Project Time and Cost Notes

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 105

HEP 3110: PROJECT TIME AND COST MANAGEMENT

Jomo Kenyatta University of Science and Agriculture


Master of Science in Project Management
Unit code: HEP 3110: Project Time and Cost Management
Lecture: Dr. Muchelule Yusuf, PhD

TABLE OF CONTENTS
Course Content................................................................................................................................................................4
Inputs required in sequence activities........................................................................................11
Tools and methods used in sequence activities.........................................................................12
Types of Dependency Determination in Project Management..................................................12
Types of Dependencies or Logical Relationships.....................................................................14
Schedule Network Diagrams.....................................................................................................15
Arrow Diagramming Method (Activity on Arrow Method)......................................................15
Arrow Diagramming Method – Dummy Activity.................................................................16
When to Use the Arrow Diagramming Method (ADM)...........................................................16
How to Use the Arrow Diagramming Method (ADM).............................................................16
Summary................................................................................................................................17
Leads and Lags..........................................................................................................................18
Outputs of sequence activities...................................................................................................19
Product-based planning.............................................................................................................19
Detection of activities and dependencies in product-based planning........................................20
1.4 ACTIVITY RESOURCE ESTIMATION...............................................................................................................29
1.5 ACTIVITY DURATION ESTIMATING................................................................................................................31
Activity Duration Estimating technique include:......................................................................32
a) Analogous Estimating.........................................................................................................32
b) Parametric Estimating.........................................................................................................32
c) Three-Point Estimating.......................................................................................................33
Basic concepts used in PERT and CPM.......................................................................................................................33
Step 1: Forward Pass Calculation..........................................................................................35
Step 2: Backward Pass Calculation.......................................................................................35
Step 3: Float Calculation for Each Activity / Arrow Diagramming Method Example.........36
Step 4: Identifying the critical path / Arrow Diagramming Method Example......................36
Summary................................................................................................................................36
Guidelines for construction of network diagrams.........................................................................................................37

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 1


Time Estimates In Network Analysis...........................................................................................................................39
Critical Path Method.....................................................................................................................................................39
Advantages of CPM......................................................................................................................................................40
Drawbacks of CPM.......................................................................................................................................................40
PROJECT EVALUATION AND REVIEW TECHNIQUE (PERT)...........................................................................40
Summary................................................................................................................................43
Advantages of PERT.....................................................................................................................................................45
Shortcomings of PERT.................................................................................................................................................46
Differences between PERT and CPM...........................................................................................................................46
Key Points..............................................................................................................................47
d) Heuristic Estimating...........................................................................................................47
e) Reserve Analysis................................................................................................................47
f) Work Breakdown................................................................................................................47
g) Historical.............................................................................................................................47
h) Expert Judgment.................................................................................................................48
i) Effort required....................................................................................................................48
j) Units to produce..................................................................................................................48
Activities in Control Schedule Process......................................................................................49
Examples of potential cost driver..............................................................................................52
Step 4 Plot the data on a graph..................................................................................................53
Step 6: Test the reliability of the cost function..........................................................................53
a) Engineering method...............................................................................................................54
b) Account analysis (Inspection of accounts) method...............................................................54
c) Work Breakdown Structure...................................................................................................54
d) Resource Costing................................................................................................................54
e) Unit Costs...........................................................................................................................54
f) Historical Costing...............................................................................................................55
Illustration 2.1............................................................................................................................55
Solution......................................................................................................................................56
Simple Regression.....................................................................................................................57
Illustration 2.2............................................................................................................................59
NET PRESENT VALUE...........................................................................................................60
Solution:.................................................................................................................................62
PAY BACK PERIOD...................................................................................................................................................63
Formula......................................................................................................................................64

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 2


Decision Rule.............................................................................................................................64
Examples....................................................................................................................................64
Merits and demerits of payback period are as follows;.............................................................65
Accept or Reject Criteria of payback period.........................................................................65
Advantages And Disadvantages Of Pay Back Period(PBP)..................................................66
BENEFIT COST RATIO ANALYSIS......................................................................................67
EARNED VALUE MANAGEMENT (EVM).............................................................................................................68
EVM - Basic Elements..................................................................................................................................................68
Planned Value............................................................................................................................69
Actual Cost................................................................................................................................69
Earned Value.............................................................................................................................69
% Completed Planned................................................................................................................69
% Completed Actual..................................................................................................................69
EVM - Cost Variance....................................................................................................................................................70
Cost Variance %........................................................................................................................70
Cost Performance Indicator.......................................................................................................70
To Complete Cost Performance Indicator.................................................................................71
EVM - Schedule Variance............................................................................................................................................71
Schedule Variance %.................................................................................................................72
Schedule Performance Indicator................................................................................................72
To Complete Schedule Performance Indicator..........................................................................73
EVM - Miscellaneous Formula.....................................................................................................................................73
Budget at Completion................................................................................................................73
Estimate to Complete.................................................................................................................73
Estimate at Completion..............................................................................................................74
Variance at Completion.............................................................................................................74
% Completed Planned................................................................................................................74
% Completed Actual..................................................................................................................74
EVM - Examples...........................................................................................................................................................74

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 3


PURPOSE OF THE COURSE

The purpose of the course is to make the student understand the processes required to make the
most effective use of time and costs involved in project.

COURSE OBJECTIVES
At the end of the course the student will be able to:

i. Determine how to effectively sequence activities.


ii. Determine how to effectively estimate resource requirements and estimate durations.
iii. Develop an effective schedule.
iv. Effectively utilize schedule controls to keep their projects on schedule.
v. Effectively 'Crash' and 'Fast Track' their projects to meet time and cost requirements.
vi. Determine how to estimate costs.

Course Content
Wk Topic Key Coverage Methodology Evaluation
Introduction - The Triple Constraint Theory (Time, Cost - Power Point - Interactive
and Scope) Presentations questions
- Discussions - Assignments
1 Written 1. Critically evaluate the progress of - Research - To be
assignment major Jubilee government submitted by
projects in relation to the triple end of the
constraint theory focussing much semester
on time and cost since it took over
power.
2. Discuss portfolio theory

- Project Management Processes - Power Point - Interactive


- Initiate & Align the Project Team Presentations questions
1-2 - Plan the Work - Discussions - Assignments
- Endorse the Plan
Project Time - Work the Plan
and Cost - Transition & Closure
Management - Project Management Plan - Power Point - Interactive
Overview - Project Performance Baseline Management Presentations questions
- Project Requirements (Scope) and Quality - Discussions - Assignments
- Project Time (Schedule)
- Project Costs (Budget) & Aging
- Work Breakdown Structure (WBS) - Power Point - Interactive

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 4


- Scheduled Activity (Task) Presentations questions
- Schedule Milestone - Discussions - Assignments
3-5 - Logical Relationship
Schedule - Precedence Diagram (Network Diagram)
Management - Critical Path
- Float (Slack)
- Critical Path Method (CPM) Scheduling - Power Point - Interactive
- Gantt Chart Presentations questions
- Tracking Schedule “Actuals” - Discussions - Assignments
- Base Cost Percent completes
- S chedule cras hing
- Schedule fast tracking
- -“What-If” Scenario Analysis
6 CAT - Sit in CAT Written
Examination
- Resource Estimating - Power Point Written
7-8 - Expert Judgment Presentations Research Paper
- Bottom-up Estimating - Discussions
Resource - Three point Estimating
Planning - Resource Histogram - Lecture - Interactive
- Resource conflict and balancing - Discussions questions
- Resource and Project Calendars - Assignments
- Resource Leveling
- Budget Development - Power Point - Interactive
9- - Analogous Es timating Presentations questions
10 - P arametric Es timating - Discussions - Assignments
Budget - Bottom- up Es timating
Management - Cost Budgeting - Group Work Oral
-Cos t Bas eline - Power Point Assessment
- Cost Control Presentations
- Cost Change Control System
- Earned Value Management
11- Portfolio theory - CAPM, APT and WACC - Discussions - Interactive
13 questions
- Assignments
14- End of - Exams Written
15 Semester examination
Examination

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 5


TEACHING METHODOLOGIES
Lectures, Case Studies, Seminars, critiques, and Term Papers.

INSTRUCTIONAL MATERIALS/EQUIPMENT
Texts, audio and video DVD’s, computer software, case studies

ASSESSMENT
Coursework 40%
Final Written Examination 60%
Total 100 %

COURSE TEXTBOOKS

Gray, C. F., Larson, E. W. (2008). Project Management: The Managerial Process, (4th ed.).
Boston: McGraw-Hill Irwin.

Hopkinson, M. (2011). The project risk maturity model, (2nd). Farnham: Gower Publishers.

Chandra, P. (2009).Projects planning analysis, selection financing implementation and review,


(7th ed.). New Delhi: Tata McGraw Hill.

REFERENCE TEXTBOOKS

Turner, R. (2008). Project Review Assurance and Governance. Farnham UK: Gower Publishers.

Hill, Gerard M. (2008). The Complete Project Management Office Handbook, Second Edition.
New York, NY: Auerbach Publications.

PMBOK Guide (2008). Guide to the Project Management Body of Knowledge: Fourth Edition

COURSE JOURNALS
Journal of Construction project management
Journal of Construction project management and innovation
Practical project management journal

REFERENCE JOURNALS
Project Management connection
Project Management Journal

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 6


International Journal of Project Management

1.1 Introduction
Cost and time estimation is crucial in project management. When getting started in a project, it is
important to set accurate cost and timelines so that progress can be made and goals can be met
successfully. When too much time is allocated for a project, things might not get done as quickly
as they could have otherwise been. If enough time is not permitted, the team may get frustrated
by constantly falling behind and work could suffer.

The ability to accurately forecast project schedule and cost is developed with experience and
through trial and error. If time and cost is not managed successfully, resources or opportunities
are to be wastes. The more time employees are spending on a specific project, the more
expensive that project becomes. When a one-month project ends up taking two, the costs in some
areas of the budget are likely to be doubled – potentially turning the success endeavor into
failure. Its isn’t good enough in most cases to just get the project finished. Rather it needs to be
finished and kept on time and on budget in order to be deemed a success. Thus, the need for
proper time and cost estimation.
What is time and cost estimation?
 It is the process of forecasting or approximating the time and cost of completing project
deliverables.
 It is the task of balancing expectations of stakeholders and need for controls while the
project is implemented.

Importance of Time and Cost Estimation


• To support good decisions.
• To schedule work.
• To determine how long the project should take and its cost.
• To determine whether the project is worth doing.
• To develop cash flow needs.
• To determine how well the project is progressing.
• To develop time-phased budgets and establish the project baseline.

Factors Influencing the Quality of Estimates


a) Organization culture
b) Skills/experience
c) Project duration

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 7


d) People
e) Project structure
f) Non-project factors
g) Planning horizon

Guidelines for Times, Costs and Resources Estimation


1. Have people familiar with the tasks make the estimate.
2. Use several people to make estimates.
3. Base estimates on normal conditions, efficient methods, and a normal level of resources.
4. Use consistent time units in estimating task times.
5. Treat each task as independent, don’t aggregate.
6. Do not make allowances for contingencies.
7. Add a risk assessment to avoid surprises to stakeholders.

Refining Estimates (Reasons for Adjusting Estimates)


 Interaction/hidden costs.
 Normal conditions do not apply.
 Things go wrong on projects.
 Changes of project scope and plans.
 Time and cost estimates of specific activities are adjusted as the risks, resources, and
situation particulars become more clearly defined.

1.2 PROJECT TIME MANAGEMENT

Introduction
Project has to be done within a limited time. Furthermore, when it comes to the main constrains
of the project, time, cost and scope require careful attention throughout the whole project life
cycle; during planning phase, executing and monitoring and control before closing the project.
Time management process happens mainly in the planning phase, although the project duration
and the milestones are already decided in the initiation phase, but it is still the project manager’s
responsibility to plan the project activities and to meet the set project duration within the planned
budget.

Processes involved in project time management;


 Define Activities.
 Sequence Activities.
 Estimate Activity Resources.
 Estimate Activity Durations.
 Develop Schedule.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 8


Project time management includes the processes required to ensure timely completion of the
project. It involves the following major processes:
 Activity Definition—identifying the specific activities that must be performed to
produce the various project deliverables.
 Activity Sequencing—identifying and documenting interactivity dependencies.
 Activity Duration Estimating—estimating the number of work periods which will be
needed to complete individual activities.
 Schedule Development—analyzing activity sequences, activity durations, and resource
requirements to create the project schedule.
 Schedule Control—controlling changes to the project schedule.

These processes interact with each other and with the processes in the other knowledge areas as
well. Each process may involve effort from one or more individuals or groups of individuals
based on the needs of the project. Each process generally occurs at least once in every project
phase. Although the processes are presented here as discrete elements with well-defined
interfaces, in practice they may overlap and interact in ways not detailed here. On some projects,
especially smaller ones, activity sequencing, activity duration estimating, and schedule
development are so tightly linked that they are viewed as a single process (e.g., they may be
performed by a single individual over a relatively short period of time). They are presented here
as distinct processes because the tools and techniques for each are different.

At present, there is no consensus within the project management profession about the
relationship between activities and tasks:
• In many application areas, activities are seen as being composed of tasks. This is the most
common usage and also the preferred usage.
• In others, tasks are seen as being composed of activities. However, the important consideration
is not the term used, but whether or not the work to be done is described accurately and
understood by those who must do the work.

1. ACTIVITY DEFINITION
This process includes defining the activities need to be implemented to achieve the project
deliverables. Activity definition involves identifying and documenting the specific activities that
must be performed in order to produce the deliverables and deliverables identified in the work
breakdown structure. Implicit in this process is the need to define the activities such that the
project objectives will be met.

The main tools and techniques used in defining activities process are;

 Decomposition.
 Rolling wave planning.
 Templates.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 9


 Expert judgment.

Decomposition in project management means to divide the project into smaller pieces that can be
easily managed and controlled. It is a technique used in Work Breakdown structure (WBS)
creation and to define the required activities.

Decomposition of project scope generally involves the following activities:


 Gather information on major project deliverables and analyze related tasks.
 Start development of work breakdown structure (WBS) at the highest level.
 Decompose the upper WBS levels into lower level detailed components.
 Identify each work package & WBS components with unique code, and Verify if the
degree of decomposition of the work is necessary and sufficient.
 Any of Levels of WBS need not be the same for all deliverables.

The work breakdown structure (WBS) is a checklist of every activity that must be performed to
create the end product. This checklist becomes the foundation for the schedule, resource
allocation, and budget plans. WBS is created using questionnaire, one-to-one personal
interviews, or group sessions.

Rolling Wave Planning is a technique that enables you to plan a project as it unfolds. This
technique, then, requires you to plan iteratively. Essentially, when you use Rolling Wave
Planning, plan until you have visibility, implement, and then re-plan. It is usually be used when
you have clarity for the activities of the first months of the project

Inputs to Activity Definition


a. Work breakdown structure (WBS). The work breakdown structure is the primary input
to activity definition.
b. Scope statement. The project justification and the project objectives contained in the
scope statement must be considered explicitly during activity definition
c. Historical information. Historical information (what activities were actually required on
previous, similar projects) should be considered in defining project activities.
d. Constraints. Constraints are factors that will limit the project management team’s
options.
e. Assumptions. Assumptions are factors that, for planning purposes, will be considered to
be true, real, or certain. Assumptions generally involve a degree of risk and will normally
be an output of risk identification

2. ACTIVITY SEQUENCING
Activity sequencing involves identifying and documenting interactivity dependencies. Activities
must be sequenced accurately in order to support later development of a realistic and achievable
schedule. Sequencing can be performed with the aid of a computer (e.g., by using project
management software) or with manual techniques. Manual techniques are often more effective

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 10


on smaller projects and in the early phases of larger ones when little detail is available. Manual
and automated techniques may also be used in combination. The relationships between the
activities of a project can be detected and documented in a process known as Sequence
Activities, which are capable of considering the rational sequence of work and all project
limitations to achieve the highest efficiency. At least a predecessor having a logical relationship
of finish-to-start or start-to-start as well as minimum one successor having a logical relationship
of finish-to-start or finish-to- finish in every activity and milestone, except for the first and last
ones. A realistic and achievable project schedule should be considered in the design of logical
relationships, which might be essentially supported using lead or lag time between the activities.
In this context, project management software or manual or automated approaches can be
beneficial in sequencing.

Inputs required in sequence activities

1. Schedule Management Plan (SMP): The SMP is a pre-project preventive thinking to identify
several points, including the scheduling process involved in the project, thus helping the
sequence activities.
2. Activity List : The activity list contains a critical pathway and basically a detailed
documentation of all schedule activities required and sequenced for a particular project. The
sequence activities can be affected by the dependencies and limitations that exist on the path to
these activities.
3. Activity Attributes : Activity attributes generally refer to active components associated with
an activity, which may be pivotal for sequencing for details like events, predecessors or
successor.
4. Milestone List : The milestone list as a project management document may schedule all
specific project milestones influencing sequence activities.
5. Project Scope Statement: The project scope statement is a good mean to describe the key
deliverables of a project, including product properties involved in sequence activities like
physical lineament of a project being implemented or the nature of a software project. Other
scope statements of project can detail constraints and assumptions associated with sequence
activities. Although these are mostly recorded in the activity list, their accuracy is explored as
product scope description.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 11


6. Enterprise Environmental Factors: The success of sequence activities is depended on either
internal or external enterprise environmental factors (EEFs), including government regulations,
industry conditions, project management information system (PMIS), scheduling tool, or work
authorisation system (WAS).
7. Organizational Process Assets : Another factor contributing to the sequence activities is the
organizational process assets (OPAs), including project plans of the corporate, formal or
informal policies, procedures, processes, scheduling methods to developing logical relationships,
and templates required for providing networks of project activities. Sequence activities can
benefit from additional descriptive data provided by information related to activity
characteristics in templates.
Tools and methods used in sequence activities

Project Dependencies

Dependencies in project management are well-defined as connections among the projects that
decide the sequence in which project management activities should be executed. These tasks
might be multiple preceding tasks which mean that two activities can be appropriate at the same
time. Furthermore, they are described by the four types of dependencies such as discrete,
mandatory, external and internal dependency. Dependency is a method utilized in recognizing
the proper sort of dependency that is used to make the relationship between two activities. The
activities are named as predecessor (which alludes to the principal action) and successor (the
work that goes before the first).

Types of Dependency Determination in Project Management

One of the most critical aspects of creating a strong project schedule is to understand the types of
dependencies that are inherent in the workspace. Characterized into mandatory or discretionary,
internal or external dependency determination attributes can be utilized at the same time in the
following ways:

1. Mandatory dependencies are those that are lawfully necessary as an integral part of the
workplace. Regularly involving physical impediments, the project team figures out the
dependencies that are required to implement amid the process of sequencing the tasks.
Mandatory Dependencies also denoted as hard logic, or hard dependencies should not be
mistaken for relegating plan imperatives in the scheduling tool.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 12


Examples of this logic include:

 Two activities must be performed at the same time (starting and/or finishing at the same
time)
 An activity cannot begin until another activity is completed
2. Discretionary dependencies also referred as preferential logic, are set up based on the
learning of best practices inside a specific application area of the project where a
particular sequence is needed, even though there might be other sequences that are
adequate. Discretionary dependencies can make random float values that can restrict
advanced scheduling options, hence, needs to be documented.

