Professional Documents
Culture Documents
Excavation Work Guidelines For Irrigation and Water Supply Projects
Excavation Work Guidelines For Irrigation and Water Supply Projects
The process will include methods to carry out the excavation and surface
preparation, in compliance with the applicable environmental and safety
measures.
Site engineer is responsible for organizing all the works on site in a safe
manner, ensuring it is in accordance with the schedule and the construction
drawing. He must also assure the method statement procedure is followed
and must notify the consultant for inspection.
Safety officer is responsible in ensuring that all activities are carried out safely
at site, establishing the site safety plan, conducting continuous safety
inspection and stopping any unsafe work.
The major equipment and machinery used for the excavation works include,
but not limited to:
Bulldozer
Excavator
Rock Breaker
Wheel loader
Tipper Trucks
Wagon Drill
Compressor (2 Jack Hammer)
Bob Cat or JCB
Water tank: 01
Vibratory Steel Roller
Safe Slope: The steepest slope, at which an excavated face is stable against
slips and slides, having regard to the qualities of the material in the face, the
height of the face, the load above the face and the moisture conditions.
A survey shall be carried out on areas on the site that may require specific
Health and Safety attention to moderate and remove any hazards or risks.
Control all activities involving moving plant using nominated banks man.
Ensure that defective or suspect equipment, which has been withdrawn from
service, does not get back into service without the inspection and approval of
a competent person.
Existing Utilities:
Use cable detector to identify and locate the underground utilities and ensure
it is protected.
Lower the underground water table if encountered to below the invert of the
excavated area and always check the pumps to ensure its workability.
Fall into Excavation:
Establish a barricaded zone, 2m back from the left excavation face, in areas
where there is a risk of falling and where the depth of excavation exceeds 2m.
Ensure that all barriers, cones and flagging warning tapes are in place prior to
leaving the site.
Excavation by Blasting:
Check that all safety measures are being taken else blasting will be prohibited.
Relocate any vehicles and equipment parked within the blasting zone to safer
locations.
Take special care in order to avoid over breaks other than geological ones.
Quality assurance and quality control covers the records formed from site
inspections, examinations and tests that serve as documentation of the
conformance of site construction and erection to the drawings, specifications
and regulations.
Develop Test and Inspection Plan in line with the work to be constructed
showing ‘Hold and Inspection’ points.
Fill the inspection check list to ensure that all activates are being
performed as per the expected quality.
The inspection check list shall include the specific requirements, safety
and environmental measures.
Prepare inspection request, as per QA/QC Plan, and submit to the
Engineer for approval.
Follow up on the Engineer’s site inspection and comments, until the IR
form is approved.
Circulate the approved IR form for records keeping, and issue order to
proceed with next activities.
Upon obtaining all the necessary survey data, carry out a survey to obtain
original ground levels and submit for the approval of the Engineer.
Set out the coordinates of excavation using steel rods driven into the ground
and indicate on these rods the required depth to be excavated, where the
maximum distance between rods is 20 meters.
Prepare access to the working area and plan for the dump truck and plant
movement avoiding any close approach to the edge of excavation. Access
shall be approved by the Engineer taking into account the site traffic
management plan and the storage area for materials.
Carry out a survey with the coordination with the relevant authorities to
identify any existing services and use cable detection tools and hand digging
measures to clearly mark these services on the ground.
It has been identified that the ground conditions will allow for the excavated
faces to stand within a slope of 1/2 without the use of supports, however if
this is not the case, obtain more information about ground conditions to
determine the appropriate support system such as benching, battering or
using steel sheets driven into the ground.
If ingress of water occurs during any time the excavation is open, install
adequate dewatering system through suction pumps to dispose water in
accordance with the method statement for dewatering excavations.
Carry out the excavation works in accordance with the relevant approved
drawings and cross sections, to the widths and slopes shown thereon.
Where the excavation is to be done starting from less than 1.2m from the top,
carry out the excavation at two stages to achieve the required slopes.
Recheck the excavated elevations and locations at the end of stage one to
ensure that the face of excavation is finished to the required slope.
Carry out excavation works using a bulldozer with ripper and / or a 360°
excavator assisted at all times by a competent banks man.
Execute drilling by hydraulic rock drill with the sides of the excavation to be
smoothly blasted in order to form straight lines.
Saw cut all the edges of excavated areas on concrete or bituminous footways
and roadways to form trimmed edges and minimize damages.
Stockpile the excavated materials that are justified by the Engineer as
suitable backfilling material, at the lower side of the excavation far away from
the area.
Upon completion of excavation, verify set out locations and check the edge
slope and the bottom founding level of excavation.
If the surface is other than rock, apply water spray and compact using a
vibratory roller, immediately prior to placing the 100 mm blinding concrete.
Replace any removed loose soil encountered at formation level, or any excess
depth excavated below the formation level, with soil-cement mix or with
approved imported fill material compacted in accordance to specification.
Wash the rocky foundation surface using water or air compressor and clean it
from dust, mud, loose or fractured material and other debris, immediately
prior to placing the 100mm blinding concrete.
Where rock surfaces reach high temperatures under the influence of the sun,
carry out washing at night or in the early morning, to avoid fracturing due to
thermal shock.