PM FROM PH AT KM 120.

925 OF TGP MAIN CANAL TO MUDIREDDYPALLE DC


Detailed Estimate for Encasement of Pipe Line at Stream Crossing at km 1.70
S.no. Description No Length Breadth Depth Quantity
1 2 3 4 5 6 7
1 Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
embankment, filter drains / catch water drains etc., including dressing bed and sides to required
level and profile, cost of all materials, machinery, labour, placing the excavated soil neatly in
dump area or for the formation of service road / embankment as directed etc., complete with
initial lead upto 1 km and all lifts.( IRR-CCDW-1-2 )
Nala Portion pipe encasement portion 1 55 2.5 2.2 302.50
Bank portion on both sides 1 5 2.5 2.2 27.50
Pitching on both sides of pipe encasement 2 3 56.8 0.825 281.16
Total quantity 611.16
Deduct HDR -1 25.650 Cum -25.65
Deduct HR -1 19.000 Cum -19.00
Cum 566.510
2 Excavation in ordinary rock without blasting for foundations of canal cross drainage and other
appurtenant structures and placing the excavated stuff neatly in specified dump area or disposing
off the same as directed etc., complete with initial lead upto 50 m and initial lift upto 3 m.( IRR-
CCDW-1-4 )
For Pipe Encasement Length 1 10.000 2.85 0.900 25.650
Cum 25.650
Excavation in hard rock requiring blasting including boulders above 0.6 m upto 1.2 m dia. For
foundations of canal cross drainage and other appurtenant structures and placing the excavated
3 stuff neatly in specified dump area or disposing off the same as directed etc., complete with initial
lead upto 50 m and initial lift upto 3 m.

For Pipe Encasement Length 1 10.000 1.900 1.000 19.000


Cum 19.000
4
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15
N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts. (Cement content: 260 kg / cum with use of super
plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20, FA :
0.40 cum) ( IRR-CCDW-2-3 )

Levelling coarse under Pipe Encasement 1 60 1.1 0.2 13.20


Cum 13.200
5 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20
N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials, machinery,
labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc., complete with initial lead upto 50 m and all lifts.(Cement content: 320 kg /
cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--
50:30:20, FA : 0.40 cum) ( IRR-CCDW-2-8 )

Encasement 1 60 0.8 0.8 38.40


Deduction Pipe portion 0.7855 60 0.4 0.4 -7.54
30.86
Cum 31.00
6 Providing and filling murum / gravely soil under approach slab including breaking clods,
spreading in layers of 10 to 15 cm, watering, compaction by power roller to achieve density
control of not less than 95 percent etc., complete with lead upto 50 m and all lifts. (IRR-
CCDW-7-3 )
below the Pitching in nala portion 1 55.000 6.000 0.225 74.250
below the Pitching on side banks 1 1.800 6.000 0.150 1.620
Cum 75.870
S.no. Description No Length Breadth Depth Quantity
1 2 3 4 5 6 7
7 Providing and Constructing 30 cm thick dry rubble stone pitching including cost of all
materials,labour,hand packing,finishing etc.,complete IRR-CAW-8-4
nala portion 1 55.000 6.000 0.300 99.000
side banks 1 1.800 6.000 0.300 3.240
Cum 102.240
8 Providing impervious hearting embankment with soil collected in embankment area in heaps as
part of disposal of excavated soil from canal including cost of all materials,machinery, labour, all
operations such as sortingout, spreading in layer of 25 cm before compaction, breaking
clods,sectioning, watering and compacting each layer to density control of not less than 95
percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller etc.,
complete with lead upto 1 km for water IRR-CAW-4-2

Execavated Area Item 1 611.160


Deduct excavated eart for pitching -1 281.16 Cum -281.160
Deduct pcc -1 13.200 Cum -13.200
Deduct Pipe with encasement -1 38.400 Cum -38.400
Cum 278.400

9 Providing, fabricating and placing in position


reinforcement steel bars for RCC works including
cleaning, straightening, cutting, bending,
hooking, lapping, welding wherever
required,tying with 1.25 mm dia soft annealed
steel wire, including cost of all materials,
machinery, labour etc., complete with initial lead Total
upto 50 and all lifts. ( IRR-CCDW-2-1 ) Length Length Unit Wt. Total Wt.
No m m in Kg in kg
Pipe Encasement reinforcement
bars around Pipe encasement 10mmdia@200 c/c 1204 1.10 1324.4 0.62 821.13
bars along Pipe encasement 10mmdia@200 c/c 16 60.30 964.8 0.62 598.18
Haunches around pipe10mmdia@200 c/c 1204 0.4 481.6 0.62 298.59
1717.90
PM FROM PH AT KM 120.925 OF TGP MAIN CANAL TO MUDIREDDYPALLE DC
Detailed Estimate for Encasement of Pipe Line at Stream Crossing at km 2.61
S.no. Description No Length Breadth Depth Quantity
1 2 3 4 5 6 7
1 Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
embankment, filter drains / catch water drains etc., including dressing bed and sides to required
level and profile, cost of all materials, machinery, labour, placing the excavated soil neatly in
dump area or for the formation of service road / embankment as directed etc., complete with
initial lead upto 1 km and all lifts. ( IRR-CCDW-1-2 )
Nala Portion pipe encasement portion 1 9 2.5 2.2 49.50
Bank portion on both sides 1 3 2.5 2.2 16.50
Pitching on both sides of pipe encasement 2 3 10.8 0.825 53.46
Total quantity 119.46
Cum 119.50
2 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15
N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts. (Cement content: 260 kg / cum with use of super
plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20, FA :
0.40 cum) ( IRR-CCDW-2-3 )

Levelling coarse under Pipe Encasement 1 12 1.1 0.2 2.64


Cum 2.64
3 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20
N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials, machinery,
labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc., complete with initial lead upto 50 m and all lifts.(Cement content: 320 kg /
cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--
50:30:20, FA : 0.40 cum) ( IRR-CCDW-2-8 )

Encasement 1 12 0.8 0.8 7.68


Deduction Pipe portion 0.7855 12 0.4 0.4 -1.51
6.17
Cum 6.20
4 Providing and filling murum / gravely soil under approach slab including breaking clods,
spreading in layers of 10 to 15 cm, watering, compaction by power roller to achieve density
control of not less than 95 percent etc., complete with lead upto 50 m and all lifts. (IRR-
CCDW-7-3 )

below the Pitching in nala portion 1 9.000 6.000 0.225 12.150


below the Pitching on side banks 1 1.800 6.0000.150 1.620
Cum 13.770
5 Providing and Constructing 30 cm thick dry rubble stone pitching including cost of all
materials,labour,hand packing,finishing etc.,complete IRR-CAW-8-4

nala portion 1 9.000 6.000 0.300 16.200


side banks 1 1.800 6.000 0.300 3.240
Cum 19.440

6 Providing impervious hearting embankment with soil collected in embankment area in heaps as
part of disposal of excavated soil from canal including cost of all materials,machinery, labour, all
operations such as sortingout, spreading in layer of 25 cm before compaction, breaking
clods,sectioning, watering and compacting each layer to density control of not less than 95
percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller etc.,
complete with lead upto 1 km for water IRR-CAW-4-2