Discretionary dependencies must be audited and considered for modifications when


optimizing systems are in use. The project team figures out which dependencies are
optional amid the way toward sequencing the tasks.

Examples of this logic include:

 Activity will take place at the same time along with another group of activities
 Activity will begin after few days of the completion of another activity
3. External dependencies include a connection between project activities and non-task
activities. Mostly outside the project team’s control, the project management group
figures out which dependencies are external during the process of sequencing the tasks.

Examples of External dependencies include:

 Get approval from the external organization must be gotten before beginning an activity.
 Finishing of a project milestone is connected to the completion of a milestone within
another project.

Developing external dependencies in your project schedule can be cultivated in diverse


ways:

 Embed an achievement that reflects the accomplishment of the external dependency.


 Embed a planning segment that reflects the scheduling of the external dependency.
 Associate definite activities in other project plans that require utilization of big business
planning tools
4. Involving a precedence relationship between project activities Internal Dependencies are
generally within the control of the project team. The project management team figures
out which conditions are inward amid the way toward sequencing the activities.

For instance,

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 13


Types of Dependencies or Logical Relationships

The Precedence Diagramming Method (PDM) includes four types’ dependencies, and each one
has its specific area of application.

 Finish-to-Start
 Finish-to-Finish
 Start-to-Start
 Start-to-Finish

Finish-To-Start: Until the predecessor activity is complete, the successor activity cannot start.

Finish-To-Finish:The successor activity can't be completed until the point that a predecessor
activity is complete.

Start-To-Start:Unless the predecessor activity has not started a successor activity cannot start.

Start-To-Finish:Until the predecessor activity has not begun, a successor activity cannot finish.

To show interdependencies, network diagrams are used.

Network Diagrams
 A network diagram is a schematic display of the logical relationships among, or
sequencing of, project activities.
 Network diagrams are the preferred technique for showing activity sequencing.
 The two main formats are the arrow and precedence diagramming methods

Arrow Diagramming Method (ADM Also called activity-on-arrow (AOA) network diagrams
 Activities are represented by arrows
 Nodes or circles are the starting and ending points of activities
 Can only show finish-to-start dependencies
 Can omit activities that have no dependencies

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 14


Schedule Network Diagrams
A project network diagram of a work schedule demonstrates the logical order that the activities
will follow. It shows a sequence of activities required to complete the project. Basically, there
are two common techniques to create network diagrams. These techniques are Arrow
Diagramming Method (ADM) (or Activity on Arrow) and Precedence Diagram Method (PDM)
(or Activity on Node). Network diagrams enable to determine the critical path of the project. The
critical path is the longest path where a delay on it results in a project delay.

Arrow Diagramming Method (Activity on Arrow Method)


Arrow diagramming method (ADM) is a network diagramming technique like the Precedence
Diagram Method (PDM). In this method, activities are shown as arrows on the diagram. It has
been used a long time to determine the critical path and identify resource problems and feasible
solutions when the approximate duration and resource requirement of all the activities of the
network diagram are known. There are two main elements of the Arrow Diagramming Method
(ADM) which are arrows and nodes. One arrow represents one activity to be performed. The
starting point of the arrow represents the start of the activity and the ending point of the arrow
represents the end of the activity. The length of the arrow represents the duration of the activity.
For better understanding lets analyze the schema below.

The circles numbered 1, 2, 3 and 4 are the nodes of this network system. They are the definable
achievement in the project. Nodes have neither duration nor resource. Activities A, B, C, D are
represented by the arrows. Each activity has a duration and allocated resource.

Arrow Diagramming Method – Dummy Activity


A dummy task which is not a real activity is added to represent dependency between tasks. It can
be used to separate tasks or to keep the sequence correct. Duration of a dummy task is often zero.

When to Use the Arrow Diagramming Method (ADM)


Arrow Diagramming Method (ADM) shows the logical order of activities that helps to determine
the critical path and identify the problems related to resources. From this aspect, it can be used
for schedule compression practices such as fast tracking and crashing. Arrow Diagramming
Method (ADM) can be used to plan and track the activities within a complex schedule with many

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 15


resources. For a successful implementation, activity durations, their sequences and project
execution strategy must be clear.

How to Use the Arrow Diagramming Method (ADM)


Below steps are used in Arrow Diagramming Method (ADM)

 Identify all the activities required to complete the project and list them.
 Estimate the activity durations considering the crews and quantity of work. Estimating
activity durations is an important process because activity durations affect the length
of the critical path. There are some techniques to estimate activity durations. Expert
judgment, analogous estimating, parametric estimating and three-point estimating are
the techniques widely used to estimate the activity durations. Unlike other techniques,
three-point estimates provide most likely, optimistic and pessimistic estimates that are
used for the PERT method.
 Determine the predecessor, successor activities and logical sequences. While
performing this step ask the questions below while using the arrow diagramming
method;
– Which activity will start first?
– Which activities will be performed simultaneously?
– Which activity will finish after this activity?
– Which activity will start after this activity?
Creating a table and organizing the columns with this information may be useful to save time.

 Draw the network diagram by using the data created in former steps. Draw the nodes
for events that represent the beginning or end of an activity. These nodes separate the
activities. Use dummy activities when needed and show them as dashed lines.
 Determine the critical path of the network diagram by performing forward pass and
backward pass calculations.
 Calculate the ES (Earliest Start), EF (Earliest Finish), LS (Latest Start), LF(Latest
Finish) dates for each activity.
 Calculate the Total Float and Free Float for each activity. Total float is the duration
that a task (or an activity) can be postponed without delaying the project. Free float is
the duration that a task can be postponed without delaying the ES of the successor
activity. Float is also known as slack.
Total Float (TF) :LS – ES , LF – EF
Free Float (FF) : ES (of successors) – EF of current activity -1

Summary
The Arrow Diagram was a common visible and practical network diagramming method used in
the past which was developed after the Gantt Charts (or bar charts). It was widely used in the

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 16


past to identify the critical path of a complex project. As a traditional project management
technique, Arrow Diagramming Method (ADM)’ s popularity has fallen away because of the
introduction of software solutions that can calculate the critical path of a project schedule easily
and automatically. In this post, we make a short review of this important network diagramming
method in scheduling. It is critical to understand the logic of network diagrams to create better
schedules.

Precedence Diagramming Method (PDM)


The PDM is a common visual tool to draw a diagram of project schedule network, which depicts
graphical rectangles known as nodes, connected by one or more logical relationships to represent
activities in these boxes. A precedence diagram is shown with the aid of activity-on-node (AON)
strategy that is applied frequently within project management software. There are four logical
relationships or dependencies in the package of PDM, including finish-to-start (FS), finish-to-
finish (FF), start-to-start (SS), and start-to-finish (SF), containing a predecessor activity depicted
logically prior to a dependent activity of a schedule, and a successor activity as a dependent
activity depicted logically after another activity of a schedule.

Figure 3: Four types of dependency in PDM. Inspired by PMBOK[2]

 In a logical relationship of FS, a successor activity can be advanced when the predecessor
activity has finished; for instance, the ceremony of awards (the successor activity) can be
advanced when the competition (the predecessor activity) has elapsed.
 In a logical relationship of FF, a successor activity can finish when a predecessor activity
has finished; for instance, a document editing (the successor activity) can end when a
document writing (the predecessor activity) has finished.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 17


 In a logical relationship of SS, a successor activity can be advanced when a predecessor
activity has advanced; for instance, Level concrete (the successor activity) can be advanced
when a pour foundation (the predecessor activity) has advanced.
 In a logical relationship of SF, a successor activity can be ended when a predecessor
activity begins; for instance, the first shift of security guard (the successor activity) can be
ended when the second shift of security guard (the predecessor activity) begins.
The most and the least commonly used logical relationships in the PDM are FS and SF,
respectively. However, all of these logical relationships are present in a complete list of the
PDM.
PDM SUMMARY
 More popular than ADM method and used by project management software
 Activities are represented by boxes
 Arrows show relationships between activities
 Better at showing different types of dependencies
 Leads and Lags

Figure 4: Lead and lag in sequence activity. Inspired by PMBOK[3]


The time required for starting a successor activity regarding a predecessor activity is called as a
lead. For example, scheduling a landscaping in a construction project of office building can
begin two weeks before the completion of the scheduled punch list. Lead is often planned as a
negative amount for lag in scheduling. The time required for delaying a successor activity
regarding a predecessor activity is called as lag. For instance, a technical writing team has a 15-
day delay time to edit a draft of a large document after writing, meaning a 15-day lag plus SS
relationship (SS+10). Lag can be appeared in diagrams of project schedule network plotted for
the relationship between H and I activities in spite of unclear offset relative to a timescale.
Determination of the need for a lead or a lag in the dependencies is undertaken by the project

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 18


management team in the exact process of defining the logical relationship. The schedule logic
should not be changed following the use of leads and lags. it is essential to document the
activities and corresponding assumptions. [2]
Outputs of sequence activities

1. Project Schedule network diagrams: The logical relationships are graphically drawn called
as project schedule network diagram, also referred to as dependencies among the project
schedule activities, which is prepared by manual manner or project management software. The
diagram can represent full details or summarized activities of the project. A summary narrative
can be illustrated with a diagram to show the used fundamental strategy in sequencing the
activities, and to describe any abnormal sequence of activity on the network.[2]
2. Updates of project documents: There are needs to update the project documents, such as
activity lists, activity attributes, milestone list and risk register.

 Only, the project product description should be prepared for a small project.
 Careful thinking is necessary to achieve quality criteria in order to distinguish whether a
product is acceptable or not. A way to test quality criteria is to scrutinise the distinction
between completed or stopped working on this product.
Product-based planning

Product-based planning is a method for identifying first a product requirements and second all
activities, dependencies and necessary resources to deliver that product. This method has
different applications such as Project planning, Stage planning and Team planning.  The
sequence involved in the development of products of the plan will be developed and the
identification of their dependencies should be detected and defined, which is possible using a
product flow diagram (PFD). The dependencies on any non-project products can be detected
through this diagram, thereby providing the required activities and data for other planning
approaches like estimating and scheduling.
Some essential items should be considered to draw the PFD:

 The PFD is generated by the Project or Team Manager. However, the people responsible for
developing or helping the plan products can be involved rationally.
 When the product breakdown structure (PBS) has been drawn, some planners will decide to
generate the PFD along with the PBS.
 There is need for very few symbols in drawing the PFD. It is essential to detect any
developed product (for instance, enclosure in a rectangle), and to exhibit any required
sequence (for instance, interconnection of rectangles by arrows) in the plan. Moreover, the
external products should be clear as any existing or non-project ongoing products (for
instance, enclosure in a different shape like ellipse).

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 19


 The PFD may be added with a starting point attached from all entry points. Although an exit
is always available in the PFD, when many entrances exist, this position indicator prevents
any of them from being ignored. The symbol of predecessor is there for all points of entry
and is the only symbol in PFD not in PBS.

Product based planning


Detection of activities and dependencies in product-based planning

 Activities:
It is inadequate to merely identify products for scheduling and controlling the objectives. To
completely illustrate the workload of a plan, it is necessary to detect all the activities needed to
establish or modify any of the planned products. The identification of activities can be achieved
through multiple approaches, as follows:

 A separate list of the activities can be provided in spite of the use of PFD as the information
source.
 The required activities can be detected by using the products from the PBS or the work
breakdown structure (WBS).
The activities involve management and quality-checking activities, and those required for
developing the specialist products or for interacting with external parties like those that a product
obtained from an outside source or for transforming external products into targeted ones. It is
needed to shield the spread of activities unnecessary for the plan. Things should be kept simple if
there is any doubt.

 Dependencies:
It is necessary to identify any internal and external dependencies of activities and products. For
example, Activity C cannot start unless activities A and B are completed (as an internal
dependency). Dependency of a delivery of a product needed for a project by another project,
Written and compiled by Dr. Muchelule Yusuf Wanjala Page 20
suggestion of a purchase order by the user and decision-making by the program manager are
examples of the external dependencies.

 Activity sequence:
In the wake of detecting the activities, and estimating related dependencies, duration and effort,
the subsequent step is to approximate the optimal sequence required. This is an iterative step
because the estimated effort and duration may be influenced by actual resource allocation. Float
or slack refers to the amount of time by which a given task in a project network can be delayed
with no influence on the deadline for the project, which can be considered as both provision
within the plan and spare time. Zero float means a condition with no excess time between
activities, which defines a critical activity through the diagram (critical path). In fact, it can be
claimed that any delay in the completion of an activity in the critical path (s) will result in
delayed completion of the entire project. The project manager will be able to monitor the plan’s
activities by detecting the critical path (s) of the plan. Such activities should be timely completed
in order to complete the whole plan in accordance with scheduling. Delay can occur for these
activities for a period if resources are re-allocated to compensate for lost activities.

3. ACTIVITY DURATION ESTIMATING


Activity duration estimating involves assessing the number of work periods likely to be needed
to complete each identified activity. The person or group on the project team who is most
familiar with the nature of a specific activity should make, or at least approve, the estimate.
Estimating the number of work periods required to complete an activity will often require
consideration of elapsed time as well. For example, if “concrete curing” will require four days of
elapsed time, it may require from two to four work periods based on (a) which day of the week it
begins on and (b) whether or not weekend days are treated as work periods.

4. SCHEDULE DEVELOPMENT
Schedule development means determining start and finish dates for project activities. If the start
and finish dates are not realistic, the project is unlikely to be finished as scheduled. The schedule
development process must often be iterated (along with the processes that provide inputs,
especially duration estimating and cost estimating) prior to determination of the project schedule.
shared resources can be especially difficult to schedule since their availability may be highly
variable.

5. SCHEDULE CONTROL
Schedule control is concerned with (a) influencing the factors which create schedule changes to
ensure that changes are beneficial, (b) determining that the schedule has changed, and (c)
managing the actual changes when and as they occur. Schedule control must be thoroughly
integrated with the other control processes.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 21


1.3 PROJECT SCHEDULE DEVELOPMENT

The project Schedule outlines the tasks and activities of the project; the duration; start and end
dates for each individual task and the project as a whole; and the resources and effort required.

For most projects there will be at least two separate Schedules developed. One will be for the
Initiation Phase (Initial Schedule) and the other for the Planning, Execution and Closure
phases. All schedules are added to Eclipse for tracking and updating.

The Initial Schedule is developed in the Initiation Phase of the project to help produce the
Project Charter. At this point, the Schedule is not expected to be very accurate or contain firm
dates; rather it gives the Project Manager (PM) a rough idea of the project timeline and the
assignment of resources. When the Charter is approved, a second Schedule is developed, with
the approval date as the Project “start date”.’

In the Planning Phase, a Project Management Plan is created (from the Charter), and the second
Schedule is updated with a more accurate and realistic timeline. In effect, the start and end dates
of the first Schedule will be replaced by the start and end dates of the second Schedule. Eclipse
allows for the development and saving of multiple schedules. This feature can help in creating
“what if” schedules without disturbing the “active” schedule.

Why prepare a Project Schedules?


 Managers often cite delivering projects on time as one of their biggest challenges.
 Time has the least amount of flexibility; it passes no matter what happens on a
project.
 Schedule issues are the main reason for conflicts on projects, especially during the
second half of projects.

Steps in Developing a project Schedule


 Work Breakdown Structure (WBS)
 Work Packages
 Activities and tasks
 Schedule

a) Work Breakdown Structure (WBS)


The WBS provides a clear description of the project’s deliverables. It describes the “what is to be
done” not the process or schedule.

Therefore the WBS:


 Is a deliverable breakdown structure
 Is a hierarchical decomposition of the work – the deliverables are decomposed to a level
where a work package can be defined (see work package below)
Written and compiled by Dr. Muchelule Yusuf Wanjala Page 22
 Is a graphical representation or textual outline of the project scope
 Represents 100% of the work defined by the project scope and captures ALL
deliverables, internal, external, and interim, including project management

The WBS helps:


 Develop the work packages
 Define the project tasks
 Develop the schedule
 Is a tool to communicate the project to stakeholders

b) Work Packages
Work packages are the lowest level in a WBS decomposition where activity duration can be
reliably estimated and managed. A Work Package can be created where a Project Manager (PM)
deems it necessary to help develop the project Schedule. A work package details a level of work
to be completed. It would contain a description of the work, details of constraints, and agreement
between the PM and the team or individual doing the work, that the work can be done within the
constraints. Assumptions would be defined in the work package depending on the needs of the
project.

Work packages are particularly useful where contractors or other departments are involved in the
project. A work package should define durations of 4 to 6 weeks. The PM would assign the work
package and authorize the work to be completed according to the project Schedule. The PM
would monitor and control the project at the work package level and not necessarily at the task
level.
c) Activities and Tasks
Tasks are the lowest level of work defined in a schedule. A task is the work to be done and
contains a description, the start and end dates, the resource assigned to work on the task and any
dependencies on other tasks. A collection of similar tasks are grouped together and summarized
as an Activity. This aids in the management of progress reporting and communication to
stakeholders, where each task does not need to be communicated individually in detail.

Tasks are usually defined by the person who will perform the task. The Project Manager,
Resource Manager and others who have knowledge of the work required, would be involved
with identifying the tasks and the tolerances for how long they will take using the estimation .

The PMs are currently using the PERT (Project Evaluation and Review Technique method to
determine the effort and duration required on a task or activity.) PERT Analysis uses a weighted
average of three duration estimates to calculate an estimated duration for a task. This is a great
tool when you don't have a specific duration but do have duration estimates from reliable
sources. Who are reliable sources? A reliable source is anyone with experience working with the
particular type of task, including, but not limited to, skilled project managers, the people who

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 23


will be performing the work, and even the data logs of a resource like a machine (to find out how
fast the equipment can get the job done).

PERT analysis requires three numbers:


1. Most Likely Time – The activity time which will likely occur most often?
2. Most Pessimistic Time –The activity duration under the least favourable conditions
3. Most Optimistic Time –The minimum activity duration under the most favourable conditions

Once this estimated duration is determined, a personal fatigue factor (PFD) should be applied.
This is typically 20% of the estimate, and will allow for factors such as; experience level and
issues which could impact the person not spending full time on the task.
d) Schedule
Once the tasks and activities are developed, the Schedule is produced. The schedule is a living
document and needs to be monitored and kept up to date. Once complete, project milestones
should be identified and incorporated into the Schedule. A “milestone” is a point in time in the
project which identifies the end of a significant set of related activities indicating the completion
of a major deliverable. A milestone has no duration or effort.
A final step in the development of the Schedule is to determine a contingency factor to be
applied to the schedule. Typically, a contingency of 10% is applied at the overall schedule level
and not at the task level. On a large project contingency can be applied at a phase, sub-phase or
activity level. Once initial and subsequent schedules are developed, they should be “baselined”.
In most cases, this is done at the completion of the Project Management Plan. A baseline
establishes a point of reference from which a comparison can be made against the plan.

