Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/225082234

Optimum design of a house and its HVAC systems using simulation-based


optimisation

Article  in  International Journal of Low-Carbon Technologies · March 2010


DOI: 10.1093/ijlct/ctq010

CITATIONS READS

20 498

3 authors:

Mohamed Hamdy Ala Hasan


Norwegian University of Science and Technology VTT Technical Research Centre of Finland
60 PUBLICATIONS   2,520 CITATIONS    95 PUBLICATIONS   3,010 CITATIONS   

SEE PROFILE SEE PROFILE

Kai Sirén
Aalto University
112 PUBLICATIONS   4,054 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Smart Energy Transition View project

Tackling the challenges of a solar community concept in high latitudes View project

All content following this page was uploaded by Mohamed Hamdy on 05 June 2014.

The user has requested enhancement of the downloaded file.


International Journal of Low-Carbon Technologies Advance Access published April 21, 2010

Optimum design of a house and its HVAC


systems using simulation-based optimisation
..............................................................................................................................................................

Mohamed Hamdy, Ala Hasan and Kai Siren *


School of Technology, Aalto University, PO Box 14400, FIN-00076 Aalto, Finland
.............................................................................................................................................
Abstract
This paper deals with a multi-objective optimisation problem where the objective is to minimise CO2-
eq emissions and investment cost of a multi-zone single-family house and its heating/cooling systems.

Downloaded from http://ijlct.oxfordjournals.org at Helsinki University of Technology on April 26, 2010


Eight design variables are subjected to study: level of building tightness, insulation thickness of the
external wall, floor and roof, type of window glazing, window shading, heat recovery and heating/
cooling systems. Simulation-based optimisation is implemented to minimise the objective functions by
finding optimum values of the design variables. This is done by combining the dynamic building
performance simulation program IDA-ICE 3.0 with a modified genetic algorithm. The optimisation
results give the optimal solutions for the problem in the form of a Pareto front, showing the trade-off
between the two objectives. The obtained solutions are much better than the initial designs of the
house in terms of lower CO2-eq emissions and investment cost. It is noted from the obtained results
that the significance of the heating system is higher than the other design variables so that the optimal
solutions can be classified according to the type of the heating system. It is also noted that there is a
need to include a thermal comfort criterion as a problem constraint to limit overheating hours during
summer.

Keywords: building energy optimisation; space heating; CO2 emissions; investment cost
*Corresponding author:
kai.siren@tkk.fi Received 15 March 2010; revised 17 March 2010; accepted 19 March 2010
................................................................................................................................................................................

1 INTRODUCTION 2 BUILDING DESCRIPTION (INITIAL


The building sector accounts for 40% of the world’s total end
DESIGN)
energy consumption. Much of this energy is required for heating A typical Finnish two-floor semi-detached house, located in
and cooling of buildings. Energy for heating and cooling are the Helsinki, Finland, is considered as a case study. The total floor
main reasons for the associated CO2 emissions. To reduce such area of the house is 143 m2. The internal height is 2.5 m. The
emissions, investment has to be made, in terms of better features two floors are connected by a staircase. In the initial design,
of the building envelope and heating, ventilation and air con- the construction materials are selected in order to achieve heat
ditioning (HVAC) system type and components. With numerous transmission coefficient (U)-values (in W/m2 K) equal to the
options for those parameters, it is a very difficult task to find maximum values stated in the Finnish building code
cost-effective designs of the house and the HVAC system. The sol- (C3-2007). The internal gains due to people, lighting and elec-
ution is to make a simulation-based optimisation, which is utilis- tric appliances are assumed according to annual values speci-
ing optimisation combined with building energy performance fied by the Finnish building code (D5) and inserted in the
programmes, to minimise the defined objective functions by calculation as a profile with hourly values.
finding the optimal values of selected design variables. There are heating and cooling units in the building to cover
To achieve this, a multi-objective optimisation problem has the heating and cooling demand. An air-handling unit (AHU)
to be formulated for the design of a house and its heating/ is supplying fresh air to bedrooms and living room and
cooling systems. In the reported case, eight design variables exhausting air from bathrooms and kitchen. The AHU heater
were chosen. The optimisation aims at minimising the keeps the supply air temperature at 188C when the incoming
energy-related CO2-eq emissions and the investment cost outdoor air temperature is lower than this temperature. The
simultaneously. average exhaust air flow from the whole house is equal to 0.65

International Journal of Low-Carbon Technologies 2010, 00, 1 –5


# The Author 2010. Published by Oxford University Press. All rights reserved. For Permissions, please email: journals.permissions@oxfordjournals.org
doi:10.1093/ijlct/ctq010 1 of 5
M. Hamdy et al.

