Professional Documents
Culture Documents
TCN Journal 2021 April Edition
TCN Journal 2021 April Edition
29 April 2021
April 2021
19
ber 20
Decem
2020
June
Jan -
2020
mber
Dece
CONTENTS
13 MOBILISE
TCN, BORNO STATE
08 TO RESTORE POWER
SUPPLY IN MAIDUGURI AND
ENVIRONS
27
TCN BOSS TASKS ELECTRICITY
05 STAKEHOLDERS ON
STRATEGIES FOR EFFICIENT
27
FG APPROVES
07
GRID MANAGEMENT CONTRACTS
FOR THREE
TRANSMISSION
07 TCN ASSURES
TRANSPARENCY AT SLA SUB-STATIONS,
MEETING WITH KEDCO EXTENSION OF
TRANSMISSION
MAINTENANCE, UPGRADE
08 AND EXPANSION: LINES
KEY TO GRID STABILITY
-MD/CEO 34
MINISTER OF STATE, POWER GRID TO
11 POWER, URGES GET 4,000MW
NAPTIN GRADUATES TO WITH ONGOING
BE ENTREPRENEURS TRANSMISSION
PROJECTS
42 TCN MANAGEMENT ASSURES REGIONAL
OFFICES OF EQUIPMENT AND SPARE PARTS
13 55 30
pag e 3 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
EDITOR’S
NOTE
pag e 4 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
GM, System Operations (SO), Engr. Nafisa Ali
T
he Ag. Managing 17th March 2021, to appraise process of attaining an efficient grid
Director and Chief operational performance related to includes setting the right
Executive Officer of generation data, available units, environment which would inspire
t h e Tr a n s m i s s i o n water, gas constraints and load confidence amongst industry
Company of Nigeria intake in the last six months, as well players, contrive the process that
( TC N ) , E n g r . S u l e as projected data for the next six players can look up to and calibrate
Ahmed Abdulaziz, has tasked months. The data will aid efficient the same to ensure an efficient,
electricity stakeholders in the operational planning and viable and economic model. All
generation, transmission and management for enhanced system these, he noted, cannot be done
distribution subsectors to come up performance and stability. without first having a proper
with strategies that will enable them planning mechanism in place.
handle risks associated with the He posited that all stakeholders
management of the nation's power should adopt the principal objective Speaking also in the meeting, the
grid as every player is an important of planning which entails General Manager, System
component of the structure that maximizing profit and conversely Operations (SO), Engr. Nafisa Ali,
produces an efficiently managed minimizing losses, managing opined that the sector had generally
grid. uncertainties and coming up with performed well in 2020 with records
ways to handle risk involved in grid of multiple maximum daily energy
Engr. Abdulaziz, represented by the management. He equally harped on peak generation amid prevalent
Executive Director Independent the importance of critical challenges, including the Covid-19
System Operator (ISO), Engr. observations in reshaping the pandemic. She pointed out that in
Maman Lawal, made this known industry. less than three months into the year
during a two-day Joint 2021, the system has continued to
Generation/Operation/ Distribution Engr. Lawal explained that the record increase in both generation
Planning meeting on Wednesday
pag e 5 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
Engr. Abdullahi highlighted achievements by all stakeholders
within this appraisal period to include; all-time peak generation and
transmission of 5,801.60MW on 1st of March, 2021 and the reduced
incidents of system collapses
peak and daily maximum energy months and gave a high score to the
peak. This, she said, signals hope that performance of industry players
the sector would do better moving within the period, evidently revealed
forward. in the multiple maximum peaks in
energy and generation experienced
She lauded the efforts of participants on the grid.
and noted that any success recorded
in the sector is a result of collective They also adopted resolutions
effort, and urged participants to expressing the concern of all
sustain the momentum for a more participating companies on a
efficient management of the country's number of issues which include the
grid network. provision of spinning reserve for
improved grid stability, deployment
In his remark, the General Manager, of a SCADA system with a coverage
National Control Centre (NCC), Engr. area beyond legacy generation
Balarabe Abdullahi, explained that the stations and fast-tracking the
Joint Generation/Operation/ upgrade and completion of various
Distribution Planning bi-annual transmission projects that would
meeting is a forum where operators further expand the grid and provide
come together to appraise grid quality power delivery to more
operations and make forecast based electricity users in the country.
on critical technical assessments.
Also mentioned in the communiqué
He also explained that the forum is an is the low load utilization by DisCos
avenue to inform the DisCos of which impacts negatively no grid
expected load supply for the next six stability and load evacuation from
( 6 ) m o n t h s a n d m a k e GenCos as well as recruitment of
recommendations on ways to plant and system operators and
improve grid facilities. The outcome general infrastructural challenges
of the meeting, he said, is expected to bewailing the industry. The
form the fulcrum for making salient communiqué also noted the poor
decisions on the operational aspect of implementation of past
the power sector. communiqué recommendations
and constituted a committee to
Engr. Abdullahi highlighted monitor and report progress made
achievements by all stakeholders on issues cited in subsequent bi-
Participants
within this appraisal period to include; annual meetings.
an increase in generation capacity to
13,014.40MW, maximum daily Energy
ever attained of 119,471.15 MWH
recorded on 5th March, all-time peak
generation and transmission of
5,801.60MW on 1st of March, 2021,
and the reduced incidents of system
collapses among others.
TCN ASSURES
include over allocation of
load, misapplication of
load schedule and wrong
compilation of invoices as
topmost among other
TRANSPARENCY AT SLA
issues contained in their
formal complaint.
S
equel to a formal complaint filed by the Kano Megawatts lost, among others.
Electricity Distribution Company (KEDCO) Plc to
the Nigerian Electricity Regulatory Commission Engr. Eje also noted that KEDCO would also need to
(NERC) on disagreements with issues contained in the disclose the availability or otherwise of its own facility
Service Level Agreement (SLA) signed with the especially the 33kV feeders upon which the SLA
Transmission Company of Nigeria (TCN), the Acting depends to enable TCN align appropriately.
Managing Director of TCN, Engr. Sule Ahmed Abdulaziz
has assured KEDCO of transparency and openness. At a subsequent meeting held on 1st March, 2020, both
TCN and KEDCO were requested to reconcile and submit
Engr. Abdulaziz gave the assurance when a team from actual data of faulty equipment by undertaking an on
KEDCO Plc led by the Chief Technical Officer to the the spot evaluation of their facilities in the affected areas
Managing Director/CEO, KEDCO, Engr. David Omoloye, and submit a report to the Market Operator within the
met with TCN on 23rd February, 2021 at the TCN specified period.
pag e 7 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
The Ag. Managing Director
and Chief Executive Officer
of TCN, Engr. Sule Abdulaziz
in this interview
speaks about the strategy
deployed by TCN to deliver
more bulk power to the end-users
in the country.
Abdulaziz explains that grid
stability is equally predicated
on the deployment of Spinning
Reserve and SCADA/EMS amidst
demand and supply from
DisCos and GenCos.
Transmission News provides
the excerpts:
pag e 8 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
MAINTENANCE,
UPGRADE AND
EXPANSION:
KEY TO GRID
STABILITY TC N œ M D /C E O
anticipation of more load up-take by reduction in downtime. place a well-articulated plan for grid
the DisCos. Recently, we completed Q. TCN's short-term goals? improvement which we are already
some new transformers installation A: Our goal in TCN is not different implementing; this has enabled us to
and reconductoring of lines in with that of the Federal Government, significantly reduce the number of
different parts of the country. which is to wheel stable and quality grid collapses in the country. We are
Presently, contracts for several new electricity to all the nooks and also working hard to ensure TCN
transmission substations and lines crannies of the country. We have in attains the level of service delivery
are in the process of being that would be at par with
awarded while efforts are in top international best practices. Our
“
gear to complete on-going goal is to continue to reposition
projects, including TCN for optimal service delivery
reinforcement of existing while maintaining a well-
substations and reconductoring Our goal in TCN is not different with motivated and trained workforce.
of existing transmission lines for that of the Federal Government, which
higher capacity. is to wheel stable and quality electricity Q. Challenges of TCN at the
to all the nooks and crannies of the moment?