During the development of the Schedule it is important for the PM to keep in mind any
“Assumptions” and “Constraints” identified in the Project Charter and/or Plan, and how they
may impact the timeline. As well, risks and issues should be taken into consideration when
creating the project schedule. Analyzes activity sequences, durations, resource requirements, and
schedule constraints to create the project schedule. No matter the size or scope of a project, the
schedule is a key part of project management. The schedule tells you when each activity should
be done, what has already been completed, and the sequence in which things need to be finished.
Because of the uncertainty involved, the schedule is reviewed regularly, and it is often revised
while the project is in progress. It continues to develop as the project moves forward, changes
arise, risks come and go, and new risks are identified. The schedule essentially transforms the
project from a vision to a time-based plan.

Tools and techniques used to develop project schedule:


 Schedule network analysis.
 Critical path method.
 Critical chain method.
 Resource leveling.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 24


 What-if scenario analysis.
 Applying leads and lags.
 Risk Analysis
 Project review.
1. Schedule Network Analysis: This is a graphic representation of the project’s activities, the
time it takes to complete them, and the sequence in which they must be done. Project
management software is typically used to create these analyses – Gantt charts and PERT Charts
are common formats.
2. Critical Path Analysis: This is the process of looking at all of the activities that must be
completed, and calculating the “best line” – or critical path – to take so that you will complete
the project in the minimum amount of time.
 CPM is a network diagramming technique used to predict total project duration
 A critical path for a project is the series of activities that determines the earliest time by
which the project can be completed
 The critical path is the longest path through the network diagram and has the least
amount of slack or float
 Slack or float is the amount of time an activity may be delayed without delaying a
succeeding activity or the project finish date

Calculating the Critical Path


 First develop a good network diagram
 Add the duration estimates for all activities on each path through the network diagram
 The longest path is the critical path
 If one or more of the activities on the critical path takes longer than planned, the whole
project schedule will slip unless the project manager takes corrective action.

Using Critical Path Analysis to Make Schedule Trade-offs


 Free slack or free float is the amount of time an activity can be delayed without
delaying the early start of any immediately following activities
 Total slack or total float is the amount of time an activity may be delayed from its early
start without delaying the planned project finish date
 A forward pass through the network diagram determines the early start and finish dates
 A backward pass determines the late start and finish dates

Using the Critical Path to Shorten a Project Schedule


Three main techniques for shortening schedules
 Shortening durations of critical activities/tasks by adding more resources or changing
their scope
 Crashing activities by obtaining the greatest amount of schedule compression for the least
incremental cost

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 25


 A 2 week task with one person working 50% could be shortened to 1 week if the person
is assigned 100% - no increase in cost
 Or, a temporary worker could be hired to work in parallel with the other worker to speed
up the task (at a cost)
3. Schedule Compression: This tool helps shorten the total duration of a project by decreasing
the time allocated for certain activities.
4. Resource leveling: Here, you re-arrange the sequence of activities to address the possibility of
unavailable resources, and to make sure that excessive demand is not put on resources at any
point in time.
5. “What if” scenario analysis: This method compares and measures the effects of different
scenarios on a project.
6. Applying leads and lags: Lead refers to a relationship whereby the successor activity begins
before the predecessor activity has completed. While lag refers to a relationship whereby the
successor activity cannot start right after the end of its predecessor’s.
7. Risk Analysis: Risk is inevitable, so you need to prepare for its impact. Adding extra time to
high-risk activities is one strategy. Another is to add a time multiplier to certain tasks or certain
resources to offset overly optimistic time estimation.
8. Project Review: after the initial schedule has been reviewed, and adjustments made, it’s a
good idea to have other members of the team review it as well. Include people who will be doing
the work – their insights and assumptions are likely to be particularly accurate and relevant.
Once you have outlined the basic schedule, you need to review it to make sure that the timing for
each activity is aligned with the necessary resources.
9. A milestone is a significant event that normally has no duration.
 Not every deliverable or output created for a project is a milestone
 It often takes several activities and a lot of work to complete a milestone
 They’re useful tools for setting schedule goals and monitoring progress
 Examples include obtaining customer sign-off on key documents or completion of
specific products such as software modules or the installation of new hardware

The five key points of using project milestones include the following:
1. Define milestones early in the project and include them in the Gantt chart to provide a
visual guide
2. Keep milestones small and frequent
3. The set of milestones must be all-encompassing
4. Each milestone must be binary, meaning it is either complete or incomplete
5. Carefully monitor the critical path

Schedule compression
Project Crashing

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 26


Projects will sometimes have deadlines that are impossible to meet using normal procedures. By
using exceptional methods it may be possible to finish the project in less time than normally
required. However, this usually increases the cost of the project. Reducing a project’s
completion time is called crashing.
 Crashing a project starts with using the normal time to create the critical path
 The normal cost is the cost for completing the activity using normal procedures
 If the project will not meet the required deadline, extraordinary measures must be taken
 The crash time is the shortest possible activity time and will require additional resources
 The crash cost is the price of completing the activity in the earlier-than-normal time.
.While crashing, you will monitor other paths as well. It is possible that the duration of other
paths could become equal or greater than your critical path.

Initially, you will get a greater reduction in duration with less input cost. However, as you
continue further, the cost will increase and the reduction will dwindle.Therefore, do a cost-
benefit analysis. A few examples of crashing techniques are:

 Overtime
 More resources
 Monetary rewards
Crashing cannot be applied to all activities. 

For example, you have to wait until the concrete dries before you can start your next activity.

Example

You are constructing a room. According to the duration estimate, two masons will take four days
to complete it. You have to reduce the duration of this activity by crashing. You add two more
masons to complete the task in two days. Sometimes, crashing may not produce the desired
result. Getting skilled resources is not easy. and they take time to settle. You cannot bring in a
new group of people and expect them to perform immediately. Therefore, it is possible that the
cost will increase without any significant gain. Perform due diligence before using crashing.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 27


Fast tracking activities by doing them in parallel or overlapping them instead of doing them in
sequence. Instead of waiting for all analysis to be completed before starting coding, some coding
could begin for those tasks that have been fully analyzed. Drawback – starting a task too soon
could lengthen the project because other tasks whose analysis has not been completed could
impact this task and cause rework. fast-tracking is a schedule compression technique in which
activities or phases normally performed in a sequence, are done in parallel for at least a portion
of their duration. In fast-tracking, you review the critical path and list all vital activities. Then
you analyze which ones can be performed partially or fully parallel with other activities.
You will not review the activities on the non-critical paths, they have float. Reducing the
duration of those activities will not affect the schedule; it will only give more float to them.

You should monitor other paths whose durations are close to the critical path. If any other path
becomes critical, you will reduce the duration of the new critical path. In this case, your current
path will no longer be critical. Afterward, you will rearrange the fast-tracked activities and
reanalyze the schedule.To compress the schedule, project managers start with fast-tracking
because it does not cost more. However, it increases risk as activities are overlapping.

As a rule of thumb, you can fast track sequential activities by 33%. This means you can start the
next activity when the previous is 66% complete. Both activities partially overlap. It will
increase the risk but within acceptable limits. Fast-tracking helps you compress the schedule up
to certain limits. Continuing beyond the limit will increase the risk, which may lead to rework
and further delays.

Example

Let’s say that you are building a school and construction work is about to finish. Afterward, you
will start carpentry and electrical works. When you review your progress, you see that you are
behind schedule; you have to move faster to complete the project on time. You will review the
carpentry and electrical work activities and see if you can perform them in parallel. Then, you
can apply fast-tracking. In this case, you can start the electrical and carpentry work at the same
time.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 28


Lead VS Fast-Tracking

On a compressed network diagram, activities with lead and fast-track activities look the same.
Hence, many aspirants often think the lead is the same as fast-tracking. Lead is a type of
dependency that you use while developing a network diagram. It is already factored into the
schedule. On the other hand, fast-tracking is a forced overlap. You do it to shorten the schedule.
Fast-tracking increases risks and possible rework, while lead is a dependency type on the
network diagram and it does not affect the risk.
Difference Between Fast Tracking and Crashing

The following are a few differences between fast-tracking and crashing:

 In fast-tracking, activities are rescheduled to be performed partially or fully in parallel,


while in crashing, you add extra resources to the activities to finish them early.
 Fast-tracking does not cost you extra money, crashing does.
 Fast-tracking increases risks. Crashing does not, significantly.
 You use fast-tracking when activities can be overlapped to decrease their duration, while
you use crashing on those where adding extra resources can decrease their duration.
When Should You Use Fast Tracking or Crashing?

This depends on your situation and requirements. For example, if the client wants to complete
the project early and is willing to pay, you use crashing. Generally, you will start with fast-
tracking to shorten the schedule. Once you are done, you can go for crashing if necessary.
Sometimes you may use both techniques. For example, the client is threatening to fine you for
the delay. To avoid this, you will compare the cost of crashing with the fine. If the crashing cost
outweighs the fine, you will use it with fast-tracking for maximum schedule compression.You
may also use crashing if the project delay can affect the company’s image or credibility.

Why are Schedule Compression Techniques Applied to the Critical Path?

As the name suggests, these are schedule compression techniques. The schedule is based on the
critical path,  the longest path of the network diagram and its duration is that of the project.
Reducing other paths won’t reduce the duration of your project. You will just give those paths
more float. If you want to reduce the duration of schedule, you will shorten the duration of the
critical path.

Summary

Projects often get delayed and you have to compress the schedule, fast-tracking and crashing are
two ways to do that. These techniques help you decrease the duration of your project. Fast-
tracking does not involve cost, but it increases risks. Crashing does not significantly increase
risk, but it is a costly process. Use these techniques carefully because you are dealing with
critical activities. Any wrong step can affect your project negatively.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 29


12. Critical chain scheduling
A method of scheduling that considers limited resources when creating a project schedule and
includes buffers to protect the project completion date

Based on the Theory of Constraints (TOC)


A management philosophy developed by Eli Goldratt and introduced in his book The Goal and

Critical Chain
Like a chain with its weakest link, any complex system at any point in time often has only one
aspect or constraint that limits its ability to achieve more of its goal
For the system to attain any significant improvements, that constraint must be identified and the
whole system must be managed with it in mind
For example, two tasks originally scheduled to be done in parallel, require the same resource
100% of the time. CCS acknowledges that either one of the tasks must be delayed or a similar
resource must be found in order to keep to the original schedule.

13 Critical Chain Project Management (CCPM), developed by Eliyahu M. Goldratt, is a


method of planning and managing projects that puts more emphasis on the resources required to
execute project tasks.
This is in contrast to the more traditional Critical Path and PERT methods, which emphasize task
order and rigid scheduling.
A Critical Chain project network will tend to keep the resources levelly loaded, but will require
them to be flexible in their start times and to quickly switch between tasks and task chains to
keep the whole project on schedule.
Typically, CCPM case studies report 95% on-time and on-budget completion when CCPM is
applied correctly

14. Buffers and Critical Chain


In traditional estimates, people often add a buffer to each task and use it if it’s needed or not. A
buffer is additional time to complete a task. This time is added to when there is multitasking,
distractions, interruptions, fear that estimates will be reduced and Murphy’s Law. Murphy’s
Law states that if something can go wrong, it will, Critical chain scheduling removes buffers
from individual tasks.

The tasks estimates in critical chain scheduling should be shorter than traditional estimates
because they do not include their own buffers. Not having tasks buffers should mean less
occurrence of Parkinson’s Law - work expands to fill the time allowed. Feeding and project
buffers protect the date that really needs to be met – the project completion date. Buffer
gives project managers a leeway when unforeseen events occur and is often associated
with scheduling in project management. A buffer can be temporal, financial or qualitative in

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 30


nature, i.e. you have additional time, money or people available for difficult project phases.
Buffers can be assigned either to the whole project or to individual activities (work packages).

Types of buffers
 Project Buffer. The project buffer is placed between the final scheduled task of the critical
chain and the estimated project end-date...
 Feeding Buffer. Adding such a buffer to the schedule makes it possible to avoid situations
when missed completion dates of non-critical chain tasks have an impact to individual tasks
of the critical chain...
 Resource Buffer. It is a portion of time required by critical resources to complete their critical
chain tasks...
 Capacity Buffer (optional). This type of buffers assumes that for a multi-project environment
there is a need to plan for on-call resources by adding more costs covering the resources to
the overall budget...

To develop a project schedule, the following needs to be completed:

 Project scope.
 Sequence of activities.
 Tasks grouped into 5 project phases (conception, definition & planning, launch,
performance, close)
 Task dependencies map.
 Critical path analysis.
 Project milestones.

Cultural Differences as a Cause of Schedule Conflicts


 One dimension of the Meyers-Briggs Type Indicator focuses on peoples’ attitudes toward
structure and deadline
 Judgment type people prefer to follow schedules, meet deadlines and have closure.
Perception types prefer to keep things open and flexible; deadlines are a signal to start
rather than to complete a project
 Different cultures and even entire countries have different attitudes about schedules

1.4 ACTIVITY RESOURCE ESTIMATION

Before estimating activity durations, you must have a good idea of the quantity and type of
resources that will be assigned to each activity. Consider important issues in estimating
resources.

 How difficult will it be to do specific activities on this project?


 What is the organization’s history in doing similar activities?

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 31


 Are the required resources available or need to be acquired?

A resource breakdown structure is a hierarchical structure that identifies the project’s resources
by category and type.

 Duration includes the actual amount of time worked on an activity plus elapsed time
 Effort is the number of workdays or work hours required to complete a task
 Effort does not normally equal duration
 People doing the work should help create estimates, and an expert should review them

Estimating projects activities is hard. Why? Because the only time you know precisely how long
it takes to complete a project is when it’s done. Up to the point of delivery, teams use educated
guesswork to predict the future. And the bigger and more complex a project is, the hazier that
future is. Faulty estimates mean missing deadlines and breaking budgets—two of the main
symptoms of project failure.

Being a skilled estimator is a crucial part of setting schedules, establishing budgets, managing
resources and running a thriving team and business. Using the best online project management
software for the job is a huge help, but knowing the methods and learning how to do them well is
how you become a great estimator. There are a number of activity resource estimation
methodologies to choose from that work for all types of projects.

1. Expert judgment

This is probably the most common way people get an estimate. Talk to the men and women with
the best hands-on experience and understanding of the project requirements. Just make sure that
everyone has the same understanding of what needs to be delivered. And try to find experts who
will actually be working on the project. Experts, with expertise appropriate to the concerned
activity, are asked to estimate the resources and/or duration and/or cost. Experts may be available
within the organization or may be provided from outside the organization.

2. Comparative or analogous estimation

If your current project is similar to past ones, take the data from previous work and extrapolate it
to provide your estimates for the new job. Before proceeding, make sure to check whether those
projects were successful. Analogous estimating is a technique where you refer to those previous
projects which were having, scope or activities, similar to your current project. Then you figure
out how much time and/or these activities have taken earlier, during that project, to make
estimation for duration and/or cost of similar activities in your project. This technique,
sometimes, also called as “Top Down Estimating” because you try to estimate the duration or
cost for whole of the activity, with reference to previous project activities, without breaking it to

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 32


Work Package Level, as it will be hard to map similarities, between previous project and current
project, till that much lower level.

3. Bottom-up Estimating

Using this technique you estimate resources or costs by breaking down complex activities into
smaller pieces and working out resource or cost assignments for these smaller activities using
other resource / cost estimating tools and techniques. It is based on detailed WBS (Work
Breakdown Structure). Here you estimate each piece and add them up. When individual
estimates are added up it becomes the project estimates. This method uses a detailed work
breakdown structure and is best for projects you’re committed to. Each task is estimated
individually, and then those estimates are rolled up to give the higher-level numbers. (If you use
the right project management software, it will roll up the estimates for you). This process makes
you think about what’s required in order to take a step back to see if the big picture still makes
sense. You’ll receive more accurate results than the top-down method, but it’s also a greater
investment of time.

5. Parametric model estimating

This is a more scientific method that essentially auto-calculates estimates using detailed data
from previous activities. This estimation, like analogous estimation technique, requires historical
information gathered from previous projects. This technique is used for both cost and time
estimates calculations. But, unlike analogous estimation technique, parametric estimation
requires plugging the historical data into a formula, spreadsheet, database, or computer program
to come up with an estimate. Let’s say you have data from your last three office network
installation projects. You can use this to get a days-per-workstation value or something similar.
You then plug in the number of workstations for your new installation and out pop the estimates.
When you need to determine what would be the total cost of construction when you have cost
per square foot or the units of work multiplied by productivity unit rate to estimate activity
duration. This can be a quick method but needs robust data to feed it. And because it’s all about
the math, it’s hard to adjust for the environmental, political and cultural differences between
projects.

6. Project Management Software Estimation These are specialized software programs or


software tools for doing estimation for project resources and various costs.

7. Published Estimating Data: This technique is used only for estimating activity resources. 
This published data can include articles, books, journals and periodicals from various industries
that have proven data with similar projects. Using the Published Estimating Data Project
Managers can make a rough estimation of how many resources they need.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 33


8. Alternatives Analysis: It is a technique where you look at various ways to assign resources
by varying the number of resources as well as the kind of resources and then decides upon the
best one.

1.5 ACTIVITY DURATION ESTIMATING

Estimate activity durations is the process of estimating the number of work periods needed to
complete individual activities with estimated resources. The key benefit of this process is that it
provides the amount of time each activity will take to complete, which is a major input into the
develop schedule process. The aim of effective project management is to bring the project to
completion on time and on schedule. Estimating project duration is a key function of scheduling.
Individual activities make up the schedule, and the estimates of their duration determine the
project timetable. The accuracy of the overall schedule depends on the accuracy of these
estimates.

Aspiring project managers must learn how to perform a variety of tasks in order to get a project
started and estimating activity duration is one of them. It’s not always an easy task to estimate
the project duration, because doing so needs a project manager’s knowledge of some theory,
along with application of some best practices and methodologies. To estimate activity duration is
a lengthy process and it takes time for a long-term project. Ideally, you should involve your core
project team in estimating the duration. You should involve the project team, who will work on
the project to achieve the project objectives, project management team, and all the identified key
stakeholders to make a consensus on the milestone dates, and delivery schedules. Depending on
this duration, you can develop a schedule, with milestones for your project.  Estimating activity
duration can be for a project phase or product phase and is iterative in nature.

Activity Duration Estimating technique include:

a) Analogous Estimating

This is a very important methodology that gives you the entire duration estimation. Based on the
information of past projects that are similar, you can get a ballpark idea of the entire duration
estimation. If the company has carried out a similar activity, it may be possible to adapt the
duration to the current case. Project managers have to study the similarities of the two activities
and adjust for any features that may result in differences in duration. Even small businesses can
often find such similar activities on which to base estimates. You may be able to get this
information from the Project Management Office or another project manager; you can use this
template for your current project. 

Analogous estimating the activity duration is not so accurate in nature; however, it is less costly
and less time consuming than other methods. You can frequently use this method when you

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 34


don’t have sufficient time to do a proper estimate, and you have a deadline. Analogous
estimating can be of a part of project as well, since you don’t have to estimate the entire project.
You can estimate activity duration for a single phase of the project, if the requirement /nature of
the phase are very similar to the previous processed project.

Key points

 It is the fastest technique to calculate the estimate; however, less accurate


 It can be used when limited information about the project is available
 It is also known as top-down estimating

b) Parametric Estimating

This method is more accurate in nature. It is based on a statistical calculation of historical data
and other variables. For example, in the design phase in case of a construction project, you may
already have the activity duration: cutting 1,000 stones will take 8 hours and so on. If your
project is of a similar nature to one performed in the past, it is worth your while to find existing
activity duration estimates and historical data from the past project.

