Reinforcement of Batinah water Transmission Pipe Line

BOQ Item Description Unit No Length Width Height Qty Remarks

11/1-1 Site Clearing


Reference Drg Nr. 400376-MMD-02-DR-MP-03121
L = 325.00m, B = 225.00m m2 1 325.000 225.000 73,125.000

Total 73,125.000

Page 1 of 13
Reinforcement of Batinah water Transmission Pipe Line
New Oman Logistics Reservoir ( 50,000m3)
BOQ Item Description Unit No Length Width Height Qty Remarks

11/20-1 Excavation
Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208
Average FGL (56.000+53.500)/2= 54.750
Average OGL 53.558
Reservoir
PCC botom = 52.500-0.75-0.10=51.65
Height 53.558-51.65 = 1.908
Grid (1-35), (A-L)
L =162.00m, B =50.55m m3 1 162.000 50.550 1.908 15,624.803
Deduct Outlet Chamber area
Alone Grid 35
L =11.75m, B =15.50m m3 -2 11.750 15.500 1.908 (694.989)
Outlet Chamber
PCC botom = 48.00-0.75-0.10=47.15
Height 53.558-47.15 =6.408
L =15.45m
B =15.50m m3 2 15.450 15.500 7.200 3,448.440
Total m3 18,378.254

11/20-2 Backfill
Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208
Average FGL (56.000+53.500)/2= 54.750
Average OGL 53.558
Reservoir
Average FGL (56.000+53.500)/2= 54.750
Alone Grid A, L
L =162.00m, B =1.50m, H = 54.75-52.50=2.25 m3 2 162.000 1.500 2.250 1,093.500
Alone Grid 1, FGL = 56.000
L =50.55m, B =1.50m, H = 56.00-52.50=3.50 m3 1 50.550 1.500 3.500 265.388
Alone Grid 35, FGL = 53.500
L =50.55m, B =1.50m, H = 53.50-52.50=1.00 m3 1 50.550 1.500 1.060 80.375
Deduct chamber base
L =15.50m, H = 53.50-52.50=1.00 m3 -2 15.500 1.500 1.000 (46.500)
Outlet Chamber-inside reservoir
L =15.50m, B =0.75m, H = 3.75m m3 2 15.500 0.750 3.750 87.188
L =9.50m, B =0.75m, H = 3.75m m3 4 9.500 0.750 3.750 106.875
Outlet Chamber -out side reservoir
FGL 53.500
L =5.20m, B =0.75m, H =53.50-48.0=5.50 m3 1 5.200 0.750 5.500 21.450
L =14.00m, B =0.75m, H =53.50-48.0=5.50 m3 2 14.000 0.750 5.500 115.500
Total m3 1,723.776

11/20-7 Disposal
Total Excavation m3 18,378.254
Total backfill m3 (1,723.776)
Total m3 16,654.478

Page 2 of 13
Reinforcement of Batinah water Transmission Pipe Line
New Oman Logistics Reservoir ( 50,000m3)
BOQ Item Description Unit No Length Width Height Qty Remarks

11/21-1 Cast in place concrete pile

1200G Polythene Sheet


Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
Grid (1-35), (A-L)
L = 162.00m, B = 50.55m, H= 0.10m m2 1 162.000 50.550 8,189.100
Deduct Outlet chamber-inside reservoir m2 -2 11.500 8.000 (184.000)
Add Outlet chamber-inside reservoir m2 2 15.500 10.250 317.750
Total m2 8,322.850

Anti-Termite
Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
Total m2 8,322.850

11/21-2 Lean Concrete


Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
Grid (1-35), (A-L)
L = 162.00m, B = 50.55m, H= 0.10m m3 1 162.000 50.550 0.100 818.910
Deduct Outlet chamber-inside reservoir m3 -2 11.500 8.000 0.100 (18.400)
Add Outlet chamber-inside reservoir m3 2 15.500 10.250 0.100 31.775
Total m3 832.285