Execavated Area Item 1 119.500


Deduct excavated eart for pitching -1 53.46 Cum -53.460
S.no. Description No Length Breadth Depth Quantity
1 2 3 4 5 6 7
Deduct pcc -1 2.640 Cum -2.640
Deduct Pipe with encasement -1 7.680 Cum -7.680
Cum 55.720

7 Providing, fabricating and placing in position


reinforcement steel bars for RCC works including
cleaning, straightening, cutting, bending,
hooking, lapping, welding wherever
required,tying with 1.25 mm dia soft annealed
steel wire, including cost of all materials,
machinery, labour etc., complete with initial lead Total
upto 50 and all lifts. ( IRR-CCDW-2-1 ) Length Length Unit Wt. Total Wt.
No m m in Kg in kg
Pipe Encasement reinforcement
bars around Pipe encasement 10mmdia@200 c/c 244 1.10 268.4 0.62 166.4
bars along Pipe encasement 10mmdia@200 c/c 16 12.30 196.8 0.62 122.0
Haunches around pipe10mmdia@200 c/c 244 0.4 97.6 0.62 60.5
348.94
PM FROM PH AT KM 120.925 OF TGP MAIN CANAL TO MUDIREDDYPALLE DC
Detailed Estimate for Encasement of Pipe Line at Stream Crossing at km 3.105
S.no. Description No Length Breadth Depth Quantity
1 2 3 4 5 6 7
1 Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
embankment, filter drains / catch water drains etc., including dressing bed and sides to required
level and profile, cost of all materials, machinery, labour, placing the excavated soil neatly in
dump area or for the formation of service road / embankment as directed etc., complete with
initial lead upto 1 km and all lifts. ( IRR-CCDW-1-2 )
Nala Portion pipe encasement portion 1 7 2.5 2.2 38.50
Bank portion on both sides 1 3 2.5 2.2 16.50
Pitching on both sides of pipe encasement 2 3 8.8 0.825 43.56
Total quantity 98.56
Cum 99.00
2 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15
N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts. (Cement content: 260 kg / cum with use of super
plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20, FA :
0.40 cum) ( IRR-CCDW-2-3 )

Levelling coarse under Pipe Encasement 1 10 1.1 0.2 2.20


Cum 2.200
3 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20
N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials, machinery,
labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc., complete with initial lead upto 50 m and all lifts.(Cement content: 320 kg /
cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--
50:30:20, FA : 0.40 cum) ( IRR-CCDW-2-8 )

Encasement 1 10 0.8 0.8 6.40


Deduction Pipe portion 0.7855 10 0.4 0.4 -1.26
5.14
Cum 5.14
4 Providing and filling murum / gravely soil under approach slab including breaking clods,
spreading in layers of 10 to 15 cm, watering, compaction by power roller to achieve density
control of not less than 95 percent etc., complete with lead upto 50 m and all lifts. (IRR-
CCDW-7-3 )

below the Pitching in nala portion 1 7.000 6.0000.225 9.450


below the Pitching on side banks 1 1.800 6.0000.150 1.620
Cum 11.070
5 Providing and Constructing 30 cm thick dry rubble stone pitching including cost of all
materials,labour,hand packing,finishing etc.,complete IRR-CAW-8-4
nala portion 1 7.000 6.000 0.300 12.600
side banks 1 1.800 6.000 0.300 3.240
Cum 15.840
6 Providing impervious hearting embankment with soil collected in embankment area in heaps as
part of disposal of excavated soil from canal including cost of all materials,machinery, labour, all
operations such as sortingout, spreading in layer of 25 cm before compaction, breaking
clods,sectioning, watering and compacting each layer to density control of not less than 95
percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller etc.,
complete with lead upto 1 km for water IRR-CAW-4-2

Execavated Area Item 1 99.000


Deduct excavated eart for pitching -1 43.56 Cum -43.560
Deduct pcc -1 2.200 Cum -2.200
Deduct Pipe with encasement -1 6.400 Cum -6.400
Cum 46.840
7 Providing, fabricating and placing in position
reinforcement steel bars for RCC works including
cleaning, straightening, cutting, bending,
hooking, lapping, welding wherever
required,tying with 1.25 mm dia soft annealed
steel wire, including cost of all materials,
machinery, labour etc., complete with initial lead Total
upto 50 and all lifts. ( IRR-CCDW-2-1 ) Length Length Unit Wt. Total Wt.
No m m in Kg in kg
Pipe Encasement reinforcement
bars around Pipe encasement 10mmdia@200 c/c 204 1.10 224.4 0.62 139.1
bars along Pipe encasement 10mmdia@200 c/c 16 10.30 164.8 0.62 102.2
Haunches around pipe10mmdia@200 c/c 204 0.4 81.6 0.62 50.6
291.90
Mudireddypalle Pressure Main Crossing the CT Road at km 0.025
Detailed Estimate for Encasement of Pipe Line at CT Road Crossing
S.no. Description No Length Breadth Depth Quantity
1 2 3 4 5 6 7
1 Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
embankment, filter drains / catch water drains etc., including dressing bed and sides to required
level and profile, cost of all materials, machinery, labour, placing the excavated soil neatly in
dump area or for the formation of service road / embankment as directed etc., complete with
initial lead upto 1 km and all lifts. ( IRR-CCDW-1-2 )
For Pipe Encasement Length 1 8.600 2.5 2.2 47.30
Cum 47.300
2 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15
N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts. (Cement content: 260 kg / cum with use of super
plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20, FA :
0.40 cum) ( IRR-CCDW-2-3 )
Under Pipe Encasement 1 8.300 1.100 0.200 1.826
Cum 1.830
3 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20
N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials, machinery,
labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc., complete with initial lead upto 50 m and all lifts.(Cement content: 320 kg /
cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--
50:30:20, FA : 0.40 cum) ( IRR-CCDW-2-8 )

Around the Pipe 1 8.00 0.80 0.80 5.12


Deduct Pipe portion -1 8.000 0.126 -1.01
Slab for Road portion over earth fill 1 5.000 4.200 0.225 4.725
Cum 8.840
4 Providing impervious hearting embankment with soil collected in embankment area in heaps as
part of disposal of excavated soil from canal including cost of all materials,machinery, labour, all
operations such as sortingout, spreading in layer of 25 cm before compaction, breaking
clods,sectioning, watering and compacting each layer to density control of not less than 95
percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller etc.,
complete with lead upto 1 km for water IRR-CAW-4-2

