Hazard Identification and Risk Assessment Hot & Cool Box Installation
Hazard Identification and Risk Assessment Hot & Cool Box Installation
Hazard Identification and Risk Assessment Hot & Cool Box Installation
1 Fall Men falling and materials H L M Keep all loose materials secured at heights. M L L
Use containers for small Items like nuts and
bolts. Do not leave them on pipes and beams.
Fall Objects Falling objects H L M Barricade the area around erection of scaffold M L
Scaffolding Scaffolder falling and provide warning sign.
2 Collapse Scaffold collapse Do not throw up or throw down clamps, boards L
or pipes. Use proper method of lifting or
lowering materials
Do not leave loose items unsecured at
elevated levels.
/conversion/tmp/activity_task_scratch/618319053.doc
DSIN 25.24 Hazard Identification and Risk assessment Dürr India Pvt. Ltd. 3 Page(s)
Hazard Identification and risk assessment worksheet Paint and Assembly Systems
PFS, APT, CTS
Version: C Operations
Issued on: 27.01.2014 S.Sridhar 1
Hazard Identification and Risk Assessment Worksheet.
Date
30/11/16 Assessed by M.Hariharan Position Safety Excecutive Signature
/conversion/tmp/activity_task_scratch/618319053.doc
DSIN 25.24 Hazard Identification and Risk assessment Dürr India Pvt. Ltd. 3 Page(s)
Hazard Identification and risk assessment worksheet Paint and Assembly Systems
PFS, APT, CTS
Version: C Operations
Issued on: 27.01.2014 S.Sridhar 2
Hazard Identification and Risk Assessment Worksheet.
/conversion/tmp/activity_task_scratch/618319053.doc
DSIN 25.24 Hazard Identification and Risk assessment Dürr India Pvt. Ltd. 3 Page(s)
Hazard Identification and risk assessment worksheet Paint and Assembly Systems
PFS, APT, CTS
Version: C Operations
Issued on: 27.01.2014 S.Sridhar 3