Professional Documents
Culture Documents
Hoke, A (2014) - Testing Advanced Photovoltaic Inverters Conforming To IEEE Standard 1547 - Amendment 1
Hoke, A (2014) - Testing Advanced Photovoltaic Inverters Conforming To IEEE Standard 1547 - Amendment 1
hardware-in-the-loop (PHIL). Finally, Section VI provides combinations of operating conditions are tested, as under the
conclusions. magnitude tests.
Both the magnitude test and time test include procedures to
II. TEST PLAN test that any adjustable ride-through settings cannot be set in a
NREL’s beta test plan follows the format and methodology manner that interferes with trip settings.
established by IEEE 1547.1, while incorporating (1) upgraded
tests for response to abnormal voltage and frequency including
ride-through, (2) a newly developed test for voltage
regulation, and (3) modified tests for unintentional islanding,
open phase, and harmonics. Although IEEE 1547a does not
mandate ride-through requirements, its language does allow
such functionality, and future revisions may require it. Hence,
test procedures for ride-through are included in NREL’s test
plan. The details of the following test procedures are in [15].
A. Test for Response to Abnormal Voltage Conditions
The purpose of this test is to verify that the PV inverter
interconnection component or system ceases to energize the
area EPS as specified in IEEE 1547a with respect to Fig. 1. Widest allowable voltage trip magnitudes and maximum clearing
overvoltage and undervoltage conditions. In contrast to the times from IEEE 1547a. (Not to scale)
original IEEE 1547.1, the NREL test plan provides a single
test procedure to cover both overvoltage and undervoltage. tC5 EUT must disconnect
The test procedure consists of two parts: magnitude testing VT5
and time testing. tC4 VT4
tR4 VR4
Under the magnitude testing, test procedures for three tR3
VR3
different inverter behaviors are developed to validate that (1) EUT must remain connected VR2
clearing voltage levels are in compliance with IEEE 1547a, (2) tR2 VT3
adjustable clearing voltage levels and associated times behave tR1 VR1
tC3
Fig. 3. Default trip frequencies and maximum clearing times from IEEE
1547a.
frequency, Hz
current, p.u.
high-frequency power curtailment interferes with the Irms
inverter’s ability to respond correctly to abnormal frequencies. 60 1
In all frequency magnitude tests, the inverter tripped within
0.02 Hz of the commanded frequency. In all frequency time
tests, the inverter tripped when 90% of the clearing time had
passed (minus a few AC line cycles). 55 0
5 10 15 20 25 30 35
time, seconds
TABLE III
Fig. 12. Inverter RMS current and grid frequency during a frequency
FREQUENCY TRIP TIME TESTS FOR SINGLE-PHASE INVERTER
magnitude test with high-frequency power curtailment running.
Frequency Volt- Frequency Trip Time Measured Result
Response VAR Trip Setting Setting (s) Trip
Setting Setting (Hz) Time (s) Although this inverter does not claim voltage or frequency
Off On (with 56 10 8.99 Pass ride-through capability, its responses to abnormal voltage and
deadband) 58 300 269.91 Pass frequency are very consistent. Therefore, by setting the trip
62 90 80.96 Pass magnitudes and times slightly outside any desired ride-through
64 10 8.98 Pass
boundaries, the inverter could be configured to remain
Off Off 57 0.16 0.12 Pass
60.5 0.16 0.11 Pass connected during a given set of voltage and frequency
64 2 1.77 Pass deviations. For example, a frequency trip setting of 62 Hz and
20% Slope Off 64 0.16 0.10 Pass 10 s could be interpreted to imply that the inverter will ride
40% Slope 56 0.16 0.12 Pass through any frequency disturbance up to 61.98 Hz and 8.94
40% Slope 64 0.16 0.13 Pass
seconds.
