This document provides a case study analysis for a building interior fit-out contractor. It identifies the key facts of the business, common issues like design mismatches or changes from the client causing delays, and recommends alternative courses of action. These include assigning staff to thoroughly review technical information for issues, raising technical queries to the client immediately if needed information is missing or there is a dispute, and securing approved change orders prior to proceeding with any changes. The best course of action is to carefully study all available data before starting the project and raise any potential issues to the client ahead of time.
This document provides a case study analysis for a building interior fit-out contractor. It identifies the key facts of the business, common issues like design mismatches or changes from the client causing delays, and recommends alternative courses of action. These include assigning staff to thoroughly review technical information for issues, raising technical queries to the client immediately if needed information is missing or there is a dispute, and securing approved change orders prior to proceeding with any changes. The best course of action is to carefully study all available data before starting the project and raise any potential issues to the client ahead of time.
This document provides a case study analysis for a building interior fit-out contractor. It identifies the key facts of the business, common issues like design mismatches or changes from the client causing delays, and recommends alternative courses of action. These include assigning staff to thoroughly review technical information for issues, raising technical queries to the client immediately if needed information is missing or there is a dispute, and securing approved change orders prior to proceeding with any changes. The best course of action is to carefully study all available data before starting the project and raise any potential issues to the client ahead of time.
Example: Case Study for a Building Interior Fit-out Contractor
1. Identify the most important facts surrounding the case.
This kind of business entity involves architecture, engineering, procurement, and construction just like a Building Construction Contractor. It requires compliance to the rules and guidelines of concerned institutions in the government; client’s approval of shop drawings, material technical data, and method of installation; buying the client’s selected materials; site implementation which should be aligned with the project timeline; and work inspection, testing and commissioning prior to the project handover.
2. Identify the key issue or issues.
One of the most common issues that arises is a Dispute on the Technical Data provided by the client (i.e., Architectural design drawings mismatching with Civil/Structural design drawings) and the concerned staffs are not able to discover it earlier or there is no clear assignment of personnel to take charge of such issue; followed by Changes from the client amidst the work implementation, so in effect, resulting to the Delay in Implementation itself.
3. Specify alternative courses of action.
There must be a staff specifically assigned to thoroughly review all technical information being received from the client. When needed information are missing or a dispute is found out, a Technical Query must immediately be raised to the client, or an alternative solution may be proposed. Changes must be carefully evaluated whether it is practical, functional, or beneficial. Secure a Change Order approval from the client prior to proceeding. A Project Timeline must be maintained and constantly be updated to monitor any delays.
4. Evaluate each course of action.
When a dispute arises, which is more beneficial and time saving? To wait for the client’s response to the Technical Query or to submit a Proposed Solution right away? Make a precise assessment to the client’s changes prior to agreeing and implementing. Consider the Project Timeline, Risk, and the corresponding Penalties to delays.
5. Recommend the best course of action.
Prior to commencement of the project contract, all available data must be carefully studied by a dedicated staff and raise any issue to the client ahead of time. Any Change Order must be duly approved by the client in terms of Time and Cost prior to implementation.