Execavated Area Item 1 47.300


Deduct pcc -1 1.830 Cum -1.830
Deduct Pipe with encasement -1 5.120 Cum -5.120
Slab for Road portion over earth fill 1 5.000 4.200 0.225 4.725
Cum 45.080
5 Providing, fabricating and placing in position
reinforcement steel bars for RCC works including
cleaning, straightening, cutting, bending,
hooking, lapping, welding wherever
required,tying with 1.25 mm dia soft annealed
steel wire, including cost of all materials, Total
machinery, labour etc., complete with initial lead Length Length Unit Wt. Total Wt.
upto 50 and all lifts. ( IRR-CCDW-2-1 ) No m m in Kg in kg
Pipe Encasement reinforcement
bars around Pipe encasement 10mmdia@200 c/c 164 1.10 180.4 0.62 111.85
bars along Pipe encasement 10mmdia@200 c/c 16 8.30 132.8 0.62 82.34
Haunches around pipe10mmdia@200 c/c 164 0.4 65.6 0.62 40.67
Slab for Road portion over earth fill
10mm Dia. @200 c/c 26 4.200 109.2 0.62 67.704
10 mm Dia. Distribution @200 c/c 22 5.000 110 0.62 68.200
Total in Kg 370.76
S.no. Description No Length Breadth Depth Quantity
1 2 3 4 5 6 7
Say in kg 371.00
Mudireddypalle Pressure Main Crossing the CT Road at km 0.30
Detailed Estimate for Encasement of Pipe Line at CT Road Crossing
S.no. Description No Length Breadth Depth Quantity
1 2 3 4 5 6 7
1 Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
embankment, filter drains / catch water drains etc., including dressing bed and sides to required
level and profile, cost of all materials, machinery, labour, placing the excavated soil neatly in
dump area or for the formation of service road / embankment as directed etc., complete with
initial lead upto 1 km and all lifts. ( IRR-CCDW-1-2 )

For Pipe Encasement Length 1 6.600 2.5 2.2 36.30


Cum 36.300
2 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15
N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts. (Cement content: 260 kg / cum with use of super
plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20, FA :
0.40 cum) ( IRR-CCDW-2-3 )
Under Pipe Encasement 1 6.300 1.100 0.200 1.386
Cum 1.390
4 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20
N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials, machinery,
labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc., complete with initial lead upto 50 m and all lifts.(Cement content: 320 kg /
cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--
50:30:20, FA : 0.40 cum) ( IRR-CCDW-2-8 )

Around the Pipe 1 6.00 0.80 0.80 3.84


Deduct Pipe portion -1 6.000 0.126 -0.75
Slab for Road portion over earth fill 1 5.000 4.200 0.225 4.725
Cum 7.811
5 Providing impervious hearting embankment with soil collected in embankment area in heaps as
part of disposal of excavated soil from canal including cost of all materials,machinery, labour, all
operations such as sortingout, spreading in layer of 25 cm before compaction, breaking
clods,sectioning, watering and compacting each layer to density control of not less than 95
percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller etc.,
complete with lead upto 1 km for water IRR-CAW-4-2
Execavated Area Item 1 36.300
Deduct pcc -1 1.390 Cum -1.390
Deduct Pipe with encasement -1 3.840 Cum -3.840
Cum 31.070
6 Providing, fabricating and placing in position
reinforcement steel bars for RCC works including
cleaning, straightening, cutting, bending,
hooking, lapping, welding wherever
required,tying with 1.25 mm dia soft annealed
steel wire, including cost of all materials, Total
machinery, labour etc., complete with initial lead Length Length Unit Wt. Total Wt.
upto 50 and all lifts. ( IRR-CCDW-2-1 ) No m m in Kg in kg
Pipe Encasement reinforcement
bars around Pipe encasement 10mmdia@200 c/c 124 1.10 136.4 0.62 84.57
bars along Pipe encasement 10mmdia@200 c/c 16 6.30 100.8 0.62 62.50
Haunches around pipe10mmdia@200 c/c 124 0.4 49.6 0.62 30.75
Slab for Road portion over earth fill
10mm Dia. @200 c/c 26 4.200 109.2 0.62 67.704
10 mm Dia. Distribution @200 c/c 22 5.000 110 0.62 68.200
Total in Kg 313.72
Say in kg 314.00
Mudireddypalle Pressure Main Crossing the CT Road at km 0.585
Detailed Estimate for Encasement of Pipe Line at CT Crossing
S.no. Description No Length Breadth Depth Quantity
1 2 3 4 5 6 7
1 Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
embankment, filter drains / catch water drains etc., including dressing bed and sides to required
level and profile, cost of all materials, machinery, labour, placing the excavated soil neatly in
dump area or for the formation of service road / embankment as directed etc., complete with
initial lead upto 1 km and all lifts. ( IRR-CCDW-1-2 )

For Pipe Encasement Length 1 6.600 2.5 2.2 36.30


Cum 36.300
2 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15
N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts. (Cement content: 260 kg / cum with use of super
plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20, FA :
0.40 cum) ( IRR-CCDW-2-3 )

Under Pipe Encasement 1 6.300 1.100 0.200 1.386


Cum 1.390
4 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20
N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials, machinery,
labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc., complete with initial lead upto 50 m and all lifts.(Cement content: 320 kg /
cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--
50:30:20, FA : 0.40 cum) ( IRR-CCDW-2-8 )

Around the Pipe 1 6.00 0.80 0.80 3.84


Deduct Pipe portion -1 6.000 0.126 -0.75
Slab for Road portion over earth fill 1 5.000 4.200 0.225 4.725
Cum 7.810
5 Providing impervious hearting embankment with soil collected in embankment area in heaps as
part of disposal of excavated soil from canal including cost of all materials,machinery, labour, all
operations such as sortingout, spreading in layer of 25 cm before compaction, breaking
clods,sectioning, watering and compacting each layer to density control of not less than 95
percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller etc.,
complete with lead upto 1 km for water IRR-CAW-4-2
Execavated Area Item 1 36.300
Deduct pcc -1 1.390 Cum -1.390
Deduct Pipe with encasement -1 3.840 Cum -3.840
Cum 31.070
6 Providing, fabricating and placing in position
reinforcement steel bars for RCC works including
cleaning, straightening, cutting, bending,
hooking, lapping, welding wherever
required,tying with 1.25 mm dia soft annealed
steel wire, including cost of all materials, Total
machinery, labour etc., complete with initial lead Length Length Unit Wt. Total Wt.
upto 50 and all lifts. ( IRR-CCDW-2-1 ) No m m in Kg in kg
Pipe Encasement reinforcement
bars around Pipe encasement 10mmdia@200 c/c 124 1.10 136.4 0.62 84.57
bars along Pipe encasement 10mmdia@200 c/c 16 6.30 100.8 0.62 62.50
Haunches around pipe10mmdia@200 c/c 124 0.4 49.6 0.62 30.75
Slab for Road portion over earth fill
10mm Dia. @200 c/c 26 4.200 109.2 0.62 67.704
10 mm Dia. Distribution @200 c/c 22 5.000 110 0.62 68.200
Total in Kg 313.72
Say in kg 314.00
Mudireddypalle Pressure Main Crossing the CT Road at km 0.70
Detailed Estimate for Encasement of Pipe Line at CT Road Crossing
S.no. Description No Length Breadth Depth Quantity
1 2 3 4 5 6 7
1 Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
embankment, filter drains / catch water drains etc., including dressing bed and sides to required
level and profile, cost of all materials, machinery, labour, placing the excavated soil neatly in
dump area or for the formation of service road / embankment as directed etc., complete with
initial lead upto 1 km and all lifts. ( IRR-CCDW-1-2 )
For Pipe Encasement Length 1 6.600 2.5 2.2 36.30
Cum 36.300
2 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15
N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts. (Cement content: 260 kg / cum with use of super
plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20, FA :
0.40 cum) ( IRR-CCDW-2-3 )

