Job No.

Project Name Work Title Task Group Task Subcontractor Approved Confirmed Prepared

- INFINEON BATAM 2 Hydrocarbon Concrete Sampling Ground Work Civil Work Elton Ilham MohD Riza F

Heavy Machines * To change the procedure, report to and consult the site manager on
- Hole Saw, Vacuum Hard Hat, Gloves & Glasses the changes, have a hazard prevention meeting, and familiarize them to
Machines Tools all the workers before resuming the work.

Lint free ESD Jumpsuit / smock


Temporary Required
Lint free ESD protecton sheet General Worker
Materials Qualifications

No Detailed Procedure Quality Points Safety Points


1 PREPARATION
- Enter the production area wear ESD jumpsuit/smock - Make sure smock & dust proof suit clean condition - Wear Facemask
jumpsuit
is in clean condition - Use suction holder - Wear ESD Shoes
- Install Lint Free ESD sheet temporary protection - Make sure it is tightly closed - Wear Handgloves
- Remove raised floor board - Make sure cotton waste clean condition - Proper Exhaust (Create Negative
- Mark the location of the concrete sampling on - Protection trunking cable or tray cable from the water Pressure Area)
the floor splash by ESD SHEET PROTECTION
- Make sure it is care from electrical wire & utility pipe

2 DRILLING ACTIVITY
- Make sure the position of the soil test sample is correct - Confirm by Surveyor for the point
- 20 cm deep drill with 4 inch diameter
- Take the sample ( Concrete )

3 CLEANING AREA
- Cleaning working area after finish the job - Cleaning from the mud
- Open ESD protection sheet then install raised - Use suction holder
floor board
DRILLING ACTIVITY SAMPLE

200 mm
Cotton Waste
( Mud Protection)
Diameter 4 inch

618415008.xls Page 1