Contract No: PROJECT: POLO ITP(PROCESS

No: OIL AND LUBEDiscipline: OIL) UNIT


FYPC/4000/POLO/C21047 C21047-2321-ITP-0600-001 INSTRUMENTATION
Client: FO/INST/COMMContractor: CABLE PULLING INSPECTIONDate: CHECKLIST
FARABI YANBU PETROCHEMICALS UTILITIES & INDUSTRIAL POWER
COMPANY SERVICES CO. LTD -------------/--------------/--------------------
Drawing No: Area / Location: Report / RFI No:
321 (POLO) / 321-POLO-RFI-INST-
---------------------------------------------------- ---------------------------------------------- --------------------------------------------------

INSPECTION DESCRIPTION:

UIPS FARABI
Item Description of Check
Check Check
01 Underground conduit has been swabbed-out
02 Cable tray is free of sharp edges
Verify number of bends between pulling points does not exceed specification
03
requirements
04 Verify cable reel assignment and cutting schedule
05 Verify cable rating, minimum pulling temperature and type of pulling compound
06 Verify arrows on high voltage cable reels for direction of pulling off reel
07 Megger metal clad cables before pulling
08 Verify instrument cable for continuity and isolation from drain wire before pulling
09 Verify maximum permitted pulling tension not exceeded
10 Continuity check after installation
11 Bending radius of cable in accordance with specifications
13 Cable is free of kinks, neat and cable lay is in accordance with drawings
14 Spacing between instrument cable and power cable in accordance with design
15 Cables identified per specification and drawings
16 Cable ends sealed after cutting
Comments (If any):

Requested By: (UIPS.) Confirmed By: (UIPS) Approved By: (FARABI)


Name Mr. Salahuddin Mr. Khezhar Ali Khan Mr. Sourabh Jhamb
Signature
& Date