Porus Concrete
Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
Expansion Joint
Grid (7-8),(14-15),(21-22,(28-29) Alone (A-L)
L = 50.55m, B =0.50m, H= 0.50m m3 4 50.550 0.500 0.500 50.550
Total m3 50.550

11/21-3 Reinforced concrete


Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
Base slab
Grid (1-35), (A-L)
L = 162.00m, B = 50.55m, H= 0.50m m3 1 162.000 50.550 0.750 6,141.825
Deduct Outlet chamber-inside reservoir m3 -2 13.000 1.500 0.750 (29.250)
Add Outlet chamber-inside reservoir
L = 15.50m, B =0.75m, H =0.50m m3 2 15.500 0.750 0.750 17.438
L = 9.50-1.0=8.50m, B =0.75m, H =0.50m m3 4 9.500 0.750 0.750 21.375
Base chamfer Alone Grid A, L 2 side
L =157.50m, B =0.50m, H= 0.50/2= 0.25m m3 2 157.500 0.500 0.250 39.375
Base chamfer Alone Grid 1
L = 46.050-0.75-0.5*2-=44.75m, B =0.50m, H= 0.50/2= 0.25m
m3 1 44.750 0.500 0.250 5.594
Base chamfer Alone Grid 35
L = 44.75-11.50*2=21.75m, B =0.50m, H= 0.50/2= 0.25mm3 1 21.750 0.500 0.250 2.719
Base chamfer Alone Grid F
L =157.50m, B =0.50m, H= 0.50/2= 0.25m m3 2 157.500 0.500 0.250 39.375
overflow chamber-outer m3 4 3.700 0.500 0.250 1.850
overflow chamber-inner m3 4 2.700 0.500 0.250 1.350
overflow chamber, Grid 2 m3 2 8.280 0.500 0.250 2.070
Wash drain (C-D), (H-J)
L = 141.10+0.75=141.85m, B =2.10m, H= 0.30m m3 2 141.850 2.100 0.300 178.731
deduct L = 141.10m, B =2.10m, H= 0.30m m3 -2 141.100 0.600 0.300 (50.796)
Wall

Page 3 of 13
Reinforcement of Batinah water Transmission Pipe Line
New Oman Logistics Reservoir ( 50,000m3)
BOQ Item Description Unit No Length Width Height Qty Remarks

Along Grid A,L


L = 159.00m, B =0.75m, H= 7.55m m3 2 159.000 0.750 7.550 1,800.675
Along Grid 1,35
L =46.05-0.75=45.30m, B =0.75m, H= 4.55+1.0=5.55m m3 2 45.300 0.750 7.550 513.023
Mid Wall, Grid F
L = 159.00-0.75*2=157.50m, B =0.75m, H= 7.55m m3 1 157.500 0.750 7.550 891.844
Outlet chamber-inside reservoir
L =13.00m, B =0.50m, H =3.75m m3 4 13.000 0.750 3.750 146.250
L =8.00m, B =0.50m, H =3.75m m3 4 8.000 0.750 3.750 90.000
overflow wall-inside reservoir
L = 9.88m, B =0.30m, H =(5.13+2.22)=7.35m m3 2 9.880 0.300 7.350 43.571
L =3.70m, B =0.30m, H =(5.13+2.22)=7.35m m3 4 3.700 0.300 7.350 32.634
Wall chamfer Grid 1A,1L,1F,35A,35L,35F
L = 0.50m, B =0.50/2 0.25m, H=7.55m m3 8 0.500 0.250 7.550 7.550
Wall chamfer overflow wall-inside reservoir
L = 0.50m, B =0.50/2 0.25m, H=3.75m m3 8 0.500 0.250 3.750 3.750
Column
π*R*R*H
Column C1, R = 0.50/2=0.25m, H= 7.55m m3 260 385.484
Column C2, R = 0.70/2=0.35m, H= 12.05m m3 4 18.552
Additional column Top m3 22.681
Additional column base m3 32.402
Roof slab
L =159.00m, B =47.55m, H= 0.275m m3 1 159.000 47.550 0.275 2,079.124
deduct roof access
L =4.85m, B =4.85m, H= 0.275m m3 -1 10.200 4.500 0.275 (12.623)
Add roof access no Roof
Wall extra height, Grid (E-G),(1-2)
L =4.85m, B =0.30m, H=3.00m m3 2 4.850 0.300 1.100 3.201
L =10.80m, B =0.30m, H= 3.00m m3 1 10.800 0.300 3.000 9.720
L =10.80m, B =0.75m, H= 3.00m m3 1 10.800 0.750 3.000 24.300
Parapet wall
Along Grid A,L
L =159.00m, B =0.20m, H=1.20m m3 2 159.000 0.200 1.200 76.320
Along Grid 1,35
L =47.55-0.2*2=47.15m, B =0.20m, H=1.20m m3 2 47.150 0.200 1.200 22.632
Grid (E-G),(1-2)
L =10.80m, B =0.20m, H=1.20m m3 1 10.800 0.200 0.625 1.350
L =5.50m, B =0.20m, H=1.20m m3 2 5.500 0.200 0.625 1.375
Total m3 12,565.470