It is equally important to country. We have in place, a well- A: There are some notable
mention here that scheduled articulated plan for grid improvement, challenges in TCN, which include
maintenance of the existing which we are already implementing the need for a very functional and
network is religiously being efficient Supervisory Control and
implemented as part of our top Data Acquisition (SCADA) system
“
priorities, and spare parts are and Automated Meter Reading
being stocked to ensure drastic System, poor budgetar y
pag e 9 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
The issue of whether TCN should
Substations respectively, line with our grid expansion plans.
be privatized has been an
among others.
ongoing discussion in the public
Apart from engineering and
space. Even though I do not We have successfully design support that we may
advocate for the privatization of reduced frequency of system render to the SPV and Siemens as
TCN, the future has a lot of collapse in the last 8 months the need arises, our role basically
unravelled mysteries, which could through ensuring grid would be to take over the projects
make TCN's privatization the next stability by recalibration and and operate them as part of newly
big step in the sector, but until reconfiguration of completed projects in the grid.
then, we are doing our best to build transmission lines, we set up When they are completed, the
TCN into a world class transmission a functional protection projects would further contribute
company comparable to any department that efficiently to our grid capacity expansion
standard grid. tackled transformers efforts.
protection schemes which
w e re f a u l t y , a n d a l s o Q. Privatization of TCN, what
resolved a number of Way- are your thoughts?
Leave/Compensation issues A: The Federal Government in its
across the country that have wisdom privatized the Generation
lingered for many years. and Distribution companies; I am
Contracts and projects which certain this must have been done
allocation for government were under litigation and after consultations and with
funded projects. Other challenges stagnated have also been regards to the Nigerian electricity
are delay in release of approved resolved. supply environment. Do not
budget, bottlenecks in the forget that the business of bulk
processing of IDEC and other port We have also made progress in electricity transmission all over
clearing documents and difficulty donor funded projects by the the world is very capital intensive,
in acquisition of land and Right of World Bank (WB), African much more than distribution and
Way for our projects. Development Bank (AfDB), generation. Moreover, our
Agence Française de terrains are quite challenging with
Q. TCN Achievements from Developpment (AFD), and Japan issues of vandalism, Right of Way,
assumption of office International Cooperation illegal mining, insecurity, among
A: We have recorded a number of Agency (JICA) which are at others, which TCN have had to
milestone achievements in the different stages of grapple with.
last 10 months. They include the implementation, among these is
successful transmission of an all- the Abuja Ring Project funded by The issue of whether TCN should
time peak generation of AFD and expected to address be privatized in the future has
5,801.6MW in March this year as green fields transmission lines been an ongoing discussion in
well as recorded the highest daily and substations aimed at the public space. Even though I do
energy peak of 119,471.15MW. reinforcing the High-Voltage not advocate for the privatization
Others are the implementation of Transmission Ring around Abuja. of TCN, the future has a lot of
re-conductoring of Sokoto- unravelled mysteries, which could
Birnin–Kebbi line from 70MW to Q. TCN's role in Presidential make TCN's privatization the next
150MW, Ikeja West-Alimosho- Power Initiative involving big step in the sector, but until
Ogba-Alausa lines from 120MW Siemens? then, we are doing our best to
to 240MW and the award of the A: TCN, as a power sector build TCN into a world class
contract for the reconductoring participant, would be one of the transmission company
of Onitsha-New Haven line from beneficiaries of the Federal comparable to any standard grid.
680MW to 1,320MW. Government initiative to improve We are determined and are
services in the power sector value diligently executing plans as laid
we also added 246MW at chain. We have made our out in our Nigerian Electricity Grid
132/33kV level by completion of submission with regards to the Maintenance, Expansion and
1x100MVA, 2x60MVA, 1x60MVA projects that we would want the Re h a b i l i t a t i o n P ro g r a m m e
and 1x30MVA projects at Ogba, Siemens project to intervene in, in (NEGMERP).
Gagarawa, Rumuosi and Iseyin
pag e 1 0 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
MINISTER OF STATE, POWER,
URGES NAPTIN GRADUATES
TO BE ENTREPRENEURS
By Stanford Nneji
acquisition. The next step now, is TCN and the DISCOs for their
how all that you have learnt can be support in mentoring the trainees.
translated to entrepreneurship”.
Highlight of the ceremony was the
He noted that entrepreneurship is presentation of certificates and
key in the world today and urged award to the best graduate in
them to strive to be employers of Generation, Transmission and
labour rather than job seekers by Distribution aspects of the power
exploiting the opportunities the sector value chain.
training presents to enable them
play a role in the ever growing The NAPTIN Graduate Skills
Minister of State for Power Nigerian power sector. Development Programme
(NGSDP) is meant for young
T
he Minister of State for
Earlier in his welcome address, the engineering graduates of
Power, Mr. Goddy Jeddy
Director-General of NAPTIN, Mr. Electrical/Electronics and
Agba, has urged graduates
Ahmed Nagode, said that Mechanical engineering. The
of the National Power Training
adequate training is imperative training provides them with
Institute of Nigeria (NAPTIN), to
especially in critical areas of requisite skills and knowledge to
apply the knowledge they
operation and maintenance, like be able to operate, maintain and
acquired during their one year
meter installation, cable jointing manage facilities in the nation's
training to becoming
and lines, to ensure that the power electricity supply industry. Two new
entrepreneurs in order to reduce
sector is built not just on local modules were introduced during
the rate of unemployment in the
content, but of highly skilled work- this training programme to ensure
country.
force that will ensure safety of lives the trainees are also equipped in
and equipment. the area of safety and solar PV
The Minister gave the
installation process.
admonition during his remarks
He expressed delight that the
via Zoom at the graduation
graduates had
ceremony of the first batch of
undergone intensive
2019/2020 Skills Development
practical training in
Programme of NAPTIN, held
generation,
recently at its Headquarters in
transmission and
Abuja.
distribution and are
now professional
According to him, “the Power
engineers that can
sector is very critical to our
a l s o o p e r a te i n
development, and as young
different areas of the
graduates, you all have gone
power network, and
through the NAPTIN one-year
thanked NAPTIN
graduate programme for skill
partners in GENCOs,
pag e 1 1 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
ENGR. ABDULAZIZ ADVOCATES FOR COMMON
POWER POOL IN AFRICA By Eric Ephraim Ene
pag e 1 2 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
TCN, Borno State Mobilise to Restore
Power Supply in Maiduguri and Environs
...Foundation and Tower Materials Ready
By Ndidi Mbah
equipment/materials and
workforce were on ground and
tower fabrication work ongoing,
mounting tower parts proper, he
said, would commence at the sites
of the damaged towers as soon as
the new concrete foundations have
been properly cured.
From L-R: TCN Ag MD/CEO, Engr. Sule Ahmed Abdulaziz. ED TSP Engr. Victor Adewumi, The Borno State Commissioner for
Managing Director, Yola Electricity Distribution Company, Engr. Baba
Housing and Energy, Engr. Yuguda
Mustapha; Borno State Commissioner for Housing and Energy, Engr. Yuguda Vungas
Sadeh Vungas, speaking on behalf of
the Borno State Governor, assured
that the government would provide
pag e 1 3 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
security personnel required at the site to facilitate work
on the permanent towers structure are on site.
pag e 1 4 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
COMPLETE AMASIRI
SUBSTATION PROJECT,
EBONYI GOVERNOR APPEALS TO TCN
By Eric Ephraim Ene
T
he Governor of Ebonyi State, Dr. David Umahi,
has appealed to TCN to direct the contractors speedy execution of the project.
handling the ongoing 2x60MVA, 132/33kV
substation and transmission line project at Amasiri, to Dr. Umahi assured the TCN Management that the state
fast track its completion in order to boost bulk power government on its part is ready to do everything
delivery to the state, before the commencement of the within its power to assist in the execution of the
rainy season. projects. He however appealed to TCN to include in
their budget the diversion of the ongoing 132kV
The Governor made the appeal when he led some transmission line from the new Ebonyi airport site.
members of his cabinet on a visit to TCN on Tuesday,
9th February 2021, in Abuja, to request for support for Responding, the Ag MD/CEO of TCN, Engr. Sule
the timely completion of the projects. Abdulaziz, also expressed dissatisfaction with the
progress of work at the site, noting that efforts were
being made to ensure that the contractors mobilise
pag e 1 5 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
back to site urgently. encountered in executing the project, but noted that
According to him, TCN has made progress in the progress, however, has been made with the
payment of compensation to farmland owners and completion of 59 towers out of the 100 contracted
appealed to the governor to jettison the idea of towers.
termination of the contract to avoid litigation and
further delay of work. He said that the contractors had The representative of NCEP Engineering Nigeria Ltd
already been warned and that they would resume (North China), Mr. Wang, on the other hand, said that
work in earnest and complete within the reviewed time the execution of their contract has reached 72 percent
frame. completion and that the equipment procured to
enable them complete the project was delayed by
Speaking at the occasion, the representative of Fluor IDEC issues which was resolved recently. He promised
Eurafric Engineering Ltd, one of the contracting firms, to fast track and complete the project as soon as all the
Mr. Godswill Egbadon, enumerated challenges equipment arrive the site.
