Professional Documents
Culture Documents
Drainage (Pond-Wetland Report)
Drainage (Pond-Wetland Report)
Drainage (Pond-Wetland Report)
0 INTRODUCTION
UKM Perunding Kejuruteraan dan Akitek Sdn Bhd has been appointed by the
Principal Consultant, UKM Pakarunding Sdn Bhd to provide drainage services for the
Project “CADANGAN PEMBANGUNAN PUSAT PENYELIDIKAN TASIK CINI,
MUKIM PENYUR, DAERAH PEKAN, PAHANG DARUL MAKMUR”. The owner of
this project is Tetuan East Coast Economic Region Development Council (ECERDC).
The works include the design of on-site detention facility (OSD) together with
wetlands which shall be designed with the control at source concept and shall comply
with Urban Stormwater Management Manual for Malaysia or MSMA (DID, 2000).
The proposed runoff quantity and quality control which is known as Pond-Wetlands
System is consistent with objectives of stormwater management approach which
focus on the both the quantity and quality control of urban runoff. This has been
embodied in the concept of ecologically sustainable development which is aimed at
ensuring that development can occur without long-term degradation of natural
resources and the environment.
Runoff quantity control using on-site detention (OSD) shall be designed based on
Swimburne Method and the design storm for calculating the required storage volume
up to 10-year ARI, where excess runoff from post-development discharge is stored at
OSD storage.
The minimum ground surface slope shall be 2% to promote free surface drainage
and minimize the possibility of pools of water remaining after the area has drained.
Side slopes should be a maximum 1(V):3(H) where possible.
Orifice and weir are constructed as outlet control structure for minor and major storm
events respectively.
Primary flow regulating device for above-ground storage is an orifice. The discharge
through orifice can be calculated using:
Secondary outlet is provided to cater for rarer storms than the OSD facilities were
designed for. Broad-crested weir is proposed to provide a controlled overflow of flows
in excess of the maximum design storm ARI for the OSD storage facility. The
equation used for a broad-crested weir is:
Trash screen will be provided to protect the outlet from blockage and to retain litter
and debris which would otherwise degrade downstream waterways.
3.2.1 Wetlands
The proposed inlet zone of the wetlands is integrated with the OSD at the wet pool
area. Inlet zone is designed as a sediment basin and serves two functions:
Extended detention of 0.30 m depth is provided for temporarily storage above the wet
pool area of OSD. During water quality storm, runoff will having a pre-treatment at
this inlet zone. The runoff will be released slowly from the wetlands outlet to achieved
the effectiveness of pollutant removal performance through the macrophyte zone and
open water zone.
The macrophyte zone should be provided around the wetland edges downstream of
the main inlets to filter out sediment, nutrients and toxicants, to disperse the inflowing
waters and to reduce their velocity. For macrophyte zones to function efficiently,
Proposed wetlands species for constructed wetland are shown as Table 1 below :
An open water zone is a deeper area that allows time for fine particles to flocculate to
the bed and allows sunlight to kill bacteria. Decomposition and grazing of organic
matter will occur in this zone. Periodic algal growth may occur here and this will also
trap dissolved nutrients and allow them to enter the food chain or to settle to the bed
of the pond.
4.0 CONCLUSION
By minimizing the surface runoff at source through the provision of on-site facilities,
the peak runoff can be reduced at the downstream area. In addition, treatment of
stormwater at source for water quality storm will give better water quality before
runoff discharge to the receiving water body (Tasik Cini) at the downstream area.
Design Storm ARI for this development is 5-year. The on-site detention (OSD) is
designed to detain the runoff from drainage system (up to 10-year ARI) before being
discharge into receiving water body. The constructed wetlands are design based on
water quality design storm with 3-month ARI rainfall depth over the contributing
catchment. Table 2 provides the summary of drainage management at development
area and Figure 1 shows the sizing of OSD using Swinburne Method.
Qa Inflow hydrograph
(Q5=1.917 m3/s;
Q10=2.090 m3/s)
SSR Outflow hydrograph
3
(=555.96 m )
PSD
(=1.451 m3/s)
0 tf tc
Figure 1 : Sizing of OSD using Swinburne Method
DESIGN CALCULATIONS
Eq 19.1 Q Qp = 9279.549
a 4 a 0.333 t c 0.75 t c 0.25 t cs
c
t Q a
b 4 Qa Q p = 11361800
a a 2 4b = 1451.4 l/s
PSD
2
td PSD
Qd (l/s) c d SSR (m3)
(mins) (l/s)
5 2971.19 1451.40 985.23 151.73 550.27
10 1998.84 1451.40 846.71 225.53 555.96
15 1450.08 1451.40 686.53 310.88 407.41
20 1135.29 1451.40 524.75 397.08 256.15
30 770.03 1451.40 171.25 585.44 24.01
Do
4A o
4 x 0.0884 = 0.335 m
Broad-crested weir is sized for the estimated major system ARI flow from
the site for time tcs (10 minutes) for 50 year ARI.
50
I20 = 229.28 mm/hr
Therefore, provide 5.00m x 5.00m brick wall sump with 6 nos. of 340
mm dia. orifice at outlet 1 and discharge to conveyance cascade drain
(external drain) by rectangular orifice 0.5 m x 0.6 m concrete box culvert.
Emergency Outlet:
Emergency spillways is provided to safely pass a major design storm
through the basin.
Wetlands Design
Figure 28.2 Determine required wetland area ratio for the targeted pollutant
– 28.4 removal efficiencies.
Design Chart 35.1 Annual Pollutant Capture Curve for Sediment as a Function of Pond Area Ratio
Design Chart 35.2 Annual Pollutant Capture Curve for SS as a function of Pond Area Ratio
Design Chart 35.3 Annual Pollutant Capture Curve for TP as a Function of Pond Area Ratio
Width, W = 25 m
Length, L = 8m
Surface area = 200 m2
(i) Area: = 72 m2
Low marsh = 33 m2
High marsh = 39 m2
(>71.50 m2
…Check)
(ii) Depth:
Low marsh = 0.6 m
High marsh = 0.3 m
Vegetation specifications:
Outlet 3 Sizing:
Primary outlet:
Provide 2 nos. of 150 mm orifice,
DRAWINGS