11/21-4 Mass Concrete

11/21-5 Neoprene support 3 cm thick

11/21-6 Wooden formwork (base)


Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
Base slab
Along Grid A,L
L = 162.00m, H= 0.75m m2 2 162.000 0.750 243.000
Along Grid 35
L = 50.55-13.0*2=24.55m, H= 0.75m m2 1 24.550 0.750 18.413
Along Grid 1
B = 50.55m, H= 0.75m m2 1 50.550 0.750 37.913
Outlet-inside reservoir

Page 4 of 13
Reinforcement of Batinah water Transmission Pipe Line
New Oman Logistics Reservoir ( 50,000m3)
BOQ Item Description Unit No Length Width Height Qty Remarks

L = 15.50m, H= 0.75m m2 2 15.500 0.750 23.250


L = 10.25m, H= 0.75m m2 4 10.250 0.750 30.750
Inside outlet
L =13.00m, H =3.75m m2 4 13.000 3.750 195.000
L = 8.75m,H =3.75m m2 4 8.750 3.750 131.250
Wash drain (C-D), (H-J)
L = 141.10+0.75=141.85m, H= 0.30m m2 4 141.850 0.300 170.220
B =2.10m, H= 0.30m m2 4 2.100 0.300 2.520
L = 141.10m, H= 0.30m m2 4 141.100 0.300 169.320
B =0.60m, H= 0.30m m2 4 0.600 0.300 0.720
Total m2 1,022.356

