Professional Documents
Culture Documents
Oman Logistic Measurement-Master
Oman Logistic Measurement-Master
Total 73,125.000
Page 1 of 14
Reinforcement of Batinah water Transmission Pipe Line
New Oman Logistics Reservoir ( 50,000m3)
BOQ Item Description Unit No Length Width Height Qty Remarks
11/20-1 Excavation
Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208
Average FGL (56.000+53.500)/2= 54.750
Average OGL 53.558
Reservoir
PCC botom = 52.500-0.75-0.10=51.65
Height 53.558-51.65 = 1.908
Grid (1-35), (A-L)
L =162.00m, B =50.55m m3 1 162.000 50.550 1.908 15,624.803
Deduct Outlet Chamber area
Alone Grid 35
L =11.75m, B =15.50m m3 -2 11.750 15.500 1.908 (694.989)
Outlet Chamber
PCC botom = 48.00-0.75-0.10=47.15
Height 53.558-47.15 =6.408
L =15.45m
B =15.50m m3 2 15.450 15.500 7.200 3,448.440
Total m3 18,378.254
11/20-2 Backfill
Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208
Average FGL (56.000+53.500)/2= 54.750
Average OGL 53.558
Reservoir
Average FGL (56.000+53.500)/2= 54.750
Alone Grid A, L
L =162.00m, B =1.50m, H = 54.75-52.50=2.25 m3 2 162.000 1.500 2.250 1,093.500
Alone Grid 1, FGL = 56.000
L =50.55m, B =1.50m, H = 56.00-52.50=3.50 m3 1 50.550 1.500 3.500 265.388
Alone Grid 35, FGL = 53.500
L =50.55m, B =1.50m, H = 53.50-52.50=1.00 m3 1 50.550 1.500 1.060 80.375
Deduct chamber base
L =15.50m, H = 53.50-52.50=1.00 m3 -2 15.500 1.500 1.000 (46.500)
Outlet Chamber-inside reservoir
L =15.50m, B =0.75m, H = 3.75m m3 2 15.500 0.750 3.750 87.188
L =9.50m, B =0.75m, H = 3.75m m3 4 9.500 0.750 3.750 106.875
Outlet Chamber -out side reservoir
FGL 53.500
L =5.20m, B =0.75m, H =53.50-48.0=5.50 m3 1 5.200 0.750 5.500 21.450
L =14.00m, B =0.75m, H =53.50-48.0=5.50 m3 2 14.000 0.750 5.500 115.500
Total m3 1,723.776
11/20-7 Disposal
Total Excavation m3 18,378.254
Total backfill m3 (1,723.776)
Total m3 16,654.478
Page 2 of 14
Reinforcement of Batinah water Transmission Pipe Line
New Oman Logistics Reservoir ( 50,000m3)
Anti-Termite
Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
Total m2 8,322.850
Porus Concrete
Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
Expansion Joint
Grid (7-8),(14-15),(21-22,(28-29) Alone (A-L)
L = 50.55m, B =0.50m, H= 0.50m m3 4 50.550 0.500 0.500 50.550
Total m3 50.550
Page 3 of 14
Reinforcement of Batinah water Transmission Pipe Line
New Oman Logistics Reservoir ( 50,000m3)
Page 4 of 14
Reinforcement of Batinah water Transmission Pipe Line
New Oman Logistics Reservoir ( 50,000m3)
11/21-7 Agglomerate board formwork for 2-sided wall (wall, roof & Column)
Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
Outer Wall
Along Grid A,L
L =159.00m, H=7.55m m2 2 159.000 7.550 2,400.900
Along Grid 1