Key points

 It uses statistical relationships between historical data and variables


 It is more accurate than the analogous technique

c) Three-Point Estimating

This kind of estimating is based on considering various options like the assignment of the
resources, uncertainty, and the risk associated—such as best scenario-based and worst-scenario
based. The three-point estimating concept is originated from PERT (Program Evaluation and
Review Technique). It gives a weighted average of these three to arrive at a more realistic
estimate. Through PERT, we generally estimate three types of duration:

 Most Likely (M)


 Optimistic (O)
 Pessimistic (P)

Of these, Most Likely (M) is based on the resources assigned and Optimistic (O) is based on the
best scenario-based analysis. And the last one—Pessimistic (P)—is based on the worst possible
scenario-based analysis. Once you have these, you can use some very useful formulas to derive
the expected duration.

They are as follows:

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 35


TE = (O + 4M + P) ÷ 6

Here, TE is expected time, and O, M, P are Optimistic, Most Likely, and Pessimistic duration
respectively. In this way, you can understand the importance of PERT in estimating the duration
for your project. These estimate values are usually taken from subject matter experts in
respective activity area.

Basic concepts used in PERT and CPM


 Network. It is a logical and chronological set of activities and events, graphically
illustrating relationships among the various activities and events of the project.
 Project. This is a group of activities and events with a definite start and end as well as
both human and financial resources. Examples include constructing a dam, building a
house, designing a new product among others.
 Activity. It is a task or job requiring resources to be accomplished. Examples include
collecting data, answering a question in an examination, painting a wall among others.
The activity is depicted by a single arrow ( ) on the project network. The activity arrows
are called arcs.
i. Predecessor activity: Are activities that must be completed prior to the start of another
activity.
ii. Successor activity: Are activities that cannot be started until one or more of the other
activities are completed.
iii. Concurrent activities: Are activities that can be accomplished together at the same
time.
 Event. An event represents a specific accomplishment in the project and takes place at a
particular instant of time. It is a time oriented reference point that signifies the end of one
activity and the beginning of another. Events are usually represented by circles( ). The
event circles are called nodes. All activity arrows must begin and end with event nodes as
shown below: -

Start Finis
Eve Activity h
Event
nt

Types of events.
i. Merge events: it’s where one or more activities join an event.
ii. Burst event: it’s where more than one activity leaves an event.
iii. Merge and burst event: It’s where more than one activity join and leave an event.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 36


Merge event burst event merge and burst event

 A path is a series of adjacent activities leading from one event to another


 Critical path. It is the sequence of critical activities that forms a continuous path between
the start of a project and its completion.
 Critical activity. It’s an activity that if slightly delayed, will hold up the scheduled
completion date of the entire project.
 Dummy activity: it is represented by a dashed arrow on the project network and is inserted
in the network to clarify activity pattern in the following situations:-
i. To make activities with common starting and finishing events distinguishable
ii. To identify and maintain the proper precedence relationship between activities that
is not connected by events.
Example:
The following example shows a simple Activity on Arrow Diagram.

Activity on Arrow Diagram


In this example A,B,C,D,E,F,G rows are representing the activities. Numbers above the rows are
activity durations. As shown in the schema above, in Arrow Diagramming Method(ADM), only
F-S Relationship is used to link activities.

Step 1: Forward Pass Calculation

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 37


Forward Pass Calculation – Arrow Diagramming Method (ADM)

Step 2: Backward Pass Calculation

Backward Pass Calculation-Arrow diagramming method (ADM)

Step 3: Float Calculation for Each Activity / Arrow Diagramming Method Example

Float Calculation-Arrow diagramming method (ADM)


Float can be calculated by subtracting the Start Date of an activity from its Finish Date.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 38


Step 4: Identifying the critical path / Arrow Diagramming Method Example

Critical Path-Arrow diagramming method (ADM)


The critical path is the longest path in the network diagram and the total float of critical path is
zero. As shown in the schema above, the critical path is marked red.

Summary

The Arrow Diagramming Method (ADM) and The Precedence Diagramming Method (PDM) are
two network scheduling techniques. The first one is the traditional one used widely in the past.
The second one is the current method that we are using widely now. In this simple arrow
diagramming method example we show how to make forward, backward, total float and critical
path calculation. Nowadays the arrow diagramming lost its popularity because of the
introduction of software solutions but in order to use this software successfully, it is important to
understand both scheduling techniques.

Guidelines for construction of network diagrams


1. Each activity must be represented by one and only one arrow in the network.
2. No two activities can be identified by the same beginning and end events. In such cases, a
dummy is introduced to resolve the problem.
3. Before an activity can be undertaken, all activities preceding it must be completed.
4. The arrows depicting various activities are indicative of the logical precedence only. The
length and bearing of the arrows are of no significance.
5. The flow of the diagram should be from left to right.
6. Arrows (activities) should be kept straight and should not be crossed.
7. Angle between the arrows should be as large as possible.
8. Dangling must be avoided. This happens when precedence and inter-relationship of the
activities are not properly identified.
9. The general rule (Fulkerson’s rule) for numbering the events is that no event can be
numbered until all preceding events have been numbered. Therefore, the number at the
head of an arrow is always larger than that at its tail.

Example 1

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 39


Draw a network for a project of erection of steel works for a shed. The various elements of the
project are as under:

Activity code Description Prerequisites


A Erect site workshop None
B Fence site None
C Bend reinforcement A
D Dig foundation B
E Fabricate steel works A, C
F Install concrete plant B
G Place reinforcement C, D
H Concrete foundation G, F
I Paint steel works E
J Erect steel work H, I
K Give finishing touch J

Solution

E
I
A C
G H J K

B D
F

Example 2
Draw a network diagram from the following activities.
Activit Immediate predecessor Activit Immediate predecessor
y y
A None G C
B A H C&D
C A I E&F
D A J G&H
E B K I&J
F C

Solution

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 40


E
3 6
B F I
A C K
1 2 4 8 9
G J
7
D
H
5

Time Estimates In Network Analysis


Activity time is a forecast of the time an activity is expected to take from its starting time to its
completion, under normal circumstances. The basic objective of the time analysis is to get a
planned schedule of the project. The plan should include:-
a. Total completion time for the project
b. Earliest time when each activity can begin
c. Latest time when each activity can be started, without delaying the total project
d. Float for each activity i.e. amount of time by which the completion of an activity can be
delayed without delaying the total project completion
e. Identification of critical activities and critical path.
 Slack time of event: It’s the difference between the latest event time and earliest event time
 Head Event slack (HES): It is the slack at the head (or terminal point) of an activity. It is the
difference between the latest event time and earliest event time at its head (or terminal point
or node)
 Tail Event Slack (TES): It is the slack at the tail (or starting point) of an activity. It is the
difference between the latest event time and the earliest event time at its tail (or starting
point or node).
 Earliest Finish Time (EFT): It’s equal to the latest finish time of the activity plus the
duration of that activity.
 Latest Start Time (LST): It is equal to the latest finish time of the activity minus the duration
of that activity.
 Total float: It represents the amount of time by which an activity can be delayed without
delaying the project completion date:
Total Float = Latest Start Time - Earliest Start Time
Total Float = Latest Finish time - Earliest Finish Time
 Free float: It is that portion of the total float within which an activity can be manipulated
without affecting the float of subsequent activities.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 41


Free Float = Total Float - Head Event Slack
 Independent float: It is that portion of the total float within which an activity can be delayed
for start without affecting the float of preceding activities.
Independent Float = Total Float - Tail Event Slack
In case negative value is obtained, it is taken as zero

Critical Path Method


CPM emphasizes the relationship between applying more men or other resources to shorten the
duration of given jobs in a project and the increased cost of these additional resources. With
CPM, the amount of time needed to complete various parts of the project is assumed to be known
with certainty. The relation between the amount of resources employed and the time needed to
complete the project is assumed to be known.
The iterative procedure of determining the critical path involves the following steps:
1. Break down the project into various activities systematically. Label all activities. Arrange all
the activities in logical sequence. Construct the arrow diagram.
2. Number all the nodes (events) and activities. Find the time for each activity considering it to
be deterministic. Indicate the activity times on the arrow diagram.
3. Calculate the earliest start time, earliest finish time, latest start time and latest finish time.
Tabulate various items i.e. activity normal times, earliest times and latest times.
4. Determine the total float for each activity by taking difference between the earliest time and
latest time for each node.
5. Identify the critical activities and connect them with the beginning node and the ending node
in the network diagram by double line arrow. This gives the critical path.
6. Calculate the total project duration.
7. If it is intended to reduce the total project duration, crash the critical activities of the network.
8. Optimize the cost.
9. Update the network and smooth the network resources.

Advantages of CPM
1. Helps the top management to concentrate their attention to the critical activities and their
completion in time.
2. Provides the knowledge of critical and non-critical activities. This helps the management
to divert the resources from non-critical to critical activities.
3. Provides a best way of planning and scheduling a construction project knowing the critical
path.
4. Gives the complete information about the importance, duration, size and performance of
an activity.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 42


Drawbacks of CPM
1. It is based on the assumption of known time for each of the activity in the project, which
may not be true in real life situations.
2. Does not incorporate statistical analysis in determining the time estimates.
3. Entire evaluation of the project is to be repeated and a new critical path is to be found out
when certain changes are introduced in the network.
4. Suitable for a situation that has a definite start and a definite finish.

PROJECT EVALUATION AND REVIEW TECHNIQUE (PERT)


Steps involved in developing PERT network
1. Develop a list of activities that make up the project including immediate predecessors.
2. A rough PERT network is drawn on the basis of the three questions for each activity i.e
which activities precede this one? Which activities follow this one? Which activities
are concurrent with this one?
3. The network is then suitably sketched to conform to rules and conventions.
4. Events are numbered in ascending order from left to right.
5. Time estimates for each activity are then obtained. They are
 The most likely estimate (m or tm). It’s the time the activity will take most
frequently if performed a number of times i.e. the modal value.
 The pessimistic estimate (b or tp). It is the longest time the activity can
conceivably take.
 The optimistic estimate (a or to): it is that time estimate of an activity when
everything is assumed to go well as per plan.
6. Then, upon the assumption of beta distribution for the activity duration, the expected
time, te for each activity is computed from the following formula
te = a + 4m + b/6.
7. Using the expected activity time estimates, determine the earliest start time and the
earliest finish time for each activity. The earliest finish time for the complete project
corresponds to the earliest finish time for the last activity.
8. After determining the latest start time and the latest finish time for each activity,
compute the float associated with each activity, the critical path activities are the
activities with zero float. Determine the critical path through the given network.
9. Using the values for b and a which were determined in step 5, calculate the variance
(2) of each activity’s time estimates by
2 = (b – a/6) 2
10. Use the variability in the activity times to estimates to estimate the variability of the
project completion date. Using this estimate, compute the probability of meeting a
specified completion date by using the standard normal equation:
 = Due date – Expected date of completion
 Project variance

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 43


Where Z = number of standard deviations the due date or target date lies from
the mean or expected date.
11. Crashing or compressing the project may have to be undertaken if the critical path
duration (as the project duration) is not acceptable to the management. Resource
allocation may have to be performed if resources are limited.
Examples
PERT – Program Evaluation and Review Technique Example
The associated network is below. All the inputs are listed in the table below.

PERT Method Example


After building a network diagram and estimating the activity durations, you will determine the
critical path by making forward and backward pass calculations.
Forward Pass Calculations specify the minimum dates at which each activity can be performed
and, ultimately, the minimum duration of a project.

PERT -Forward Pass Calculation


Backward Pass Calculations determine the latest dates by which each activity can be performed
without increasing the projects minimum duration.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 44


PERT -Backward Pass Calculation
After completing the backward pass calculation, you can easily determine the critical path. In
project management, “float” or “slack” is the amount of time that a task can be delayed without
affecting the deadlines of other subsequent tasks, or the project’s final delivery date. Total
float/slack is 0 on the critical path.

PERT Method -Activity


Total Float: LS – ES = 18-15 = 3
Total Float: LF – EF = 30-27 = 3

The total float can be calculated by subtracting the Early Start date of an activity from its Late
Start date or Early Finish date from its Late Finish date.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 45


Critical Path: When we analyze the network diagram we will see that there are some paths and
every path have duration. The critical path is the longest path in the network diagram and
the total float of the critical path is zero.

Summary

In real life, projects are not executed as it was planned all the time. Risks, unexpected events,
uncertainty, and subjective estimates are significant reasons for deviations. PERT is helpful for
estimating the project completion time in case of uncertainty. However, it may be difficult to use
without software. In this example, we talked about the pert definition and calculated the expected
duration for each activity. By making forward, backward calculations, we determined the critical
path. Accuracy of expected durations which affect the critical path depends on the optimistic,
pessimistic and most likely duration estimates. By the help of PERT software, it is easy to make
these calculations efficiently for many combinations.

Exercises
1. A small project consisting of eight activities has the following characteristics:-
Time estimates in weeks
Activity Preceding Most optimistic Most Most pessimistic
activity (a) likely (m) (b)
A None 2 12
B None 10 26
C A 8 10
D A 10 20
E A 7 11
F B, C 9 9
G D 3 7
H E, F, G 5 5
Required;
i. Draw the PERT network for the project.
ii. Determine the critical path
iii. Prepare the activity schedule for the project.
iv. If a 30 weeks deadline is imposed, what is the probability that the project will be
finished within the time limit?
v. If the project manager wants to be 99% sure that the project is completed on the
schedule date, how many weeks before that date should he start the project work?

Activity

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 46


1. A project has the following activities and other characteristics
Activity Preceding Time estimates in weeks
activity
Most Most likely Most pessimistic
optimistic
A None 4 7 16
B None 1 5 15
C A 6 12 30
D A 2 5 8
E C 5 11 17
F D 3 6 15
G B 3 9 27
H E, F 1 4 7
I G 4 19 28

Required:
i. Draw the PERT network diagram.
ii. Identify the critical path.
iii. Determine the mean project completion time.
iv. Find the probability that the project is completed in 36 weeks.
v. If the project manager wishes to be 99% sure that the project is completed on the
scheduled date, how many weeks before should he start the project?
2. A project has the following characteristics
Activity Preceding Time estimates in weeks
activity
Most Most likely Most pessimistic
optimistic
A None 3 7 11
B None 2 2.5 6
C A 2 3 4
D A 6 7 14
E A 2 3 4
F C 2.5 3 3.5
G D 2.5 4 5.5

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 47


H B, E 4.5 5.5 9.5
I H 1 2 3
J F, G, I 1 2 3
Required:
i. Draw the PERT network diagram.
ii. Identify the critical path.
iii. Determine the mean project completion time.
iv. Find the probability that the project is completed in 20 weeks.
Advantages of PERT
1. Forces management to plan carefully how the various parts fit into the whole project.
2. Focuses attention on the critical elements of the project.
3. Provides a forward looking type of control
4. Suggests areas for increasing efficiency, reduction of costs and profit improvements.
5. Makes possible the pressure for action at the right time.
6. Provides up-to-date status information through frequent reporting, data processing and
accurate programme analysis.
7. Helps to formulate new schedules when existing schedule cannot be met, and serve the
planning and evaluation at all levels.
8. Minimizes production delays, interruptions and conflicts by scheduling and budgeting
resources.
9. Co-ordinates the various parts of the total job and thereby expedite and achieve
completion of projects on time.

Shortcomings of PERT
1. Emphasizes on time only and not on costs.
2. Time estimates to perform activities constitute a major limitation of this technique.
3. Calculation of probabilities under PERT approach is done on the assumption that a large
number of independent activities operate on critical path and as such the distribution of
total time is normal but this may not be true in real life situations.
4. Using PERT for active control of a project requires frequent updating and revising the
PERT calculations and this proves quite costly.

Differences between PERT and CPM


PERT CPM
- It’s a probabilistic model with - It’s a deterministic model with well-
uncertainty in activity duration. known activity (single) times based
upon the past experience.
- It is event oriented as the results of - It is activity oriented as the results of
analysis are expressed in terms of calculation are considered in terms of

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 48


events or distinct points in time activities or operations of the project.
indicative of progress.

- The use of dummy activities is - The use of dummy activities is not


required for representing the proper necessary.
sequencing.

- It is used for repetitive jobs. - It is used for non-repetitive jobs.

- It is applied mainly for planning and - It is used for construction and


scheduling research programmes. business problems.

- PERT analysis does not usually - CPM deals with costs of project
consider costs. schedules and their minimization.

Key Points

 It uses three estimates (most likely, optimistic, and pessimistic) to calculate the average
value of activity duration
 It reduces the bias, risks, and uncertainties from the duration calculation
 It is more accurate than the rest

d) Heuristic Estimating

This is also known as Rule of Thumb. You can roughly guess that entire design phase can take
45% of your entire project time and so on…this is a very useful technique in case of known
phases where you can put an imaginary figure based on the experience.

e) Reserve Analysis

Reserve analysis includes estimation of additional time to the project schedule (to allow time for
unexpected delay) and additional cost to the project budget (in case of activity cost overruns). It
is more of like analysis for the contingency or adding buffers to the estimations. A reserve
analysis is a type of contingency reserve. After fixing a schedule for each activity level
depending on the activity attributes, you can create contingency reserve timing by adding some
percentage in the derived schedule of each activity. It can be changed as work progresses;
reducing or increasing depending on the situation.

f) Work Breakdown

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 49


Sometimes an activity is too large or complex for a reliable duration estimate. Project guidelines
state that an individual activity that takes up more than 10 percent of the project schedule has to
be broken down. A project manager uses a work breakdown technique to reduce the activity to
smaller tasks. Ideally, the project manager can estimate the duration of tasks that individual
workers perform more accurately than the whole activity.

g) Historical

An effective way of estimating activity duration is to use historical data. If data on the duration
of the same activities is available, project managers take the average duration of the historical
records and use that in the project schedule. For small businesses which have not completed
many projects, other methods are preferable.

h) Expert Judgment

If expert judgment is available at reasonable cost, a project manager will often use such duration
estimates as superior to internally generated ones. Expert judgment means using specialists who
have a reputation for knowledge of the particular field and experience in estimating activity
duration within it.

i) Effort required

A project manager who knows what resources are necessary for an activity may calculate the
effort the activity requires and arrive at duration. He adds the amount of time it takes to obtain
materials to the labor time it takes to complete the tasks. Such an estimate has the advantage that
it allows the project manager to track resource use and compare it to the estimate.

j) Units to produce

Calculation based on units of activity is a method available to both the largest and smallest
businesses. Typical units are numbers of products or size of the product. Project managers can
calculate how much time it took to produce a certain number or a certain size and adjust for the
number or size they want to produce. Project managers have to adjust for economies of scale for
these calculations.

Network diagram (sequencing the activities). It can be changed as work progresses and as new
activities identified in your project. Initially, you can estimate your project based on the network
diagram (sequencing the activities). It can be further modified based on the changes done in the
project during the execution, controlling and monitoring process. While project managers can't

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 50


know the actual time, it will take to complete an activity, there are six methods they can use to
obtain reliable estimates.

