SHIFT REPORT
PT. Bakti Pertiwi Nusantara Site Sepo PT. Djava Berkah Mineral
SHIFT 2 (Night Shift) 09/10/2022
SHIFT 1 PRODUCTION REPORT HEAVY EQUIPMENT & MANPOWER
ACTIVITY PLAN EXISTING UNIT ACH. (%) Model EQ Class Populasi RFU BD MP Deviasi
OB Removal (Bcm) 2,882 1,267 44 Exca 300 Loader 5 3 2 2 -3
Ore Getting (Ton) 2,880 2,174 75 Exca 200 Loader 7 5 2 5 -2
Hauling ETO- EFO (Ton) 2,765 1,113 40 DT 20 Ton Hauler 26 26 0 18 -8
Barging (Ton) 7,875 7,875 100 Dozer 85 SS Unit Support 2 2 0 1 -1
Breaker Unit Support 1 1 0 1 0
REVIEW SHIFT 1 PRODUCTION REPORT Grader Unit Support 2 1 1 1 0
ACTIVITY PLAN ACTUAL ACH. (%) Vibro Case Unit Support 2 2 0 1 -1
OB Removal (Bcm) 2,882 0 0 Fuel Truck Unit Support 2 2 0 1 -1
Ore Getting (Ton) 2,880 456 16 Water Truck Unit Support 1 1 0 1 0
Hauling ETO- EFO (Ton) 2,765 219 8
Barging (Ton) 5,250 0 0
Remarks : Update 9 Oktober (Shift 1)