air change per hour. The heating system keeps the air tempera- consumption Q (in kW h/year) consists of the energy required
ture at a lower set-point of 218C. There is a heat exchanger for for space heating, system heat losses and domestic hot water.
heat recovery from exhaust air with an yearly efficiency of The first objective, CO2-eq emissions (kg/a), is calculated by
70%. Each floor has a total fixed glassing area of 5 m2. In the following equation, using the primary greenhouse gas
addition, a small openable window (0.9 m2) exists, which pro- emission factors, EF (in kg CO2-eq/kW h),
vides natural ventilation for summer cooling. It is assumed
that the building tightness at the initial design is n50 ¼ 4 1/h, Q  EF
CO2 -eq emission ¼ ð1Þ
where n50 is the number of air changes per hour at 50 Pa h
pressure difference across the building envelope.
The building energy simulation is carried out using where Q is the total heating energy consumption, h is effi-
IDA-ICE 3.0 software [1] and Helsinki-2001 hourly weather ciency of the heating system (Systems 1– 3) or the coefficient
data. To reduce the simulation execution time, the building of performance (COP) of the heat pump (Systems 4 and 5).

Downloaded from http://ijlct.oxfordjournals.org at Helsinki University of Technology on April 26, 2010


model is simplified into three zones (upper floor, lower floor For sources of emission in Finland, the values of EF for the
and staircase). The simplified building model needs about two studied systems are taken from [2] and shown in Table 6.
and a half minute to execute a 1-year simulation run of the Emissions considered are related to three major greenhouse
house and its HVAC system. gases: CO2, sulphur and nitrogen emissions.
The second objective, the investment cost, is the total cost
related to the eight design variables. Different types of
3 THE OPTIMISATION PROBLEM
Table 3 Ventilation unit.
3.1 Design variables
In the current study, eight design variables are chosen. Table 1 Type Efficiency Specification (%) Price (E)
presents the initial values, lower bounds, upper bounds and 1 60 Plate heat exchanger 3172
types (discrete or continuous) of the eight design variables. For 2 70 Rotating wheel 3443
the continuous variables, X refers to the insulation thickness 3 80 Rotating wheel 3715
(m). Tables 2– 6 give details of the discrete variables.

3.2 Objective functions Table 4 Shading [6].


The aim of this study was to achieve a cost-effective low- Type MSC MSSC Description Price
emission design of the building. Therefore, CO2-eq emissions
1 0.14 0.09 External blind, horizontal laths 200 E/m2
of the heating energy and the investment cost were selected as
2 1.0 1.0 No shading 0
two objective functions to be minimised. The heating energy
MSC, multiplier for shading coefficients of window (–); MSSC, multiplier
for short-wave shading coefficients (–).
Table 1 Design variables.
Variable Type Initial Lower Upper
design bound bound Table 5 Building tightness.

Xwall (m) Continuous 0.124 0.024 0.424 Type n50 (1/h) Price (E/m2)
Xroof (m) Continuous 0.210 0.110 0.510
1 4.0 0
Xfloor (m) Continuous 0.140 0.040 0.440
2 3.0 5
Windows type Discrete 1 1 5
3 2.0 12
Heat recovery type Discrete 2 1 3
4 1.0 22
Shading type Discrete 1 1 2
5 0.5 30
Building tightness level Discrete 1 1 5
Heating/cooling system type Discrete 5 1 5

Table 6 Heating/cooling system.


Table 2 Window.
Type System Price (E/m2) EF (kg/kW h) h or COP
2
Type U-value (W/m K) SSC factor (– ) Price (E)
1 Direct electric radiator 30 0.459 1.0
1 1.4 0.656 180 2 Oil fire boiler 93.93 0.267 0.9
2 1.1 0.656 185 3 District heating 101.07 0.226 1.0
3 1.0 0.530 205 4 GSHP no free cooling 125.56 0.459 3.0
4 0.85 0.482 240 5 GSHP with free cooling 132.71 0.459 3.0
5 1.1 0.437 210
GSHP, ground-source heat pump; EF, greenhouse gas emission factor; h,
SSC, short-wave shading coefficient. efficiency.