11/21-7 Agglomerate board formwork for 2-sided wall (wall, roof & Column)
Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
Outer Wall
Along Grid A,L
L =159.00m, H=7.55m m2 2 159.000 7.550 2,400.900
Along Grid 1
L = 47.55m, H= 7.55m m2 1 47.550 7.550 359.003
Along Grid 35
L = 47.55-13.0*2=21.55m, H= 7.55m m2 1 21.550 7.550 162.703
L =-13.0*2=26.00m, H= 7.55-1.45=6.10m m2 1 26.000 6.100 158.600
Inside Wall
Along Grid A,L
L =157.50-0.5*2=156.50m, H=7.55m m2 2 156.500 7.550 2,363.150
Along Grid 1,35
L = 46.05-0.50*4-0.75=43.30m, H= 5.05m m2 2 43.300 7.550 653.830
Mid Wall
L =157.50-0.5*2=156.50m, H=7.55m m2 2 156.500 7.550 2,363.150
base chamfer 2 side
Along Grid A,L
L = 157.50m, H= 0.7075m m2 2 157.500 0.707 222.705
Along Grid F mid wall
L = 157.50-0.50*2=156.50m, H= 0.7075m m2 2 156.500 0.707 221.291
Along Grid 1
L =46.05-0.50*4-0.75=43.30m, H= 0.7075m m2 1 43.300 0.707 30.613
Along Grid 35
L =43.30-11.50*2=20.30m, H= 0.7075m m2 1 20.300 0.707 14.352
Outlet chamber-inside reservoir
L =11.55-0.5*2=10.55m, H =3.75m m2 4 10.550 3.750 158.250
L = 7.00m, H =3.75m m2 4 7.000 3.750 105.000
wall chamfer
Grid 1A,35A, 1L, 35L, 1F, 35F
L = 0.707m, H= 7.55m m2 8 0.707 7.550 42.703
L = 0.707m, H= 3.75m m2 8 0.707 3.750 21.210
overflow wall-inside reservoir
L = 9.88m, H =(5.13+2.22)=7.35m m2 2 9.880 7.350 145.236
L = 9.28m, H =(5.13+2.22)=7.35m m2 2 9.280 7.350 136.416
L =4.00m, H =(5.13+2.22)=7.35m m2 4 4.000 7.350 117.600
L =3.70m, H =(5.13+2.22)=7.35m m2 4 3.800 7.350 111.720
Column
2*π*R*H
Column C1, R = 0.50/2=0.25m, H= 0.7.50m m2 260 3,083.873
Column C1, R = 0.70/2=0.35m, H= 12.05m m2 4 106.011
Additional column base & top
Roof slab

Page 5 of 13
Reinforcement of Batinah water Transmission Pipe Line
New Oman Logistics Reservoir ( 50,000m3)
BOQ Item Description Unit No Length Width Height Qty Remarks

Grid (1-35), (A-F), (F-L)


L = 157.50m, B = 22.65m m2 2 157.500 22.650 7,134.750
Inlet wall extra height
L =5.90m, H=3.00m m2 4 5.900 3.000 70.800
L =5.90-0.75-0.30=4.85m, H=3.275m m2 2 4.850 3.275 31.768
L =10.8m, H= 3.00m m2 2 10.800 3.000 64.800
L =10.20m, H= 3.275m m2 4 10.200 3.275 133.620
Parapet wall
Along Grid A,L
outer L =159.00m, H=1.20+0.275=1.475m m2 2 159.000 1.475 469.050
1nner L =159.00-0.2*2=158.60m, H=1.20m m2 2 158.600 1.200 380.640
Along Grid 35
outer L =47.55m, H=1.475m m2 2 47.550 1.475 140.273
Along Grid 1
1nner L =47.55-0.2*2=47.15m, H=1.20m m2 1 47.150 1.200 56.580
1nner L =47.55-10.80=36.75m, H=1.20m m2 2 36.750 1.200 88.200
Inlet wall extra height Grid (1-2),(D-H)
L =10.80m, H=0.625m m2 2 10.800 0.625 13.500
L =10.40m, H=0.625m m2 2 10.400 0.625 13.000
L =5.90m, H=0.625m m2 2 5.900 0.625 7.375
L =5.40m, H=0.625m m2 2 5.500 0.625 6.875
Total m2 21,589.547

11/21-8 Corrugated steel B 500 S


Reservoir Base (Foundation) Kg 618,992
Reservoir Wall Kg 690,337
Reservoir Column Kg 103,257
Reservoir Roof Kg 188,773
Parapet wall Kg
Total m2 1,601,359

11/21-9 Vertical ladder of fixed steps


Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
Internal Ladder-GRP
Reservoir m 4 6.300 25.200
Outlet Chamber m 8 5.250 42.000
Sub Total m 67.200
External Ladder
Reservoir m 3 6.300 18.900
Total m 86.100

11/21-10 PVC joint A = 240 mm, with central bulb and tabs
Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
Grid (A, L ), L =157.5+0.375*2=158.25m m 2 158.250 316.500
Inlet L = 10.50m m 1 10.500 10.500
Grid F, L =157.5+0.375*2=158.25m m 2 158.250 316.500
Grid (1,35 ), L =46.050+0.375*2=46.80m m 4 46.800 187.200
outlet chamber inside
L =7.00+0.375*2=7.75m m 8 7.750 62.000
L =10.50+0.375*2=11.25m m 4 11.250 45.000
outlet chamber
L =3.70+0.375*2=4.45m m 4 4.450 17.800
L =11.50+0.375*2=12.25m m 2 12.250 24.500
Sub Total-A m 980.000
Expansion Joint