Under Pipe Encasement 1 6.300 1.100 0.200 1.386


Cum 1.390
4 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20
N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials, machinery,
labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc., complete with initial lead upto 50 m and all lifts.(Cement content: 320 kg /
cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--
50:30:20, FA : 0.40 cum) ( IRR-CCDW-2-8 )

Around the Pipe 1 6.00 0.80 0.80 3.84


Deduct Pipe portion -1 6.000 0.126 -0.75
Slab for Road portion over earth fill 1 5.000 4.200 0.225 4.725
Cum 7.810
5 Providing impervious hearting embankment with soil collected in embankment area in heaps as
part of disposal of excavated soil from canal including cost of all materials,machinery, labour, all
operations such as sortingout, spreading in layer of 25 cm before compaction, breaking
clods,sectioning, watering and compacting each layer to density control of not less than 95
percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller etc.,
complete with lead upto 1 km for water IRR-CAW-4-2

Execavated Area Item 1 36.300


Deduct pcc -1 1.390 Cum -1.390
Deduct Pipe with encasement -1 3.840 Cum -3.840
Cum 31.070
6 Providing, fabricating and placing in position
reinforcement steel bars for RCC works including
cleaning, straightening, cutting, bending,
hooking, lapping, welding wherever
required,tying with 1.25 mm dia soft annealed
steel wire, including cost of all materials,
Total
machinery, labour etc., complete with initial lead
Length Length Unit Wt. Total Wt.
upto 50 and all lifts. ( IRR-CCDW-2-1 )
No m m in Kg in kg
Pipe Encasement reinforcement
bars around Pipe encasement 10mmdia@200 c/c 124 1.10 136.4 0.62 84.57
bars along Pipe encasement 10mmdia@200 c/c 16 6.30 100.8 0.62 62.50
Haunches around pipe10mmdia@200 c/c 124 0.4 49.6 0.62 30.75
Slab for Road portion over earth fill
10mm Dia. @200 c/c 26 4.200 109.2 0.62 67.704
10 mm Dia. Distribution @200 c/c 22 5.000 110 0.62 68.200
Total in Kg 313.72
S.no. Description No Length Breadth Depth Quantity
1 2 3 4 5 6 7
Say in kg 314.00
Mudireddypalle Pressure Main Crossing the CT Road at km 1.14
Detailed Estimate for Encasement of Pipe Line at CT Road Crossing
S.no. Description No Length Breadth Depth Quantity
1 2 3 4 5 6 7
1 Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
embankment, filter drains / catch water drains etc., including dressing bed and sides to required
level and profile, cost of all materials, machinery, labour, placing the excavated soil neatly in
dump area or for the formation of service road / embankment as directed etc., complete with
initial lead upto 1 km and all lifts. ( IRR-CCDW-1-2 )

For Pipe Encasement Length 1 8.600 2.5 2.2 47.30


Cum 47.300
2 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15
N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts. (Cement content: 260 kg / cum with use of super
plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20, FA :
0.40 cum) ( IRR-CCDW-2-3 )
Under Pipe Encasement 1 8.300 1.100 0.200 1.826
Cum 1.830
4 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20
N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials, machinery,
labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc., complete with initial lead upto 50 m and all lifts.(Cement content: 320 kg /
cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--
50:30:20, FA : 0.40 cum) ( IRR-CCDW-2-8 )

Around the Pipe 1 8.00 0.80 0.80 5.12


Deduct Pipe portion -1 8.000 0.126 -1.01
Slab for Road portion over earth fill 1 5.000 4.200 0.225 4.725
Cum 8.840
5 Providing impervious hearting embankment with soil collected in embankment area in heaps as
part of disposal of excavated soil from canal including cost of all materials,machinery, labour, all
operations such as sortingout, spreading in layer of 25 cm before compaction, breaking
clods,sectioning, watering and compacting each layer to density control of not less than 95
percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller etc.,
complete with lead upto 1 km for water IRR-CAW-4-2

Execavated Area Item 1 47.300


Deduct pcc -1 1.830 Cum -1.830
Deduct Pipe with encasement -1 5.120 Cum -5.120
Cum 40.350
6 Providing, fabricating and placing in position
reinforcement steel bars for RCC works including
cleaning, straightening, cutting, bending,
hooking, lapping, welding wherever
required,tying with 1.25 mm dia soft annealed
steel wire, including cost of all materials, Total
machinery, labour etc., complete with initial lead Length Length Unit Wt. Total Wt.
upto 50 and all lifts. ( IRR-CCDW-2-1 ) No m m in Kg in kg
Pipe Encasement reinforcement
bars around Pipe encasement 10mmdia@200 c/c 164 1.10 180.4 0.62 111.85
bars along Pipe encasement 10mmdia@200 c/c 16 8.30 132.8 0.62 82.34
Haunches around pipe10mmdia@200 c/c 164 0.4 65.6 0.62 40.67
Slab for Road portion over earth fill
10mm Dia. @200 c/c 26 4.200 109.2 0.62 67.704
10 mm Dia. Distribution @200 c/c 22 5.000 110 0.62 68.200
Total in Kg 370.76
S.no. Description No Length Breadth Depth Quantity
1 2 3 4 5 6 7
Say in kg 371.00
MudireddyPalle Pressure Main Crossing the CT Road at km 2.36
Detailed Estimate for Encasement of Pipe Line at BT Road Crossing
S.no. Description No Length Breadth Depth Quantity
1 2 3 4 5 6 7
1 Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
embankment, filter drains / catch water drains etc., including dressing bed and sides to required
level and profile, cost of all materials, machinery, labour, placing the excavated soil neatly in
dump area or for the formation of service road / embankment as directed etc., complete with
initial lead upto 1 km and all lifts. ( IRR-CCDW-1-2 )

For Pipe Encasement Length 1 8.600 2.5 2.2 47.30


Cum 47.300
2 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15
N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts. (Cement content: 260 kg / cum with use of super
plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20, FA :
0.40 cum) ( IRR-CCDW-2-3 )

Under Pipe Encasement 1 8.300 1.100 0.200 1.826


Cum 1.830
4 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20
N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials, machinery,
labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc., complete with initial lead upto 50 m and all lifts.(Cement content: 320 kg /
cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--
50:30:20, FA : 0.40 cum) ( IRR-CCDW-2-8 )

Around the Pipe 1 8.00 0.80 0.80 5.12


Deduct Pipe portion -1 8.000 0.126 -1.01
Slab for Road portion over earth fill 1 5.000 4.200 0.225 4.725
Cum 8.840
S.no. Description No Length Breadth Depth Quantity
1 2 3 4 5 6 7
5 Providing impervious hearting embankment with soil collected in embankment area in heaps as
part of disposal of excavated soil from canal including cost of all materials,machinery, labour, all
operations such as sortingout, spreading in layer of 25 cm before compaction, breaking
clods,sectioning, watering and compacting each layer to density control of not less than 95
percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller etc.,
complete with lead upto 1 km for water IRR-CAW-4-2

