water Transmission Pipe Line, T

Insurance Claim for Damages Due to Heavy Rain on 18th July 2021

Signed snag list/Pre RFI


ref./progress report
Sl. Description/exte Status before (issued before this
No. Location/Chainage nt of damage storm incident) Repair Procedure Unit No Qty Total Qty Rate RO Amount

Laid/Finished pipeline is lifted up, Pipe laid with Removal of non-aligned Pipe out of trench,
1
required to be removed & relaid bedding and BAT-PL/244, 246, 253, cleaning and stacking of Pipe 2,475 m (48m/per
surround 260, & 266 day )- 3 Gangs working simultaneously
Flushing cannot be done next to trench, crane
to carry away, remove sleeve flush and bring
pipe next to trench
3 Gangs for 17 days= 51 gangdays
36+400 - 36+500 Chargehand (1 Head in each gang) Days 3 17.00 51.00 2.500 127.500
36+800 - 37+050 4 Labour (4 Heads in each gang) Days 12 17.00 204.00 13.850 2,825.400
37+050 - 37+175 2 Pipe Fitter (2 Heads in each gang) Days 6 17.00 102.00 16.000 1,632.000
38+500 - 38+700 Mobile Crane Days 1 17.00 17.00 150.000 2,550.000
38+700 - 39+775 Excavator Days 2 17.00 34.00 160.000 5,440.000
39+775 - 39+950 De watering pump Days 3 17.00 51.00 52.000 2,652.000
39+950 - 40+375 2 Operator (2 Heads in each gang) Days 6 17.00 102.00 23.000 2,346.000
40+375 - 40+700 Water tankers 5000 gallons Days 2 17.00 34.00 185.000 6,290.000
Drivers of trucks over 3T (Water tanker) Days 2 17.00 34.00 45.000 1,530.000
Water for cleaning of pipe @ 100 G per pipe length G 1 41,250.00 5.000 206,250.000
Sand bags to keep Pipe (3 Nos/6m pipe) No 1237.5 1.00 1,237.50 8.000 9,900.000
Cleaning of trench 2,475 m (50m/per day) - 3
Gangs working simultaneously
Removal of debris and contaminated sand
bedding, disposal and cleaning of Right of Way
3 Gangs for 17 days= 51 gangdays day 3 17.00 51.00 2.500 127.500
Chargehand (1 Head in each gang) day 6 17.00 102.00 13.850 1,412.700
2 Labour (2 Heads in each gang) day 3 17.00 51.00 16.000 816.000
Excavator day 3 17.00 51.00 150.000 7,650.000
JCB (for cleaning Right of Way and other side) day 3 17.00 51.00 160.000 8,160.000
Wheeled loader day 3 17.00 51.00 52.000 2,652.000
De watering pump day 12 17.00 204.00 23.000 4,692.000
4 Operator (4 Heads in each gang) Shift 2 17.00 34.00 25.000 850.000
Watchmen 18.000
Re-laying of Pipe, sand bedding for 2,475 m 5.000
Leveling on excavation m2 1 4,455.00 4,455.00 8.000 35,640.000
Pipe laying m 1 2,475.00 2,475.00 15.294 37,852.650
Sand Bedding m3 1 6,776.00 6,776.00 3.733 25,294.808

Trench are clear BAT-PL/147, 227, 231, Cleaning trench 13,000 m (150m/per day )
2 Cleaning of trench up to OBC duct level
and ready to 226, 235, 269, 270 FOC- Dewatering & Removal of debris and soil on top
received OBC duct 085, 090

1 of 4
water Transmission Pipe Line, T
Insurance Claim for Damages Due to Heavy Rain on 18th July 2021

Signed snag list/Pre RFI


ref./progress report
Sl. Description/exte Status before (issued before this
No. Location/Chainage nt of damage storm incident) Repair Procedure Unit No Qty Total Qty Rate RO Amount
5 Gangs for 17 days= 85 gangdays
Chargehand (1 Head in each gang) day 5 17.00 85.00 2.500 212.500
16+000 - 29+000 6 Labour (6 Heads in each gang) day 30 17.00 510.00 13.850 7,063.500
1 JCB day 5 17.00 85.00 16.000 1,360.000
2 De-watering pump day 10 17.00 170.00 150.000 25,500.000
Water tankers 5000 gallons day 3 17.00 51.00 160.000 8,160.000
Drivers of trucks over 3T (Water tanker) day 3 17.00 51.00 52.000 2,652.000
Wheeled loader day 5 17.00 85.00 23.000 1,955.000
2 Operator day 10 17.00 170.00 10.000 1,700.000

Chambers base
Cleaning, flushing, dewatering of cast in situ
slab casted,
Cleaning, flushing, dewatering of cast chambers, Removal of debris and soil inside
3 reinforcement & WO-22 5.000
in situ chambers chambers, re-excavation, removal of damage
shutter of wall
shutter, flushing and cleaning.
already installed
25+875 for 5 days 8.000
Chargehand day 1 5.00 5.00 25.000 125.000
5 Labours day 5 5.00 25.00 13.000 325.000
2 Carpenter day 2 5.00 10.00 16.000 160.000
Water tankers 5000 gallons day 1 5.00 5.00 100.000 500.000
Driver (1 Head in each gang) day 1 5.00 5.00 20.000 100.000
Water for cleaning of chamber @ 5000G for each chamber
G 1 25,000.00 25,000.00 5.000 125,000.000
De watering pump day 1 5.00 5.00 50.000 250.000
Operator day 1 5.00 5.00 20.000 100.000
Water Jetting Equipment with Operator 50% day 1 2.50 2.50 35.000 87.500
2 Excavator day 2 5.00 10.00 140.000 1,400.000

4 Supply of Damage Materials Damaged Materials


Polythene sleeve for pipes; removal and replacing m 2,475.00 5.000 12,375.000
Bedding Materials for DI pipes 2,475 m m3 3,507.93 5.000 17,539.645
Staff/ Labour
Procurement Manager Hr 2.00 5.000 10.000
Procurement Engineer Hr 8.00 5.000 40.000

Total Amount 573,305.70

2 of 4
Supporting document to justify the cost
(Rate Ref./BOQ rate/Subcontractor RFI
rate/material purchase invoice/ time or Ref/progress Photo after
work sheet to justify equipment utilisation report (post Photo of re-
cost ) repair) damaged item instement

BAT-PL/303,
308, 314, &
323

3 of 4
Supporting document to justify the cost
(Rate Ref./BOQ rate/Subcontractor RFI
rate/material purchase invoice/ time or Ref/progress Photo after
work sheet to justify equipment utilisation report (post Photo of re-
cost ) repair) damaged item instement

4 of 4