Page 6 of 13
Reinforcement of Batinah water Transmission Pipe Line
New Oman Logistics Reservoir ( 50,000m3)
BOQ Item Description Unit No Length Width Height Qty Remarks

Grid (7-8), (14-15), (21-22), (28-29)


Base slab L =50.55m m 4 50.550 202.200
Wall H =7.825m m 4 7.825 31.300
Sub Total-B m 233.500
Actual qty depend on construction sequence
Total-A+B 1,213.500

11/21-11 Sealing of joints with one-component mastic, based on elastomers, with acetate polymer
Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
Expansion Joint
Grid (7-8), (14-15), (21-22), (28-29)
Base slab L =50.55m m 4 50.550 202.200
Roof slab L =50.55m m 8 50.550 404.400 2 side
Wall H =7.825m m 8 7.825 62.600 2 side
Actual qty depend on construction sequence
Total m 669.200

11/21-12 Shoring in structural elements

11/21-13 Waterproofing of reservoir walls with flexible mortar suitable for drinking water (HDPE lining)
Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
Reservoir Floor
Grid (1-35), (A-F), (F-L)
L = 157.50-0.50*2=156.50m, B = 22.65-0.50*2=21.65m m2 2 156.500 21.650 6,776.450
Wash drain (C-D), (H-J)
L = 141.10m, H= 0.30m m2 4 141.100 0.300 169.320
B =0.60m, H= 0.30m m2 4 0.600 0.300 0.720
Reservoir Inside Wall
Along Grid A,L
L =157.50-0.5*2=156.50m, H=7.55m m2 2 156.500 7.550 2,363.150
Along Grid 1,35
L = 46.05-0.50*4-0.75=43.30m, H= 5.05m m2 2 43.300 7.550 653.830
Reservoir Mid Wall
L =157.50-0.5*2=156.50m, H=7.55m m2 2 156.500 7.550 2,363.150
base chamfer 2 side
Along Grid A,L
L = 157.50m, H= 0.7075m m2 2 157.500 0.707 222.705
Along Grid F mid wall
L = 157.50-0.50*2=156.50m, H= 0.7075m m2 2 156.500 0.707 221.291
Along Grid 1
L =46.05-0.50*4-0.75=43.30m, H= 0.7075m m2 1 43.300 0.707 30.613
Along Grid 35
L =43.30-11.50*2=20.30m, H= 0.7075m m2 1 20.300 0.707 14.352
Outlet chamber-inside reservoir
L =11.00m, H =3.75m m2 4 11.000 3.750 165.000
L = 7.00m, H =3.75m m2 4 7.000 3.750 105.000
wall chamfer
Grid 1A,35A, 1L, 35L, 1F, 35F
L = 0.707m, H= 7.55m m2 8 0.707 7.550 42.703
L = 0.707m, H= 3.75m m2 8 0.707 3.750 21.210
overflow wall-inside reservoir
L = 9.88m, H =(5.13+2.22)=7.35m m2 2 9.880 7.350 145.236
L = 9.28m, H =(5.13+2.22)=7.35m m2 2 9.280 7.350 136.416
L =4.00m, H =(5.13+2.22)=7.35m m2 4 4.000 7.350 117.600
L =3.70m, H =(5.13+2.22)=7.35m m2 4 3.800 7.350 111.720
Column

Page 7 of 13
Reinforcement of Batinah water Transmission Pipe Line
New Oman Logistics Reservoir ( 50,000m3)
BOQ Item Description Unit No Length Width Height Qty Remarks