Execavated Area Item 1 47.300


Deduct pcc -1 1.830 Cum -1.830
Deduct Pipe with encasement -1 5.120 Cum -5.120
Cum 40.350
6 Providing, fabricating and placing in position
reinforcement steel bars for RCC works including
cleaning, straightening, cutting, bending,
hooking, lapping, welding wherever
required,tying with 1.25 mm dia soft annealed
steel wire, including cost of all materials,
machinery, labour etc., complete with initial lead Total
upto 50 and all lifts. ( IRR-CCDW-2-1 ) Length Length Unit Wt. Total Wt.
No m m in Kg in kg
Pipe Encasement reinforcement
bars around Pipe encasement 10mmdia@200 c/c 164 1.10 180.4 0.62 111.85
bars along Pipe encasement 10mmdia@200 c/c 16 8.30 132.8 0.62 82.34
Haunches around pipe10mmdia@200 c/c 164 0.4 65.6 0.62 40.67
Slab for Road portion over earth fill
10mm Dia. @200 c/c 26 4.200 109.2 0.62 67.704
10 mm Dia. Distribution @200 c/c 22 5.000 110 0.62 68.200
Total in Kg 370.76
Say in kg 371.00
Mudireddypalle Pressure Main FC Pressure Main Crossing the CT Road at km 2.585
Detailed Estimate for Encasement of Pipe Line at CT Road Crossing
S.no. Description No Length Breadth Depth Quantity
1 2 3 4 5 6 7
1 Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
embankment, filter drains / catch water drains etc., including dressing bed and sides to required
level and profile, cost of all materials, machinery, labour, placing the excavated soil neatly in
dump area or for the formation of service road / embankment as directed etc., complete with
initial lead upto 1 km and all lifts. ( IRR-CCDW-1-2 )

For Pipe Encasement Length 1 8.600 2.5 2.2 47.30


Cum 47.300
2 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15
N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts. (Cement content: 260 kg / cum with use of super
plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20, FA :
0.40 cum) ( IRR-CCDW-2-3 )

Under Pipe Encasement 1 8.300 1.100 0.200 1.826


Cum 1.830
3 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20
N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials, machinery,
labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc., complete with initial lead upto 50 m and all lifts.(Cement content: 320 kg /
cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--
50:30:20, FA : 0.40 cum) ( IRR-CCDW-2-8 )

Around the Pipe 1 8.00 0.80 0.80 5.12


Deduct Pipe portion -1 8.000 0.126 -1.01
Slab for Road portion over earth fill 1 5.000 4.200 0.225 4.725
Cum 8.840
4 Providing impervious hearting embankment with soil collected in embankment area in heaps as
part of disposal of excavated soil from canal including cost of all materials,machinery, labour, all
operations such as sortingout, spreading in layer of 25 cm before compaction, breaking
clods,sectioning, watering and compacting each layer to density control of not less than 95
percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller etc.,
complete with lead upto 1 km for water IRR-CAW-4-2

Execavated Area Item 1 47.300


Deduct pcc -1 1.830 Cum -1.830
Deduct Pipe with encasement -1 5.120 Cum -5.120
Cum 40.350
5 Providing, fabricating and placing in position
reinforcement steel bars for RCC works including
cleaning, straightening, cutting, bending,
hooking, lapping, welding wherever
required,tying with 1.25 mm dia soft annealed
steel wire, including cost of all materials,
machinery, labour etc., complete with initial lead Total
upto 50 and all lifts. ( IRR-CCDW-2-1 ) Length Length Unit Wt. Total Wt.
No m m in Kg in kg
Pipe Encasement reinforcement
bars around Pipe encasement 10mmdia@200 c/c 164 1.10 180.4 0.62 111.85
bars along Pipe encasement 10mmdia@200 c/c 16 8.30 132.8 0.62 82.34
Haunches around pipe10mmdia@200 c/c 164 0.4 65.6 0.62 40.67
Slab for Road portion over earth fill
10mm Dia. @200 c/c 26 4.200 109.2 0.62 67.704
10 mm Dia. Distribution @200 c/c 22 5.000 110 0.62 68.200
Total in Kg 370.76
S.no. Description No Length Breadth Depth Quantity
1 2 3 4 5 6 7
Say in kg 371.00
Mudireddypalle Pressure Main Crossing the CT Road at km 3.385
Detailed Estimate for Encasement of Pipe Line at CT Road Crossing
S.no. Description No Length Breadth Depth Quantity
1 2 3 4 5 6 7
1 Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
embankment, filter drains / catch water drains etc., including dressing bed and sides to required
level and profile, cost of all materials, machinery, labour, placing the excavated soil neatly in
dump area or for the formation of service road / embankment as directed etc., complete with
initial lead upto 1 km and all lifts. ( IRR-CCDW-1-2 )
For Pipe Encasement Length 1 8.600 2.5 2.2 47.30
Cum 47.300
2 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15
N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts. (Cement content: 260 kg / cum with use of super
plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20, FA :
0.40 cum) ( IRR-CCDW-2-3 )
Under Pipe Encasement 1 8.300 1.100 0.200 1.826
Cum 1.830
3 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20
N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials, machinery,
labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc., complete with initial lead upto 50 m and all lifts.(Cement content: 320 kg /
cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--
50:30:20, FA : 0.40 cum) ( IRR-CCDW-2-8 )

Around the Pipe 1 8.00 0.80 0.80 5.12


Deduct Pipe portion -1 8.000 0.126 -1.01
Slab for Road portion over earth fill 1 5.000 4.200 0.225 4.725
Cum 8.840
4 Providing impervious hearting embankment with soil collected in embankment area in heaps as
part of disposal of excavated soil from canal including cost of all materials,machinery, labour, all
operations such as sortingout, spreading in layer of 25 cm before compaction, breaking
clods,sectioning, watering and compacting each layer to density control of not less than 95
percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller etc.,
complete with lead upto 1 km for water IRR-CAW-4-2

Execavated Area Item 1 47.300


Deduct pcc -1 1.830 Cum -1.830
Deduct Pipe with encasement -1 5.120 Cum -5.120
Cum 40.350
5 Providing, fabricating and placing in position
reinforcement steel bars for RCC works including
cleaning, straightening, cutting, bending,
hooking, lapping, welding wherever
required,tying with 1.25 mm dia soft annealed
steel wire, including cost of all materials,
Total
machinery, labour etc., complete with initial lead
Length Length Unit Wt. Total Wt.
upto 50 and all lifts. ( IRR-CCDW-2-1 )
No m m in Kg in kg
Pipe Encasement reinforcement
bars around Pipe encasement 10mmdia@200 c/c 164 1.10 180.4 0.62 111.85
bars along Pipe encasement 10mmdia@200 c/c 16 8.30 132.8 0.62 82.34
Haunches around pipe10mmdia@200 c/c 164 0.4 65.6 0.62 40.67
Slab for Road portion over earth fill
10mm Dia. @200 c/c 26 4.200 109.2 0.62 67.704
10 mm Dia. Distribution @200 c/c 22 5.000 110 0.62 68.200
Total in Kg 370.76
S.no. Description No Length Breadth Depth Quantity
1 2 3 4 5 6 7
Say in kg 371.00
KONDRAJUPALLI LIS
Detailed Estimate for THRUST BLOCK at km 0.150 of Pressure main