L = 47.55m, H= 7.55m m2 1 47.550 7.550 359.003
Along Grid 35
L = 47.55-13.0*2=21.55m, H= 7.55m m2 1 21.550 7.550 162.703
L =-13.0*2=26.00m, H= 7.55-1.45=6.10m m2 1 26.000 6.100 158.600
Inside Wall
Along Grid A,L
L =157.50-0.5*2=156.50m, H=7.55m m2 2 156.500 7.550 2,363.150
Along Grid 1,35
L = 46.05-0.50*4-0.75=43.30m, H= 5.05m m2 2 43.300 7.550 653.830
Mid Wall
L =157.50-0.5*2=156.50m, H=7.55m m2 2 156.500 7.550 2,363.150
base chamfer 2 side
Along Grid A,L
L = 157.50m, H= 0.7075m m2 2 157.500 0.707 222.705
Along Grid F mid wall
L = 157.50-0.50*2=156.50m, H= 0.7075m m2 2 156.500 0.707 221.291
Along Grid 1
L =46.05-0.50*4-0.75=43.30m, H= 0.7075m m2 1 43.300 0.707 30.613
Along Grid 35
L =43.30-11.50*2=20.30m, H= 0.7075m m2 1 20.300 0.707 14.352
Outlet chamber-inside reservoir
L =11.55-0.5*2=10.55m, H =3.75m m2 4 10.550 3.750 158.250
L = 7.00m, H =3.75m m2 4 7.000 3.750 105.000
wall chamfer
Grid 1A,35A, 1L, 35L, 1F, 35F
L = 0.707m, H= 7.55m m2 8 0.707 7.550 42.703
L = 0.707m, H= 3.75m m2 8 0.707 3.750 21.210
overflow wall-inside reservoir
L = 9.88m, H =(5.13+2.22)=7.35m m2 2 9.880 7.350 145.236
Page 5 of 14
Reinforcement of Batinah water Transmission Pipe Line
New Oman Logistics Reservoir ( 50,000m3)
11/21-10 PVC joint A = 240 mm, with central bulb and tabs
Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
Page 6 of 14
Reinforcement of Batinah water Transmission Pipe Line
New Oman Logistics Reservoir ( 50,000m3)
11/21-11 Sealing of joints with one-component mastic, based on elastomers, with acetate polymer
Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
Expansion Joint
Grid (7-8), (14-15), (21-22), (28-29)
Base slab L =50.55m m 4 50.550 202.200
Roof slab L =50.55m m 8 50.550 404.400 2 side
Wall H =7.825m m 8 7.825 62.600 2 side
Actual qty depend on construction sequence
Total m 669.200
11/21-13 Waterproofing of reservoir walls with flexible mortar suitable for drinking water (HDPE lining)
Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
Reservoir Floor
Grid (1-35), (A-F), (F-L)
L = 157.50-0.50*2=156.50m, B = 22.65-0.50*2=21.6 m2 2 156.500 21.650 6,776.450
Wash drain (C-D), (H-J)
L = 141.10m, H= 0.30m m2 4 141.100 0.300 169.320
B =0.60m, H= 0.30m m2 4 0.600 0.300 0.720
Reservoir Inside Wall
Along Grid A,L
L =157.50-0.5*2=156.50m, H=7.55m m2 2 156.500 7.550 2,363.150
Along Grid 1,35
L = 46.05-0.50*4-0.75=43.30m, H= 5.05m m2 2 43.300 7.550 653.830
Reservoir Mid Wall
L =157.50-0.5*2=156.50m, H=7.55m m2 2 156.500 7.550 2,363.150
base chamfer 2 side
Along Grid A,L
L = 157.50m, H= 0.7075m m2 2 157.500 0.707 222.705
Along Grid F mid wall
L = 157.50-0.50*2=156.50m, H= 0.7075m m2 2 156.500 0.707 221.291
Along Grid 1