1.6 PROJECT SCHEDULE CONTROL


Controlling Schedule is the project management activity in which progress on project
activities is compared against Schedule baseline to understand whether project is ahead of the
schedule or behind. Based on the deviation you can plan on corrective or preventive actions and
manage changes to baseline. Control schedule is the last process of time management
knowledge area. Control schedule is the process of monitoring the status of the project
activities to update project progress and manage changes to the schedule baseline to
achieve the plan. After develop schedule process is complete, you will have the project schedule
and it will include start and end dates of each project activity. During project execution, actual
results of the project will differ from the planned values. While some activities could be
completed earlier than planned, some activities will take longer to complete. During control
schedule process, actual results of the activities will be compared with the schedule baseline to
determine any variances.

During control schedule process, project managers must measure against the plan and control the
project. If there is a variance based on the schedule performance control, and if the project
cannot be completed on time, corrective actions must be planned and taken. For instance,
schedule compression can be planned to complete the remaining project activities earlier than
planned to complete the project on time. During project execution, if factors causing lots of
changes are found, these factors must be eliminated to prevent the root cause of changes. If
they cannot be eliminated, the impact of these factors must be minimized by taking preventive
actions.

Activities in Control Schedule Process

1. Re-estimation of the remaining components of a project: During the planning of the


project, all future activities of the project are estimated based on very limited information
on hand. While project progresses, unclear points will be cleared, the project team will
have more information about the project and by this way, remaining activities will be
estimated healthier respectively. Therefore, re-estimation for the remaining activities of
the project is done during control schedule process to check whether the target project
completion date will be achieved.
2. Conduct performance reviews: Actual results of each activity will be measured against
the planned values in the schedule baseline during control schedule process. Based on the
performance review, whether the project is on track is determined.
3. Adjust future parts of the project to deal with delays: If the project is behind the
schedule, appropriate actions must be taken to get back on track. This is why you conduct
the control schedule process. If the project is behind the schedule, the future parts of the

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 51


project must be adjusted to deal with delays. For instance, schedule compression
techniques like fast tracking or crashing can be applied for a project behind the schedule.
4. Measure variances against schedule: Schedule variance and schedule performance
index of the project will show how far behind is the project from the planned values.
These are measured during control schedule process. For instance, if the project duration
is 12 months, and if the schedule variance is 1 month, this means the project will be
completed in 13 months with a 1-month delay. Or, if schedule performance of the project
shows 0.90, this means, 90 percent of the planned activities could have been completed to
date. So, there is a delay for the remaining part and project is behind the schedule. 
5. Level resources to distribute work: Based on the actual results of the project, some
remaining activities of the project may cause overload on some project resources. In
order to offload the project activities to available resources, resource leveling can be done
during control schedule process.
6. Continue to play “what if…” to better optimize: Planning is an iterative process in
project management as we mentioned previously. Therefore, during control schedule
process, if there are any alternatives to shorten the duration of the remaining project
activities, these must be identified and applied respectively.
7. Adjust progress and project reports: During project progression, you need to report to
project stakeholders about the status of the project. And depending on the stakeholders
you are reporting to, you need to adjust appropriate reports. For instance, if you are
reporting to executive managers, you need to prepare high-level milestones in your report
and if you are preparing for your project team, you need to prepare a detailed report
showing the status of activities, remaining activities etc. You adjust the reports 
8. Utilize change control process: Once project schedule is complete, schedule baseline is
taken, and it can be changed only if there is an approved change request in the project.
Change requests are evaluated by change control board in a project and if approved,
appropriate changes must be aligned in the project plan to accommodate this change. For
instance, in order to implement change request, new project activities need to be added to
project schedule and maybe the critical path of the project will change. During control
schedule process, it is ensured that changes are applied through change control process
and only approved change requests are applied.
9. Identify the need for change requests: What is the reason for the change request? Is it
because an improper planning or is it a new requirement coming from the customer? As a
project manager, you have to avoid unnecessary changes in your project. These are
analyzed during control schedule process as well.

Importance of Re-Estimating in Control Schedule Process

Re-estimate the remaining components of the project at least once over the life of the project to
make sure you can still meet deadline, budget, and objectives. In the planning phase of your
project, you have planned the project activities appropriately. You have got a cost baseline, you

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 52


have got a schedule baseline and you have a project management plan to execute the project.
With these baselines and plan, you know what to deliver at what time and at what cost. However,
during the execution of your project, the actual values of these activities might be different
than what you planned in the beginning.

And based on your actual values, you have to do frequent re-evaluations, frequent reviews, and
frequent re-estimation on your project to check whether you will be able to still meet your
project schedule and whether you will be able to still meet your target budget at the end of
your project. If there are problems, for instance, if there is any variance that is showing that you
will exceed your budget or that you will exceed the agreed end date of the project, then, you
have to take corrective actions to meet the schedule baseline and to meet the cost baseline of
your project.

In order to detect these variances and then take corrective actions respectively, you have to do re-
estimating in your project frequently, and these should be determined at the beginning of your
project. For example, you might say that I will be doing re-estimating each month or I will be
doing re-estimating in every two weeks. Because re-estimation will take a time and you need
to determine the appropriate frequency for re-estimating. And, based on this frequency, you
have to do re-estimating and check whether you are still meeting the baselines of your project.

1.7 COST ESTIMATION AND FORECASTING

1.0 Introduction
Cost estimation may be defined as ‘a study which attempts to predict the relationship between
costs and the activity level or cost driver that causes those costs. In practice, managers frequently
encounter such cost drivers (what is a cost driver?) as machine hours, number of transaction,
work cells, labour hours, and units of output e.t.c.
Types of Costs
• Direct Costs
– Costs that are clearly chargeable to a specific work package. Labor, materials, equipment, and
others.
• Direct (Project) Overhead Costs
– Costs incurred that are directly tied to an identifiable project deliverable or work package.
Salary, rents, supplies, specialized machinery
• General and Administrative Overhead Costs
– Organization costs indirectly linked to a specific package that are apportioned to the project

The cost estimating function is;


Y = a + bx
Where y is the total cost
Written and compiled by Dr. Muchelule Yusuf Wanjala Page 53
a is the fixed cost component of the total cost
bx is the variable cost component of the total cost
However,
b represent the variable cost/slope or the gradient of the equation.
x represent the output level Q

1.1 Purpose of Estimation


It assists in estimating the future expenditure (cost prediction) as the expenditure will depend on
the cost of the respective activities
a) It assists in determining the net benefits anticipated in a specific activity based on the
relationship between projected costs and projected revenue.
b) Cost estimation is useful in business planning, cost control, performance evaluation and
decision making.
1.2 Steps of Developing a Cost Estimating Relationship. 
Strictly speaking, a CER is not a quantitative technique. It is a framework for using appropriate
quantitative techniques to quantify a relationship between an independent variable and cost or
price. Development of a CER is a 6-step process shown below:

Step 1. Define (or select) the dependent variable (Y)

Will the CER be used to estimate price, cost, labor hours, material cost, or some other measure
of cost? Will the CER be used to estimate total product cost or estimate the cost of one or more
components? The better the definition of the dependent variable, the easier it will be to gather
comparable data for CER development.
The dependent variable is the cost to be predicted and it is choice depends on the purpose of the
cost function. It may also be referred to as response variable.

Step 2. Select the cost driver(s)


This may also be referred to as independent, explanatory or predictor variable. A cost driver can
be defined as any factor whose change causes a change in the total cost of an activity.

Examples of potential cost driver


 Direct labour hours
 Machine hours
 Number of units
 Number of production runs
 Number of orders, etc.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 54


The potential cost driver should make economic sense and should be accurately measured. In
selecting potential cost drivers for CER development Consider the following factors:
Variables should be quantitatively measurable. Parameters such as maintainability are difficult to
use in estimating because they are difficult to measure quantitatively. Data availability is also
important. If you cannot obtain historical data, it will be impossible to analyze and use the
variable as a predictive tool. For example, an independent variable such as physical dimensions
or parts count would be of little value during the conceptual phase of system development when
the values of the independent variables are not known.

Be especially wary of any CER based on 2 or 3 data observations. If there is a choice between
developing a CER based on performance or physical characteristics, performance characteristics
is generally the better choice, because performance characteristics are usually known before
design characteristics.

Step 3. Collect data concerning the relationship between the dependent and independent
variables.
Collecting data is usually the most difficult and time-consuming element of CER development. It
is essential that all data be checked and double checked to ensure that all observations are
relevant, comparable, relatively free of unusual costs. A sufficient number of past observations
must be obtained to derive an acceptable cost function. This should be adjusted to reflect any
change of circumstances e.g. changes in price levels caused by inflation, changes in types of
equipment used, etc. The time period used to measure the dependent variable and the cost driver
should be the same.

Step 4 Plot the data on a graph


The graph (usually referred to as a scatter diagram) will indicate the general relationship between
the dependent variable and the cost driver and will give a visual indication as to whether a lineal
cost function can approximate the cost behaviour. It will also highlight extreme observations
(outliers).

Step 5. Select the relationship that best predicts the dependent variable.
After exploring a variety of relationships, you must select the one that can best be used in
predicting the dependent variable. Normally, this will be the relationship that best predicts the
values of the dependent variable. A high correlation (relationship) between a potential
independent variable and the dependent variable often indicates that the independent variable
will be a good predictive tool. However, you must assure that the value of the independent
variable is available in order for you to make timely estimates. If it is not, you may need to
consider other alternatives.

There are various methods that can be used to estimate the cost function. Examples include:

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 55


i. Engineering method
ii. Account analysis
iii. High low method
iv. Regression method
v. Visual fit (scatter graph method)
vi. Learning curve Theory
Step 6: Test the reliability of the cost function

There are three main tests that should always be done. These include:
a) Logical relationship tests
b) Goodness of fit test
c) Specification tests (Tests of the assumptions of the model)

1.3 Cost Estimation Method


a) Engineering method
These methods are based on the use of engineering analysis of technological relationship
between inputs and outputs e.g. method studies and time and motion studies. The procedure in
such a study is to make an analysis based on direct observation of the underlying physical
quantities required for an activity and then to convert the final result into cost estimate. This
method is useful for estimating costs of repetitive processes where input and output relationship
is clearly defined e.g. the cost associated with direct materials, direct labour and machine time.

b) Account analysis (Inspection of accounts) method


This method requires that departmental managers and the accountant inspect each item of
expenditure within the accounts for some output level and then classify each of these items as
wholly fixed, wholly variable or mixed.

A single average unit cost figure is selected for the items categorized as variable whereas a single
total cost for the period is used for the items categorized as fixed. Mixed costs are decomposed
into their variable and fixed components.

c) Work Breakdown Structure

Dividing the project into smaller tasks lets a project manager get an overview of cost. One
method that accomplishes such a simplification is the work breakdown structure. Once the
project is broken up into small tasks, the project manager can assign costs. For equipment that he
has to purchase, he can contact suppliers to get accurate estimates. For other tasks, he can
estimate the number of hours and use an hourly rate.

d) Resource Costing
Written and compiled by Dr. Muchelule Yusuf Wanjala Page 56
A common technique for cost estimating is to list the resources you need for the project and to
total their costs. Typical resources include equipment, material, services and labor. You can get
costs for equipment, material and services by consulting price lists or by going out for bids for
the larger pieces. Labor costs are hourly, and you can base the total costs on estimates from
similar projects or ask for bids to carry out the work. Small businesses use resource costing for
larger or more complicated projects.

e) Unit Costs
Small or simple projects can be evaluated using a cost-per-unit that is characteristic of the
project. The characteristic unit is a measure of the size of the project that is indicative for the
particular project. It might be a cubic foot, a square foot or a work station. Typical applications
are for building costs, paving, renovating or for standard systems such as data processing. Costs
are a dollar amount per unit. To get the total cost, you decide how large the building or surface is
or how many people will be working on the data. Multiply that by the unit cost to get the total.
You can get typical unit costs from prospective suppliers or from industry associations.

f) Historical Costing
One of the most transparent ways of estimating the cost of a project is to base it on previous
work. If your company has completed a similar project recently, all the required costing
information is available from the project files. If you don't have such a project, other work your
company has done in the past can help determine the cost of similar work on the new project. If a
local business that is not a competitor has completed a similar project, it might be willing to help.
Where available, historical data often gives the most accurate prediction of future costs.

1. Cost of Quality: Cost of Quality estimation is used for determining overall cost
estimates. It includes Cost of Conformance ( i.e money spend on Quality training,
studies, surveys, inspection, validation & audits) and Cost of Non Conformance ( i.e
money spent on  rework , scrap, inventory and warranty costs ).
2. Vendor Bid Analysis: This technique is usually used when you need to work with
external vendor or contractor to get your project activities done. This technique helps you
to analysis what the project cost should be based on the bids from vendors and estimate
the price of individual deliverables.

g) High low method (Two point method)


Under this method, records of costs in the previous period are reviewed and the costs of 2
periods are selected. These are the period with the highest level of outputs and the period with
the lowest output. A line passing through these two points is then established and used in
estimating costs. The high‐low method divides the change in costs for the highest and lowest
levels of activity by the change in units for the highest and lowest levels of activity to estimate
variable costs

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 57


Illustration 2.1
The production manager of XYZ Company, is concerned about the apparent fluctuation in
efficiency and wants to determine how labour costs (in Sh.) are related to volume.
The following data presents results of the 12 most recent weeks.

Week No. Units Produced(X) Labour Costs(Y)


1 34 340
2 44 346
3 24 287
4 36 262
5 30 220
6 49 416
7 39 337
8 21 180
9 41 376
10 47 295
11 34 215
12 24 275

Required:
Estimate the cost function using the high low method

Assume that the Company intends to produce;


45 units
34 units next period
Estimate the labour cost to be incurred.

Solution
Highest point X Y
49 416
Lowest point 21 180
Difference 28 236

Gradient/slope = b = 236 = 8.43


28

The function will be:

Y= a + bx

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 58


We can Substitute the lowest points (21,180)
180 = a + 8.43(21)
a = 2.97. This can be approximated to 3

The predicting equation is therefore Y = 3 + 8.43 x

i. if X=45 units

Y = 3 + 8.43*45
= Sh.382.35
i. if X =34

Y = 3 + 8.43(34)
= Sh.289.62

Note:
The main problems of the high low method are:
a. Reliability is low
b. It ignores all the other points except the highest and lowest which in most cases are
outliners.

h) Regression Analysis
A regression equation identifies an estimated relationship between a dependent variable (the
cost) and one or more independent variables (the cost driver). When the equation includes only
one independent variable then it is referred to as simple regression and its form is:

Ỹ= a + bx

Where, Ỹ is the predicted value of Y


a and b are Constant
x is the cost driver
When the equation includes 2 or more independent variables, it is referred to as multiple
regression and is of the form:

Y = a + b 1 x1 + b2 x2 + …….bn xn for n independent variables.


Simple Regression
Regression analysis determines mathematically the regression line of best fit. It is based on the
principle that the sums of squares of the vertical deviation from the line established is the least
possible

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 59


(Y  Yˆ ) 2
I.e.  is minimized
Where Y is the observed value of the dependent variable
Ŷ is the predicted value of Y

The equation can be solved by the use of normal equations and these are:
1. y = na + b (x)
xy = a (x) + b (x2)

From these normal equations:


b = n xy – x y
nx 2– (x)2
a= Y - bx
n n
Looking at illustration 2.1, then we first compute the sum of X, Y, XY, X 2 and Y2. The table
below shows these summations.

Week No. Units X) L.Costs(Y) XY X2 Y2

1 34 340 11560 1156 115600


2 44 346 15224 1936 119716
3 24 287 8897 961 82369
4 36 262 9432 1296 68644
5 30 220 6600 900 48400
6 49 416 20384 2401 173056
7 39 337 13143 1521 113569
8 21 180 3780 441 32400
9 41 376 15416 1681 141376
10 47 295 13865 2209 87026
11 34 215 7310 1156 46225
12 24 275 6600 576 75625
430 3549 132,211 16234 1104005

Value of b can be calculated as follows:


b= 12(132211) - 430(3549) = 6.10
12(16234) - (430) 2

a = 3549 - 6.10( 430) = 77.08


12 12

NB. Remember that Y = a + bx

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 60


Therefore the predicting function is Ŷ = 77.08 + 6.1X
b. i. If X = 45 units, then

Ŷ = 77.08 + (6.1 x 45)


= Sh.351.58

ii. If X = 34 units, then

Ŷ = 77.08 + (6.1 x 34)


= Sh.284.48
Illustration 2.2
Assume that the company (in illustration 2.1) intends to spend Sh.400 on labour cost next period.
Compute the number of units that the company may produce.

i) Visual Fit (scatter graph method)


Cost estimation is based on past data regarding the dependent variable and the cost driver.
The past data on cost levels and the output levels) is plotted on a graph (called a scatter
graph) and a line of best fit is drawn as shown in the diagram. A line of best fit is a line
drawn so as to cover the most points possible on a scatter graph. Its intersection with the
vertical axis indicates the fixed cost while the gradient indicates the variable cost per unit.

Illustration:
Assume a firm has total costs of 8m, 4m and 1m respectively when the output units are 400,000
200,000 and 0 respectively. Estimate its cost equation using the visual fit method.
10
9
Dependant 8 X
Variable 7 X X X
(Total Cost) 6 X X X
5 X X X X X
4 X

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 61


3 X X X X X
2 X X

1m X

X2 X3
0 200,000 400,000
Independent Variable
(Output Level)
Fixed Cost  X
 0  1m
Note :  Change in Y
 Gradient   Y3 - Y2  Variable Cost Per Unit
 Change in X X3  X2

Variable cost = Change in cost = 8m – 4m = 20


Per unit Change in activity level 400,000 – 200,000

Total cost equation y = 1m + 20 x
On the basis of the existing data, fixed cost is Shs 1m and the variable cost per unit is 20. On the
basis of the developed model, estimates can be made regarding future cost. When the activity
level is 600,000 units, total cost will be estimated as:
TC = 1M + 20 (600,000) = 1M + 12M = 13 M
Discussion Question
The theory of the experience curve is that an organization may increase its profitability through
obtaining greater familiarity with supplying its products or services to customers. This reflects
the view that profitability is solely a function of market share.
Required:
Discuss the extent to which the application of experience curve theory can help an organization
to prolong the life cycle of its products or services.

NET PRESENT VALUE

Net present value in its simplest form can be explained as the calculation that compares the
amount invested today to the present value of the future cash receipts from the investment. In
other words, the amount invested is compared to the future cash amounts after they are
discounted by a specified rate of return. When assessing any given project or initiatives,

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 62


organizations use the NPV as a technique of evaluating their relative profitability to ensure that
the most profitable ones are undertaken. A larger NPV indicates that the selected project has a
higher revenue. The formula for NPV varies slightly depending on the consistency with which
returns are generated. If each period generates returns in equal amounts, the formula for the net
present value of a project is:

NPV = C * {(1 - (1 + R) ^ -T) / R} − Initial Investment

where C is the expected cash flow per period, R is the required rate of return and T is the number
of periods over which the project is expected to generate income.

However, many projects generate revenue at varying rates over time. In this case, the formula for
NPV is: NPV = {C for Period 1 / (1 + R) ^ 1} + {C for Period 2 / (1 + R) ^ 2} ... - Initial
Investment. Besides, there are other ways to compute the NPV as follows in the examples below
using the even cash inflows and the uneven cash inflows.