S.no. Description No Length Breadth Depth Quantity


1 2 3 4 5 6 7
1 Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
embankment, filter drains / catch water drains etc., including dressing bed and sides to
required level and profile, cost of all materials, machinery, labour, placing the excavated
soil neatly in dump area or for the formation of service road / embankment as directed
etc., complete with initial lead upto 1 km and all lifts.( IRR-CCDW-1-2 )

Thrust block 1 0.900 0.900 1.900 1.539


1 1.050 1.000 1.200 1.260
Cum 2.800
2 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less
than 20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean,
hard, graded aggregates for sub-structure / super- structure works including cost of all
materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in
position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and
all lifts.( IRR-CCDW-2-8 )
Thrust block 1 0.900 0.900 0.900 0.729
deduct pipe portion -1 0.900 0.071 -0.064
1 0.950 0.950 0.700 0.632
1 1.050 1.050 0.200 0.221
Cum 1.520
3 Providing, fabricating and placing in position reinforcement steel bars for RCC works
including cleaning, straightening, cutting, bending, hooking, lapping, welding wherever
required,tying with 1.25 mm dia soft annealed steel wire, including cost of all materials,
machinery, labour etc., complete with initial lead upto 50 and all lifts.( IRR-CCDW-2-1 )

bar
Top & Bottom dia. spacing length No's Weight
main 12 200 0.900 36 24.00
Distribution 10 200 0.900 28 15.56
Sides
Verticals 12 200 0.900 36 24.00
Horizantals 10 200 0.900 28 15.56
Total kgs 80.0
MUDIREDDYPALLE LIS
Detailed Estimate for THRUST BLOCK at km 0.00 of Pressure main

S.no. Description No Length Breadth Depth Quantity


1 2 3 4 5 6 7
1
Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
embankment, filter drains / catch water drains etc., including dressing bed and sides to
required level and profile, cost of all materials, machinery, labour, placing the excavated
soil neatly in dump area or for the formation of service road / embankment as directed
etc., complete with initial lead upto 1 km and all lifts. ( IRR-CCDW-1-2 )

Thrust block 1 2.650 1.500 2.300 9.143


Cum 9.140
2
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less
than 15 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard,
graded aggregates for foundation filling including cost of all materials, machinery, labour,
formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 260 kg /
cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending
Ratio of CA--50:30:20, FA : 0.40 cum) ( IRR-CCDW-2-3 )

Thrust block 1 1.200 1.200 0.200 0.288


Cum 0.290
3
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less
than 20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean,
hard, graded aggregates for sub-structure / super- structure works including cost of all
materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in
position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and
all lifts.( IRR-CCDW-2-8 )

Thrust block 1 0.900 0.900 0.900 0.729


deduct pipe portion -1 0.786 0.40x0.40 -0.126
Cum 0.600
4
Providing, fabricating and placing in position
reinforcement steel bars for RCC works
including cleaning, straightening, cutting,
bending, hooking, lapping, welding wherever
required,tying with 1.25 mm dia soft annealed
steel wire, including cost of all materials,
machinery, labour etc., complete with initial Total Unit
lead upto 50 and all lifts.( IRR-CCDW-2-1 ) Length Length Wt. in Total Wt.
No m m Kg in kg
Thrust block Reinforcemnt
Vertical bars -12mmdia@200 c/c 20 1.00 20 0.89 17.80
Horizontal Bars-10 mmdia@200 c/c 24 1.00 24 0.62 14.88
Haunches around pipe-10 mmdia@200 c/c 20 0.4 8 0.62 4.96
Total in Kg 37.64
Say in kg 37.70
MUDIREDDYPALLE LIS
Detailed Estimate for THRUST BLOCK at km 0.350 of Pressure main

S.no. Description No Length Breadth Depth Quantity


1 2 3 4 5 6 7
Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
embankment, filter drains / catch water drains etc., including dressing bed and sides to
1 required level and profile, cost of all materials, machinery, labour, placing the excavated
soil neatly in dump area or for the formation of service road / embankment as directed
etc., complete with initial lead upto 1 km and all lifts. ( IRR-CCDW-1-2 )
Thrust block 1 2.650 1.500 2.300 9.143
Cum 9.140
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less
than 15 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard,
graded aggregates for foundation filling including cost of all materials, machinery, labour,
2 formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 260 kg /
cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending
Ratio of CA--50:30:20, FA : 0.40 cum) ( IRR-CCDW-2-3 )

Thrust block 1 1.200 1.200 0.200 0.288


Cum 0.290
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less
than 20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean,
hard, graded aggregates for sub-structure / super- structure works including cost of all
3
materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in
position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and
all lifts.( IRR-CCDW-2-8 )
Thrust block 1 0.900 0.900 0.900 0.729
deduct pipe portion -1 0.786 0.40x0.40 -0.126
Cum 0.600

Providing, fabricating and placing in position


reinforcement steel bars for RCC works
including cleaning, straightening, cutting,
Total Unit
bending, hooking, lapping, welding wherever Length Total Wt.
4 No Length Wt. in
required,tying with 1.25 mm dia soft annealed m in kg
m Kg
steel wire, including cost of all materials,
machinery, labour etc., complete with initial
lead upto 50 and all lifts.( IRR-CCDW-2-1 )

Thrust block Reinforcemnt


Vertical bars -12mmdia@200 c/c 20 1.00 20 0.89 17.80
Horizontal Bars-10 mmdia@200 c/c 24 1.00 24 0.62 14.88
Haunches around pipe-10 mmdia@200 c/c 20 0.4 8 0.62 4.96
Total in Kg 37.64
Say in kg 37.70
MUDIREDDYPALLE LIS
Detailed Estimate for THRUST BLOCK at km 0.740 of Pressure main

S.no. Description No Length Breadth Depth Quantity


1 2 3 4 5 6 7

Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
embankment, filter drains / catch water drains etc., including dressing bed and sides to
1 required level and profile, cost of all materials, machinery, labour, placing the excavated
soil neatly in dump area or for the formation of service road / embankment as directed
etc., complete with initial lead upto 1 km and all lifts. ( IRR-CCDW-1-2 )

Thrust block 1 2.650 1.500 2.300 9.143


Cum 9.140
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less
than 15 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard,
graded aggregates for foundation filling including cost of all materials, machinery, labour,
2 formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 260 kg /
cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending
Ratio of CA--50:30:20, FA : 0.40 cum) ( IRR-CCDW-2-3 )
Thrust block 1 1.200 1.200 0.200 0.288
Cum 0.290
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less
than 20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean,
hard, graded aggregates for sub-structure / super- structure works including cost of all
3
materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in
position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and
all lifts.( IRR-CCDW-2-8 )
Thrust block 1 0.900 0.900 0.900 0.729
deduct pipe portion -1 0.786 0.40x0.40 -0.126
Cum 0.600

Providing, fabricating and placing in position


reinforcement steel bars for RCC works
including cleaning, straightening, cutting,
Total Unit
bending, hooking, lapping, welding wherever Length Total Wt.
4 No Length Wt. in
required,tying with 1.25 mm dia soft annealed m in kg
m Kg
steel wire, including cost of all materials,
machinery, labour etc., complete with initial
lead upto 50 and all lifts.( IRR-CCDW-2-1 )