2 of 5 International Journal of Low-Carbon Technologies 2010, 00, 1– 5


Optimum design of a house and its HVAC systems

insulation are used in the external wall, roof and ground floor, the studied house, shown in Figure 1. These solutions are
which have prices of 56.3, 32.5 and 100 E/m3, respectively. The classified on the Pareto front according to the heating
prices of the other design variables are presented in Tables 2– system type. There is a remarkable influence of the type of
6, and are mainly from [3]. heating system on the results. The main reason for this is
that EF in equation (1) is directly dependent on the type
of the heating system. Besides, a part of the heating energy
4 OPTIMISATION AND SIMULATION Q is almost constant (those related to the domestic hot
water production and the system loss) and is not changing
A large number of design variables usually require a large by variations in the envelope-related design variables.
number of simulation-runs to get feasible solutions in a multi- Another reason is that the investment cost of the heating/
objective optimisation problem. Thus, in order to perform the cooling systems is often higher than the cost related to
optimisation process in shorter times, a modified multi- other design variables.

Downloaded from http://ijlct.oxfordjournals.org at Helsinki University of Technology on April 26, 2010


objective genetic algorithm (PR_GA) is implemented. It is a For comparison with the obtained solutions, four initial
two-phase, multi-objective optimisation solver that works under designs are also presented on Figure 1. All the initial
MATLAB environment and was developed by the authors. designs have the same values for the design variables
Details about PR_GA can be found in [4]. Briefly, in PR_GA, (Table 1) except for the type of the heating system. It is
the genetic algorithm (GA) from MATLAB 2008a Genetic and evident from Figure 1 that the optimisation solver suc-
Direct Search Toolbox [5] was modified to be able to deal with ceeded in providing a set of solutions which have much
discrete and continuous variables. Then, it was combined with a lower CO2-eq emissions and investment costs compared
deterministic optimisation algorithm in order to supply GA with the initial designs.
with a good collection of individuals as an initial population. Figure 2 shows the house annual space heating energy, for
This process is called preparation phase (PR). The major advan- the room units and AHU, for the optimal solutions indicated
tage of PR_GA is that it tries to reduce the random behaviour by Figure 1. From right to left, the solver has found solutions
of GA in an attempt to obtain good solutions with lower inside one heating system where the average U-value of the
number of simulation iterations. The current study uses PR_GA building is decreasing and the investment cost is increasing,
combined with IDA-ICE 3.0, whole-building dynamic simu- until it is more economical to switch to another heating
lation program, to perform the optimisation process. In the case system than continue reducing the U-value. By changing the
under study, 1010 simulation iterations are used: 290 for the heating system, the emission factor is decreasing and more
preparation phase and 720 for GA phase (using 40 population energy can be used by reducing the insulation level of the
individuals and 18 generations). The execution time was about building envelop. This cycle is repeated from right to left as
44 h on a computer with Windows Vista system (Intelw core shown in Figure 2.
TM
2 Quad CUP 2.40 GHz processor, 3061 MB RAM). The average U-value for the building is defined by the fol-
lowing equation:

5 RESULTS AND DISCUSSIONS Ubldg ¼ ðUwall  Awall þ Uroof  Aroof þ Ufloor  Afloor
þ Uwindow  Awindow Þ=Atotal ð2Þ
Altogether 41 Pareto optimal solutions were obtained in
terms of lower CO2-eq emissions and investment cost for

Figure 2. Annual space heating energy of the optimal designs as a per cent of
Figure 1. Pareto front and the initial designs. the space heating energy of the corresponding initial design.

International Journal of Low-Carbon Technologies 2010, 00, 1 –5 3 of 5


M. Hamdy et al.

where A is the area (m2), Atotal ¼ Awall þ Aroof þ Afloor þ when the ground-source heat pump system with free cooling
Awindow and Ubldg is the average U-value for the whole building heat-exchanger (System 5) is selected as a solution, because
envelop (W/m2 K). it is the only system which offers the cooling option.
The average U-values of the optimal solutions are shown in However, a procedure is made available in all cases to open
Figure 3. From Figures 2 and 3 it is obvious that for a lower the small window at each zone via a proportional-integral
Ubldg lower space heating energy is required. Variations in the controller when the indoor air temperature (Ti, 8C) is
type of heat recovery and building tightness explain the small .248C and the outdoor air temperature is lower than the
deviation in the relation between the results of the two figures. indoor air temperature. This procedure emulates the human
It is worthwhile mentioning that the average Ubldg of the behaviour to open the window and provides natural venti-
optimal solutions is 0.238 W/m2K, where 80.5% of the solutions lation when overheating occurs.
have Ubldg less than that for the initial design (Ubldg ¼ 0.3 W/ It can be seen from the results shown in Figure 1 that
m2 K). However, reducing Ubldg ,0.17 W/m2 K seems not to be System 5 was not selected in the optimal solutions. The optim-

