Hazard Identification and Risk Assessment Hot & Cool Box Installation

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 3

Hazard Identification and Risk Assessment Worksheet.

Project Name : Project No : IN13-2910959


RE VV 1
Page: 1 of 2
Location : Paint Shop Work Activity Work at Height & Scaffolding

INITIAL RISK INITIAL RISK


S.No HAZARDS HARAM / EFFECTS CONTROLS
Severity Probability Risk Severity Probability Risk
  Avoid working at heights those works  which
can be done at ground level, like          
assembling of structure/ equipment,
fixing ladder etc.
    Provide safe access for the work. Install   
static lines where ‘tie off’ points are not
available.
 Conduct regular training on fall prevention.

1 Fall Men falling and materials H L M Keep all loose materials secured at heights. M L L
Use containers for small  Items like nuts and
bolts. Do not leave them on pipes and beams.

Full body safety harness will be worn and   


used while working at height beyond
1.8M
Take only those items to elevated levels
which will be used immediately.

Fall Objects Falling objects H L M Barricade the area around erection of scaffold M L
Scaffolding Scaffolder falling and  provide warning sign.
2 Collapse Scaffold collapse Do not throw up or throw down clamps, boards L
or pipes. Use proper method of lifting or
lowering materials
Do not leave loose items unsecured at
elevated levels.

/conversion/tmp/activity_task_scratch/618319053.doc
DSIN 25.24 Hazard Identification and Risk assessment Dürr India Pvt. Ltd. 3 Page(s)
Hazard Identification and risk assessment worksheet Paint and Assembly Systems
PFS, APT, CTS
Version: C Operations
Issued on: 27.01.2014 S.Sridhar 1
Hazard Identification and Risk Assessment Worksheet.

Work Activity : Page: 2 of 2


INITIAL RISK
S.No INITIAL RISK
HAZARDS HARAM / EFFECTS CONTROLS
Severity Probability Risk Severity Probability Risk
Conduct TBT meeting before the work  begins
Use ladder where required and wherever
possible during erection.
 Place scaff-tag with yellow label as soon as
the  first ladder has been installed.
Ensure the scaffold is plumb and level as it goes
up.
Secure the scaffold to the structure          
/building or provide outriggers.
Use the right couplings and ensure their
tightness.
Ensure the load on the scaffold does not exceed
the rated capacity.
During the daily inspection, look at the bottom of
standards for any undermining due to rain, flood
or  any other reason.

Date
30/11/16 Assessed by M.Hariharan Position Safety Excecutive Signature

/conversion/tmp/activity_task_scratch/618319053.doc
DSIN 25.24 Hazard Identification and Risk assessment Dürr India Pvt. Ltd. 3 Page(s)
Hazard Identification and risk assessment worksheet Paint and Assembly Systems
PFS, APT, CTS
Version: C Operations
Issued on: 27.01.2014 S.Sridhar 2
Hazard Identification and Risk Assessment Worksheet.

/conversion/tmp/activity_task_scratch/618319053.doc
DSIN 25.24 Hazard Identification and Risk assessment Dürr India Pvt. Ltd. 3 Page(s)
Hazard Identification and risk assessment worksheet Paint and Assembly Systems
PFS, APT, CTS
Version: C Operations
Issued on: 27.01.2014 S.Sridhar 3