Don’t
be afraid to lose people,
Be afriad of losing
yourself by trying to please
everyone around you.
pag e 1 6 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
TCN is Working to Further
Expand the Nation's Grid
By Ndidi Mbah
pag e 1 7 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
In TCN's Abuja Region for instance, the company is incremental improvement in grid performance on
implementing the Abuja Feeding Scheme which is at TCN's part has enabled it continue to transmit
various stages of implementation. The project, which seamlessly all generated power to distribution load
involves the addition of five (5) new substations and centers nationwide. The company's successes is an
one 330kV transmission line, is ongoing. The projects indication of professionalism and best practices that
take between 3 to 5years to complete and will solve was brought in by the new Management in TCN.
transmission constraints in Abuja.
To better serve the 11 DisCos, TCN entered into
TCN is rehabilitating and reinforcing projects Service Level Agreement (SLA) with them, aimed at
nationwide. In Kubwa Substation for instance, one of ensuring proper synergy and effective service
the 60MVA power transformers which developed delivery via identification and execution of projects
fault is being repaired. Meanwhile, a brand new one that would further improve the grid and deliver
has been installed in the substation by TCN quality electricity to consumers across the country.
engineers. The transformer was commissioned on
the 2nd of March, 2021. This has added 46MW TCN, like every other participant in the value chain,
capacity to the substation which will take care of the has its own challenges. There have been repeated
load requirement for Kubwa axis and environs. vandalism of major transmission lines in recent times,
which the company promptly repairs any time it
TCN in recent times has taken a more responsive occurs. Vandalism is a social menace over which TCN
approach to serving the GenCos has no control; however, TCN is
in its upstream and the doing all it can with TCN lines
DisCos in its downstream, patrol department working
through effective in conjunction with
TCN can only transport
maintenance of the security agencies to
what is available(generated),
existing grid network while monitor the lines and
applying best practice in and what is generated reduce incidences of
completing ongoing low depends on what the DisCos vandalism.
hanging fruits projects to nominated. In other words,
improve the overall grid DisCos can only off take what In Abuja alone, between
capacity. is generated, while GenCos 31st of October, 2019 to-
can only generate what date, the region has
This approach paid off Discos can off take. witnessed 21 acts of
quickly as evidenced in the vandalism on 330kV and
seamless transmission of 132kV aluminum
multiple all-time peak conductors by unknown
generation recorded in the persons, and on each occasion,
sector within the last six months; 5377.8MW TCN has promptly replaced or repaired the lines. The
achieved on 1st of August 2020 at 20:30hrs, extent of damage on each line determines the length
5,420.30MW on August 19, 2020 at 19:15hrs, of time it would take to complete repairs. Recently,
5,459.50MW achieved on the 28th of October, 2020 the system lines maintenance crew of Abuja Region
at 20:15hrs and two days later on the 30th of October, replaced 2000 meters of 350mmsq aluminum steel
2020, the Nigerian Grid network recorded yet reinforced conductor on Gwagwalada-Westmain
another all-time peak of 5,520.40MW. 330kV Double Circuit (DC) vandalized by unknown
persons.
The Transmission Company of Nigeria on
Wednesday 6th January, 2021 and Thursday 7th On the outskirts of Maiduguri, three towers were
January, 2021 seamlessly transmitted another all- vandalized causing the towers to collapse, affecting
time peak generation of 5,552.40MW and power supply to Maiduguri and environs.
5,584.40MW respectively; on the 25th of February,
2021, it transmitted another all-time peak generation In Ughelli, Delta State, TCN Engineers recently
of 5,593.40MW; on the 28th of February, 2021, a new completed the repair and replacement of tower
peak of 5,615.40MW, and on the 1st of March 2021, members of towers 2-4 Delta – Benin – Ughelli
another new peak of 5,801.60MW was successfully double circuit transmission line recently vandalized
transmitted. This is an uncommon record in the by unknown persons. TCN has carried out the
Nigerian power sector, and the consistency in replacement work. The 68.4 kilometers line
pag e 1 8 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
evacuates electricity from Transcorp Power Ltd into the
grid.
SERVICOM
HARPS ON NERC ENFORCEMENT OF
Also towers 41 and 42 along the Benin-Delta Oghara SERVICE DELIVERY IN POWER SECTOR
132kV double circuit line in Warri, Delta State collapsed By Stanford Nneji
due to heavy rainfall. Repair work is currently ongoing.
pag e 1 9
Transmission Grid Records
Fastest Power Grid Recovery,
After System Disturbance
during the grid disturbance, while affected parts were The Ag. MD/CEO further noted that the grid recovered
fully recovered within 45 minutes, the fastest in the from the partial system collapse within 45 minutes. This
history of the power sector in Nigeria. he attributed to the commitment of President
Muhammadu Buhari and the Minister of Power, Engr.
The Ag. MD/CEO of TCN, Engr. Sule Ahmed Abdulaziz, Sale Mamman towards bequeathing an improved power
confirmed the swift recovery of the grid, noting that sector to Nigeria, noting that TCN is working towards
TCN's system operators acted promptly to salvage the zero system collapse.
situation.
According to the Ag. MD/CEO, the company is gradually
According to him, “We had one system collapse late last completing old projects and also executing new ones to
year and one partial collapse yesterday. The partial grid further improve bulk power capacity delivery. “As we
collapse is the second time the grid is experiencing speak, our engineers are working on the replacement of
system disturbance in the last eight months; this has corroded glass disc insulators on Tower 425 of Ikeja West
never been the case in the history of the Nigerian power to Osogbo 330 kilovolt (kV) line; one of our contractors is
sector and is happening at a time when the capacity of also reconductoring the Kebbi-Sokoto Transmission
the national grid has improved. I can assure you that Line”.
pag e 2 0 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
REHABILITATION/RECONDUCTORING
OF IKEJA-WEST /ALIMOSHO/OGBA
132kV LINES 1AND 2, OGBA/OTTA
TEE-OFF 132kV LINE, AND OGBA/
ALAUSA 132kV LINES 1 AND 2.
By Tosin Olashinde
pag e 2 1 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
T CN is reconductoring the Birnin Kebbi
/Sokoto line to keep up with the
anticipated increase in bulk power
RECONDUCTORING
OF BIRNIN KEBBI
transmission and also tackle the issue of
lines constraints being experienced on that
line route.
pag e 2 2 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
The Ag. MD TCN and his management Team
Project Site
In his words, “Our purpose here is to check and see if
this site will be suitable for the construction of a
would have functional Supervisory Control and Data
second National Control Center like the one we have in
Acquisition (SCADA) system, Energy Management
Osogbo". Engr Abdulaziz said the civil engineering
System (EMS), and modern communication
department of TCN would further assess the site and
equipment compatible with international standards.
make recommendations to Management for final
approval.
He also noted that the new Control Center project
would be completed within 18 months and when
He disclosed that the contract for the execution of the
completed, it would complement NCC in Osogbo and
project would soon be signed as the Bureau for Public
help forestall breach in the system.
Procurement (BPP) has already issued a Certificate of
"No Objection" to TCN for the commencement of
work.
pag e 2 3 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
NAPTIN PROPOSES CAPACITY
BUILDING PLAN FOR TCN
By Stella Ejikonye
he Management of the National TCN and other companies in the power sector deliver
Power Training Institute of Nigeria, more effectively on their mandate”.
NAPTIN, has called for more synergy
İ with TCN in the area of capacity Mr. Nagode further explained that NAPTIN, as a center
building to enhance productivity. of excellence, also trains staff of other power utilities in
the African Sub-Region, including the West African
The Director General of NAPTIN, Mr. Ahmed Bolaji Power Pool (WAPP) and assured Management of their
Nagode, made this known when he led the readiness to tailor training schemes to fit TCN's
management of the company on a courtesy visit to capacity building requirement.
TCN.
Responding, the Ag. MD/CEO, TCN, Engineer Sule
According to him, the Agency was out to ensure that Ahmed Abdulaziz, said the visit was strategic, as the
industry players fully utilize the potentials of NAPTIN current management was in the process of concluding
in meeting their goal of human capacity development. its training plan for the year 2021 which is focused on
“I remember very well that the Honorable Minister of specific skills set to further build required capacity. He
Power and the Honorable Minister of State for Power, directed the Human Resources Division to liaise with
have always enjoined us to work together as agencies NAPTIN to properly streamline training for the year.
under power, to ensure that we collectively utilize our
potentials towards realizing the goals and objectives The Executive Director, Human Resources and
of the power sector” he said. Corporate Services at TCN, Barr. Justin Ishaya Dodo, in
his response, said that TCN Management is committed
The institute, he informed, has trained about 1,000 to implementing the capacity building policy of the
staff of TCN in technical and non-technical areas company and assured NAPTIN of TCN's support for
between 2019 and 2020, and feedback shows that the structured and impactful training.
training positively impacted their jobs.
