their
• Additional scope of work for site geotechnical analysis.
decision-making process for the coating requirement of buried
Based on the experience gained in this work, this would
steel should collect the required soil properties in the planning
result in approximately three additional days of labour (field
phase of the project (e.g., as part of a site’s geotechnical
and office work) and laboratory testing costs on the order of
assessment). The field and laboratory procedures described in
a few hundred dollars per sample. These activities would
the standards and the insight gained from this work provide a
likely result in a relatively small cost increase to the
good starting point for such work. For many projects, the upfront
geotechnical scope of work.
soil corrosivity assessment costs would likely justify the cost
• Additional internal scope of work would include application
avoidances achieved by allowing uncoated buried structural steel
of the soil data to the standards to determine corrosivity and
components.
assess the results. The application of the models can be done
quickly using an automated tool, such as the one described 6. ACKNOWLEDGEMENTS
in section 2.4. The time for internal assessment could vary The authors would like to thank: TCE’s Technology &
depending on the perceived risk. Further time would be Innovation Management Office (TIMO) for funding this study,
required to update drawings and alignment sheets where TCE field staff and site construction managers for facilitating
coated or uncoated steel components must be used, steel and soil sample collection, TCE’s Aissa Van Der Veen and
including engineering acceptance. Nora Zhao for their technical inputs, Kristina Montesa of NOVA
Chemicals for laboratory support and Sai Rajajayavel and Jillian
Mitton of Ecometrix for their work conducting site sample
collection and coordinating laboratory analysis.
7. REFERENCES
[1] AASHTO (American Association of State Highway and
Transportation Officials). “Standard Practice for Assessment of
Corrosion of Steel Piling for Non-Marine Applications.”
AASHTO R 27-01 (2019). AASHTO, Washington, D.C. 2019.
7 © 2022 by ASME
[5] Beauregard, Yannick and Mah, Andrea. “Assessing Soil
Corrosivity for Buried Structural Steel.” Proceedings of the 2020
13th International Pipeline Conference (IPC). IPC2020-9285:
Online, Virtual. September 28 – October 2, 2020.
8 © 2022 by ASME
8. APPENDIX
Table A-2: Description of decommissioned sites Meter Station
8.1 Site Description E, Meter Station F, Meter Station G and Light Industrial
Table A-1 and Table A-2 describe the decommissioned sites Building examined in this study.
examined in this study.
Meter Station E Meter Station F Meter Station G Light Industrial
Description
Building
Table A-1: Description of decommissioned sites Meter Station
D, Meter Station B, Meter Station A, Meter Station H and Area Overview
Meter Station C examined in this study. Location in Central Alberta Northern Alberta Northern Alberta Central Alberta
Alberta
Meter Meter Meter Meter Meter Station
Description Immediate Cropland Primarily Primarily Primarily
Station D Station B Station A Station H C
Surrounding surrounds work undeveloped forest undeveloped forest. developed
Area area to west, N Highway 2.5 km E industrial
Area Overview and S of site. buildings
Location in Northeast Southern Alberta Southern Central Alberta Central Alberta Broader Includes Includes oil & gas Includes oil &gas Includes developed
Alberta Alberta Alberta Surrounding agricultural land facilities facilities urban living spaces
Area and farmyards
Immediate Primarily Primarily Primarily Primarily Primarily
Surrounding undeveloped undeveloped undeveloped agricultural agricultural Distance to 3.9 km E of 500 m S of Unnamed 4.2 km SE of large 1.4 km S of small
Area forest pastureland. pastureland. land. Oil & gas land. Oil & gas Closest Whitford Lake Creek waterbody lake.
Wetland 1.8 km Wetland 220 m facility N of facility S of Surface Water 12.5 km south of 5 km N of the Bow
NE of site NW of site site. Wetland site. Bodies The North River.
175 m E of site Saskatchewan River
Broader Includes oil & Includes oil & gas Includes oil & Includes Includes Likely Shallow Water level records Water level Water appears Technical report
Surrounding gas facilities, facilities, CFB gas facilities, agricultural land agricultural land Groundwater within 5 km of site records indicate present in the ditch indicates presence
Area Janvier Suffield CFB Suffield and farmyards and farmyards Depth1 indicate groundwater is on certain images. of ground water,
Hamlet groundwater is present at a depth moisture in soil.
present at a depth of of 1.5 m - 3 mbgs.