Example1: Even Cash Inflows:


 Calculate the net present value of a project which requires an initial investment of $243,000 and
it is expected to generate a cash inflow of $50,000 each month for 12 months. Assume that the
salvage value of the project is zero. The target rate of return is 12% per annum.
Solution
We have,
Initial Investment = $243,000
Net Cash Inflow per Period = $50,000
Number of Periods = 12
Discount Rate per Period = 12% ÷ 12 = 1%
Net Present Value
= $50,000 × (1 − (1 + 1%)^-12) ÷ 1% − $243,000
= $50,000 × (1 − 1.01^-12) ÷ 0.01 − $243,000
≈ $50,000 × (1 − 0.887449) ÷ 0.01 − $243,000
≈ $50,000 × 0.112551 ÷ 0.01 − $243,000
≈ $50,000 × 11.2551 − $243,000
≈ $562,754 − $243,000
≈ $319,754

Example 2: Uneven Cash Inflows: 


An initial investment of $8,320 thousand on plant and machinery is expected to generate cash
inflows of $3,411 thousand, $4,070 thousand, $5,824 thousand and $2,065 thousand at the end of
first, second, third and fourth year respectively. At the end of the fourth year, the machinery will
be sold for $900 thousand. Calculate the net present value of the investment if the discount rate is
18%.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 63


Solution
PV Factors:
Year 1 = 1 ÷ (1 + 18%)^1 ≈ 0.8475
Year 2 = 1 ÷ (1 + 18%)^2 ≈ 0.7182
Year 3 = 1 ÷ (1 + 18%)^3 ≈ 0.6086
Year 4 = 1 ÷ (1 + 18%)^4 ≈ 0.5158
The rest of the calculation is summarized below:
Year 1 2 3 4
Net Cash Inflow $3,411 $4,070 $5,824 $2,065
Salvage Value 900
Total Cash Inflow $3,411 $4,070 $5,824 $2,965
× Present Value Factor 0.8475 0.7182 0.6086 0.5158
Present Value of Cash $2,890.68 $2,923.0 $3,544.67 $1,529.31
Flows 1
Total PV of Cash Inflows $10,888
− Initial Investment − 8,320
Net Present Value $2,568 thousand
INTERNAL RATE OF RETURN

The internal rate of return (IRR), is a profitability metric used by businesses to determine which


projects are likely to yield the greatest return per dollar of capital investment. Though it is
closely related to the net present value, the IRR reflects anticipated gains as a percentage of the
initial investment rather than as a net dollar amount.

Intenal Rate of return is used to evaluate the beauty of a assignment or investment. If the IRR of
a new project exceeds a enterprise’s required fee of return, that venture is fascinating. If IRR
falls under the desired cost of return, the mission must be rejected.

The following is the formula for calculating the IRR;

0 = P0 + P1/(1+IRR) + P2/(1+IRR)2 + P3/(1+IRR)3 + . . . +Pn/(1+IRR)n

where P0, P1, . . . Pn equals the cash flows in periods 1, 2, . . . n, respectively; and

IRR equals the project's internal rate of return.

IRR example in its simplest form;

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 64


A machine can reduce annual cost by $40,000. The cost of the machine is 223,000 and the useful
life is 15 years with zero residual value.
Required:
1. Compute internal rate of return of the machine.
2. Is it an acceptable investment if cost of capital is 16%?
Solution:
(1) Internal rate of return (IRR) computation:
Internal rate of return factor = Net annual cash inflow/Investment required
= $223,000/$40,000
= 5.575
Now see internal rate of return factor (5.575) in 15 year line of the present value of an annuity if
$1 table. After finding this factor, see the corresponding interest rate written at the top of the
column. It is 16%.  Internal rate of return is, therefore, 16%.
(2) Conclusion:
The investment is acceptable because internal rate of return promised by the machine is equal to
the cost of capital of the company. A general rule of thumb is that the IRR value cannot be
derived analytically. Instead, IRR must be found by using mathematical trial-and-error to derive
the appropriate rate. However, most business calculators and spreadsheet
programs will automatically perform this function. IRR can be used to calculate anticipated
returns on shares or investments, including the yield to maturity on bonds. IRR calculates the
yield on an funding and is for that reason one-of-a-kind than internet present worth (NPV) price
of an investment

Advantages of IRR
The various advantages of internal rate of return method of evaluating investment projects are as
follows:
Time Value of Money: The first and the most important thing is that it considers the time value
of money in evaluating a project which is a big lacking in accounting rate of return.
Simplicity: The most attractive thing about this method is that it is very simple to interpret after
the IRR is calculated. It is very easy to visualize for managers and that is why this is preferred
till the time they come across certain occasional situations such as mutually exclusive projects.
Hurdle Rate / Required Rate of Return has Not Required: The hurdle rate is a difficult and
subjective thing to decide. In IRR, the hurdle rate or the required rate of return is not required for
finding out IRR. It is not dependent on the hurdle rate and hence the risk of a wrong
determination of hurdle rate is mitigated.

IRR also allows managers to rank projects by means of their total rates of return rather than their
web reward values, and the investment with the absolute best IRR is most often favored. Ease of
comparison makes IRR attractive, but there are limits to its usefulness.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 65


PAY BACK PERIOD

Payback interval is the time in which the preliminary money outflow of an funding is anticipated
to be recovered from the cash inflows generated by means of the investment. It is among the
simplest investment appraisal strategies.

Formula

The formula to calculate payback period of a project depends on whether the cash flow per
period from the project is even or uneven. In case they are even, the formula to calculate payback
period is:

Initial Investment
Payback Period =
Cash Inflow per Period

When cash inflows are uneven, we need to calculate the cumulative net cash flow for each period
and then use the following formula for payback period:

:Payback Period = A B
+ C

Within the above system,

A is the final interval with a bad cumulative money go with the flow;

B is the absolute value of cumulative money flow on the end of the interval A;

C is the total money glide in the course of the period after


the above instances are utilized in the following examples.

Decision Rule

Accept the project only if its payback period is LESS than the target payback period.

Examples

Example 1: Even Cash Flows

Company XYZ is planning to undertake a task requiring preliminary investment of $105million.


The venture is expected to generate $25 million per 12 months for 7 years. Calculate its payback
period.

Solution.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 66


Payback interval = initial funding ÷ Annual cash go with the flow = $105M ÷ $25M = 4.2 years

Example 2: Uneven cash Flows

Company XYZ is planning to undertake another assignment requiring initial funding of $50
million and is expected to generate $10 million in year 1, $13 million in 12 months 2, $16
million in year three, $19 million in year four and $22 million in year 5. Calculate the payback
price of the project
Solution
(cash flows in millions)Cumulative
Year Cash Flow Cash Flow
0 (50) (50)
1 10 (40)
2 13 (27)
3 16 (11)
4 19 8
5 22 30
Payback Period
= 3 + (|-$11M| ÷ $19M)
= 3 + ($11M ÷ $19M)
≈ 3 + 0.58
≈ 3.58 years

Merits and demerits of payback period are as follows;

a. Pay back period gives more importance on liquidity for making decision about the investment
proposals.

b. Pay back period deals with risk. The project with a shortest PBP has less risk than with the
project with longest PBP.

c. The short term approach of pay back period is an added advantage of calculation of capital
expenditure

Demerits are;
a. Pay back period gives high emphasis on liquidity and ignores profitability.
b. Only cash flow before the pay back period is considered. Cash flow occurred after
the PBP is not considered.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 67


Accept or Reject Criteria of payback period
A undertaking is also approved or rejected on the groundwork of the per-decided (average) pay
again interval if just one unbiased mission is to be evaluated. The general pay back interval relies
on the management in phrases of maximum period in the course of which preliminary investment
must be recovered.
A undertaking is accredited if the actual pay back period is less than the regular pay again period.
When two or more jointly wonderful projects are regarded for selection, they could also be
ranked according to the length of payback interval. Consequently, the mission having the
shortest pay again period could also be assigned first rank, adopted in that order so that the
undertaking with the longest pay back period would be assigned lowest rank.
How do you calculate the payback period?
The payback period is calculated through counting the quantity of years it will take to recuperate
the money invested in a assignment.
Let's anticipate that a corporation invests $400,000 in additional effective gear. The money
savings from the new equipment is predicted to be $100,000 per 12 months for 10 years. The
payback interval is 4 years ($four hundred,000 divided via $100,000 per year). A 2nd venture
requires an funding of $200,000 and it generates money as follows: $20,000 in 12 months 1;
$60,000 in year 2; $eighty,000 in yr three; $100,000 in yr 4; $70,000 in 12 months 5. The
payback interval is three.4 years($20,000 + $60,000 + $eighty,000 = $160,000 in the first three
years + $40,000 of the $100,000 occurring in yr four). Notice that the payback calculation uses
money flows, no longer internet revenue. Also, the payback calculation does not handle a task's
complete profitability. Rather, the payback period simply computes how speedy a manufacturer
will recuperate its cash investment.

Advantages And Disadvantages Of Pay Back Period(PBP)

Advantages

1. Pay again interval is modest and effortless to appreciate and compute.


2. Pay again period is universally used and handy to have an understanding of.
3. Pay back period offers extra value on liquidity for making choice concerning the investment
proposals.
4. Pay again period deals with risk. The undertaking with a shortest PBP has much less danger
than with the task with longest PBP.
5. The quick term strategy of pay again period is an added competencies of calculation of capital
expenditure.
Disadvantages of using the payback period;
1. In the calculation of pay again period, time price of cash is just not famous.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 68


2. Pay again period gives high emphasis on liquidity and ignores profitability.
BENEFIT COST RATIO ANALYSIS
Using the benefit fee ratio enables businesses and governments to make decisions on the
negatives and positives of investing in distinct initiatives. In other phrases, utilizing advantage
fee ratio evaluation allows for an entity to decide whether or not the benefits of a given task or
proposal outweigh the genuine expenses that go into the creation of the task or suggestion.
Advantage cost ratio is understated ample to determine, nevertheless, there are benefit fee ratio
calculators available that consider different causes that make the calculation just a little extra
problematic. Causes equivalent to genuine worker construction or production line breakdowns
can cause the advantage fee ratio to vary dramatically and so they ought to be accounted for
when delving into the small print of a exact notion or challenge.
A benefit-cost ratio (BCR) Is an indicator, used within the formal discipline of price-benefit
evaluation, that attempts to summarize the total price for money of a assignment or inspiration. A
BCR is the ratio of the benefits of a project or suggestion, expressed in economic terms, relative
to its bills, additionally expressed in fiscal phrases. All advantages and expenses should be
expressed in discounted gift values. Benefit cost ratio (BCR) takes into account the amount of
monetary achieve realized by means of performing a venture versus the amount it expenditures
to execute the undertaking. The greater the BCR the easier the funding. General rule of thumb is
that if the advantage is higher than the fee the challenge is an effective funding. BCR =
Discounted worth of incremental benefits ÷ Discounted price of incremental expenses be given
all initiatives with a BCR greater than 1, when charges and benefits are discounted at the
possibility price of capital.

Example: Suppose a tunnel is proposed to be built to save travel time and road construction cost
around a mountain. In order to save on first cost, a twin tunnel system is proposed with 1/2
capacity in each shaft. 
Construction = $3,000,000  --- Shaft 1 -- Now
                       $4,000,000  --- Shaft 2 --Built in 20 years ( N = 20 )
Maintenance (Shaft lining) = $160,000/Half  -- every 10 years
Benefits   = $260,000/yr    N =    1-20
                  $300,000/yr    N = 21-50
If  i = 5% and   N=50yrs, is the project justified?
Solution :  1st cost       PW = $3,000,000 + $4,000,000(P/F,5,20) = $4,507,600
       Relining cost       PW = $160,000(P/F,5,10+20) + $320,000(P/F,5,30+40)
                                          =  $160,000(0.9908) + $320,000(0.3734)
                                          =  $278,016 
Note: (P/F,5,10 + 20) = (P/F,5,10) + (P/F,5,20)

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 69


Benefits  PW = $260,000(P/A,5,20) + $300,000(P/A,5,30)(P/F,5,20)
                    = $260,000(12.4622) + $300,000(15.3725)(0.3769)
                     =  $4,978,340

B/C =        4,978,340         = 1.040


          4,507,600 + 278,016

Modified B/C =   4,978,340 - 278,016 = 1.042


                                4,507,600

The project is justified in either case, since B/C >1.0


Note that if the B/C ratio is greater than 1.0, the modified B/C will also be greater than 1.0

EARNED VALUE MANAGEMENT (EVM)

Earned Value Management (EVM) is a project management technique that objectively tracks
physical accomplishment of work. More elaborately:

 EVM is used to track the progress and status of a project and forecasts the likely future
performance of the project.
 EVM integrates the scope, schedule, and cost of a project.
 EVM answers a lot of questions to the stakeholders in a project related to its
performance.
 EVM can be used to show the past and the current performance of a project and predict
the future performance of the project by the use of statistical techniques.
 Good planning coupled with effective use of EVM will reduce a lot of issues arising out
of schedule and cost overruns.

EVM has emerged as a financial analysis specialty in United States Government programs in the
1960s, but it has since become a significant branch of project management. In the late 1980s and
early 1990s, EVM emerged as a project management methodology to be understood and used by
managers and executives, not just EVM specialists. Today, EVM has become an essential part of
every project tracking.

EVM - Basic Elements

EVM consists of the following three basic elements:

 Planned Value
 Actual Cost

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 70


 Earned Value

All the three elements are captured on a regular basis as of a reporting date.

Planned Value

Planned value (PV) is also referred to as Budgeted Cost of Work Scheduled (BCWS). PV or
BCWS is the total cost of the work scheduled/planned as of a reporting date.

It is calculated as: PV or BCWS = Hourly Rate × Total Hours Planned or Scheduled

NOTE: Hourly Rate is the rate at which effort will be valued.

Actual Cost

Actual cost (AC) is also referred to as Actual Cost of Work Performed (ACWP). AC or ACWP
is the total cost taken to complete the work as of a reporting date. It is calculated as:

AC or ACWP = Hourly Rate × Total Hours Spent

Earned Value

Earned value (EV) is also referred to as Budgeted Cost of Work Performed (BCWP). EV or
BCWP is the total cost of the work completed/performed as of a reporting date.It is calculated as:

EV or BCWP = Baselined Cost × % Complete Actual

All these three elements can be derived from Work Breakdown Structure by associating the costs
to each of the tasks. For a big project, it will be a tedious task to calculate these elements
manually. Scheduling software tools like Microsoft Project is used to calculate these three
elements.

NOTE: % Completed Planned and % Completed Actual are defined below.

% Completed Planned

The percentage of work which was planned to be completed by the Reporting Date. It is
calculated using the following formula:

% Completed Planned = PV / BAC

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 71


% Completed Actual

The percentage of work which was actually completed by the Reporting Date. It is calculated
using the following formula:

% Completed Actual = AC / EAC

EVM - Cost Variance

Cost Variance (CV) is a very important factor to measure project performance. CV indicates how
much over - or under-budget the project is.

CV can be calculated using the following formula:

Cost Variance (CV) = Earned Value (EV) − Actual Cost (AC)

OR

Cost Variance (CV) = BCWP − ACWP

 The formula mentioned above gives the variance in terms of cost.


 Positive CV indicates the project is under-budget.
 Negative CV indicates the project is over-budget.

Cost Variance %

Cost Variance % indicates how much over - or under-budget the project is in terms of
percentage.

Cost Variance % can be calculated using the following formula:

CV % = Cost Variance (CV) ⁄ Earned Value (EV)

OR

CV % = CV ⁄ BCWP

 The formula mentioned above gives the variance in terms of percentage.


 Positive Variance % indicates % under budget
 Negative Variance % indicates % over budget.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 72


Cost Performance Indicator

Cost Performance Indicator (CPI) is an index showing the efficiency of the utilization of the
resources on the project. CPI can be calculated using the following formula:

CPI = Earned Value (EV) ⁄ Actual Cost (AC)

OR

CPI = BCWP ⁄ ACWP

 The formula mentioned above gives the efficiency of the utilization of the resources
allocated to the project.
 A CPI value above 1 indicates the efficiency of utilizing the resources allocated to the
project is good.
 A CPI value below 1 indicates the efficiency of utilizing the resources allocated to the
project is not good.

To Complete Cost Performance Indicator

To Complete Cost Performance Indicator (TCPI) is an index showing the efficiency at which the
resources on the project should be utilized for the remainder of the project. It can be calculated
using the following formula:

TCPI = ( Total Budget − EV ) ⁄ ( Total Budget − AC )

OR

TCPI = ( Total Budget − BCWP ) ⁄ ( Total Budget − ACWP )

 The formula mentioned above gives the efficiency at which the project team should be
utilized for the remainder of the project.
 A TCPI value above 1 indicates the utilization of the project team for the remainder of
the project can be stringent.
 A TCPI value below 1 indicates the utilization of the project team for the remainder of
the project should be lenient.

EVM - Schedule Variance

Schedule Variance (SV) indicates how much ahead or behind the schedule a project is running.

It can be calculated using the following formula:


Written and compiled by Dr. Muchelule Yusuf Wanjala Page 73
Schedule Variance (SV) = Earned Value (EV) − Planned Value (PV)

OR

Schedule Variance (SV) = BCWP − BCWS

 The formula mentioned above gives the variance in terms of cost which indicates how
much cost of the work is yet to be completed as per schedule or how much cost of work
has been completed over and above the scheduled cost.
 A positive SV indicates we are ahead of schedule.
 A negative SV indicates we are behind schedule.

Schedule Variance %

Schedule Variance % indicates how much ahead or behind the schedule a project is running in
terms of percentage.

Schedule Variance % can be calculated using the following formula:

SV % = Schedule Variance (SV) ⁄ Planned Value (PV)

OR

SV % = SV ⁄ BCWS

 The formula mentioned above gives the variance in terms of percentage which indicates
how much percentage of work is yet to be completed as per schedule or how much
percentage of work has been completed over and above the scheduled cost.
 Positive Variance % indicates % ahead of schedule.
 Negative Variance % indicates % behind of schedule.

Schedule Performance Indicator

Schedule Performance Indicator (SPI) is an index showing the efficiency of the time utilized on
the project. SPI can be calculated using the following formula:

SPI = Earned Value (EV) ⁄ Planned Value (PV)

OR

SPI = BCWP ⁄ BCWS

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 74


 The formula mentioned above gives the efficiency of the project team in utilizing the
time allocated for the project.
 An SPI value above 1 indicates the project team is very efficient in utilizing the time
allocated to the project.
 An SPI value below 1 indicates the project team is less efficient in utilizing the time
allocated to the project.

To Complete Schedule Performance Indicator

To Complete Schedule Performance Indicator (TSPI) is an index showing the efficiency at which
the remaining time on the project should be utilized. It can be calculated using the following
formula:

TSPI = ( Total Budget − EV ) ⁄ ( Total Budget − PV )

OR

TSPI = ( Total Budget − BCWP ) ⁄ ( Total Budget − BCWS )

 The formula mentioned above gives the efficiency at which the project team should
utilize the remaining time allocated for the project.
 A TSPI value below 1 indicates the project team can be lenient in utilizing the remaining
time allocated to the project.
 A TSPI value above 1 indicates the project team needs to work harder in utilizing the
remaining time allocated to the project.