Also speaking, the Executive Director, Independent
According to him, TCN staff that participated in the System Operator, Engr. Maman Lawal, stressed the
training gained practical experience which has need for quality training for the power sector and
positively impacted job execution. “This kind of emphasized the need for NAPTIN to liaise with TCN's
feedback”, he said, “is what encourages me to say that training department in order to put in place a
there's always the need to build capacity to ensure that meaningful programme for the company.
L-R, ED-TSP Engr. V. Adewumi, ED-HR & CS Mr J. Dodo, ED-ISO Engr. M. Lawal, Ag MD/CEO, TCN Engr S. Abdulaziz
and DG NAPTIN, Mr Ahmed Nagode, Director Legal-NAPTIN Barr. K Oyenusi
pag e 2 3 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
TCN
ENGINEERS
INSTALL AND ENERGIZE
40MVA
TRANSFORMER
The new 330kV reactor
pag e 2 5 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
BRAND NEW 60MVA
POWER TRANSFORMER COMMISSIONED
IN KUBWA SUBSTATION
By Grace Sambe-Jauro
The brand new 60MVA transformer Third Left, ED TSP, Engr. Victor Adewumi during the site visit
pag e 2 6 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
FG Approves Contracts for Three
Transmission Sub-Stations &
Transmission Lines Extension
By Grace Sambe-Jauro
T he Federal Executive
Council (FEC), has
a p p r o v e d t h e
construction of three
transmission sub-stations, two
in Kano State and one in Benue
State, and the extension of
transmission lines in Abia and
Imo States.
Engr. Mamman further explained that the Ministry of Commenting on the development, the Ag. MD/CEO of
Power embarked on these new projects as part of TCN, Engr. Sule Abdulaziz noted that the approval of
efforts aimed at expanding the national grid for funds for the substation and line projects further
sustainable supply of electricity, and to improve the shows that the Federal Government was bent on
wheeling capacity of TCN. ensuring incremental expansion of the capacity of the
nation's transmission grid in line with its plan for the
Validating the Minister's position, the Minister of sector. He expressed appreciation to the Federal
Information and Culture, Mr. Lai Mohammed said, government and pledged to ensure the timely delivery
“You see, before now, there's been complaints that of the projects by the contractors.
pag e 2 7 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
ENUGU REGION STAFF ATTEND
SLA SENSITIZATION WORKSHOP
By Mary Philip Udom
evacuation of bulk power on the grid. Engr. Sule further informed that TCN's live line crew
has been detailed to tackle the job. The crew, he said, is
The Assistant General Manager, Live line, Engr. very experienced and would efficiently replace the
Abdulahi Sule, made this known when he played host conductors to solve the challenge of corrosion which
to his colleague, the Assistant General Manager, causes the drooping of conductors.
Transmission, Omotosho Sub–Region, Engr. Nuhu
Abdulraheem, on Tuesday, 8th March 2021, in Benin, In his remarks, the Assistant General Manager,
Edo State. The meeting strategized on the Transmission, Omotosho Sub-Region, Engr. Nuhu
methodology to adopt in efficiently replacing Abdulraheem, revealed that the Omotosho lkeja West
detached insulators on live lines along Ondo axis. 330kV Lines had four detachments on the same spot
within a month last year, which informed the exercise.
Speaking during the meeting, Engr. Sule explained The complete change of the insulators, he noted,
that Benin Region had embarked on replacing glass would permanently solve the corrosion problem.
insulators with composite insulators as a result of
corrosion which sometimes causes the glass insulators Engr. Abdulraheem further explained that the ongoing
to detach from conductors. He noted that air pollution replacement work would affect about 500 towers
and salty rain witnessed regularly in the area are the along the Benin-Egbin-Ikeja West 330kV transmission
major causes of corrosion of glass insulators. lines. He said that the exercise would impact positively
on TCN's wheeling capacity in the region while at the
According to him, TCN management considered it same time, ensure that the conductors are properly
wise to replace the glass insulators with composite separated and secured.
insulators to solve the problem of corrosion. He noted
pag e 2 9 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
TCN COMPLETES NEW TOWER,
RECOVERS SECOND 600MW
EGBIN-AJAH TRANSMISSION LINE
By Ndidi Mbah
pag e 3 0 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
ISO-TCN REGIONAL
OPERATION MANAGERS
ROM OSOGBO REGION Mr. Olaniyi Yisa Gbadebo is the Regional Operations Manager (ROM) Osogbo.
Prior to this, he was the Regional Operations Coordinator (ROC), Osogbo RCC.
He holds a BSC in Accounting from University of Lagos and HND in Electrical
Electronics from Osun State College of Technology Esa-Oke.
He is an experienced Electrical Operator who has passed through K1-K5 from
Professional Skill Training Centre, Kainji and as well as Senior Electrical Operator
Course and other System Operator Courses.
He attended several Workshops for System Electrical Operators and served in a
good number of Committees.
Engr. Wasiu Adedeji Tijani is the Regional Operations Manager (ROM) Benin
Region. Prior to his appointment, Engr. Wasiu Tijani was the Assistant General
ROM BENIN REGION
Manager (AGM) – Corporate Planning, at Lagos Region.
Engr. Wasiu Tijani holds a Master's Degree, MBA (Production and Operations
Management) from Lagos State University, Post Graduate Diploma and a Higher
National Diploma in Electrical/Electronics from the Federal University of
Technology, Akure, and Ibadan Polytechnic respectively.
He is a member of Nigerian Society of Engineers (NSE), Nigerian Institute of
Management (NIM), Council for the Regulation of Engineering in Nigeria
(COREN), and Member, Certified, Project Management Professional (PMI, USA).
pag e 3 1 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
ISO-TCN REGIONAL
OPERATION MANAGERS
ROM ABUJA REGION Engr. Sobande Adekoyejo Oladipo is the Regional Operations Manager (ROM),
Abuja Region. Before his appointment, he was the Assistant General Manager,
NCC, SCADA and RTU Maintenance NCC and the Technical Head, Operation and
Maintenance of TCN SCADA and RTU networks and adaptation writing for TCN
grid.
He had earlier served as the Team Lead and Technical Support, TCN SCADA
Reactivation Project. He holds a B.Sc in Electronic and Electrical Engineering,
specialized in High Voltage Engineering from the then University of Ife, Ile Ife.
Engr. Sani B. Gwarzo is the Regional Operations Manager (ROM) for Shiroro.
ROM SHIRORO REGION Before his appointment, Engr. Sani B. Gwarzo was the Acting Assistant General
Manager Transitional Electricity Market (TEM). National Control Centre, Osogbo.
Engr. Sani B. Gwarzo developed the present frame work template of the Service
Level Agreement (SLA) signed between TCN and the DisCos. He also participated
in the review of Operational Procurement for System Operators.
pag e 3 2 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
ISO-TCN REGIONAL
OPERATION MANAGERS
Engr. Agupusi Jude Ikechukwu is the Regional Operations Manager for Port
ROM PORTHARCOURT Harcourt. Before his appointment, Engr. Agupusi was the Principal Manager
(Communications), Benin Region, in charge of planning, installation,
REGION commissioning and maintenance of power line carrier equipment, optic
fibre and SCADA equipment.
ROM KADUNA REGION Engr. Abdulkareem Abdullahi Shafa is the Regional Operations Manager,
Kaduna Region. Before his appointment, he was the Principal Manager
(Regional Operations Coordinator, Kaduna Region), and also the Area
Control Coordinator, Gombe.
pag e 3 3 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
POWER GRID TO GET 4,000MW WITH
ONGOING TRANSMISSION PROJECTS
T he Acting Managing Director of TCN, Engineer
Sule Ahmed Abdulaziz has said that the
company has acquired a new office for its
Project Implementation Units (PIUs), to enhance the
delivery of projects that would add about 4,000
engineers and support staff in line with international
standards.
pag e 3 4 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
substations and four 120MW capacity 330kV
transmission lines. These lines will also connect the
West African Power Pool (WAPP) to enable Nigeria
export more power when the projects are
completed.