Distance to 1 km E of 39 km S of The 16.5 km S of 9.8 km W of 5 km SW of The 27 ft (8 m).
Closest Christina Lower Red Deer The Lower Red The Lower Red North
Surface Water River. 3.2 km River. 12 km SE Deer River Deer River Saskatchewan Site Specific Details
Bodies W of of Tide Lake River
Bohn Lake
Date of Site July 30, 2021 September 22, 2021 February 22, 2021 August 30 & 31
Visit 2021
Likely Shallow 2 - 5 mbgs Groundwater in the upper 3 m is Groundwater Water level
Groundwater likely, no water level records present at 1m records within 5
Site A sump pump was Gravel fill saturated Winter conditions. Structure was
Depth1 were found within 5 km radius at blowdown km of site
Observations observed at pipe with rainwater. Soil generally originally covered
of the sites. Water level records support. Wet indicate
depth (<3 m) at the Underlain by Sandy appears clayey/sandy by a layer of
for the town of Brooks found soils noted on groundwater
time of clay with some larger concrete, underlain
shallow (1.5 to 2.0 m) water west side of present at a
the site visit. rocks near surface. by gravel and clay.
levels. site at similar depth of 26 ft -
depth (~1m). 46 ft (8 m -
14m). Soil Silty Clay Fill with Sandy Clay, fine- No description from Gravel and rocks.
Characteristics organics, fine- grained, moist to wet, site. Soil below gravel
– Approx. 0.3 grained, low plastic, low plastic, brown, sandy silt, dry,
Site Specific Details
m brown firm to soft brown.
Date of Site April 4 & 5, April 9 & 10, April 9 & 10, July 9, 2021 July 19, 2021
Soil Silty Clay Fill and Sandy Silty Clay, No description from Clayey sand, very
Visit 2021 2021 2021
Characteristics sand, trace organics trace hard silt site. moist, brown to
– Approx. 1.0 and gravel, fine to pockets, non to low black.
Site Gravel fill Gravel Fill Mixtures of Gravel fill Gravel fill m coarse-grained, low plastic, dry to damp
Observations saturated from underlain by Silty Clay and Sand, underlain by underlain by to medium plastic,
rainfall Clay frozen patches Silty Clay Silty Clay damp
underlain by of clay present to moist, brown
frozen ground onsite as deep as
1m
Steel 1 - blowdown 1 - pile 1 – pile 2 – support
Structures of support 2 - pile 2 – I-beam columns
Soil Sandy Silty, Sandy Silty Clay, Sand, trace silt Silty Clay & Sandy, Silty Interest 2 - blowdown 3 - I beam 3 – pile cap
Characteristics fine-grained, fine-grained, & clay, fine- organics, firm, Clay & organics, support
– Approx. 0.3 frozen, brown damp, cohesive, grained non-to low plastic, fine-grained,
m medium plastic, low plastic, damp, brown low plastic
brown damp, brown with black
Soil Silty Clay, Sandy Silty Clay, Clayey sand, Sandy Silty Clayey Sand,
Characteristics some sand, fine-grained, fine-grained, Clay, fine- some organics,
– Approx. 1.0 fine-grained, damp, cohesive, trace organics, grained, firm, fine-grained, low
m damp, medium plastic, non to low damp to wet, to medium
medium brown plastic, damp, medium plastic, plastic
plastic, brown brown dark brown
9 © 2022 by ASME
8.2 Summary of Measured Corrosion Rates and Remaining Wall Loss
The corrosion rates were calculated from the measured pit depths and the years in service for each surface analyzed. Minimum,
maximum, and average corrosion rates are tabulated in Table A-3.
10 © 2022 by ASME
8.3 Results from Corrosion Models
Table A-4 to and Table A-6display the results obtained from each of the sites from DIN 50929-3 [2] (Table A-4), ANSI/AWWA
C105/A21.5 (Table A-5), and AASHTO R27-01 [1] (Table A-6) corrosion models
11 © 2022 by ASME
Table A-5: Results from the ANSI/AWWA C105/A21.5 [3] Table A-6: Results from the AASHTO R27-01 model.
model.
12 © 2022 by ASME