Thrust block Reinforcemnt


Vertical bars -12mmdia@200 c/c 20 1.00 20 0.89 17.80
Horizontal Bars-10 mmdia@200 c/c 24 1.00 24 0.62 14.88
Haunches around pipe-10 mmdia@200 c/c 20 0.4 8 0.62 4.96
Total in Kg 37.64
Say in kg 37.70
MUDIREDDYPALLE LIS
Detailed Estimate for THRUST BLOCK at km 1.42 of Pressure main

S.no. Description No Length Breadth Depth Quantity


1 2 3 4 5 6 7
Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
embankment, filter drains / catch water drains etc., including dressing bed and sides to
1 required level and profile, cost of all materials, machinery, labour, placing the excavated
soil neatly in dump area or for the formation of service road / embankment as directed
etc., complete with initial lead upto 1 km and all lifts. ( IRR-CCDW-1-2 )

Thrust block 1 2.650 1.500 2.300 9.143


Cum 9.140

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less
than 15 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard,
graded aggregates for foundation filling including cost of all materials, machinery, labour,
2 formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 260 kg /
cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending
Ratio of CA--50:30:20, FA : 0.40 cum) ( IRR-CCDW-2-3 )

Thrust block 1 1.200 1.200 0.200 0.288


Cum 0.290

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less
than 20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean,
hard, graded aggregates for sub-structure / super- structure works including cost of all
3
materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in
position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and
all lifts.( IRR-CCDW-2-8 )

Thrust block 1 0.900 0.900 0.900 0.729


deduct pipe portion -1 0.786 0.40x0.40 -0.126
Cum 0.600

Providing, fabricating and placing in position


reinforcement steel bars for RCC works
including cleaning, straightening, cutting,
Total Unit
bending, hooking, lapping, welding wherever Length Total Wt.
4 No Length Wt. in
required,tying with 1.25 mm dia soft annealed m in kg
m Kg
steel wire, including cost of all materials,
machinery, labour etc., complete with initial
lead upto 50 and all lifts.( IRR-CCDW-2-1 )

Thrust block Reinforcemnt


Vertical bars -12mmdia@200 c/c 20 1.00 20 0.89 17.80
Horizontal Bars-10 mmdia@200 c/c 24 1.00 24 0.62 14.88
Haunches around pipe-10 mmdia@200 c/c 20 0.4 8 0.62 4.96
Total in Kg 37.64
Say in kg 37.70
MUDIREDDYPALLE LIS
Detailed Estimate for THRUST BLOCK at km 3.20 of Pressure main

S.no. Description No Length Breadth Depth Quantity


1 2 3 4 5 6 7

Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
embankment, filter drains / catch water drains etc., including dressing bed and sides to
1 required level and profile, cost of all materials, machinery, labour, placing the excavated
soil neatly in dump area or for the formation of service road / embankment as directed
etc., complete with initial lead upto 1 km and all lifts. ( IRR-CCDW-1-2 )

Thrust block 1 2.650 1.500 2.300 9.143


Cum 9.140

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less
than 15 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard,
graded aggregates for foundation filling including cost of all materials, machinery, labour,
2 formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 260 kg /
cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending
Ratio of CA--50:30:20, FA : 0.40 cum) ( IRR-CCDW-2-3 )

Thrust block 1 1.200 1.200 0.200 0.288


Cum 0.290

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less
than 20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean,
hard, graded aggregates for sub-structure / super- structure works including cost of all
3
materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in
position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and
all lifts.( IRR-CCDW-2-8 )

Thrust block 1 0.900 0.900 0.900 0.729


deduct pipe portion -1 0.786 0.40x0.40 -0.126
Cum 0.600

Providing, fabricating and placing in position


reinforcement steel bars for RCC works
including cleaning, straightening, cutting,
Total Unit
bending, hooking, lapping, welding wherever Length Total Wt.
4 No Length Wt. in
required,tying with 1.25 mm dia soft annealed m in kg
m Kg
steel wire, including cost of all materials,
machinery, labour etc., complete with initial
lead upto 50 and all lifts.( IRR-CCDW-2-1 )

Thrust block Reinforcemnt


Vertical bars -12mmdia@200 c/c 20 1.00 20 0.89 17.80
Horizontal Bars-10 mmdia@200 c/c 24 1.00 24 0.62 14.88
Haunches around pipe-10 mmdia@200 c/c 20 0.4 8 0.62 4.96
Total in Kg 37.64
Say in kg 37.70
MUDIREDDYPALLE LIS
Detailed Estimate for THRUST BLOCK at km 3.30 of Pressure main

S.no. Description No Length Breadth Depth Quantity


1 2 3 4 5 6 7
Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
embankment, filter drains / catch water drains etc., including dressing bed and sides to
1 required level and profile, cost of all materials, machinery, labour, placing the excavated
soil neatly in dump area or for the formation of service road / embankment as directed
etc., complete with initial lead upto 1 km and all lifts. ( IRR-CCDW-1-2 )

Thrust block 1 2.650 1.500 2.300 9.143


Cum 9.140

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less
than 15 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard,
graded aggregates for foundation filling including cost of all materials, machinery, labour,
2 formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 260 kg /
cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending
Ratio of CA--50:30:20, FA : 0.40 cum) ( IRR-CCDW-2-3 )

Thrust block 1 1.200 1.200 0.200 0.288


Cum 0.290

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less
than 20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean,
hard, graded aggregates for sub-structure / super- structure works including cost of all
3
materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in
position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and
all lifts.( IRR-CCDW-2-8 )

Thrust block 1 0.900 0.900 0.900 0.729


deduct pipe portion -1 0.786 0.40x0.40 -0.126
Cum 0.600

Providing, fabricating and placing in position


reinforcement steel bars for RCC works
including cleaning, straightening, cutting,
Total Unit
bending, hooking, lapping, welding wherever Length Total Wt.
4 No Length Wt. in
required,tying with 1.25 mm dia soft annealed m in kg
m Kg
steel wire, including cost of all materials,
machinery, labour etc., complete with initial
lead upto 50 and all lifts.( IRR-CCDW-2-1 )

Thrust block Reinforcemnt


Vertical bars -12mmdia@200 c/c 20 1.00 20 0.89 17.80
Horizontal Bars-10 mmdia@200 c/c 24 1.00 24 0.62 14.88
Haunches around pipe-10 mmdia@200 c/c 20 0.4 8 0.62 4.96
Total in Kg 37.64
Say in kg 37.70
MUDIREDDYPALLE LIS
Detailed Estimate for THRUST BLOCK at km 3.45 of Pressure main

S.no. Description No Length Breadth Depth Quantity


1 2 3 4 5 6 7
1 Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
embankment, filter drains / catch water drains etc., including dressing bed and sides to
required level and profile, cost of all materials, machinery, labour, placing the excavated
soil neatly in dump area or for the formation of service road / embankment as directed
etc., complete with initial lead upto 1 km and all lifts. ( IRR-CCDW-1-2 )
Thrust block 1 2.650 1.500 2.300 9.143
Cum 9.140
2 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less
than 15 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard,
graded aggregates for foundation filling including cost of all materials, machinery, labour,
formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 260 kg /
cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending
Ratio of CA--50:30:20, FA : 0.40 cum) ( IRR-CCDW-2-3 )
Thrust block 1 1.200 1.200 0.200 0.288
Cum 0.290
3
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less
than 20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean,
hard, graded aggregates for sub-structure / super- structure works including cost of all
materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in
position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and
all lifts.( IRR-CCDW-2-8 )