2*π*R*H
Column C1, R = 0.50/2=0.25m, H= 0.7.50m m2 260 3,083.873
Column C1, R = 0.70/2=0.35m, H= 12.05m m2 4 106.011
Additional column base & top
Total m2 16,850.350

11/21-14 Expansive joint


Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
Grid (7-8), (14-15), (21-22), (28-29)
Base slab L =50.55m m 4 50.550 202.200
Wall H =7.825m m 4 7.825 31.300
Roof slab L =50.55m m 4 50.550 202.200
Actual qty depend on construction sequence
Total 435.700

11/21-15 Screed /light weight concrete


Above Roof slab
L =158.60m, B =47.15m, H= 0.025m m3 1 158.600 47.150 0.025 186.950
deduct roof access
L =4.85m, B =4.85m, H= 0.025m m3 -1 10.200 4.500 0.025 (1.148)
deduct roof access
L =2.40m, B =2.40m, H= 0.025m m3 -2 2.400 2.400 0.025 (0.288)
L =1.30m, B =1.30m, H= 0.025m m3 -6 1.300 1.300 0.025 (0.254)
Total m3 185.260

11/21-16 Gargoyle for roof drain


Gargoyle No 40
Total No 40

11/21-17 HDPE sheet, 2 mm thick ( Bitumious Waterproofing Membrane)


Roof slab
L =158.60m, B =47.15m m2 1 158.600 47.150 7,477.990
deduct roof access
L =10.80m, B =5.90m m2 -1 10.800 5.900 (63.720)
deduct roof access
L =2.40m, B =2.40m m2 -2 2.400 2.400 (11.520)
L =1.30m, B =1.30m m2 -6 1.300 1.300 (10.140)
Total m2 7,392.610

Geotextie Membrane m2 7,392.610

25mm thick Sand bedding m2 7,392.610

175mm thick, 20mmsize Rounded Gravel m2 7,392.610

11/21-20 Roof access hatch


L =1.0m, B =1.0m m2 6 1.000 1.000 6.000
L =2.0m, B =2.0m m2 2 2.000 2.000 8.000
Total m2 14.000

Chamber

Polythene Sheet
Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
L =15.50m, B = 5.20m, H= 0.10m m2 2 15.500 5.200 161.200

Page 8 of 13
Reinforcement of Batinah water Transmission Pipe Line
New Oman Logistics Reservoir ( 50,000m3)
BOQ Item Description Unit No Length Width Height Qty Remarks

Total m2 161.200

11/21-24 Lean Concrete


Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
L =15.50m, B = 5.20m, H= 0.10m m3 2 15.500 5.200 0.100 16.120
Total m3 16.120

11/21-25 Reinforced concrete


Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
Base slab
L =15.50m, B = 5.20m, H= 0.75m m3 2 15.500 5.200 0.750 120.900
base chamfer 2 side
L = 12.50-0.50*2=11.50m, B =0.50m, H= 0.50/2= 0.25m m3 4 11.500 0.500 0.250 5.750
L =3.70-0.5*2=2.70m, B =0.50m, H= 0.50/2= 0.25m m3 4 2.700 0.500 0.250 1.350
Wall
L = 14.00m, B =0.75m, H= 5.95m m3 2 14.000 0.750 5.950 124.950
L = 3.70m, B =0.75m, H= 5.95m m3 4 3.700 0.750 5.950 66.045
wall chamfer
L = 0.50m, B =0.50/2 0.25m, H= 5.95m m3 8 0.500 0.250 5.950 4.050
Roof slab
L =12.50m, B = 3.70m, H= 0.20m m3 2 12.500 3.700 0.200 18.500
Total m3 341.545

11/21-26 Wooden formwork in slabs, basements, bracing beams


Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
Base slab
L = 15.50m, H= 0.75m m2 2 15.500 0.750 23.250
B = 5.20m, H= 0.75m m2 4 5.200 0.750 15.600
Total m2 38.850