L =46.05-0.50*4-0.75=43.30m, H= 0.7075m m2 1 43.300 0.707 30.613
Page 7 of 14
Reinforcement of Batinah water Transmission Pipe Line
New Oman Logistics Reservoir ( 50,000m3)
Along Grid 35
L =43.30-11.50*2=20.30m, H= 0.7075m m2 1 20.300 0.707 14.352
Outlet chamber-inside reservoir
L =11.00m, H =3.75m m2 4 11.000 3.750 165.000
L = 7.00m, H =3.75m m2 4 7.000 3.750 105.000
wall chamfer
Grid 1A,35A, 1L, 35L, 1F, 35F
L = 0.707m, H= 7.55m m2 8 0.707 7.550 42.703
L = 0.707m, H= 3.75m m2 8 0.707 3.750 21.210
overflow wall-inside reservoir
L = 9.88m, H =(5.13+2.22)=7.35m m2 2 9.880 7.350 145.236
L = 9.28m, H =(5.13+2.22)=7.35m m2 2 9.280 7.350 136.416
L =4.00m, H =(5.13+2.22)=7.35m m2 4 4.000 7.350 117.600
L =3.70m, H =(5.13+2.22)=7.35m m2 4 3.800 7.350 111.720
Column
2*π*R*H
Column C1, R = 0.50/2=0.25m, H= 0.7.50m m2 260 3,083.873
Column C1, R = 0.70/2=0.35m, H= 12.05m m2 4 106.011
Additional column base & top
Total m2 16,850.350
Page 8 of 14
Reinforcement of Batinah water Transmission Pipe Line
New Oman Logistics Reservoir ( 50,000m3)
Total m2 7,392.610
Chamber
Polythene Sheet
Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
L =15.50m, B = 5.20m, H= 0.10m m2 2 15.500 5.200 161.200
Total m2 161.200
Page 9 of 14
Reinforcement of Batinah water Transmission Pipe Line
New Oman Logistics Reservoir ( 50,000m3)
Inside Wall
L = 12.50-0.5*2m, H= 5.95m m2 4 11.500 5.950 273.700
L = 3.7-0.5*2=2.70m, H= 4.05m m2 4 2.700 5.950 64.260
base chamfer 2 side
L = 12.50-0.50*2m, H= 0.707m m2 4 11.500 0.707 32.522
L = 2.70m, H= 0.707m m2 4 2.700 0.707 7.636
wall chamfer
L = 0.707m, H= 5.95m m2 8 0.707 5.950 33.653
Roof slab
L =12.50m, B = 3.70m m2 2 12.500 3.700 92.500
Total m2 776.781
External Painting
Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
Outer Wall
Grid (A-L)
L =159.00m, H=8.025m m2 2 159.000 8.025 2,551.950
Along Grid 1
L =47.55m, H=8.025m m2 1 47.550 8.025 381.589
Along Grid 35
L = 19.55m, H=8.025m m2 1 19.550 8.025 156.889
L =-14.00*2=28.00m, H=7.575m m2 1 28.000 7.575 212.100
Extra-Inlet m2 1 10.800 3.000 32.400
Total m2 3334.928
Page 10 of 14
Reinforcement of Batinah water Transmission Pipe Line
New Oman Logistics Reservoir ( 50,000m3)
BOQ Item Description Unit No Length Width Height Qty Remarks
11/23 Baffles (plug flow) or jet plume (mixing nozzles) for circulation of water
Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
Inside reservoir
L = 18.825m, H =7.55-0.450=7.10m m2 26 18.825 7.100 3,475.095 489.45
Total m2 3,475.095
Page 11 of 14
Grid-01
Ogl Ogl Ogl Ogl Ogl Ogl Ogl Ogl Ogl Ogl Ogl Ogl Ogl Ogl Ogl Ogl Ogl FGl BOT level
SNO chainage
1 54.455 54.650 54.513 54.313 54.167 54.137 53.929 53.926 53.786 53.633 53.550 53.478 53.373 53.290 53.190 53.053 52.935