Thrust block 1 0.900 0.900 0.900 0.729


deduct pipe portion -1 0.786 0.40x0.40 -0.126
Cum 0.600
4
Providing, fabricating and placing in position
reinforcement steel bars for RCC works
including cleaning, straightening, cutting,
Total Unit
bending, hooking, lapping, welding wherever Length Total Wt.
No Length Wt. in
required,tying with 1.25 mm dia soft annealed m in kg
m Kg
steel wire, including cost of all materials,
machinery, labour etc., complete with initial
lead upto 50 and all lifts.( IRR-CCDW-2-1 )

Thrust block Reinforcemnt


Vertical bars -12mmdia@200 c/c 20 1.00 20 0.89 17.80
Horizontal Bars-10 mmdia@200 c/c 24 1.00 24 0.62 14.88
Haunches around pipe-10 mmdia@200 c/c 20 0.4 8 0.62 4.96
Total in Kg 37.64
Say in kg 37.70
MUDIREDDYPALLE LIS
Detailed Estimate for THRUST BLOCKS at at NALA Crossing at km 1.70 of Pressure main

S.no. Description No Length Breadth Depth Quantity


1 2 3 4 5 6 7
1 Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
embankment, filter drains / catch water drains etc., including dressing bed and sides to
required level and profile, cost of all materials, machinery, labour, placing the excavated
soil neatly in dump area or for the formation of service road / embankment as directed etc.,
complete with initial lead upto 1 km and all lifts. ( IRR-CCDW-1-2 )

Thrust block 2 2.650 1.500 2.300 18.285


Cum 18.290
2 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard,
graded aggregates for foundation filling including cost of all materials, machinery, labour,
formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts. (Cement content: 260 kg /
cum with use of super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending
Ratio of CA--50:30:20, FA : 0.40 cum) ( IRR-CCDW-2-3 )

Thrust block 2 1.200 1.200 0.200 0.576


Cum 0.580
3 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard,
graded aggregates for sub-structure / super- structure works including cost of all materials,
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
( IRR-CCDW-2-8 )
Thrust block 2 0.900 0.900 0.900 1.458
deduct pipe portion -2 0.786 0.40x0.40 -0.251
Cum 1.210
4 Providing, fabricating and placing in
position reinforcement steel bars for
RCC works including cleaning,
straightening, cutting, bending, hooking,
lapping, welding wherever required,tying
with 1.25 mm dia soft annealed steel
wire, including cost of all materials,
machinery, labour etc., complete with Total Total
initial lead upto 50 and all lifts.( IRR- Length Length Unit Wt. Wt. in
CCDW-2-1 ) No m m in Kg kg
Thrust block Reinforcemnt
Vertical bars -12mmdia@200 c/c 20 1.00 20 0.89 17.80
Horizontal Bars-10 mmdia@200 c/c 24 1.00 24 0.62 14.88

Haunches around pipe-10 mmdia@200 c/c 20 0.4


8 0.62 4.96
37.64
For 2 Nos Thrust Blocks 2 x 37.64 Cum 75.28
Total in Kg 75.28
Say in kg 75.30
MUDIREDDYPALLE LIS
Detailed Estimate for THRUST BLOCKS at at NALA Crossing km 2.61 of Pressure main

S.no. Description No Length Breadth Depth Quantity


1 2 3 4 5 6 7
1 Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
embankment, filter drains / catch water drains etc., including dressing bed and sides to
required level and profile, cost of all materials, machinery, labour, placing the excavated soil
neatly in dump area or for the formation of service road / embankment as directed etc.,
complete with initial lead upto 1 km and all lifts. ( IRR-CCDW-1-2 )

Thrust block 2 2.650 1.500 2.300 18.285


Cum 18.290
2 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15
N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts. (Cement content: 260 kg / cum with use of
super plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20,
FA : 0.40 cum) ( IRR-CCDW-2-3 )

Thrust block 2 1.200 1.200 0.200 0.576


Cum 0.580
3 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20
N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials,
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
( IRR-CCDW-2-8 )
Thrust block 2 0.900 0.900 0.900 1.458
deduct pipe portion -2 0.786 0.40x0.40 -0.251
Cum 1.210
4 Providing, fabricating and placing in position
reinforcement steel bars for RCC works
including cleaning, straightening, cutting,
bending, hooking, lapping, welding
wherever required,tying with 1.25 mm dia
soft annealed steel wire, including cost of
all materials, machinery, labour etc., Total Total
complete with initial lead upto 50 and all Length Length Unit Wt. Wt. in
lifts.( IRR-CCDW-2-1 ) No m m in Kg kg
Thrust block Reinforcemnt
Vertical bars -12mmdia@200 c/c 20 1.00 20.00 0.89 17.80
Horizontal Bars-10 mmdia@200 c/c 24 1.00 24.00 0.62 14.88

Haunches around pipe-10 mmdia@200 c/c


20 0.40 8.00 0.62 4.96
37.64
For 2 Nos Thrust Blocks 2 x 37.64 Cum 75.28
Total in Kg 75.28
Say in kg 75.30
MUDIREDDYPALLE LIS
Detailed Estimate for THRUST BLOCKS at NALA Crossing km 3.105 of Pressure main

S.no. Description No Length Breadth Depth Quantity


1 2 3 4 5 6 7
1
Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
embankment, filter drains / catch water drains etc., including dressing bed and sides to required
level and profile, cost of all materials, machinery, labour, placing the excavated soil neatly in
dump area or for the formation of service road / embankment as directed etc., complete with
initial lead upto 1 km and all lifts. ( IRR-CCDW-1-2 )

Thrust block 2 2.650 1.500 2.300 18.285


Cum 18.290
2 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15
N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts. (Cement content: 260 kg / cum with use of super
plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20, FA :
0.40 cum) ( IRR-CCDW-2-3 )

Thrust block 2 1.200 1.200 0.200 0.576


Cum 0.580
3 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20
N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials, machinery,
labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc., complete with initial lead upto 50 m and all lifts.( IRR-CCDW-2-8 )

Thrust block 2 0.900 0.900 0.900 1.458


deduct pipe portion -2 0.786 0.40x0.40 -0.251
Cum 1.210
4
Providing, fabricating and placing in position
reinforcement steel bars for RCC works including
cleaning, straightening, cutting, bending,
hooking, lapping, welding wherever
required,tying with 1.25 mm dia soft annealed
steel wire, including cost of all materials,
Total Total
machinery, labour etc., complete with initial lead
Length Length Unit Wt. Wt. in
upto 50 and all lifts.( IRR-CCDW-2-1 )
No m m in Kg kg
Thrust block Reinforcemnt
Vertical bars -12mmdia@200 c/c 20 1.00 20.00 0.89 17.80
Horizontal Bars-10 mmdia@200 c/c 24 1.00 24.00 0.62 14.88
Haunches around pipe-10 mmdia@200 c/c 20 0.40 8.00 0.62 4.96
37.64
For 2 Nos Thrust Blocks 2 x 37.64 Cum 75.28
Total in Kg 75.28
Say in kg 75.30