Workschedule For Belase For Milestone 1 Shifting
Workschedule For Belase For Milestone 1 Shifting
Workschedule For Belase For Milestone 1 Shifting
1
Item Description Unit Quantity Rate Total Amount After V.O.1 Amount
Qty 2074 2075 2076
A Surveying 10-Falgun Chaitra Baisakh Jestha Asar Shrawan Bhadra Ashoj Kartik Mangshir Poush Magh Falgun Chaitra Baisakh Jestha Asar Shrawan 10 Bhadra
B General items
1 Manpower mobilisation
2 Machinery mobilisation
3 Site office setup
B Earthwork
Contractor: Employer
After V.O.1
Item Description Unit Quantity Rate Total Amount After V.O.1 Amount
Qty 2074 2075 2076
x Grader with minimum 130 HP all complete hrs. 55.00 5000.00 Rs.275,000.00 55.00 Rs.275,000.00
G Insurance
Insurance of the works, plants and materials
also including other property, personal injury
1 Ls 1.00 ### Rs.25,000,000.00 1.00 Rs.25,000,000.00 6,250,000.00 6,250,000.00 6,250,000.00 6,250,000.00
or death of contractor employee, employer's
employee and other people.
Contractor: Employer
Government of Nepal
Ministry of Physical Infrastructure &Transport
Department of Road
Federal Highway Supervision & Monitoring Office
Road Division Ilam
Name of the Road:- Upgrading Works Of Belase-Rakase Bhanjyang,Ilam Section Of Kechana-Kanchanjanga (Mechi Corridor) Road.
Contract No: RDILAM/337011754-077/078-57
Name of Contractor:- Khadka-Krishna/ Sakcham JV
Contract Amount : (without VAT and PS): 238188516.19
Date of work order : 2078-03-29
Intended Date of Completion : 2080-09-29
May
May
13/07/2021 14/1/2024
Aug
Sep
Aug
Sep
Aug
Sep
Nov
Dec
Nov
Dec
Nov
Dec
Feb
Feb
Mar
Mar
Jan
Jun
Jan
Jun
Apr
Apr
Oct
Oct
Oct
Jul
Jul
0.1900 0.1900 0.1900 0.1900 0.1900 0.1900 0.1900 0.1900 0.1900 0.1900 0.1900 0.1900 0.1900 0.1900 0.1900 0.2400 0.2400 0.2400 0.2400 0.2000
1.5700 1.5700 1.5700 1.5700 1.5700 1.5700 1.5700 1.5700 1.5700 1.5700 1.5700 1.5700 1.5700 1.5700 1.3610 1.4040 1.4040 1.4040 1.4040 3.5760 3.5760 3.5790 3.5760 3.5760
R 1.3300 1.3300 1.3300 1.3300 1.3290 5.3730 5.3730 5.3730 5.3730 5.3730 5.3730 5.3730
A
3 PAVEMENT WORKS 44.26% I
N
Y
MISCELLANEOUS
5 1.73%
WORKS
Total 100.00%
Total of all items 0.190 1.760 1.760 1.760 1.760 1.760 1.760 1.760 1.760 1.760 1.760 1.760 1.760 1.760 1.760 0.000 2.931 2.974 2.974 3.166 3.125 9.594 9.594 0.000 0.000 0.000 9.597 9.594 9.594 6.018 6.0184
Cummulative Total 0.190 1.950 3.710 5.470 7.230 8.990 10.750 12.510 14.270 16.030 17.790 19.550 21.310 23.070 24.830 24.830 27.761 30.735 33.709 36.875 40.000 49.594 59.188 59.188 59.188 59.188 68.785 78.379 87.973 93.991 100.000
S - CURVE