The inverter is capable of adjusting its reactive power
TABLE IV
FREQUENCY TRIP MAGNITUDE TESTS output as a function of voltage (volt-VAR control). It can do
Frequency Volt- Frequency Trip Time Measured Result so following a Q(V) characteristic with or without deadband
Response VAR Trip Setting Setting (s) Trip Freq. or hysteresis. Various tests were completed with different
Setting Setting (Hz) (Hz) Q(V) characteristics chosen to thoroughly verify the inverter’s
Off Off 56 0.16 56.01 Pass
range of volt-VAR settings. Fig. 13 shows sample results from
58 10 58.00 Pass
62 10 62.02 Pass one volt-VAR test in which the inverter Q(V) characteristic
64 0.16 64.00 Pass was set with deadband. Note that the measured Q(V)
P(f) 20% Slope Off 64 0.16 64.01 Pass characteristic follows discrete steps. The measured results
P(f) 40% Slope 64 0.16 64.00 Pass follow the Q(V) characteristic well in the deadband regions
and near nominal voltage but deviate slightly when voltage
Figs. 11 and 12 show the inverter RMS current and AC goes away from nominal.
frequency during frequency magnitude tests at the 64 Hz level
without and with high-frequency power curtailment running, 2000
re a c tiv e p o w e r, V A r
TABLE VI
Q ISLAND TRIP TIMES FOR SINGLE-PHASE INVERTER
-800 Frequency Volt- Trip Load Quality Measured Trip Result
Qcmd
reactive power, VAr
2000
1 0
grid-support features running. It was generally found to be the
VA
1
from IEEE 1547a; and 1547a2 uses the widest voltage trip Grid on
settings from IEEE 1547a, along with the original IEEE 1547
frequency trip settings. Table VI shows the trip times for the 0.5
unintentional islanding tests.
Trip time = 0.259 s
0
TABLE V
DISCONNECTION SETTING CONFIGURATIONS FOR ISLANDING TESTS 1.6 1.8 2 2.2 2.4 2.6 2.8 3
Name Fast Slow Slow Fast Overfreq. Underfreq. time, seconds
Overvolt. Overvolt. Undervolt. Undervolt.
Fig. 16. Unintentional islanding test without advanced grid support on.
1547 120% 110% 88% 50% 60.5 Hz 59.3 Hz,
0.16 s 1s 2s 0.16 s 0.16 s 0.16 s
1547a 120% 110% 60% 45% 64 Hz 56 Hz
0.16 s 13 s 10 s 0.16 s 10 s 10s Vrms
voltage, current, p.u.
0.5
Five islanding tests were performed with the quality factor 1.5
IV. THREE-PHASE INVERTER TEST RESULTS Tables IX and X show frequency trip times and magnitudes,
The test setup for the three-phase prototype inverter was respectively. Fig. 19 shows an overfrequency time test at the
similar to the single-phase setup (Fig. 7). The nominal DC 64 Hz level with a 6 s disconnection time, without advanced
voltage was 450 V and the nominal AC line-to-line voltage grid support running. The inverter passes the test, but note that
was 208 V RMS in a three-wire delta configuration. the frequency step induces significant ringing in the current
Responses to abnormal voltage and frequency were waveform, which should be addressed as the prototype is
generally similar to those for the single-phase inverter. Tables refined.
VII and VIII show voltage trip times and magnitudes,
TABLE IX
respectively. Both disconnection magnitudes and
THREE-PHASE INVERTER FREQUENCY TRIP TIME TESTS
disconnection times were very close to the commanded Trip Magnitude Trip Time Measured Trip Result
magnitudes and times, though disconnection times were Setting (Hz) Setting (s) Time (s)
typically one to four cycles longer than commanded because 56 0.16 0.18 Pass*
this prototype inverter does not account for fixed delays in the 56 6 6.021 Pass*
59.5 300 299.98 Pass
disconnection process. Volt-VAR control did not impact
64 6 6.02 Pass*
disconnection times. Fig. 18 shows a voltage magnitude test at 64 0.16 0.183 Pass*
the 110% voltage level. *Trip timer needs adjustment for fixed delays
60 11 11.024 Pass*
current, p.u.
0 0
TABLE VIII 0 1 2 3 4 5 6 7 8 9
THREE-PHASE INVERTER VOLTAGE TRIP MAGNITUDE TESTS time, seconds
Volt-VAR Voltage Trip Trip Time Measured Result Fig. 19. An overfrequency time test without advanced grid support running.
Setting Setting (%) Setting (s) Trip Time (s)
Off 45 0.16 45.19 Pass
Fig. 20 shows the measured and commanded Q(V)
60 2 60.14 Pass
88 2 88.06 Pass
characteristic for a quasistatic volt-VAR test. The measured
110 2 109.82 Pass reactive power matches the command very well.