…The Archives
pag e 3 5 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
Table 2.2. PMU/PIU Funding Sources
The project has recorded some milestone achievements Table 2.5. AFD Abuja Ring Project- Project Impact on Completion
within the project preparation conditions, but has not
been made effective as fund is yet to be made available
by JICA for drawdown.
pag e 3 6 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
CONTINGENCY ANALYSIS OF ABUJA
TRANSMISSION NETWORK
Bemdoo Saka, Sadiq Thomas, Yekini Suberu Mohammed, Ismail Dalhatu Inuwa, Edith Ahiriame Aja, Suleiman U. Hussein
Abstract—This paper presents the contingency analysis for the Abuja transmission network using DIgSILENT Power
Factory software. The contingency analysis showed the results for the worst loading violations from the most severe to
the least severe case for both the base case and the case study contingencies. For the base case condition, the most
severe continuous loading condition was 200.2% while the least severe continuous loading condition was 93.7%. After
the reinforcement of the identified weak section of the network, the security and the stability of the network improved
greatly with the most severe continuous loading condition of 138.9% and the least severe continuous loading condition of
80.4%. Contingency analysis for Abuja transmission network was conducted to identify the weakest part of the network
and then take measures to ensure the stability of the network.
pag e 3 8 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
An optimal contingency assessment model using two- · Gwagwalada 330/132/33kV substation
stage stochastic linear programming including wind · Katampe 330/132/33kV substation
power generation was presented. The optimization · Apo 132/33kV substation
model was applied to find the best radial topology by · Kukwaba 132/33kV substation
determining the best switching sequence to solve · Apo 132/33kV substation
contingencies. The proposed model was applied to a · Central Area 132/33kV substation
69-node distribution system and the results of all · Kubwa 132/33kV substation
possible contingencies in the network were examined · Karu 132/33kV substation
considering three different case studies with several
scenarios. Two new contingency screening methods The following transmission lines are under Abuja
considering impacts of distribution grids were transmission network;
proposed. The first one was based on global power flow ·Shiroro – Katampe 330kV single circuit line
and the second utilized distribution network ·Shiroro – Gwagwalada 330kV single circuit line
equivalence. The study concentrated on the ·Gwagwalada - Katampe 330kV single circuit line
contingency analysis of the Sebeta to Kaliti transmission ·Lokoja – Gwagwalada 330kV double circuit line
line of the Ethiopian 230kV transmission network. The ·Katampe – Apo 132kV double circuit line
outage of this line caused overload of the Gefersa to ·Gwagwalada – Kukwaba 132kV single circuit line
Kaliti transmission line and made the system insecure ·Kukwaba – Apo 132kV double circuit line
and unreliable. Analysis were conducted by considering ·Katampe – Kubwa 132kV single circuit line
four scenarios such as a normal state, single line outage, ·Katampe – Suleja 132kV double circuit line
cascaded line outage and inserting Distributed Static ·Apo – Karu 132kV single circuit line
Series Compensator (DSSC) into the overloaded line.
The system became reliable and secure by inserting the The closest generating stations to Abuja are the Shiroro
device in the most sensitive line of the network. hydro power plant and the Geregu gas fired power plant
which connects Lokoja – Gwagwalada double circuit
Contingency analysis and reliability evaluation of the 330kV line, Shiroro – Gwagwalada 330kV single circuit
Nigerian power system was performed using the load line, and Shiroro – Katampe 330kV single circuit line. The
flow method. The result of this analysis was used to base case and the case study contingencies will be
determine the security level of the Nigeria power system studied in the next section.
and suggestions were made on the level of protection to
be applied on the Nigeria power system with the aim of A. The Base Case Contingency Analysis
improving system security. The N-1 reliable DC optimal The base case scenario represents the contingency
dispatch with transmission switching was analyzed. The analysis for the existing network without any proposed
model used was a mixed integer program with binary reinforcements in Abuja Transmission Network. The
variables representing the state of the transmission power flow diagram in Fig. 1 shows that the 3 x 150MVA
element (line or transformer). The IEEE 118-bus and the transformers at Katampe 330/132/33kV substation, the
RTS 96 system test cases were used. The IEEE 118-bus 7.5MVA transformer at Suleja substation and the
test case was analyzed at varying load levels. Part of the Katampe – Kubwa 132kV line were heavily loaded as can
document showed that optimal transmission switching be seen from the red and orange coloring on the single
as a congestion management tool was utilized to line diagram (SLD) in Fig. 1 below.
change network topology which, in turn, led to higher
electricity market efficiency. Transmission switching was
formulated as an optimization problem to determine
the most influential lines as candidates for
disconnection.
METHODOLOGY
The contingency analysis was conducted using
DIgSILENT Power Factory simulation software. Different
330/132kV transmission lines and substations connect
the transmission network in Abuja, the capital city of
Nigeria. The following substations are under the Abuja
transmission network:
Fig. 1 Power Flow Single Line Diagram
pag e 3 9 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
132kV line was ranked the least severe with 35.3% in the base
case loading and 93.7% in the continuous loading. Also, it can
be observed that the 3 x 150MVA transformers at Katampe
were heavily loaded to 117.9% and 173.8% for the base case
and continuous loading condition respectively.
A. Contingency Analysis (Proposed New Projects)
For the case study, contingency analysis was carried out for
the security assessment of the Abuja transmission network
with the following proposed new projects;
·Turn in and out the second Katampe – Kubwa – Suleja line to
double circuit
·Turn in and out the second Gwagwalada – Kukwaba– Apo line
to double circuit
·Install additional 150MVA transformer at Katampe
330/132/33kV substation.
Fig. 2 shows the colour legend block for the lower voltage
range, upper voltage range and line loading range. The
yellow colours shows the line loading above 80% while the
red colours shows the loading range above 90%.
pag e 4 0 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
e company
e w or ks by TC N engineers as th
Highlights of som bilitate and expa
nd the grid
continues to reha
pag e 4 1 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
Management Commends
TCN’s Regional Managers,
Assures Provision of Equipment And Spare Parts
By Eric Ephraim Ene
efficiency in their operations and This kind of progress, he said, can only While presenting a paper on “Grid
drastically reduce downtime. get better with the support of all. Capacity Development Study”, the
Assistant General Manager (System
The Ag. Managing Director and Chief Engr. Abdulaziz also disclosed that so Planning) ISO, Engr. Kabiru Adamu,
Executive Officer of TCN, Engr. Sule much has also been done in the area of said that System Planning department
Abdulaziz, gave the assurance while staff welfare and that efforts would be conducted the Grid Capacity
addressing Regional Transmission made to further deal with other issues Development study to determine the
M a n a g e r s ( RT M s ) a n d G e n e r a l pertaining to the staff. priority projects which will increase
Managers of Transmission Service wheeling capacities.
Provider (TSP), on Thursday, 11th March He charged the RTMs to do more to
2021, in Abuja. ensure challenges posed by trace According to him, the result of the
clearing is eradicated, saying that each study identified critical transmission
Engr. Abdulaziz stated that TCN had RTM would be held responsible and projects (transmission lines and
already procured some work vehicles, accountable for the performance of transformers on 330kV and 132kV
spare parts, and major HV equipment their substation as well as general voltage levels) necessary for the
some of which were on ground and that maintenance of all substations, addition of every milestone. He noted
plans are ongoing to procure more. He equipment in their regions. He harped that the list of identified projects for
commended the RTMs for their support on the need to ensure quick resolution each milestone had a combination of
and dedication to duty, and urged to interface issues, especially with the ongoing and proposed solutions from
them to keep up the good work, noting signing of Service Level Agreement different project packages to address
that reward for good work is more with the DisCos. some of the critical constraints on the
work. grid.