40.0004
6 Structure work 44.04% 33.709
36.8752
30.735
27.761
23.07 24.83 24.83
19.55 21.31
7 Road miscellaneous work 3.42% 14.27 16.03 17.79
10.75 12.51
8.99
8 DAY WORKS 0.89% 3.71 5.47 7.23
0.19 1.95
Total 100.00%
Total of all items 0.19 1.76 1.76 1.76 1.76 1.76 1.76 1.76 1.76 1.76 1.76 1.76 1.76 1.76 1.76 0 2.931 2.974 2.974 3.1662
Cummulative Total 0.19 1.95 3.71 5.47 7.23 8.99 10.75 12.51 14.27 16.03 17.79 19.55 21.31 23.07 24.83 24.83 27.761 30.735 33.709 36.8752
S - CURVE
2021
March April May June July
100
93.9914
87.9734
78.3794
68.7854
49.5944
40.0004
36.8752
33.709
30.735
27.761
23.07 24.83 24.83
19.55 21.31
16.03 17.79
12.51 14.27
S-Curve
District: Jhapa
Name of Road /
Upgrading of Ilam Bazzar Sandakpur Paryatakiya Road (Package-1),Ilam
Project:
NCB Contract: Contract No.: IDOJHP/NCB/W-68/076-77
S-Curve of Gufa Bhuje Deurali Gorja Change Dovan Ro
Revised
SN Period
Plan Revised P
1 Jul-19 0.20 120.00
2 Aug-19 2.90
3 Sep-19 5.6
4 Oct-19 8.3
5 Nov-19 11
6 Dec-19 13.7 100.00
7 Jan-20 16.4
8 Feb-20 19.1
9 Mar-20 21.8
10 Apr-20 24.5
27.7 80.00
11 May-20
12 Jun-20 30.9
13 Jul-20 34.1
14 Aug-20 37.3
15 Sep-20 40.5
60.00
16 Oct-20 40.5
17 Nov-20 45.672
18 Dec-20 50.844
19 Jan-21 56.016
20 Feb-21 61.3802
40.00
21 Mar-21 66.7444
22 Apr-21 72.5614
23 May-21 78.3404
24 Jun-21 78.3404
25 Jul-21 78.3404 20.00
26 Aug-21 78.3404
27 Sep-21 82.6534
28 Oct-21 86.9664
29 Nov-21 91.2794
30 Dec-21 95.5924 -
31 Jan-22 100 Jul-19 Sep-19 Nov-19 Jan-20 Mar-20 May-20 Jul-20 Sep-20
100
0.20 2.90 5.6 8.3
0.20
2.90
5.6
8.3
11
13.7
16.4
19.1
21.8
24.5
27.7
30.9
34.1
37.3
40.5
40.5
45.672
50.844
56.016
61.3802
66.7444
72.5614
78.3404
78.3404
78.3404
78.3404
82.6534
86.9664
91.2794
95.5924
100
Department of Road
hway Supervision & Monitoring Office
Road Division Ilam
S-Curve
Reporting Month: Ashad
Reporting Year: 2079
uje Deurali Gorja Change Dovan Road (CH : 0+000 to 7+350), Taplejung
Ashad 2079
Revised Plan
May-20 Jul-20 Sep-20 Nov-20 Jan-21 Mar-21 May-21 Jul-21 Sep-21 Nov-21 Jan-22
11 13.7 16.4 19.1
1 Jan-22
21.8 24.5 27.7 30.9 34.1 37.3 40.5 40.5
45.672 50.844 56.016 61.3802 66.7444 72.5614 78.3404 78.3404 78.3404 78.3404
82.6534 86.9664 91.2794 95.5924 100
0.2 2.9 5.6 8.3 11 13.7 16.4 19.1 21.8
0.2
2.9
5.6
8.3
11
13.7
16.4
19.1
21.8
24.5
27.7
30.9
34.1
37.3
40.5
40.5
45.672
50.844
56.016
61.3802
66.7444
72.5614
78.3404
78.3404
78.3404
78.3404
82.6534
86.9664
91.2794
95.5924
100
24.5 27.7 30.9 34.1 37.3 40.5 40.5 45.672 50.844 56.016
61.3802 66.7444 72.5614 78.3404 78.3404 78.3404 78.3404 82.6534 86.9664 91.2794
95.5924 100