National Rural Infrastructure Development Agency
National Rural Infrastructure Development Agency
VIII. Sanctioned length: 3.640 km, Flexible pavement: 3.25 km,Rigid/Semi-Rigid pavement: 0.39 km
IX. Executed length: 0 km, Flexible pavement: 0.000 km, Rigid/Semi-Rigid pavement: 0.000 km
(in case of completed works only)
3. QUALITY CONTROL:
I. Location of field laboratory: * Tape Para Ch-1/800 km
II. Geo-tagged photograph of laboratory uploaded on: (date/ month/ year) * 19/08/2022
V. Details of contractor’s engineer available at site: (Responsible for maintaining quality control register part-1) *
Sl. Name of contractor’s Duration of posting at site
no. Identity number Mobile number
engineer at site From To
✔ 1 Tanmaya Kumar Mishra 8 8249463109 22/06/2022 30/07/2022
2
3
VI. Details of contractor’s lab technician: *
Sl. Name of contractor’s Duration of posting at site
no. Identity number Mobile number
lab technician From To
✔ 1 Ashok Kumar Sethy 10 8596952324 20/02/2022 22/06/2023
2
VII. Details of Head of PIU supervising the work: *
Sl. Head of PIU Duration of posting at site
no. Employ number
(Executive engineer) From To
✔ 1 Ramesh Chandra Jalli 66001134 09/06/2022 22/06/2023
2
3
*
VIII. Details of Assistant engineer supervising the work and maintaining quality control register Part-II:
Sl.
Name of Junior Duration of posting at site
no. Employ number Mobile number
engineer
From To
✔ 1 Ramakanta Dubey 91445358 9437714438 27/06/2022 26/06/2023
2
3
Available equipments that are in working condition Available equipments that are not in working
(1) * condition (2)*
All equipments are in working condition N/A
XII. Reasons put forth by PIU for non availability of equipments in field lab:
N/A
XIII. Equipments and documents ready to be made available to QM before or during the inspection:*
Equipments mentioned in the item no.10 and all documents like agt, DPR, Estimate QCR part-1 and 2 etc are ready to be
made available to QM
Date Name and Road distance Level of Major observations Action taken by PIU
of Designation of (RD) work at the with date
visit inspecting officer time of
(NQM/SQM/CE/ From To inspection
(1) SE)(2) (3) (4) (6) * (7) *
(5) *
Satisfactory N/A
06/07/2022 SE 0.000 3.25 Earth Work& Subgrade
Satisfactory N/A
26/07/2022 SE 0.000 3.25 CC Pavement