The Executive Director, Transmission
According to him, TCN had made Service Provider (TSP), Engr. Victor In his presentation on Service Level
significant progress in various areas of Adewumi, expressed appreciation for Agreement (SLA), the General
operations since their last meeting, their contributions in the area of Manager, Programme Coordination,
with the completion and maintenance and transformers TCN, Engr. Joseph Ciroma, disclosed
commissioning of new transmission installation, which enabled TCN that 107 number projects approved in
lines and substations and other efficiently transmit the new generated line with the SLA with 11 DisCos, have a
rehabilitation projects across the grid peak of 5,801.60MW to distribution proposed budget of N114.8billion
to enhance the company's wheeling load centers nationwide. which has been sent to the Nigerian
capacity. Electricity Regulatory Commission
He stated that the meeting will address (NERC) for approval by Central Bank of
He explained that improved and important issues that impact Nigeria (CBN).
efficient maintenance has also helped transmission services, saying that there
in stabilizing the system, reducing is need for the RTMs to challenge The meeting featured robust
equipment down-time and ultimately themselves in order to take the submissions from all RTMs on the way
improving overall system performance company to the next level. forward which would ultimately further
which is the main reason for the He revealed that the System Planning strengthen the transmission network in
consistent increase in peak generated department came up with a study on Nigeria.
pag e 4 2 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
TCN CHARGES HYDRO GENERATION
STAKEHOLDERS TO OBEY GRID CODE TO ENHANCE
T CN has charged the Hydro stations together to He therefore urged the hydro
generation stakeholders to reconcile hydro data before the stations to cooperate with NCC to
obey and respect the Grid operational planning meeting. He ensure seamless operation of the
described planning as an integral Grid for the benefit of everyone
Code, and follow all operational
part of reservoir management and disclosed that there have been
instructions from the National
particularly in hydro power plants reports of inconsistencies by
Control Centre (NCC), to enhance
where daily monitoring of reservoir several hydro stations, including
smooth operation of the national
is necessary for proper and making inaccurate day ahead
grid.
efficient operation. Reservoir declaration etc, and charged them
operation planning therefore, he to shun every act that will be
The charge was made by the
explained, “is a decision-making inimical to the progress of the
General Manager, NCC, Engr.
tool in the process of hydro power industry. The meeting addressed
Balarabe Abdullahi, during the 43rd
generation activities so that a near several issues affecting Generation
bi-annual hydro generation
balance between inflow and and the National Control Center
planning meeting which was held
outflow of water may be achieved;. (NCC) operations, with participants
recently at the National Control
hence the importance and agreeing on the need to make
Center, Osogbo. Welcoming
necessity of such meeting, as no specific changes towards a more
participants to the meeting, Engr.
reservoir is to be operated by trial robust power delivery.
Abdullahi said the meeting was
and error.
pag e 4 3 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
...Continued from last edition
lines 40
20
3 2 X 300kV line bay USD 2,400,000
0
extension
UPFC New Transmission Asset
Table 1 : Transmission and Substation Unit Cost [2] Figure : Bar chart showing Cost of UPFC and New
S/N E Q U IPM E N TS NEW transmission lines
1. 2 X 330k V D o u b le 88 ,00 0,00 0U SD
C irc u it Lin e s (200K M ) It is observed that using UPFC is far cheaper in this case of
2 2 X 300k V lin e b a y 2,400 ,0 00 U SD achieving better voltage profile at the various busbars in
e xte n sio n Lagos region compared to the other alternative.
3 C o n su lta n c y (3% o f 1 .) 2,640 ,0 00 U SD
CONCLUSION
4 R ig h t o f w a y 6,160 ,0 00 U SD
The following studies were carried out; load-flow analysis,
c o m p e n sa tio n (7% o f voltage stability studies and economic analysis on the
1.)
different cases. The cases are:
To ta l 99 ,20 0,00 0U SD · New transmission assets
· UPFC installation
Table 2 : Cost investment Table From the cases studied, the latter alternative which is the
application of UPFC was seen to be most beneficial in the
Case B following ways; least cost, mitigation of right of way issues
For case B, the following investments are made in as a result of which down time is reduced, improvement of
voltage profile on the busbar studied & de-loading of lines.
installation of UPFC devices at the transmission lines at
Egbin busbar connecting to Ikeja West substation. The
RECOMMENDATIONS
following costs are culled from the EPRI reports
The study shows good prospect for the future in the
regarding FACTS application.
development of TCN grid system but using FACTS devices
S/N Equipment Estimated cost Source of Year of does not eliminate the installation of new transmission lines;
kUSD/MVA(MVAr) Information Publication it gives more flexibility and control to how the power
transfer is managed. FACTS is not the solution to the grid
1. UPFC(shunt portion) 75 EPRI-TR-1064- 1996
645
but a part of the solution. The TCN 330kV grid system is
fragile with a lot of voltage stability issues due to
2. UPFC(series portion) 85 EPRI-TR-1064- 1996 concentrated generation in the south-east and south-south
645 regions of the country, and lack of generation in the north.
3. SVC 40 kEURO/MVA Realise grid 2011 The FACTS devices will give more flexibility of power control
draft to the north and less installation or reinforcement of
transmission lines, or delay part of the construction of new
lines. To achieve high sustainability, further studies should
Table 3 : UPFC Unit Cost Table [7] be carried out to determine the optimal location of these
FACTS devices to be able to provide the best possible results
S/N Type of Rating[MVA] Cost of
series
and reduction in transmission line construction which is cost
Controller
controller
beneficial.
1 2 X UPFC 185/185 59,200,000USD In general, for active power control, a series controller such
device as the TCSC or the UPFC is much more effective than a shunt
2. Consultancy 1,776,000USD connected controller such as the SVC. For reactive power
3% of 1. control, either the shunt or series controller will be effective,
depending on the specific case.
Total 60,976,000USD
pag e 4 4 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
ARE YOU
GUARDING
THE
CONCRETE
SLAB?
... An army barrack had four soldiers guarding a concrete slab in front of the barracks at all times.
Different commanders came and went but the tradition remained; the soldiers changed shifts guarding the
slab.
After 80 years, a new commander was assigned to the barracks. One of the things he did was to ask why things
were done the way they were. When he asked why soldiers were guarding the slab, he was told, We've always
done it this way. It's our tradition. Our former commanders instructed us to do that. The commander was bent
on finding out the reason for this practice.
He went to the Archives to look for answers and came across a document that had the explanation. The
document was very old. It had instructions written by one of the retired commanders who had even passed
away.
The new commander learnt that over 80 years ago, the barracks wanted to build a platform where events could
be performed. When the concrete slab was laid, wild animals walked over it at night before the slab could dry.
The soldiers would fix it the next morning but when evening came the same thing would happen. So the
commander ordered that four soldiers should guard the concrete slab for three weeks to allow it to dry.
The following week the commander was transferred to handle another assignment elsewhere, and a new
commander was brought in.
The new commander found the routine and continued to enforce it without asking any question. And since
then, every other commander that came did the same.Thus, eighty years later; soldiers continued guarding the
concrete slab. An assignment that was ordinarily designed to last just three weeks . . . 80yrs of ignorance with
hard labour has passed.
Are you carrying on obsolete beliefs, attitudes traditions/culture that were relevant to certain people or a
certain time?
What is your opinion about yourself, people of a different race, politics, certain business opportunities, new
products etc.?
You might just be guarding a concrete slab!
Without deviation from the norm, progress is not possible (Ignorance can make you work hard without
progress).
Find out why you do what you do. Change the way you work and be creative. Do new things, try newer ways and
always be open to Change.
Culled from the net
pag e 4 5 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
DID YOU KNOW ? ?
That the history of power industry in Nigeria would that in 1924, the two phase three wire 80 cycles
?
be incomplete if the old Public Works Department system was replaced with the three phase four
(PWD) of Government, which in 1896 installed the wire 50 cycles which is still being maintained
first 60 kW generating set in Lagos, is not today.
mentioned.
that in 1929, Meter Section was established. A
that in 1895, preliminary investigation and planning two-part tariff was introduced as against the
carried out by PWD in Lagos was at a cost of 3,206 flat rate hitherto being charged. Domestic
pounds. consumers paid 10p per unit up to a certain
number of units and 1.5 per unit for
that in 1896, 12,000 pounds was allocated for the consumption in excess.
establishment of the first power station which was
sited at the present location of former NEPA that following an electrical exhibition at Glover
Headquarters in Lagos. Hall, Lagos, during which the various uses of
electricity were demonstrated, consumer
that Mr. T. Rooke was the Chief Electrical Engineer of population in the Lagos area rose from 1,560 in
this establishment, which was known as the Lagos 1930 to 3,550 in 1932.
Electricity Supply. The power station operated from
6.00pm to 11.00pm daily and the maximum power that the exhibition highlighted the fact that use
demand was only 24kW. of electricity was not an exclusive preserve of
the rich but an essential factor in development,
that in 1915, due to the extension of power to Iddo and following the success in Lagos area, the
and Ebute Meta areas, generating capacity Government in 1926 started an electricity
increased to 320kW. In 1921 it was further development scheme throughout the country.
increased to 420kW.
FAREWELL
When the lights go out
for our loved ones, the memories
of their existence remain.
Late Engr. Mike Oyigbo, AGM (TS) When like flowers they fall off the stalk, Late Mr Adetokunbo Ashogbon,
Enugu Region wither, disintegrate, become soil. SM (HR), Lagos Region
The pain from our loss, our helplessness
become our grief
But time like the balm, will in time
preserve in us the joys, dreams and
laughter’s we once shared
And in time we would come to realise
we were privileged to have loved
and be loved.
pag e 4 6 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
Quotes
If you are ruled by mind,
you are a King;
if by body, a slave.
