Time Line For Dhodak Gas Field

SR No. Sub No. Description of activities Duration (Days) Start Finish W1

TOTAL PROJECT COMPLETION PERIOD 300 Days


1 1 1 Issuance of LOI By Client 1
2 29 2 Preparation and Signing of Gas Sale Agreement 28
3 3 Design and Engineering
3.1 Finalization of Conceptual design for Plant 7
3.2 Finalization of Plot Plan of plant 7
3.3 Finalzation of PFD and PID 7
3.4 Survey Design and engineering of gas flow line 14
3.5 Mechanical Design calculation and drawings 14
3.6 Civil Design calculation and drawings 7
3.7 Design and engineering for Electrical, Instruments & HSE 7
3.8 Material off take and BOQ 3
3.9 Survey Design and engineering of gas flow line
4 PROCUREMENT OF MATERIAL
4.1 Procurement of Civil work material 3
4.2 Procurement of Flow line material 42
4.3 Procurement of plant machine and equipment 70
4.4 Procurement of instrument, Electrical & HSE equipment 56
5 Construction and Erection of flow line and facility
5.1 Construction of flow line 32
5.2 construction of facility and equipment erection 28
5.3 Hook up of instruments and Electrical system 14
5.4 pressure testing and precommissioning 14
5.5 Commissioning of flow line and facility 14
W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31 W32

TOTAL PROJECT COMPLETION PERIOD (245 Days)


W = 1 week
W33 W34 W35
Sub
No. Description of activities

TOTAL PROJECT COMPLETION PERIOD


1 1 Issuance of LOI By Client
30 2 Preparation and Signing of Gas Sale Agreement
37 3.1 Finalization of Conceptual design for Plant
44 3.2 Finalization of Plot Plan of plant
51 3.3 Finalzation of PFD and PID
65 3.4 Survey Design and engineering of gas flow line
79 3.5 Mechanical Design calculation and drawings
86 3.6 Civil Design calculation and drawings
93 3.7 Design and engineering for Electrical, Instruments & HSE
96 3.8 Material off take and BOQ
96 3.9 Survey Design and engineering of gas flow line
99 4.1 Procurement of Civil work material
141 4.2 Procurement of Flow line material
213 4.3 Procurement of plant machine and equipment
269 4.4 Procurement of instrument, Electrical & HSE equipment
301 5.1 Construction of flow line
329 5.2 construction of facility and equipment erection
343 5.3 Hook up of instruments and Electrical system
357 5.4 pressure testing and precommissioning
371 5.5 Commissioning of flow line and facility

1 30 37 44 51 65 79
1 30 37 44 51 65 79
Durati
on
(Days)
300
Days
1 1
-29 29
7 7
-7 7
7 7
-14 14
14 14
-7 7
7 7
-3 3
3
3
-42 42
72 72
-56 56
32 32
-28 28
14 14
-14 14
14 14

Timeline Graph of Dhodhak Project

37 44 51 65 79 86 93 96 96 99 141 213 269 301 32


37 44 51 65 79 86 93 96 96 99 141 213 269 301 32
3 269 301 329 343 357 371
3 269 301 329 343 357 371