EVM - Miscellaneous Formula

Budget at Completion

 Budget at Completion (BAC) is the total budget allocated to the project.


 BAC is generally plotted over time. For example, periods of reporting (Monthly, Weekly,
etc.)
 BAC is used to compute the Estimate at Completion (EAC), explained in the next
section.
 BAC is also used to compute the TCPI and TSPI.

BAC is calculated using the following formula:

BAC = Baselined Effort − hours × Hourly Rate

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 75


Estimate to Complete

 Estimate to Complete (ETC) is the estimated cost required to complete the remainder of
the project.
 ETC is calculated and applied when the past estimating assumptions become invalid and
a need for fresh estimates arises.
 ETC is used to compute the Estimation at Completion (EAC).

Estimate at Completion

Estimate at Completion (EAC) is the estimated cost of the project at the end of the project.
There are three methods to calculate EAC:

 Variances are typical - This method is used when the variances at the current stage are
typical and are not expected to occur in the future.
 Past estimating assumptions are not valid - This method is used when the past
estimating assumptions are not valid and fresh estimates are applied to the project.
 Variances will be present in the future - This method is used when the assumption is
that the current variances will continue to be present in the future.

The formulas for calculation of the three methods are as given below:

 AC + (BAC − EV)
 AC + ETC (Estimate To Complete)
 AC + (BAC − EV) ⁄ CPI

Variance at Completion

Variance at completion (VAC) is the variance on the total budget at the end of the project.

This is the difference between what the project was originally expected (baselined) to cost versus
what it is now expected to cost. VAC is calculated using the following formula:

VAC = BAC − EAC

% Completed Planned

The percentage of work which was planned to be completed by the Reporting Date. It is
calculated using the following formula: % Completed Planned = PV ⁄ BAC

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 76


% Completed Actual

The percentage of work which was actually completed by the Reporting Date. It is calculated
using the following formula: % Completed Actual = AC ⁄ EAC

EVM - Examples

To illustrate the concept of EVM and all the formulas, assume a project that has exactly one task.
The task was baselined at 8 hours, but 11 hours have been spent and the estimate to complete is 1
additional hour. The task would have been completed already.

Assume an Hourly Rate of $100 per hour.

Using this information:

PV or BCWS = Hourly Rate × Total Hours Planned or Scheduled

PV = $100 * 8 hours = $800

AC or ACWP = Hourly Rate × Total Hours Spent

AC = $100 * 11 hours = $1100

EV or BCWP = Baselined Cost × % Complete Actual

EV = baseline of $800 * 91.7% complete = $734

(NOTE % Complete Actual (below) to get the 91.7%)

BAC = Baselined Effort − hours × Hourly Rate

BAC = 8 hours * $100 = $800

EAC = AC + ETC

EAC = 1100 + 100 = $1200

VAC = BAC − EAC

VAC = $800 − $1200 = −$400

% Completed Planned = PV ⁄ BAC

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 77


% Complete Planned = $800 PV ⁄ $800 BAC = 100%

% Completed Actual = AC ⁄ EAC

% Complete Actual = $1100 AC ⁄ $1200 EAC = 91.7%

SV = Earned Value (EV) − Planned Value (PV)

SV = $734 EV − $800 PV = −$66

SPI = Earned Value (EV) ⁄ Planned Value (PV)

SPI = $734 EV ⁄ $800 PV = 0.91

CV = Earned Value (EV) − Actual Cost (AC)

CV = ($734 EV − $1100 AC) = −$366*

* indicates a cost overrun

CPI = Earned Value (EV) ⁄ Actual Cost (AC)

CPI = $734 EV ⁄ $1100 AC = 0.66*

* indicates over-budget

PORTFOLIO THEORY

Definition:
A portfolio is a combination of assets held by the investor for investment purposes. Portfolio
theory therefore attempts to show an investor how to combine a set of assets to maximise the
assets' returns as well as minimise the assets' risk (Risk Diversification).

Diversification is defined as combining assets whose returns are not perfectly positively correlated
to reduce the aggregate risk of the total asset holdings (or the portfolio).

1.2 PORTFOLIO EXPECTED RETURN


If the investor holds only two assets in the portfolio, we can therefore be able to compute the
portfolio's expected return (sometimes referred to as the portfolio mean). This will be a weighted

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 78


average of the expected return of each asset held in isolation, and can be given by the following
formula:

E(RP) = E(αXA + ßXB) ... (3.a)


Where (E(RP) is the expected portfolio return
α is the investment in asset A
ß is the investment in asset B
XA is the expected return of asset A
XB is the expected return of asset B

Formula 3.a can be simplified as follows:

E(RP) = αEXA + ßEXB ... (3.b)

Not also that α + ß = 1. This is because all the investor's wealth is invested in either asset A or
asset B.

Illustration
Consider two investments, A and B each having the following investment characteristics;

Investment Expected Return (%) Proportion


A 10 2/3
B 20 1/3

REQUIRED:
Compute the expected return of a portfolio of the two assets.

Solution
Using formula (3.b)

Note α = 2/3 ß = 1/3


EXA = 10 EXB = 20

E(RP) = 2 (10%) + 1 (20%)


3 3

= 13.3%

Note that the expected return is a weighted average of the expected return of assets held in
isolation.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 79


1.3 PORTFOLIO STANDARD DEVIATION

Remember that standard deviation is a measure of risk of the investment. Portfolio standard
deviation therefore measure the risk of investing in a combination of assets.

The portfolio standard deviation is not a weighted average of standard deviations of assets held in
isolation. This is because of the inter-relatedness of the assets, which reduces the risk when assets
are held together. This relationship is measured by the correlation co-efficient (τ),

The coefficient of correlation (τ) lies between -1 and +1. Therefore -1  τ +1.

If τAB = +1, this means that A and B are perfectly positively correlated and therefore the outcomes
of A and B move in the same direction at the same time.

If τAB = -1, then A and B are perfectly negatively correlated and their results are inversely related.
That is they move in opposite directions simultaneously.

If we consider the two asset case, then the portfolio standard deviation (δ A+B) can be given by the
following formula.

δ A + B = √(α )2 δ 2A + β 2 δ 2B + 2 (γ AB )(α )( β)(δ A )(δ B )...(3. c)


11
Where δA is the standard deviation of A
δB is the standard deviation of B
τAB is the correlation coefficient of asset A and B

Illustration

Consider two investments A & B each having the following characteristics:

Investment Expected Return (%) Proportion


A 20 2/3
B 40 1/3

REQUIRED:
Compute the portfolio standard deviation if the correlation coefficient between the assets is

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 80


a. 1
b. 0
c. -1

Solution

δ A+B =
√( )
22
3
(20% )2 +
1 2
3 ()
( 40%)2 + 2( γ AB )
2 1
3 3( )( )
(20% )(40%)

12
Using
formula (3.c) we can compute the portfolio standard deviation as follows:

= √ 0.0178 + 0 . 0178 + 0 .036( γ AB ) = √ 0.036 + 0 .036( γ AB )


13
Note that the standard deviation depends on the correlation coefficient if the proportion of
investment is fixed. Therefore if
a. rAB = 1
δA+B = (0.036 + 0.036) = 26.8%
b. If rAB = 0 then
δA+B = (0.036) = 18.7%
c. If rAB = -1
δA+B = (0.036 - 0.036) = 0 = 0
There is no risk at all.
Note: If assets are perfectly negatively correlated then holding them in a portfolio greatly reduces
their risk.

1.4 PORTFOLIO OF MORE THAN 2 ASSETS

Usually investors will not hold only 2 assets. If the assets held in the portfolio are more than 2 then
the following general formulas may be used:

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 81



N n

δP =
∑∑ t=1
¿
j=1
¿ α i α j γ ij δ i δ j . . .(3. e ) ¿¿

14

E (R P ) =
∑t=1
¿ α t E (R t ) .. .( 3 . d ) ¿

15
Where δP is the portfolio standard deviation.
Note: we shall not spend much time on analysis of more than 2 assets due to the complication
involved. It is however, assumed that the student can be able to extend the two asset case to
more assets.

1.5 COVARIANCE AND THE CORRELATION COEFFICIENT

We have already introduced the correlation coefficient. We shall consider the Covariance and its
relationship with the correlation coefficient.

The covariance is a measure which reflects both the variance of an asset's returns and the tendency
of those returns to move up and down at the same time other assets move up or down. The
covariance between two asset's return can be given by the following formula:

Cov ( AB ) =
∑ i=1
¿ ( R Ai - E ( R Ai ) ) ( R Bi - E( R B ) ) Pi ¿

16
Where Cov(AB) is the covariance between And B
RAi is the return on asset A under the Ith state.
E(RA) is the expected return of A
RBi is the return on asset B under the ith state
E(RB) is the expected return of B
Pi is the probability of the ith state.

The correlation coefficient can be given by the following formula.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 82


Cov ( AB)
γ AB = ...(3.g)
δ A δB
17

Illustration:
Four assets have the following distribution of returns.

Probability Rate of return (%)


Occurrence A B C D
0.1 10.0% 6.0% 14.0% 2.0%
0.2 10.0 8.0 12.0 6.0
0.4 10.0 10.0 10.0 9.0
0.2 10.0 12.0 8.0 15.0
0.1 10.0 14.0 6.0 20.0

REQUIRED:

a. Compute the expected return and standard deviation of each asset.

b. Compute the covariance of asset


i. A and B
ii. B and C
iii. B and D

c. Compute the correlation coefficient of the combination of assets in b above.

Solution

a. E(RA)= 10(0.1) + 10(0.2) + 10(0.4) + 10(0.2) + 10(0.1) = 10%

E(RB)= 6(0.1) + 8(0.2) + 10(0.4) + 12(0.2) + 14(0.1) = 10%

E(RC)= 14(0.1) + 12(0.2) + 10(0.4) + 8(0.2) + 6(0.1) = 10%

E(RD)= 2(0.1) + 6(0.2) + 9(0.4) + 15(0.2) + 20(0.1) = 10%

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 83



5

δA =
∑ i=1
2
¿ ( R Ai - E ( R A )) Pi ¿

18
= 0 since (RAi - E(R)A) = 0%

δ B = √(6 - 10)† 0 .1 + ( 8 - 10)† 0. 2 + (10 - 10)† 0. 4 + (12 - 10)† 0 .2 + (14 - 10)† 0 .1


19
= 4.8 = 2.2%

Likewise δC = 2.2% and δD = 5.0%

b. i.

Cov( AB ) =
∑ i=1
¿ ( R Ai - E( R A ) )( R Si - E( R B ) ) P i ¿

20
Note that since (RAi - ERA) = 0
Cov(AB) = 0

ii Cov(BC) = (6-10)(14-10)(0.1) + (8-10)(12-10)0.2 + (10-10)(10-10)0.4


+ (12-10)(8-10)0.2 + (14-10)(6-10)0.1

= -4.8

iii Cov(BD) = (6-10)(2-10)(0.1) + (8-10)(6-10)0.2 + (10-10)(9-10)0.4 +


(12-10)(15-10)0.2 + (14-10)(20-10)0.1

= 10.8

Assets B and C tend to move in opposite directions and therefore their covariance is negative
while Assets B and D tend to move in the same directions and therefore their covariance is
positive.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 84


Returns of A has no correlation with the returns of other assets and therefore the covariance
between A and any other asset is zero.

c. Correlation coefficient

i. τAB = Cov(AB) = 0 = 0
δAδB (0)(2.2)

ii. τBC = Cov(BC) = -4.8 = -1.0


δBδC (2.2)(2.2)

i. τBD = Cov(BD) = 10.8 = 0.98


δBδD (2.2)(5.0)

Therefore Assets B and C are perfectly negatively correlated while B and D have a strong
positive correlation.

1.6 EFFICIENT PORTFOLIO AND THE EFFICIENT FRONTIER

Efficient portfolios can be defined as those portfolio which provide the highest expected return for
any degree of risk, or the lowest degree of risk for any expected return.

The investor should ensure that he holds those assets which will minimise his risk. He should
therefore diversify his risk.

The risk can be divided into two:

a. The diversifiable (unsystematic) risk;


b The non-diversifiable (systematic) risk.

The diversifiable risk is that risk which the investor can be able to eliminate if he held an efficient
portfolio.
The non-diversifiable risk on the other hand is those risks that still exist in all well diversified
efficient portfolios.
The investor therefore seeks to eliminate the diversifiable risk. This can be shown below:

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 85


Diversification of Risk

From the graph shown above as the number of assets increases, the portfolio risk reduces up to
point M. At this point the lowest risk has been achieved and adding more assets to the portfolio
will not reduce the portfolio risk.

An efficient portfolio therefore is well diversified portfolio.

Note: The non-diversifiable risk can also be referred to as the market risk.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 86


EFFICIENT SET OF INVESTMENT

If consider many assets, the feasible set of investment will be given by the following graph

The shaded area is the attainable set of investment. However, investors will invest in a portfolio
with the highest return at a given risk or the lowest risk at a given return. The efficient set of
investment, therefore, will be given by the frontier B C D E. This frontier is referred to as the
Efficient Frontier. Any point on the efficient frontier dominates all the other points on the feasible
set.

2.1 THE CAPITAL ASSET PRICING MODEL

The Capital Asset Pricing Model (CAPM) specifies the relationship between risk and required rate
of return on assets when they are held in well-diversified portfolios.

Basic assumptions of CAPM

1. Investors are rational and they choose among alternative portfolios on the basis of each
portfolio's expected return and standard deviation.
2. Investors are risk averse.
3. Investors maximise the utility of end of period wealth. Thus CAPM is a single period model.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 87


4. Investors have homogeneous expectations with regard to asset return. Thus all investors will
perceive the same efficient set.
5. There exist a risk-free asset and all investors can borrow and lend at this rate.
6. All assets are marketable and perfectly divisible.
7. The capital market is efficient and perfect.

The CAPM is given as follows:

Ri = RF + [E(RM - RF)]ß

Where Ri is required return of security i


RF is the risk free rate of return
E(RM) is the expected market rate of return
ß is Beta.

Note ßi = Cov(im)
δ²m

Where Cov(im) is the covariance between asset i and the market return.
δ²m is the variance of the market return.

If we graph ßi and E(Ri) then we can observe the following relationship

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 88


All correctly priced assets will lie on the security market line. Any security off this line will either
be overpriced or underpriced. The security market line therefore shows the pricing of all asset if
the market is at equilibrium. It is a measure of the required rate of return if the investor were to
undertake a certain amount of risk.
Illustration:

Assume that the risk free rate of return is 8%, the market expected rate of return is 12%. The
standard deviation of the market return is 2% while the covariance of return for security A and the
market is 2%.

REQUIRED:

What is the required rate of return on Security A?

Solution

Ri = RF + (E(RM) - RF)ß

ß = Cov(AM) = 2 = 2 = 0.5
Written and compiled by Dr. Muchelule Yusuf Wanjala Page 89
δM² 2² 4

Ri = 8% + (12 - 8)0.5 = 10%

The required rate of return on security A is therefore 10%.

2.2 LIMITATIONS OF CAPM

CAPM has several weaknesses e.g.

a. It is based on some unrealistic assumptions such as:

i. Existence of Risk-free assets


ii. All assets being perfectly divisible and marketable (human capital is not divisible)
iii. Existence of homogeneous expectations about the expected returns
iv. Asset returns are normally distributed.

b. CAPM is a single period model—it looks at the end of the year return.
c. CAPM cannot be empirically tested because we cannot test investors expectations.
d. CAPM assumes that a security's required rate of return is based on only one factor (the stock
market—beta). However, other factors such as relative sensitivity to inflation and dividend
payout, may influence a security's return relative to those of other securities.

The Arbitrage pricing theory is designed to help overcome these weaknesses.

ARBITRAGE PRICING THEORY (APT)


Formulated by Ross(1976), the Arbitrage Pricing Theory(APT) offers a testable alternative to
the capital market pricing model(CAPM). The main difference between CAPM and APT is that
CAPM assumes that security rates of returns will be linearly related to a single common factor-
the rate of return on the market portfolio. The APT is based on similar intuition but is much more
general.

APT assumes that, in equilibrium, the return on an arbitrage portfolio (i.e. one with zero
investment, and zero systematic risk) is zero. If this return is positive, then it would be
eliminated immediately through the process of arbitrage trading to improve the expected
returns. Ross (1976) demonstrated that when no further arbitrage opportunities exist, the
expected return (E(Ri)) can be shown as follows:

E(Ri)=Rf + β1(R1-Rf)+β2(R2 -Rf)+--------+ βn(Rn-Rf)+έi

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 90


Where,

E(Ri) is the expected return on the security

Rf is the risk free rate

Βi is the sensitivity to changes in factor i

έi is a random error term.

3.2 APT and CAPM compared


The Arbitrage Pricing Theory (APT) is much more robust than the capital asset pricing model for
several reasons:
a) The APT makes no assumptions about the empirical distribution of asset returns. CAPM
assumes normal distribution.
b) The APT makes no strong assumption about individuals’ utility functions (at least nothing
stronger than greed and risk aversion).
c) The APT allows the equilibrium returns of asset to be dependent on many factors, not just
one (the beta).
d) The APT yields a statement about the relative pricing of any subset of assets; hence one need
not measure the entire universe of assets in order to test the theory.
e) There is no special role for the market portfolio in the APT, whereas the CAPM requires that
the market portfolio be efficient.
f) The APT is easily extended to a multi-period framework.
Since APT makes fewer assumptions than CAPM, it may be applicable to a country like Kenya.
However, the model does not state the relevant factors. Cho(1984) has, however, shown the
security returns are sensitive to the following factors: Unanticipated inflation, Changes in the
expected level of industrial production, Changes in the risk premium on bonds, and
Unanticipated changes in the term structure of interest rates
Illustration
Security returns depend on only three riskfactors-inflation, industrial production and the aggregate
degree of risk aversion. The risk free rate is 8%, the required rate of return on a portfolio with unit
sensitivity to inflation and zero-sensitivity to other factors is 13.0%, the required rate of return on a
portfolio with unit sensitivity to industrial production and zero sensitivity to inflation and other
factors is 10% and the required return on a portfolio with unit sensitivity to the degree of risk
aversion and zero sensitivity to other factors is 6%. Security i has betas of 0.9 with the inflation
portfolio, 1.2 with the industrial production and-0.7 with risk bearing portfolio—(risk aversion)
Assume also that required rate of return on the market is 15% and stock i has CAPM beta of 1.1

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 91


REQUIRED:

Compute security i's required rate of return using


a. CAPM
b. APT
Using APT Ri = 8% + (13% - 8%)0.9 + (10% - 8%)1.2 + (6% - 8%)(-.7)
= 16,3%
Using CAPM Ri = RF + (E(RM) - RF)ßi
Ri = 8% + (15% - 8%)1.1 = 15.7%

3.3 LIMITATIONS OF APT


APT does not identify the relevant factors that influence returns nor does it indicate how many
factors should appear in the model. Important factors are inflation, industrial production, the
spread between low and high grade bonds and the term structure of interest rates.

