RENCANA KERJA HARIAN (RKH)

SHIFT REPORT

PT. Bakti Pertiwi Nusantara Site Sepo PT. Djava Berkah Mineral
SHIFT 2 (Night Shift) 05/10/2022
SHIFT 1 PRODUCTION REPORT HEAVY EQUIPMENT & MANPOWER
ACTIVITY PLAN EXISTING UNIT ACH. (%) Model EQ Class Populasi RFU BD MP Deviasi
OB Removal (Bcm) 2,882 889 31 Exca 300 Loader 5 4 1 2 -3
Ore Getting (Ton) 2,880 1,100 38 Exca 200 Loader 7 6 1 5 -2
Hauling ETO- EFO (Ton) 2,765 1,113 40 DT 20 Ton Hauler 26 26 0 15 -11
Barging (Ton) 7,875 7,875 100 Dozer 85 SS Unit Support 2 2 0 1 0
Grader Unit Support 2 2 0 1 0
REVIEW SHIFT 1 PRODUCTION REPORT Vibro Case Unit Support 2 2 0 1 0
ACTIVITY PLAN ACTUAL ACH. (%) Fuel Truck Unit Support 2 2 0 1 0
OB Removal (Bcm) 2,882 1080 37 Water Truck Unit Support 1 1 0 1 0
Ore Getting (Ton) 2,880 177 6
Hauling ETO- EFO (Ton) 2,765 0 0
Barging (Ton) 5,250 0 0
Remarks : Update 1 Oktober (Shift 2)

REVIEW MONTHLY 1 PRODUCTION REPORT RAIN & SLIPPERY


ACTIVITY PLAN MTD ACTUAL MTD ACH. (%) ACTIVITY SHIFT 1 SHIFT 2 REMARK
OB Removal (Bcm) 86,460 2616 3 RAIN
Ore Getting (Ton) 86,400 801 1 SLIPPERY
Hauling ETO- EFO (Ton) 82,950 0 0 LOST TIME
Barging (Ton) 31,500 0 0 REFUELING
Remarks : Update 3 Oktober (Shift 2) Remarks : Update 3 Oktober (Shift 2)

SHIFT 2 (Night Shift) 05/10/2022


ACTIVITY PIT_ID FLEET PLAN LOADER HAULER SUPPORT Note :
OB Removal Pit_Timur 1 1 PC300, 1 PC200 6 *Priority Expose Ore in PIT
Ore Getting Pit_Timur 1 1 PC300 10 1 PC200 *OB removal, Optional 2 Fleet 6 DT (33,36,4)
Hauling ETO-EFO *Production, DT
Barging (42,43,44,45,11,12)
Supporting GRADER VIBRO WT *Selective Ore, Optional Production
Piling Waste Dump 2 PC200 Dozer *Optional Hauling, 10 DT
Piling ETO 1 PC200 *Optional Maintanance Hauling Road
Piling EFO * Pengawas (Yakson, Dior)
Prepare Barging
General Area #CONDITIONAL