112 0.16 111.72 Pass
On, 45 0.16 45.10 Pass
without 60 2 60.001 Pass
deadband 88 2 88.13 Pass
0.5
VAR, p.u
AN2011-001, Mar. 2011.
1 0 [6] IEC 61850 Object Models for Photovoltaic, Storage and Other DER
-0.5 Inverters, IEC 61850-90-7, version 27a, 2012.
0.8
V -1 [7] Common Functions for Smart Inverters, Version 3, EPRI, Palo Alto, CA,
0 5 10 15 20 25 30
Q Feb 2014.
time, seconds
[8] J. Johnson, S. Gonzalez, M. E. Ralph, A. Ellis, and R. Broderick, “Test
Fig. 21. A three-phase dynamic voltage step response test of volt-VAR. Protocols for Advanced Inverter Interoperability Functions,” Sandia
National Laboratories, SAND2013-9880, Nov. 2013.
V. FUTURE WORK [9] R. Bravo, S. Robles, and R. Yinger, “SCE Solar PV Inverter Test
Procedure,” Southern California Edison, July 2013.
Future work will investigate other emerging inverter [10] “Rule 21 Smart Inverter Working Group Technical Reference
features, including ceasing to export power without Materials,” California Energy Commission. [Online] Available:
disconnecting during transient undervoltage events, returning http://www.energy.ca.gov/electricity_analysis/rule21/. [Accessed: 18-
Jun-2014].
to service after those events, other methods of voltage support,
[11] “Small Generator Interconnection Agreements and Procedures,” U.S.
and methods of frequency support. FERC, RM13-2-000, Jan. 2013.
Inverter test procedures have historically focused on testing [12] NIST Smart Grid Interoperability Panel, “Overview of IEC 61850-7-420
a single inverter at a single PCC. However, some advanced and IEC 61850-7-90 Inverter Functions.” [Online] Available:
inverter functions (such as volt-VAR) will impact the EPS in http://collaborate.nist.gov/twiki-sggrid/bin/view/SmartGrid/IEC61850-
7-420_Overview. [Accessed: 18-Jun-2014].
which the inverter is connected, requiring dynamic feedback
[13] VDE Verlag Gmbh, “The German Roadmap - E-Energy / Smart Grids
between the inverter test article and the EPS. Significant 2.0: Smart Grid Standardization Status, Trends, and Prospects,” Berlin,
future work using PHIL is planned for testing the advanced Mar. 2013.
grid-support features under conditions that simulate EPS [14] “Technical Guideline ‘Generating Plants Connected to the Medium-
dynamics for realistic testing of one or more inverters. Voltage Network,’” Bundesverband der Energie- und Wasserwirtschaft
(BDEW), Berlin, Jun. 2008.
[15] A. Hoke, S. Chakraborty, T. Basso, and M. Coddington, “Beta Test Plan
VI. CONCLUSIONS for Advanced Inverters Interconnecting Distributed Resources with
Due to the emerging nature of interconnection standards, Electric Power Systems,” NREL Technical Report, NREL/TP-5D00-
test procedures for the new interconnection functions—such as 60931, Jan. 2014.
[16] B. Lundstrom, B. Mather, M. Shirazi, and M. Coddington, “Methods
voltage regulation and wider voltage and frequency operating and Implementation of Advanced Unintentional Islanding Testing using
ranges—are not yet fully harmonized. This paper covers the Power Hardware-in-the-Loop (PHIL),” IEEE Photovoltaic Specialists
important topic of advanced inverter testing based on a Conference (PVSC), June 9–13, Tampa Bay, FL, USA.
recently published NREL report. The test plan summarized [17] IEEE Std 929-2000: IEEE Recommended Practice for Utility Interface
here follows the framework established by IEEE 1547.1 while of Photovoltaic (PV) Systems. IEEE Std 929-2000, 2000.
establishing new and modified tests for the advanced grid-
support features. These test procedures consider not only the
individual interconnection functions but also the interactions
among various new and existing features.
The preliminary test plan was applied to two inverters and
worked well for both. Some interesting observations were
made from initial testing such as (1) separate voltage and
frequency ride-through settings may not be necessary if the
trip test results adhere closely to commanded values, and (2)
performing voltage or frequency ride-through (or having a