2 54.372 54.515 54.369 54.276 54.161 54.075 53.865 53.826 53.732 53.486 53.395 53.419 53.334 53.220 53.186 53.039 52.931
3 54.289 54.379 54.225 54.239 54.154 54.012 53.800 53.725 53.678 53.339 53.240 53.359 53.294 53.150 53.182 53.025 52.927
4 54.434 54.363 54.147 54.029 53.905 54.050 53.780 53.700 53.492 53.359 53.188 53.219 53.314 53.281 52.968 52.900 52.823
5 54.390 54.141 54.086 54.080 53.979 53.885 53.784 53.670 53.703 53.647 53.442 53.049 52.950 52.882 53.203 53.131 52.943
6 54.324 54.290 54.409 53.981 54.127 53.942 53.737 53.510 53.569 53.463 53.406 53.338 53.278 53.163 52.936 53.085 52.928
7 53.808 54.139 54.129 53.772 53.850 53.815 53.575 53.482 53.230 53.371 53.349 53.349 53.048 53.158 52.787 52.829 52.601
8 53.922 53.905 54.034 53.746 53.693 53.763 53.770 53.610 53.268 53.125 53.305 53.305 52.951 53.068 52.959 52.556 52.720
9 53.794 53.676 53.666 53.516 53.475 53.768 53.513 53.513 53.415 53.269 53.104 53.105 52.923 52.754 52.905 52.604 52.416
11/20-2 Backfill
Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208
Average FGL (56.000+53.500)/2= 54.750
Average OGL 53.558
Reservoir
Average FGL (56.000+53.500)/2= 54.750
L =164.00m, B =1.00m, H = 54.75-51.75=3.00 m3 2 164.000 1.000 3.000 984.000
L =162.00m, B =1.50m, H = 54.75-52.50=2.25 m3 2 162.000 1.500 2.250 1093.500
L =52.55m, B =1.00m, H = 56.00-51.75=4.25 m3 1 52.550 1.000 4.250 223.338
L =50.55m, B =1.50m, H = 56.00-52.50=3.50 m3 1 50.550 1.500 3.500 265.388
L =52.55m, B =1.00m, H =53.50-51.75=1.75 m3 1 52.550 1.000 1.750 91.963
L =50.55m, B =1.50m, H = 53.50-52.50=1.00 m3 1 50.550 1.500 1.060 80.375
Deduct chamber
L =14.50+1.00*2=16.50m H =53.50-51.75=1.75 m3 -2 16.550 1.000 1.750 -57.925
L =14.50+1.00*2=16.50m, H = 53.50-52.50=1.00 m3 -2 16.550 1.500 1.000 -49.650
Outlet Chamber
L =14.50+1.00*2=16.50m, B =1.0m, H = 3.75+0. m3 2 16.500 1.000 4.600 151.800
L =14.50m, B =0.75m, H = 3.75m m3 2 14.500 0.750 3.750 81.563
L =10.25m, B =1.0m, H = 3.75+0.1+0.75=4.60 m3 4 10.250 1.000 4.600 188.600
L =9.50m, B =0.75m, H = 3.75m m3 4 9.500 0.750 3.750 106.875
chamber out side
L =5.20+1.0=6.20m, B =1.00m, H =53.50-48.0=5. m3 4 6.200 1.000 6.350 157.480
L =5.20m, B =0.75m, H =53.50-48.0=5.50 m3 1 5.200 0.750 5.500 21.450
L =14.50m, B =1.00m, H =53.50-48.0=5.50+0.75+ m3 2 14.500 1.000 6.350 184.150
L =5.20m, B =0.75m, H =53.50-48.0=5.50 m3 2 13.000 0.750 5.500 107.250
Total m3 3630.157
11/20-7 Disposal
Total Excavation m3 19723.891
Total backfill m3 -3630.157
Total m3 16093.734
Page 13 of 14
Reinforcement of Batinah water Transmission Pipe Line
New Oman Logistics Reservoir ( 50,000m3)
BOQ Item Description Unit No Length Width Height Qty Remarks
Page 14 of 14