-Cato the Elder
S O C I A L S
BARAYA OF DUTSE
pag e 4 9 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
TCN Management team led by Ag. MD/CEO, Engr. Sule Abdulaziz, during a visit to the Executive Governor of Borno State, to brief him
on efforts by TCN to rebuild the damaged towers in his state and to request additional assistance in terms of security for TCN Engineers.
TCN Management team led by the Ag.MD/CEO Engr. Sule Ahmed Abdulaziz, during an inspection of the TCN-PIU office complex
housing staff in charge of the WB, JICA, AFD and AfDB funded projects.
GM (Program Coordination) PIU-TCN, Engr. Joseph Ciroma accompanied by Project Manager, (AFD), Engr. Mrs Jane Okemini, other
TCN engineers and EPC contractor, on a visit to the construction site of the ongoing brand new 2x60MVA 132/33kV GIS
transmission substation to assess progress made in executing the project at Dawaki, Abuja, .
pag e 5 0 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
TCN Management and NUEE Executives in a National Joint Advisory Committee Meeting. Discussions were on issues that impact
capacity of the company and its staff.
(Standing), Executive Director ISO, Engr. Maman Lawal during a meeting with the firm engaged to assist TCN towards
compliance with the provisions of the Nigerian Data Protection Regulations (NDPR).
Training session for Finance and Account staff on Stamp Duty computation and recent development in the taxation
environment in Nigeria.
pag e 5 1 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
IN-HOUSE ENGINEERS AT WORK
On-going work on 20/30MVA power transformer at the new 132 /33kV Bichi substation in Kano State
Replacement of corroded glass disc insulators on Tower number 425 at Ikeja West - Osogbo 330kV line.
pag e 5 2 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
RETIREMENT
Engr. Adebola Lamina Ishola, RTM Lagos Region. Mr. Adediran Fadahunsi, PM procurement TSP
Mr. Enyo Alexander, PM(F&A) TSP Enugu Region Engr. Adegun Aderemi Olanrewaju, SM (ICT) SO
Mr. John Onyeali Aliri, SM (Admin/Corporate Services) TSP Mr Babatunde Muriana, SM (F&A) TSP
pag e 5 3 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
Borno State Governor Prof. Babagana Zulum’s visit to the Min. of Power, Engr. Sale Mamman & TCN's Ag.
MD/CEO, Engr. Abdulaziz to solicit support for the quick repair of damaged & collapsed towers in Maiduguri.
Hon. Minister of Power, Engr. Sale Mamman, in a meeting with the Egyptian Ambassador to Nigeria, H.E. Ihab Moustafa
Awad. Discussions centered on ways to understudy the Egyptian model in the effective implementation of Siemens
power project
pag e 5 4 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
KNOW YOUR
SUBSTATIONS
HISTORICAL BACKGROUND OF
NEW HAVEN
330/132/33KV TRANSMISSION SUBSTATION
N
ew Haven 330/132/33kV Substation was In 2012, TCN engineers installed and commissioned an
commissioned in 1982 with 2No 150MVA additional 60MVA 132/33kV power transformer, bringing the
330/132/33kV power transformer s at number of transformers in the substation to four with the total
330/132/33kV level and 2No 15MVA 132/66kV and capacity to 180MVA (144MW) on 132kV level.
30MVA mobitra transformer on 132kV level. Located at
New Haven, Enugu, the substation gives supply to Enugu With the growing population and the increasing demand for
State, Ebonyi State, Benue State and some parts of Cross power in Enugu State and environs, the 2No 30MVA 132/33kV
power transformers were further upgraded to 2No 60MVA
Rivers and Anambra States.
132/33kV transformers in the year 2018, which further
increased the substation capacity to 240MVA (192MW).
The sub-station is fed from Onitsha-New Haven 330kV line
(T3H), Ugwuaji-New Haven 330kV Line 1 (H1U) and
TCN is in the process of adding another 150MVA
Ugwuaji –New Haven 330kV Line 2 (H2U).
330/132/33kV transformer to bring the total number of
150MVA, 330/132/33kV power transformers in the substation
In 1985, one of the 15MVA 132/66kV transformers in the
to three. The 2No 60MVA 132/33kV transformers will also be
substation was decommissioned due to a fire incident and
upgraded to 2No 100MVA 132/33kV power transformers,
in 1986, the remaining 15MVA 132/66kV and 30MVA
these would bring the total capacity of the new Haven
mobitra transformers were upgraded to 30MVA 132/33kV
substation to 450MVA on 330kV level and 260MVA on 132kV
power transformers. To further increase the capacity of the
level.
substation, a new 60MVA 132/33kV power transformer
was also commissioned in 2002, by TCN engineers. This
Other planned projects that would impact the substation
increased the substation’s wheeling capacity to 120MVA
include the New Haven – 9th Mile 132kV double circuit line and
(96MW).
reconductoring of the New Haven – Onitsha 330kV line.
pag e 5 5 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
THE NIGERIA ELECTRICITY
SUPPLY INDUSTRY (NESI)
SERVICE LEVEL AGREEMENT (SLA)
AS IT APPLIES TO NERC ORDER
By H.B. Mohammed
Introduction to and overview of NERC Orders: the right to address the following:
NERC/GL/195/2019 and NERC/198/2020a · The provision of cost reflective tariffs
· Prices charged by Licensees are fair to consumers
NERC ORDER · Prices charged by Licensees are sufficient
A NERC Order is any interim or final command, enough for licenses to operate efficiently, recover
direction or instruction to persons as deemed their full cost, and obtaina reasonable return on
necessary in accordance with section 46 of the EPSR capital invested.
Act 2005 which states:
This led to the Commission in its Multi Year Tariff
1) The Chairman shall ensure that all Commission Order 2.1 2015 to address the issue of Cost
decisions and orders: Reflective Tariff in NESI.
3 The Commission may issue written reason in o Cost of fuel (Gas price); and
respect of any other decision or Order as the o Actual available generation capacity.
commission deems necessary.
This led to the Commission's MYTO Minor Review
4 Every recommendation, declaration, decision or
December 2019, minor for 2020 to not only reflect
order of the Commission if purporting to be signed
on the above mentioned variables but also DisCos
by a person describing himself as the Chairman of
Minimum Market Charge Remittance.
the Commission, or by a person describing himself
as the Vice-Chairman acting in the capacity of the
Chairman. OVERVIEW OF NERC ORDER NO: NERC/GL/
5 The Commission may make interim Orders 195/2019
pending the final disposition of the matter before it. The Commission (NERC) issued the NERC Order No:
NERC/GL/195/2019 also known as the “December
EPSR ACT AND NERC 2019 Minor Review of Multi Year Tariff Order
The EPSR ACT Section 32 (d) gave the commission ("MYTO") and Minimum Remittance on Market
pag e 5 6 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
Operator's (MO) Invoice for the Year 2020.” On the NESI BETWEEN DEC 2019 TO MARCH 2020
31stDecember 2019. o T h e 1 1 D i s C o s s u b m i t t e d Pe r f o r m a n c e
Improvement Plans (PIPs) to NERC for consideration.
The Orders therefore focuses on achieving o The PIPs were based o n P l a n n e d
o Extra-ordinary Tariff Review in Nigerian Electricity Improvement of Service to end user customers in
Supply Industry (NESI) NESI
o Framework for Full Revenue Recovery in NESI o The DisCos filed application for a review of their
respective end user tariff as path to financial
o Pathway to elimination of payment of Tariff
sustainability.
Shortfall by FGN in NESI
o TCN on the other hand, submitted an application for
o Guarantee quality power supply, hours of service review of rates payable to Generation Companies
and adequate metering (GenCos) with regards to Ancillary Service of Spinning
Reserve.
o To consider all these concerns, NERC held
WHAT ORDER NO. NERC/195/2019 SEEKS TO ACHIEVE:
consultations and public hearings with customers of
o Developing and implementing a framework the 11 DisCos who thereafter, expressed willingness
to manage future revenue shortfalls for year 2020 to pay appropriate tariffs provided that there would
through a minimum market remittance requirement be quality Power supply, guaranteed hours of service,
to account for differences between cost reflective and adequate metering.
tariffs and allowed tariffs in the settlement of invoices o It is to guarantee a resolution of the concern of
issued by the Nigerian Bulk Electricity Trading the end user customer that the Order was made.
Company Plc ("NBET") and the MO.
o Steering the market towards gradual activation of
OVERVIEW OF NERC ORDER NO: NERC/198/2020
market contracts in line with the requirements of the
o The Commission (NERC) issued the NERC Order
Transitional Electricity Market ("TEM").