11/21-27 Agglomerate board formwork for 2-sided walls 3m <h <= 6m


Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
Outer Wall
L = 14.00m, H= 5.95m m2 2 14.000 5.950 166.600
L = 4.45m, H= 5.95m m2 4 4.450 5.950 105.910
Inside Wall
L = 12.50-0.5*2m, H= 5.95m m2 4 11.500 5.950 273.700
L = 3.7-0.5*2=2.70m, H= 4.05m m2 4 2.700 5.950 64.260
base chamfer 2 side
L = 12.50-0.50*2m, H= 0.707m m2 4 11.500 0.707 32.522
L = 2.70m, H= 0.707m m2 4 2.700 0.707 7.636
wall chamfer
L = 0.707m, H= 5.95m m2 8 0.707 5.950 33.653
Roof slab
L =12.50m, B = 3.70m m2 2 12.500 3.700 92.500
Total m2 776.781

11/21-32 DN 100 perforated pipe (UPVC)


below Expansion joint m 4 50.550 202.200
Connection pipe m 4 5.250 21.000
Total m 223.200

11/21-35 Pipe UPVC DN 315, 8 kN / m2


MH-1 to MH-3 m 1 96.000 96.000
MH-3 to End m 1 42.700 42.700
Total m 138.700

Page 9 of 13
Reinforcement of Batinah water Transmission Pipe Line
New Oman Logistics Reservoir ( 50,000m3)
BOQ Item Description Unit No Length Width Height Qty Remarks

External Painting
Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
Outer Wall
Grid (A-L)
L =159.00m, H=8.025m m2 2 159.000 8.025 2,551.950
Along Grid 1
L =47.55m, H=8.025m m2 1 47.550 8.025 381.589
Along Grid 35
L = 19.55m, H=8.025m m2 1 19.550 8.025 156.889
L =-14.00*2=28.00m, H=7.575m m2 1 28.000 7.575 212.100
Extra-Inlet m2 1 10.800 3.000 32.400
Total m2 3334.928

Page 10 of 13
Reinforcement of Batinah water Transmission Pipe Line
New Oman Logistics Reservoir ( 50,000m3)
BOQ Item Description Unit No Length Width Height Qty Remarks

11/23 Baffles (plug flow) or jet plume (mixing nozzles) for circulation of water
Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208 R4
Inside reservoir
L = 18.825m, H =7.55-0.450=7.10m m2 26 18.825 7.100 3,475.095 489.45
Total m2 3,475.095

Page 11 of 13
Grid-01
Ogl Ogl Ogl Ogl Ogl Ogl Ogl Ogl Ogl Ogl Ogl Ogl Ogl Ogl Ogl Ogl Ogl FGl BOT level
SNO chainage

1 54.455 54.650 54.513 54.313 54.167 54.137 53.929 53.926 53.786 53.633 53.550 53.478 53.373 53.290 53.190 53.053 52.935
2 54.372 54.515 54.369 54.276 54.161 54.075 53.865 53.826 53.732 53.486 53.395 53.419 53.334 53.220 53.186 53.039 52.931
3 54.289 54.379 54.225 54.239 54.154 54.012 53.800 53.725 53.678 53.339 53.240 53.359 53.294 53.150 53.182 53.025 52.927
4 54.434 54.363 54.147 54.029 53.905 54.050 53.780 53.700 53.492 53.359 53.188 53.219 53.314 53.281 52.968 52.900 52.823
5 54.390 54.141 54.086 54.080 53.979 53.885 53.784 53.670 53.703 53.647 53.442 53.049 52.950 52.882 53.203 53.131 52.943
6 54.324 54.290 54.409 53.981 54.127 53.942 53.737 53.510 53.569 53.463 53.406 53.338 53.278 53.163 52.936 53.085 52.928
7 53.808 54.139 54.129 53.772 53.850 53.815 53.575 53.482 53.230 53.371 53.349 53.349 53.048 53.158 52.787 52.829 52.601
8 53.922 53.905 54.034 53.746 53.693 53.763 53.770 53.610 53.268 53.125 53.305 53.305 52.951 53.068 52.959 52.556 52.720
9 53.794 53.676 53.666 53.516 53.475 53.768 53.513 53.513 53.415 53.269 53.104 53.105 52.923 52.754 52.905 52.604 52.416

