Daily Progress of Parnai HEP by PMC

S No. Detail description of activities at project site on 07.10.2022 No. of Labours deployed
1. Barrage:-
a) Shuttering of Breast wall and reinforcement placing in fish pass 16 (Day shift)
wall 1 & 2 in progress. No work in night.
b) Concreting of fish pass wall -02 shall be done today.

2. HRT & Adit 1.


a) HRT Face 1:-
a) No activity in face -01 other than dewatering. 04 (02 for Day shift + 02
for night shift)
b) Face 4:-
a) Face drilling, loading , blasting and mucking completed at 777.8 m 08
from C/L of Adit -02
b) Blast taken and mucking in progress.
c) Face RD 779.5 m from C/L of Adit -02 .
c) Face 5:-
a) Drilling, loading , blast and mucking completed at 797.5 m from (Day Shift 09 +
C/L of Adit -02 Night Shift 08) = 17

d) Face 6:- (Day Shift 08 +


a) 7.5 Cum Backfill concreting done between 1691.6 to 1698.1 Night Shift 08)= 16
from outer face.
b) Loosefall muck removal in progress between 1698.1 to 1704
m from outer face.
e) Adit 1:-
a) Backfill concrete 12 cum completed at RD 232.2 m. (Day Shift 09 +
b) Face drilling and loading completed and blast taken at 234.1 m Night Shift 09) = 18
3. Penstock:-
a) Earthwork excavation in progress between AB 13 to AB 14. 02
4. Power House :-
a) 02 cum stone filling and concreting 0.375 cum for two vertical 15
bands completed.

Note:- The Contractor has submitted the target for the month of Oct 2022.