No: NERC/198/2020 also known as the “Order on the
Transition to Cost Reflective Tariffs in the Nigerian
Electricity Supply Industry” On the 31stMarch 2020.
c. All DisCos shall be liable for payment of
capacity charge computed on the basis of SUMMARY OF NERC ORDER
their pro-rata load allocation in the Vesting o All future tariff review shall be on the basis of
Contracts executed with NBET. consultation between the DisCos and Customer
clusters with firm commitments on rates and quality
of service.
pag e 5 7 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
a. A firm improvement in supply by DisCos would SERVICE LEVEL AGREEMENT (SLA)
require investments in reinforcing feeders,
transformers and protection equipment. TCN
shall be directed to align and priotize its PURPOSE OF SERVICE LEVEL AGREEMENT
investments towards resolving transmission/ • The purpose of this Agreement is to outline the
distribution interface bottlenecks and reducing performance commitments of each Party with
the high incidence of tripping at 132/33KV respect to the transmission network and system
substations. operation services provided by TCN in furtherance of
NERC's Order NERC/198/2020 dated 31st March
2020 and DisCo's Performance Improvement Plans.
HOW THE ORDER AFFECTS TCN
( a) (Section 10(e ) of the Order)
• A firm improvement in supply by DisCos would
o TCN Shall prioritise its projects towards eliminating require investments in reinforcing feeders,
interface bottle necks transformers and protection equipment. TCN shall be
o Reduce high incidence of tripping in 32/33kV directed to alignand prioritise its investments
Substations – invariably accusing TCN for the towards resolving transmission/distribution interface
trippings. bottlenecks and reducing the high incidence of
tripping at 132/33kV substations.
b. The Commission acknowledges that the
services provided by DisCos is a composite • The financial remedies for TCN and DisCos shall be
that is defined by a number of parameters based on Liquidated Damage Factors to adjust TCN
which include “hours of supply” as Tariffs.
indicated by availability, “reliability” as
defined by frequency and duration of
• Both parties shall be held responsible for loss of
interruptions and “quality” as measured by
capacity due to inaction by either party in accordance
voltage and operating frequency
with the MYTO allocation and as enshrined in the
prescribed in governing industry codes.
NERC order No. GL/184/2019.
CONCLUSION
The operational performance of TCN shall
• The SLA aims to ensure that Electricity Consumers
be anchored on firm agreements with
receive the best Electricity service.
DisCos with key performance indicators and
financial remedies for non-performance by • Consequently, the TCN and DisCos, as parties to the
either party. Agreement, have their respective roles to play in
order to achieve the set objectives.
( c) Section 10(f) of the Order • Therefore, to whom much is given, much more is
• TCN's performance was therefore anchored on a expected. The recent increase in tariff must be
firm agreement with DisCos for quality service complemented by a more satisfactory service
delivery delivery.
• This agreement is thereby known as the SERVICE •Hence, Service Level Agreement is key to ensure
LEVEL AGREEMENT. Service Based Tariff is achieved.
pag e 5 8 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
EDO STATE GOVERNOR DECRIES VANDALISM
OF TCN INFRASTRUCTURE IN THE STATE
Mr. Obaseki who made his feeling known when he granted Earlier in his remarks, the RTM, Benin Region, Engr. Isaac
audience to TCN delegation from Benin Regional Office led Okpe thanked the governor for his support towards
by the Regional Transmission Manager, Engr. Isaac Okpe, making the construction of Etsako 132/33kV substation a
recently at the Government House, Benin City, ordered a reality, and solicited his support in tackling the menace of
thorough investigation into circumstances that led to the vandalism of TCN equipment.
incident.
M
any a time, terminologies employed in Sags or dips as the case may be are a decrease in
the power sector could be ambiguous, voltage from power source. It is a reduction of ac
and rather confusing. Below are some voltage at a given frequency for the duration of 0.5
simplified terminologies that could be used to cycles to 1 minute's time. Sags are usually caused by
describe some common electricity faults or system faults, and are also often the result of
problems. switching on loads with heavy startup currents. It
involves voltages of about 80-85% below normal
CATEGORIES OF POWER PROBLEMS voltage for a short period of time. Survey shows that
voltage sags represent 87% of short term power
SURGES disturbances.
Simply put, they are voltage increase (from source)
to electrical equipment, often for a tiny fraction of a The probable causes are heavy equipment being
second (milliseconds). The trouble is that this turned on (large electric motors), short circuit, fault
fraction can be dangerous and destructive than we on power distribution grid and switching of power
think. mains.
It takes place when the voltage is 110 per cent above
normal, and most commonly caused by turning off a BLACKOUTS
heavy electrical equipment, lightning strikes and If an electricity pylon/poles delivering power to your
hunger for more power. When power grid is over- neighborhood is knocked down, you would notice it.
burdened and switching between power sources Consider this as power failure/interruption which is
create so-called rolling surges which disrupt power the easiest power problem to diagnose.
for a second, that's a surge.
SAGS/DIPS/UNDERVOLTAGES Any temporary, or not so temporary, interruption in
pag e 6 0 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
the flow of electricity will result in a power failure. into systems. Also, poorly grounded sites make the
Precisely, blackout or power failure is defined as a system more susceptible to noise.
zero voltage condition that lasts for more than two
cycles. It could be Instantaneous (0.5-30 cycles), SPIKES
Momentary (30 cycles- 2 secs), Temporary (2 secs- They occur when there is a sudden, rapid voltage
2mins), or Sustained (> 2mins). peak of up to 6kV (a very short over voltage
conditions). They are usually the result of nearby
Supply grid damage, such as lightning strikes, lightning strikes which is measured in nanoseconds
animals, trees, vehicle accidents, destructive weather (ns).
(high winds, etc.), equipment failure, or a basic circuit
breaker tripping, even human error may cause it. SWITCHING TRANSIENTS
This takes place when there is a rapid voltage peak of
BROWNOUTS/UNDERVOLTAGES up to 20kV with duration of 10 µs to 100 µs. They are
These are periods of low voltage in utility lines that commonly caused by arcing faults and static
can cause lights to dim and equipment to fail i.e. a discharges. In addition, major power system
steady lower voltage state (last more than 1sec.). It is switching disturbances initiated by the utilities to
a situation where voltage supply falls below correct line problems may introduce transient
operating limit of equipment. They are caused by voltage into the system.
overburdened utility grid during peak demands. In
addition, damage to electrical lines, overloading on FREQUENCY VARIATIONS
primary power source, and the like can also cause This is simply a change in frequency from the
brownouts. normally stable utility frequency of 50 or 60 cycle/s
(Hz), depending on the geographical location. This
FLICKERS may be caused by erratic operation of emergency
This is a small regular variation in voltage that creates generators or unstable frequency power sources.
an annoying change in light. Human perception is Frequency variation is extremely rare in stable utility
sensitive to light that change at a frequency between power systems, especially systems interconnected
2 - 15 Hz. via a power grid. Where there is poor power
infrastructure, frequency variation is more common
It only bothers people and does not affect especially if the generator is heavily loaded.
components and mechanics because voltage
change is so small. HARMONIC DISTORTION
Harmonic distortion is the corruption of the
LINE NOISE fundamental sine wave at frequencies that are
Line noise is ubiquitous. It is unwanted voltage or multiples of the fundamental. (e.g.180 Hz - 3rd
current superimposed on the power system voltage harmonic). The distortion of the normal line
or current waveform. It's a random fluctuation of waveform is transmitted into the line by non-linear
electrical impulses that are carried along with loads i.e. the non-linearity of the magnetizing
standard alternating current. Turning on the characteristics of transformers being heated up.
fluorescent lights, refrigerators, laser printers, Non-linear loads are caused by variable speed
electric motors, motor control devices, arc welding, motors and drives, copiers, fax machines e.t.c.
switching power supplies can all introduce line noise
pag e 6 1
NEWLY INSTALLED TRANSFORMERS
(JANUARY TO MARCH 2021)
1X60MVA 120MVA
LINES
OLD LINE
CAPACITY (MVA)
150MW
pag e 6 2 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
EDITORIAL TEAM
Sub-Editors:
Engr. A. Tahir Maimuna Isah-Ladan
Eric E. Ene Tosin Olashinde
Engr. A. Aguiyi Grace Sambe-Jauro
Omideji Oluwakayode Engr. Dr. A. Oladeji
Gabriel Gandu H.B. Mohammed
Stanford Nneji
Rufus Imafidon
pag e 4 7 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A
pag e 6 4 T R A N S M I S S I O N C O M PA N Y O F N I G E R I A