Average Original Level 53.558

Up to Bottom of the PCC Bottom Level 51.650 47.200


Height 1.908
Reinforcement of Batinah water Transmission Pipe Line
New Oman Logistics Reservoir ( 50,000m3)
BOQ Item Description Unit No Length Width Height Qty Remarks

11/20-1 Excavation (including 1m working spase)


Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208
Average FGL (56.000+53.500)/2= 54.750
Average OGL 53.558
Reservoir
PCC botom = 52.500-0.75-0.10=51.65
Height 53.558-51.65 = 1.908
L =162.00+1.00*2=164.00m
B =50.55+1.00*2=52.55m m3 1 164.000 52.550 1.908 16443.526
Deduct chamber
L =11.75+1.00*2=13.75m
B =14.50+1.00*2=16.50m m3 -2 13.750 16.500 1.908 -865.755
Outlet Chamber
PCC botom = 48.00-0.75-0.10=47.15
Height 53.558-47.15 =6.408
L =15.45+1.00*2=17.45m
B =14.50+1.00*2=16.50m m3 2 17.450 16.500 7.200 4146.120
Total m3 19723.891

11/20-2 Backfill
Reference Drg Nr. 400376-MMD-02-DR-CS-02204-02208
Average FGL (56.000+53.500)/2= 54.750
Average OGL 53.558
Reservoir
Average FGL (56.000+53.500)/2= 54.750
L =164.00m, B =1.00m, H = 54.75-51.75=3.00 m3 2 164.000 1.000 3.000 984.000
L =162.00m, B =1.50m, H = 54.75-52.50=2.25 m3 2 162.000 1.500 2.250 1093.500
L =52.55m, B =1.00m, H = 56.00-51.75=4.25 m3 1 52.550 1.000 4.250 223.338
L =50.55m, B =1.50m, H = 56.00-52.50=3.50 m3 1 50.550 1.500 3.500 265.388
L =52.55m, B =1.00m, H =53.50-51.75=1.75 m3 1 52.550 1.000 1.750 91.963
L =50.55m, B =1.50m, H = 53.50-52.50=1.00 m3 1 50.550 1.500 1.060 80.375
Deduct chamber
L =14.50+1.00*2=16.50m H =53.50-51.75=1.75 m3 -2 16.550 1.000 1.750 -57.925
L =14.50+1.00*2=16.50m, H = 53.50-52.50=1.00 m3 -2 16.550 1.500 1.000 -49.650
Outlet Chamber
L =14.50+1.00*2=16.50m, B =1.0m, H = 3.75+0.1+0.75=4.60
m3 2 16.500 1.000 4.600 151.800
L =14.50m, B =0.75m, H = 3.75m m3 2 14.500 0.750 3.750 81.563
L =10.25m, B =1.0m, H = 3.75+0.1+0.75=4.60 m3 4 10.250 1.000 4.600 188.600
L =9.50m, B =0.75m, H = 3.75m m3 4 9.500 0.750 3.750 106.875
chamber out side
L =5.20+1.0=6.20m, B =1.00m, H =53.50-48.0=5.50+0.75+0.1
m3 4 6.200 1.000 6.350 157.480
L =5.20m, B =0.75m, H =53.50-48.0=5.50 m3 1 5.200 0.750 5.500 21.450
L =14.50m, B =1.00m, H =53.50-48.0=5.50+0.75+0.1
m3 2 14.500 1.000 6.350 184.150
L =5.20m, B =0.75m, H =53.50-48.0=5.50 m3 2 13.000 0.750 5.500 107.250
Total m3 3630.157

11/20-7 Disposal
Total Excavation m3 19723.891
Total backfill m3 -3630.157
Total m3 16093.734

Page 13 of 13