CAPITAL STRUCTURE
Factors That Affect Capital Structure
1. Availability of securities – This influences the company’s use of debt finance which
means that if a company has sufficient securities, it can afford to use debt finance in large
capacities.
2. Cost of project finance (both implicit and explicit) – If low, then a company can use more
of debt or equity finance.
3. Company gearing level – if high, the company may not be able to use more debt or equity
finance because potential investors would not be willing to invest in such a company.
4. Sales stability – If a company has stable sales and thus profits, it can afford to use various
finances in particular debt in so far as it can service such finances.
5. Competitiveness of the industry in which the company operates – If the company
operates in a highly competitive industry, it may be risky to use high levels of debt
because chances of servicing this debt may be low and may lead a company into
receivership.

COST OF PROJECT FINANCE


Definition
This is the price the company pays to obtain and retail finance. To obtain finance a company
will pay implicit costs which are commonly known as floatation costs. These include:
Underwriting commission, Brokerage costs, cost of printing a prospectus, Commission costs,
legal fees, audit costs, cost of printing share certificates, advertising costs etc. For debt there are
legal fees, valuation costs (i.e. security, audit fees, Bankers commission etc.) such costs are
knocked off from:

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 92


i) The market value of shares if these have only been sold at a price above par value.
ii) For debt finance – from the par value of debt.

I.e. if flotation costs are given per share then this will be knocked off or deducted from the
market price per share. If they are given for the total finance paid they are deducted from the
total amount paid.
Cost of Retaining Finance
This will include dividends for share capital and interest for debt finance (tax deducted) or
effective cost of debt. However, when computing the Cost of project finance apart from
deducting implicit costs, explicit costs are the most central elements of cost of finance.
Importance of Cost of Finance
The cost of capital is important because of its application in the following areas:

i) Long-term investment decisions – In capital budgeting decisions, using NPV method, the
cost of capital is used to discount the cash flows. Under IRR method the cost of capital is
compared with IRR to determine whether to accept or reject a project.
ii) Capital structure decisions – The composition/mix of various components of capital is
determined by the cost of each capital component.
iii) Evaluation of performance of management – A high cost of capital is an indicator of high
risk attached to the firm. This is usually attributed to poor performance of the firm.
iv) Dividend policy and decisions – E.g if the cost of retained earnings is low compared to
the cost of new ordinary share capital, the firm will retain more and pay less dividend.
Additionally, the use of retained earnings as an internal source of finance is preferred
because:
 It does not involve any floatation costs
 It does not dilute ownership and control of the firm, since no new shares are issued.
v) Lease or buy decisions – A firm may finance the acquisition of an asset through leasing
or borrowing long-term debt to buy an asset. In lease or buy decisions, the cost of debt
(interest rate on loan borrowed) is used as the discounting rate.
Factors That Influence the Cost of project Finance
1. Terms of reference – if short term, the cost is usually low and vice versa.
2. Economic conditions prevailing – If a company is operating under inflationary
conditions, such a company will pay high costs in so far as inflationary effect of finance
will be passed onto the company.
3. Risk exposed to venture – if a company is operating under high risk conditions, such a
company will pay high costs to induce lenders to avail finance to it because the element
of risk will be added on the Cost of project finance which may compound it.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 93


4. Size of the business – A small company will find it difficult to raise finance and as such
will pay heavily in form of Cost of project finance to obtain debt from lenders.
5. Availability – Cost of project finance (COF) prices will also be influenced by the forces
of demand and supply such that low demand and low supply will lead to high cost of
finance.
6. Effects of taxation – Debt finance is cheaper by the amount equal to tax on interest and
this means that debt finance will entail a saving in Cost of project finance equivalent to
tax on interest.
7. Nature of security – If security given depreciates fast, then this will compound implicit
costs (costs of maintaining that security).
8. Company’s growth stage – Young companies usually pay less dividends in which case
the cost of this finance will be relatively cheaper at the earlier stages of the company’s
development.

Term Structure of Interest Rates


The term structure of interest rate describes the relationship between interest rates and the term
to maturity and the differences between short term and long term interest rates.

The relationship between short and long interest rates is important to corporate managers
because:

1. They must decide whether to buy long term or short term bonds and whether to borrow
by issuing long-term or short-term bonds.
2. It enables them to understand how long term and short term rates are related and what
causes the shift in their relative positions.

Several theories had been advanced to explain the nature of yield curve – These are:

1. Liquidity preference theory


2. Expectation theory
3. Market segmentation theory

1. Liquidity Preference Theory


This theory states that short term bonds are more favourable than long term bonds for 2
reasons.

i) Investors generally prefer short term bonds to long-term securities because such
securities are more liquid in the sense that they can be converted to cash with little danger

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 94


of loss of principal. Therefore – investors will accept lower yields on short term
securities.
ii) At the same time borrowers react in exactly the opposite way.
Generally borrowers prefer long term debt because short-term debt exposes them to the
risk of having to repay the debt under adverse. Conditions, accordingly borrowers are
willing to pay higher rate other things held constant for long-term process than short
ones.

Taking together this two sets of preferences implies that under normal conditions, a positive
maturity risk premium exist which increases with maturity thus the yield curve should be upward
sloping. Lenders prefer liquidity (short term hands) while borrowers prefer long term bonds and
are willing to pay a “premium” for long term borrowing.

2. Expectation Theory
This theory states that the yield curve depends on the expectation about future inflation rates. If
inflation rate is expected to increase, then the rate on long-term bonds will exceed that of short-
term loan. The expected future interest rates are equal to forward rates computed from the
expectations with regard to future interest rates are. Other factors which affect the expectations
with regard to future interest rates are:

 Political stability
 Monetary policy of the government
 Fiscal policy of the government (government expedition)
 Other economic related factors including social factors.

The following conditions are necessary for the expectation theory to hold.
i) Perfect capital markets exists where there are many buyers and sellers of security with
non having a significant influence on the interest rates.
ii) Investors have homogeneous expectations about future interest rates and returns on all
investments.
iii) Investors are rational wealth maximizers
iv) Bankruptcy of firms due to use of borrowing is unlikely.

3. Market Segmentation Theory


This theory states that the major investors (borrowers and lenders) are confined to a particular
segment of the market and will not change even if the forecast of the likely future interest rates
changes. The lenders and borrower thus have a preferred maturity e.g a person borrowing to buy
a house or a company borrowing to build a power plant would want a long term loan. However a
retailer borrowing to build up stock in readiness for a peak reason would prefer a short term loan.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 95


Similar differences exist among savers e.g a person saving to pay school fees for next semester
would want to lend on in the short-term market.

A person saving for retirement 20 years ahead would probably buy long-term security in L.T
market. The thrust of market segmentation theory is that the slope of yield curve depends on
demand and supply mechanism. An upward sloping curve would occur if there was a large
supply of funds relative to demand in the short term marketing but a relative shortage of funds in
the long-term market would produce an upward sloping curve.

Tests of the 3 theories


Various test have been conducted mainly in USA and they indicate that all the 3 theories have
some validity and thus the shape of the yield curve of any firm is affected by the following:

1. Supply and demand conditions in the short and long term market.
2. Liquidity preferences of lenders and borrowers
3. Expectation of future inflation. While any of the 3 factors may dominate the market
all the 3 effect the term structure of interest rate.

Factors influencing interest rates

There are four most important factors that influence interest rates and the shape of yield curve.

1. CBK – Monetary policy


2. The level of government budget deficit
3. Balance of trade position
4. Business activity (circle) in the economy

METHODS/MODELS OF COMPUTING COST OF CAPITAL


The following models are used to establish the various costs of capital or required rate of return
by the investors:

 Risk adjusted discounting rate


 Market model/investors expected yield
 Capital asset pricing model (CAPM)
 Dividend yield/Gordon’s model.

i) Risk adjusted discounting rate – This technique is used to establish the discounting rate to
be used for a given project. The cost of capital of the firm will be used as the discounting
rate for a given project if project risk is equal to business risk of the firm. If a project has a

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 96


higher risk than the business risk of the firm, then a percentage risk premium is added to the
cost of capital to determine the discounting rate i.e. discounting rate for a high risk project =
cost of capital + percentage risk premium. Therefore a high risk project will be evaluated at
a higher discounting rate.

ii) Market Model – This model is used to establish the percentage cost of ordinary share capital
cost of equity (Ke). If an investor is holding ordinary shares, he can receive returns in 2
forms:

 Dividends
 Capital gains

Capital gain is assumed to constitute the difference between the buying price of a share at the
beginning of the (P0), the selling price of the same share at the end of the period (P1). Therefore
total returns = DPS + Capital gains = DPS + P1 – P0.
The amount invested to derive the returns is equal to the buying price at the beginning of the
period (P0) therefore percentage return/yield =

Total returns x 100 = DPS + P1 – P0 x 100


Investment P0

Illustration:
For the past 5 years, the MPS and DPS for XYZ Ltd were as follows:

1998 1999 2000 2001 2002


Shs. Shs. Shs. Shs. Shs.
MPS as at 31st Dec 40 45 53 50 52
DPS for the year - 3 4 3 -

Required
Determine the estimated cost of equity/shareholders percentage yield for each of the years
involved.

Solution

Year MPS Capital gain DPS % Return


1998 40 - - -

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 97


1999 45 5 3 5+3 8
x 100= x 100=20 %
40 40

2000 53 8 4 8+4 12
= x 100=27 %
45 45

2001 50 -3 3 −3+3 0
= x 100=0 %
53 53

2002 52 2 - 2+0 2
= x 100=4 %
50 50

iii) Capital asset pricing model (CAPM) – CAPM is a technique that is used to establish
the required rate of return of an investment given a particular level of risk. According to
CAPM, the total business risk of the firm can be divided into 2:

Systematic Risk – This is the risk that affects all the firms in the market. This risk cannot be
eliminated/diversified. It is thus called undiversifiable risk. Since it affects all the firms in the
market, the share price and profitability of the firms will be moving in the same direction i.e.
systematically. Examples of systematic risk are political instability, inflation, power crisis in the
economy, power rationing, natural calamities – floods and earthquakes, increase in corporate tax
rates and personal tax rates, etc. Systematic risk is measured by a Beta factor.

Unsystematic risk – This risk affects only one firm in the market but not other firms. It is
therefore unique to the firm thus unsystematic trend in profitability of the firm relative to the
profitability trend of other firms in the market. The risk is caused by factors unique to the firm
such as:

 Labour strikes by employees of the firm;


 Exit of a prominent corporate personality;
 Collapse of marketing and advertising programs of the firm on launching of a new
product;
 Failure to make a research and development breakthrough by the firm, etc

CAPM is only concerned with systematic risk. According to the model, the required rate of
return will be highly influenced by the Beta factor of each investment. This is in addition to the
excess returns an investor derives by undertaking additional risk e.g cost of equity should be
equal to Rf + (Rm – Rf)BE

Cost of debt = Rf + (Rm – Rf)Bd

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 98


Where:Rf = rate of return/interest rate on riskless investment e.g T. bills
Rm = Average rate of return for the entire stock as shown by average
Percentage return of the firms that constitute the stock index.
Be = Beta factor of investment in ordinary shares/equity.
Bd = Beta factor for investment in debentures/long term debt capital.

Illustration
KK Ltd is an all equity firm whose Beta factor is 1.2, the interest rate on T. bills is currently at
8.5% and the market rate of return is 14.5%. Determine the cost of equity Ke, for the company.

Solution
Rf = 8.5% Rm = 14.5% Beta of equity = 1.2

Ke = Rf + (Rm – Rf)BE
= 8.5% + (14.5% - 8.5%) 1.2
= 8.5% + (6%)1.2
= 15.7%

iv) Dividend yield/Gordon’s Model – This model is used to determine the cost of various
capital components in particular:

 Cost of equity - Ke
 Cost of preference share capital (perpetual) – Kp
 Cost of perpetual debentures – Kd

a) Cost of equity (Ke)– This can be determined with respect to:

d0
Zero growth firm – P0 = d0 Therefore = P0

R = Ke

Where:d0 = DPS
R0 = Current MPS

d 0 ( 1+ g )
Constant growth firm – P0 = Ke g

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 99


d 0 (1+ g )
K e= +g
Therefore P0

b) Cost of perpetual preference share capital (Kp)

Recall, value of a preference share (FRS) = Constant DPS


Kp

Therefore: dp = Preference dividend per share


Pp = Market price of a preference share

c) Cost of perpetual debenture (Kd) – Debentures pay interest charges, which an allowable
expenses for tax purposes.

Recall, Value of a debenture (Vd) = Interest charges p.a. in ∞


Cost of debt Kd

Int .
( 1−T )
Therefore Kd = V d

Where:Kd = % cost of debt


T = Corporate tax rate
Vd = Market value of a debenture

Cost of Redeemable Debentures and Preference Shares


Redeemable fixed return securities have a definite maturity period. The cost of such securities is
called yield to maturity (YTM) or redemption yield (RY). For a redeemable debenture Kd (cost
of debt) = YTM = RY, can be determined using approximation method as follows:

1
Int ( 1−T ) + ( M −V d )
n
K d / VTM / RY = 1
( M +V d ) 2

Where:Int. = Interest charges p.a.


T = Corporate tax rate
M = Par or maturity value of a debenture
Vd = Current market value of a debenture
n = Number of years to maturity

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 100


WEIGHTED AVERAGE COST OF CAPITAL (W.A.C.C.)
This is also called the overall or composite cost of capital. Since various capital components
have different percentage cost, it is important to determine a single average cost of capital
attributable to various costs of capital. This is determined on the basis of percentage cost of each
capital component.

Market value weight or proportion of each capital component.

W.A.C.C =
Ke ( VE )+K ( VP )+K (1−T )( VD )
p d

Where:Ke, Kp and Kd = Percentage cost of equity, preference share capital and debt capital
respectively
E, P and D = Market value of equity, preference share capital and debt capital
respectively.
NB: Market value = Market price of a security x No. of securities.
V = Total market value of the firm = E + P + D.
Illustration
The following is the capital structure of XYZ Ltd as at 31/12/2002.

Shs.M
Ordinary share capital Sh.10 par value 400
Retained earnings 200
10% preference share capital Sh.20 par 100
value 200
12% debenture Sh.100 par value 900

Additional information
1. Corporate tax rate is 30%
2. Preference shares were issued 10 years ago and are still selling at par value MPS = Par
value
3. The debenture has a 10 year maturity period. It is currently selling at Sh.90 in the
market.
4. Currently the firm has been paying dividend per share of Sh.5. The DPS is expected to
grow at 5% p.a. in future. The current MPS is Sh.40.

Required

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 101


a) Determine the WACC of the firm.
b) Explain why market values and not book values are used to determine the weights.
c) What are the weaknesses associated with WACC when used as the discounting rate, in
project appraisal.

a) i) Compute the cost of each capital component


Cost of equity (Ke) – Since the growth rate in dividends is given, use the constant growth
rate dividend model to determine the cost of equity.

d0 = Sh.5 P0 = Sh.40 g = 5%

d 0 (1+ g ) 5 ( 1+0 . 05 )
K e= + g= +0 . 05=0 .18125=18. 13 %
P0 40

Cost of perpetual preference share capital (Kp) – preference shares are still selling at par
thus MPS = par value. If this is the case, Kp = coupon rate = 10%.

MPS = Par value = Sh.20

Dp = 10% x Sh.20 = Sh.2

DPS d p Sh. 2
K p= = = =10 %
MPS P p Sh. 20

Cost of debentures (Kd) – the debenture has a 10 year maturity period. It is thus a
redeemable fixed return security thus the cost of debt is equal to yield to maturity.

Redemption yield:

Interest charges p.a. = 12% x Sh.100 par value = Sh.12


Maturity period (n) = 10 years
Maturity value (m) = Sh.100
Current market value (Vd) = Sh.90
Corporate tax rate (T) = 30%

1
Int ( 1−T ) + ( M −V d )
n
K d =YTM =RY =
( M +V d ) ½

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 102


1
Sh .12(1−0.3 )+(100−90)
10
=9 .9 %≈10 %
= (100+90)½

ii) Compute the market value of each capital component


Market value of Equity (E) = MPS x No. of ordinary shares
Sh.400 MDSC
Sh.40 x
= Sh.10 parvalue = 1,600

Market value of preference share capital (P)


= Par value, since MPS = Par value per share = 100

Market value of debt (D) = Vd x No. of debentures

Sh.200 Mdebentures
Sh.90 x
= Sh .100 parvalue = 180

E + P + D = V = total Market Value = 1,880

iii) Compute W.A.C.C using Ke = 18.13%, Kp = 10%, Kd(1-T) = 10%

a) Using weighted average cost method,, WACC =

=
Ke ( VE )+K ( VP )+K ( 1−T ) ( VD )
p d

=
18 .13 % ( 1,1, 600880 )+10% (1001,880 )+10 %( 1801,880 )
= 15.43 + 0.5319 + 0.9574

= 0.169193

≈ 16.92%

b) By using percentage method,


WACC = Total monetary cost
Total market value (V)

Where:Monetary cost = % cost x market value of capital


Monetary cost of E = 18.13% x 1,600 = 290.08

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 103


Monetary cost of P = 10% x 100 = 10.00
Monetary cost of D = 10% x 180 = 18.00
318.08

Total market value (V) 1,880

318 .08
x 100
Therefore WACC = 1,880 = 16.92%

b) In computation of the weights or proportions of various capital components, the


following values may be used:

 Market values
 Book values
 Replacement values
 Intrinsic values

Market Value – This involves determining the weights or proportions using the current market
values of the various capital components. The problems with the use of market values are:

The market value of each security keep on changing on daily basis thus market values can be
computed only at one point in time.

The market value of each security may be incorrect due to cases of over or under valuation in the
market.
Book values – This involves the use of the par value of capital as shown in the balance sheet.
The main problem with book values is that they are historical/past values indicating the value of
a security when it was originally sold in the market for the first time.

Replacement values – This involves determining the weights or proportions on the basis of
amount that can be paid to replace the existing assets. The problem with replacement values is
that assets can never be replaced at ago and replacement values may not be objectively
determined.

Intrinsic values – In this case the weights are determine on the basis of the real/intrinsic value of
a given security. Intrinsic values may not be accurate since they are computed using
historical/past information and are usually estimates.

e) Weaknesses of WACC as a discounting rate


WACC/Overall cost of capital has the following problems as a discounting rate:

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 104


 It can only be used as a discounting rate assuming that the risk of the project is equal to the
business risk of the firm. If the project has higher risk then a percentage premium will be
added to WACC to determine the appropriate discounting rate.
 It assumes that capital structure is optimal which is not achievable in real world.
 It is based on market values of capital which keep on changing thus WACC will change over
time but is assumed to remain constant throughout the economic life of the project.
 It is based on past information especially when determining the cost of each component e.g
in determining the cost of equity (Ke) the past year’s DPS is used while the growth rate is
estimated from the past stream of dividends.

Note
When using market values to determine the weight/proportion in WACC, the cost of retained
earnings is left out since it is already included or reflected in the MPS and thus the market value
of equity. Retained earnings are an internal source of finance thus, when they are high there is
low gearing, lower financial risk and thus highest MPS.

Written and compiled by Dr. Muchelule Yusuf Wanjala Page 105

You might also like