Downloaded from http://ijlct.oxfordjournals.org at Helsinki University of Technology on April 26, 2010


the optimal solution whatever the type of heating system. isation algorithm preferred to invest in better properties of the
Figure 3 indicates that the optimisation solver preferred to building envelope and in other types of systems, which have
change the heating system from System 1 (Solution 23, Ubldg ¼ lower price and no cooling, instead of investing in the higher
0.17 W/m2 K) to System 2 (Solution 22, Ubldg ¼ 0.34 W/m2 K) price system (System 5). Same reason applies for not getting
instead of continuing in reducing Ubldg with System 1 as what solutions with window shading. As a result, the indoor air
occurred from solutions 41 to 23, knowing that the minimum temperature increased above 248C during summer for the
bound for Ubldg in the space solution is 0.131 W/m2 K. obtained solutions. In order to evaluate this overheating, a
In addition, at solution (23), building tightness (n50 ¼ degree-hour parameter (DH24, in 8C h) is defined as the sum-
1.0 1/h) and heat recovery efficiency (h ¼ 70%) were selected, mation of the degrees higher than 248C at the warmest zone at
while the solution space includes higher building tightness each hourly time step in a 1-year simulation (8760 h)
(n50 ¼ 0.5 1/h) as well as better heat recovery (h ¼ 80%),
which provide higher savings in the space heating energy. This X
i¼8760
DH24 ¼ ðT i  24Þ dt ð3Þ
illustrates that changing the type of the heating system from
i¼1
System (1) to System (2) is a better solution for the two objec-
tive functions than reducing the space heating energy with Ti  24  0
System 1. On the other hand, the district heating solutions
(System 3) dominated most of the oil fire boiler solutions where Ti is the indoor air temperature [8C] and dt is a 1-h
(System 2). The reason is that, there is no considerable differ- time period.
ence in the price between the two systems, while the emission It is noted that overheating occurred in all the optimal sol-
factor of System 3 is less than that for System 2. utions with a range of DH24 from 4181 to 62548C h, while the
It is to note that the minimum required air temperature reference value for the initial design case without a cooling system
inside the zones, 218C, was maintained in all the optimal is 24008C h. Minimum overheating occurred at solution number
solutions with the different types of envelope parameters and 41, which has a maximum value of Ubldg (0.496 W/m2 K) and
systems. This is achieved by the controller acting on the CO2-eq emission.
zone-heating units. The higher set-point (248C) of the zone
air temperature is applicable only during the summer season,
6 CONCLUSIONS
By using simulation-based optimisation, the multi-objective
optimisation solver succeeded in finding designs of the house
and its HVAC systems that have lower CO2-eq emissions and
investment costs compared with the initial designs. The
heating system seems to have the largest influence on the
objective values and the optimal solutions. Other variables
characterising the insulation level and tightness of the building
envelop as well as the system features have a smaller effect.
Using CO2 emissions and investment cost as objectives led to
optimal solutions where the building insulation and tightness
caused increased room air temperatures and overheating
during the summer season. Therefore, to limit this phenom-
enon, there is a need to include a constraint for the maximum
value of the allowable overheating of air temperature inside the
Figure 3. Average U-value of the house (Ubldg) for the optimal solutions. zones in the problem set-up. This will be considered in the

4 of 5 International Journal of Low-Carbon Technologies 2010, 00, 1– 5


Optimum design of a house and its HVAC systems

continuation work of this study, which will be done by includ- (in Finnish). Tampere University of Technology, Institute of Construction
ing a thermal comfort criterion as a problem constraint in the Economics.
multi-objective optimisation process. [3] Hasan A, Vuolle M, Siren K. Minimisation of life cycle cost of a detached
house using combined simulation and optimisation. Build Environ 43:
2022 – 34.
[4] Hamdy M, Hasan A, Siren K. Combination of optimisation algorithms for
REFERENCES a multi-objective building design problem. In: Proceedings of Building
Simulation ’09 Conference, IBPSA, 2009, pp. 173 – 9.
[1] http://www.equa.se/eng.ice.html. [5] Deb K. Multi-objective Optimization Using Evolutionary Algorithms. John
[2] Heljo J, Laine H. Electrical heating and Heat pumps as consumers Wiley and Sons, 2001.
of electricity and causes of emissions in Finland. Report 2005:2 [6] http://www.tamar.fi.

Downloaded from http://ijlct.oxfordjournals.org at Helsinki University of Technology on April 26, 2010

International Journal of Low-Carbon Technologies 2010, 00, 1 –5 5 of 5

View publication stats

You might also like